Issue/Remarks:-
1) Last footing pad line of shear wall infront of Grid K, comes over topmost 9th step. Top most step demolishing in progress
3) Steel demand not yet raised - The project will stuck due to non availability of steel at site.
4) Some footings are of 4'6" and other are 5'6" deep. Excavation can only be completed once Dwgs are issued
Remarks
Grid
p demolishing in progress
gs are issued
Contractor Representative:
he step in progress