Microsoft Project 2013 Essentials
1st edition
2015 Shelley Fishel & bookboon.com
ISBN 978-87-403-1141-9
3
Microsoft Project 2013 Essentials Contents
Contents
5 The Ribbon 17
5.1 The Task Ribbon 17
5.2 The Backstage View 18
www.sylvania.com
We do not reinvent
the wheel we reinvent
light.
Fascinating lighting offers an infinite spectrum of
possibilities: Innovative technologies and new
markets provide both opportunities and challenges.
An environment in which your expertise is in high
demand. Enjoy the supportive working atmosphere
within our global group and benefit from international
career paths. Implement sustainable ideas in close
cooperation with other specialists and contribute to
influencing our future. Come and join us in reinventing
light every day.
Light is OSRAM
6 Settings 20
6.1 Tools Options Now Backstage 20
7 Setting the Project Options for your Project in Microsoft Project 2013 21
7.1 Set a Start Date or a Finish Date for the Project 22
7.2 Setting Public Holidays 25
8 Default Duration 27
8.1 Changing the Default Duration 27
8.2 Task Options 28
9 Tasks 31
9.1 Entering a task name and duration 31
360
.
10 Selecting Parts of the Screen 33
thinking
360
thinking . 360
thinking .
Discover the truth at www.deloitte.ca/careers Dis
Discover the truth at www.deloitte.ca/careers Deloitte & Touche LLP and affiliated entities.
11 Outlining 37
11.1 What is Outlining 37
11.2 Saving Projects 40
11.3 Adding Notes to a Task 41
11.4 Creating Hyperlinks to other documents 42
Do you like cars? Would you like to be a part of a successful brand? Send us your CV on
We will appreciate and reward both your enthusiasm and talent. www.employerforlife.com
Send us your CV. You will be surprised where it can take you.
AXA Global
Graduate Program
Find out more and apply
8
Microsoft Project 2013 Essentials Contents
21 Templates 140
21.1 What advantages are there to creating a template? 140
21.2 Copying a picture of a Project into another program 144
23 Reports 154
23.1 What benefits do I gain by creating a Report? 154
24 Appendices 155
24.1 Working with more than one project 155
24.2 Elapsed Time 156
24.3 Costs 157
25 Glossary 161
Index 162
9
Microsoft Project 2013 Essentials About Shelley Fishel
Why waste time and money on training people in areas that are not relevant to them? Its common
sense to invest that time and effort on what they really need.
That was the light bulb moment and the IT Training Surgerys unique approach has resulted in a growing
business with a team of highly qualified IT trainers.
If trainees get bored they forget most of what they learn. We like to offer a range of training approaches
to suit different people and, most of all; we aim to make training fun!
Shelley and her team have worked hard to achieve accreditation by the Learning and Performance Institute
for the IT Training Surgery, as a recognized high quality provider of IT training.
To find out more about our training give us a call on 020 8203 1774 or visit our website
www.theittrainingsurgery.com
10
Microsoft Project 2013 Essentials About Microsoft Project 2013 Essentials
When you see this icon you know that the information next to it is essential
11
Microsoft Project 2013 Essentials Getting Help in Microsoft Project 2013
7\SHZKDW\RX
DUHORRNLQJIRU
KHUH
3UHVV5HWXUQ
2. Type what you are looking for into the white box
3. Press Return
4. A list of subjects that match your criteria will appear
12
Microsoft Project 2013 Essentials Getting Help in Microsoft Project 2013
13
Microsoft Project 2013 Essentials What is Microsoft Project 2013?
Objective
Tasks
Time
Resources (people, equipment, facilities)
Tasks:
Resources:
Reports:
Reports provide a way to inform others of the project schedule i.e. who is doing what when?
14
Microsoft Project 2013 Essentials The Project Screen
7DEV
3URMHFW
7KH5LEERQ
7KH*DQWW
7KH(QWU\
&KDUW
7DEOH
e Graduate Programme
I joined MITAS because for Engineers and Geoscientists
I wanted real responsibili www.discovermitas.com
Maersk.com/Mitas e G
I joined MITAS because for Engine
I wanted real responsibili Ma
Month 16
I was a construction Mo
supervisor ina const
I was
the North Sea super
advising and the No
Real work he
helping foremen advis
International
al opportunities
Internationa
ree wo
work
or placements ssolve problems
Real work he
helping fo
International
Internationaal opportunities
ree wo
work
or placements ssolve pr
Download free eBooks at bookboon.com
Microsoft Project 2013 now has the Ribbon which was introduced to the main office programs in the
2007 release. Microsoft Project 2007 did not have the general new interface which was added to Microsoft
Project with the 2010 version.
16
Microsoft Project 2013 Essentials The Ribbon
5 The Ribbon
5.1 The Task Ribbon
17
Microsoft Project 2013 Essentials The Ribbon
The Backstage looks on the surface just like the old File Menu however it does much more than that.
93%
OF MIM STUDENTS ARE
WORKING IN THEIR SECTOR 3 MONTHS
FOLLOWING GRADUATION
MASTER IN MANAGEMENT
STUDY IN THE CENTER OF MADRID AND TAKE ADVANTAGE OF THE UNIQUE OPPORTUNITIES
Length: 1O MONTHS
THAT THE CAPITAL OF SPAIN OFFERS
Av. Experience: 1 YEAR
PROPEL YOUR EDUCATION BY EARNING A DOUBLE DEGREE THAT BEST SUITS YOUR
Language: ENGLISH / SPANISH
PROFESSIONAL GOALS
Format: FULL-TIME
STUDY A SEMESTER ABROAD AND BECOME A GLOBAL CITIZEN WITH THE BEYOND BORDERS
Intakes: SEPT / FEB
EXPERIENCE
Info Get information about the Project file and any other apps that you may have installed.
New Create a new Project file here or select one of the templates.
Open Open a Project File from a list of recent Project Files or locations accessed.
Save Save your Project so that you dont lose your changes
Save as Select where to save your Project from a choice of online and offline locations.
Print The print dialogue is accessed from here and you can set how many copies and see a preview here too
Share Allows you to share a project file with others via email or as a pdf or to share your Project to a server.
Export Export or save your Project in different formats including PDF-older versions and as an Excel file.
Account Information about your Microsoft Account is shown here. If you are using a standalone version
of Microsoft Project 2013 then any other accounts that are connected will be shown here.
Options This replaces Tools Options in previous versions of Project and is where you control
how Project 2013 behaves we will be looking at this later in the course.
Once you do this however, you will notice that many of the new features have been disabled.
19
Microsoft Project 2013 Essentials Settings
6 Settings
In Project 2013 there are some fundamental differences to previous versions. If you are a new user, this
will not make any difference to you however if you have been using Project in earlier versions 2000,
2002, 2003 or 2007 there are a few radical differences which we will explore here.
We are going to take a look at the Options here in more detail before we start to create a project as these
Options control how Microsoft Project 2013 behaves.
2QWKHOHIWLVDOLVWHDFK
RIWKHOLVWHQWULHVZLOORSHQ
XSLWVRZQVHWRIRSWLRQV
+HUHZHDUHORRNLQJDWWKH
*HQHUDO2SWLRQVZKLFK
FRQWUROVWKHFRORXUVFKHPH
DQGWKHRSHQLQJYLHZ
WRJHWKHUZLWKWKHGDWH
IRUPDWDQGWKH8VHU1DPH
20
Setting the Project Options for your
Microsoft Project 2013 Essentials Project in Microsoft Project 2013
Choose a project start date and see how long the project will take (recommended!)
or
Choose project end date and see when you will have to start the project to finish on time.
22
Setting the Project Options for your
Microsoft Project 2013 Essentials Project in Microsoft Project 2013
Individual resources have their schedules based on one of these calendars and one of the first things you
must do is define what the standard working hours are.
23
Setting the Project Options for your
Microsoft Project 2013 Essentials Project in Microsoft Project 2013
CLICK HERE
to discover why both socially
and academically the University
of Groningen is one of the best
places for a student to be
www.rug.nl/feb/education
To select more than one day, hold down shift as you select to choose days next to each
other or hold down Control as you select to choose days not next to each other.
Public Holidays
Only Saturdays and Sundays are set up as non-working time in MS Project as standard,
so unless you want to work Christmas day you will have to edit the Calendars.
Type in the dates that you want to set as holidays probably public holidays to begin with unless your
organisation has holiday dates follow this link to find public holidays in the UK.
(http://www.dti.gov.uk/employment/bank-public-holidays)
4. Click Ok
To view the changes scroll through the calendar to see the dates marked as non-working time.
25
Setting the Project Options for your
Microsoft Project 2013 Essentials Project in Microsoft Project 2013
7.2.1 Define the length of the working day How many hours does Project assign to a one
day task?
Once you have set the working times for the whole project you need to let MS Project know how many
hours there are in a working day.
Project can then schedule tasks correctly if you set a one day task Project needs to know
what time to start the task and what time to end it.
From a cost point of view it is necessary for Project to know how many hours there are in a
day. A 7 hour day will cost 70 whereas an 8 hour day will cost 80.
If you have set a day as a 7 hour day and given a resource more than 7 hours work that
resource will show up as over-allocated. This will be governed by the settings you make here.
Essential
The default start/end times are entered with a colon e.g. 08:30 = eight thirty
(colon represents hours and minutes). Hours per day and hours per week are
entered with a decimal point, e.g., 7.50 = seven and a half hours.
26
Microsoft Project 2013 Essentials Default Duration
8 Default Duration
8.1 Changing the Default Duration
If your project is measured in months or years rather than days, it may be worth changing the default
duration measure so that tall tasks have a default as such.
American online
LIGS University
is currently enrolling in the
Interactive Online BBA, MBA, MSc,
DBA and PhD programs:
4. Click the down arrow next to Duration is entered in and make your selection
5. Click OK
This process sets the default duration for this project only!
When starting a project you would expect that as you schedule tasks Project will automatically work out
the start and finish dates for the task based on the start/finish date of the project.
Manually Scheduled
Automatically Scheduled
The default setting for tasks is now Manually Scheduled. This setting does not set default duration or
place the task in the timeline:
1RWHWKDWWKLVWDVNGRHVQRWKDYH
GXUDWLRQRUWDVNLQWKH*DQWWFKDUW
Tasks that need to be noted, but that you dont have enough information about to schedule
can now be recorded easily
You can add detail later on when the information is confirmed
You can use this kind of scheduling for Top Down planning when you wish to concentrate
on getting things listed without being distracted by time and dependencies
28
Microsoft Project 2013 Essentials Default Duration
In versions of Project p prior to Project 2010 tasks were always scheduled automatically. This means
that when you add a task to the list, a default duration of one day is shown and Project will place the
task on the timeline relative to the start or finish date of the project (Depending on whether you are
scheduling forwards or backwards).
1. Click File
2. Click Options
3. Click Schedule on the left
4. Decide if you are changing the Scheduling Option for this project or All New Projects!
5. Change the drop down to Auto Scheduled
6. Click Ok
When you look at the task bar you will see which scheduling method is currently being used.
29
Microsoft Project 2013 Essentials Default Duration
You can also change the Scheduling Method for all tasks using the Mode icon in the Tasks group on
the Tasks Tab:
In the Entry Table, you can select the mode from the Task Mode column
9 Tasks
9.1 Entering a task name and duration
1. Make sure you are in Gantt Chart View
2. Type the task name in the Task Name column
3. Type the duration in the duration column
4. Repeat for all tasks
OR
If you are unsure of your task duration because you are awaiting information you can still enter them
into Project you can mark them as estimated durations and update them at a later time.
31
Microsoft Project 2013 Essentials Tasks
When you schedule automatically all new tasks can have a default setting of Estimated Durations. To
change this:
9.1.3 Milestones
Milestones are simply important checkpoints in your project. They are points at which you review the
projects progress so far and decide on any changes to the plan that need to be made.
32
Microsoft Project 2013 Essentials Selecting Parts of the Screen
Delete a task
Move a task
Insert a task
Link tasks
Selecting a Task
Maastricht
University is
the best specialist
university in the
Visit us and find out why we are the best! Netherlands
(Elsevier)
Masters Open Day: 22 February 2014
www.mastersopenday.nl
Or
1. Click on the first task
2. Hold down SHIFT
3. Click on the last task
Selecting a row
Note that the cursor looks like a black arrow pointing to the right.
34
Microsoft Project 2013 Essentials Selecting Parts of the Screen
&OLFNRQWKH6HOHFWDOOFHOO
KHUH<RXUPRXVHZLOOORRN
OLNHDELJZKLWHSOXVVLJQ
Inserting a Task
1. Click on the line below where you want the new task
2. In the Task Group on the Task Tab click Task
Deleting a Task
1.1.1
35
Microsoft Project 2013 Essentials Selecting Parts of the Screen
Moving a Task
<RXUPRXVHZLOOORRNOLNH
DIRXUSRLQWHGDUURZILUVW
DQGWKHQ\RXZLOOVHHD
GRWWHGOLQHZKHQ\RXGUDJ
WRWKHQHZORFDWLRQ
11 Outlining
11.1 What is Outlining
Outlining is the process of organising your project into phases by creating Summary Tasks and Sub
Tasks. In Project, Sub Tasks are indented under Summary Tasks.
A Summary Tasks duration is determined by the sum of the Sub Tasks within it.
6XPPDU\7DVN
6XE7DVNV
Summary Tasks appear in BOLD and Sub Tasks are indented below the Summary.
37
Microsoft Project 2013 Essentials Outlining
Note that the tasks you had selected have now been indented underneath your new Summary Task.
To undo outlining, out-dent all your subtasks until all your tasks return to the same outline level.
You can collapse or expand Summary Tasks to view either the full detail or just the summary.
You can add a Summary Task that represents the whole project. The name of the Project Summary Task
will be the file name. You can change this task name in the same way as any other task name.
39
Microsoft Project 2013 Essentials Outlining
40
Microsoft Project 2013 Essentials Outlining
Hold your mouse over the icon in the first column of the table
3. Navigate to the folder that holds the document you wish to link
42
Microsoft Project 2013 Essentials Outlining
As mentioned earlier, if you are scheduling your tasks automatically, by adding links between tasks,
Project will slot the tasks into the correct time and make them follow on from the previous task you
have selected.
Finish to Start
Start to Start
Finish to Finish
Start to Finish
When you link tasks in Project, the default link type is finish-to-start. However, a finish-to-start link
does not work in every situation.
Task B cannot start until Task A has finished. For example, if you have two tasks: Create Timetable and
Create Exercises, the Create Exercises task cannot start unitl the Create Timetable task has finished.
Start to Start
The dependent task can start at any time after the task that it depends on begins. The SS link type does
not require that both tasks begin at the same time.
For example, if you have two tasks, Pour concrete and Level concrete, the Level concrete task cannot
begin until the Pour concrete task begins.
Download free eBooks at bookboon.com
44
Microsoft Project 2013 Essentials Creating the Schedule
Finish to Finish
The dependent task can be completed at any time after the task that it depends on is completed. The FF
link type does not require that both tasks be completed at the same time.
For example, if you have two tasks, Add wiring and Inspect electrical, the Inspect electrical task
cannot be completed until the Add wiring task is completed.
Start to Finish
The dependent task can be completed at any time after the task that it depends on begins. The SF link
type does not require that the dependent task be completed concurrent with the beginning of the task
on which it depends.
For example, the roof trusses for your construction project are built off-site. Two of the tasks in your
project are Truss delivery and Assemble roof. The Assemble roof task cannot be completed until
the Truss delivery task begins.
45
Microsoft Project 2013 Essentials Creating the Schedule
2.1.1
12.1.3 Linking Tasks on the Gantt chart using click and drag
Hover your mouse over the first task in the Gantt chart until you see a four headed arrow
47
Microsoft Project 2013 Essentials Creating the Schedule
12.1.6 Adding Tasks into a list of tasks that are already linked
If you add a new task into a list of tasks which have already been linked it can be automatically linked
to the surrounding tasks. This means that Project 2013 will place a Start to Finish link on both sides of
the new task depending on where it is inserted in the list.
This feature is switched off by default and here are the instructions to switch it on.
48
Microsoft Project 2013 Essentials Creating the Schedule
3. Click OK
You create the links in exactly the same way as Automatically Scheduled tasks.
As you can see the Gantt bars look a little different. Project does place the tasks in date order.
This is the default behaviour for Manually Scheduled Tasks. You can change it so that when you link
Manually Scheduled Tasks they stay on the date that they first began on and do not move.
50
Microsoft Project 2013 Essentials Creating the Schedule
12.4 Zooming
12.4.1 Zooming into the Gantt chart
In Project 2013 it is much easier to zoom around the Gantt chart and to focus on different timescales.
First display the View tab on the Ribbon and select the relevant icon from the Zoom group.
This icon enables you to set the timescale:- to any of the following
If you have a task in the table and the Gantt bar is somewhere
off screen, clicking this icon will bring the task bar to view
51
Microsoft Project 2013 Essentials Creating the Schedule
12.4.2 Changing the balance between the Table and the Gantt Chart
1. Place the cursor on the dividing line between the Gantt chart and the table
2. Click and Drag
RUN FASTER.
RUN LONGER.. READ MORE & PRE-ORDER TODAY
RUN EASIER WWW.GAITEYE.COM
Examples
Sending invitations and then calling a week later to see who is coming
Giving the first coat of paint time to dry before applying the second
2QHGD\ODJ
EHWZHHQFRDWV
53
Microsoft Project 2013 Essentials Creating the Schedule
Example
A one week overlap between one member of staff leaving and the replacement member starting to allow
for on the job training of the new member of staff.
GD\RYHUODS
EHWZHHQWDVNV
1. Double click the dependency arrow on the 1.Double click the dependency arrow on the
Gantt Chart between two tasks Gantt Chart between the two tasks
Type a duration in the Lag box Type a negative duration in the Lag box
Click OK Click OK
Instead of defining the number of days for lead, you can also type in a percentage. For
Example: -50% would start the second task when 50% of the first task has been finished.
Remember that New Tasks always appear above the row your cursor is in when you add them.
1. Click on the row below where the new Recurring Task will be
2. Click on the drop down arrow under Task in the Insert Group on the Task Ribbon
54
Microsoft Project 2013 Essentials Creating the Schedule
5. Click OK
The recurring task will appear in the Gantt chart as a number of small unconnected bars.
The task can be unrolled by clicking on the plus sign next to the task name. A recurring task is really a
special form of summary task.
When the task has been unrolled each individual occurrence may be customised by, for example, the
date or duration by simply double clicking it.
Example:
A resource spends all day on Monday on a task, waits a few days for information to arrive from a supplier,
and then spends Friday afternoon finishing the task. The resource is only working for 1.5 days.
The task appears as a full week, while project uses 1.5 days of work to calculate the resources commitment.
We need to see a Gantt bar on the Monday for a full day and a Gantt bar on the Friday for half a day.
The actual duration of the task is 1.5 days.
1. Format the dates so that you can see the times of the day that tasks are scheduled
2. Change the zoom level to half day scale
3. Use the Split icon to move the second half of the task to Friday afternoon
56
Microsoft Project 2013 Essentials Creating the Schedule
If you dont already see the date and time in the date column of the Entry Table do the following:
5. Click OK
www.sylvania.com
We do not reinvent
the wheel we reinvent
light.
Fascinating lighting offers an infinite spectrum of
possibilities: Innovative technologies and new
markets provide both opportunities and challenges.
An environment in which your expertise is in high
demand. Enjoy the supportive working atmosphere
within our global group and benefit from international
career paths. Implement sustainable ideas in close
cooperation with other specialists and contribute to
influencing our future. Come and join us in reinventing
light every day.
Light is OSRAM
Click on the zoom in icon until your scale looks like this:
The task has a duration of 1.5 days. The first day will take place on Monday and the extra half a day on
Friday afternoon.
4. Move the pointer to the date you wish to move the unfinished part to
58
Microsoft Project 2013 Essentials Creating and Assigning Resources
Resources are usually the people working on your project but they can also be the materials that are
used. Once you have created your resource list you can:
Work Resource These are usually people who do the work in the project
Material Resource Consumable items used in the project such as paper, paint, bricks etc.
Cost Resources Miscellaneous costs such as airfare or meal expenses (not covered in this course)
A new view has been added called Team Planner more about this a little later.
59
Microsoft Project 2013 Essentials Creating and Assigning Resources
You will see the Resource Sheet View together with an extra contextual Ribbon to enable formatting of
the Resource Sheet.
360
13.2.2 Creating a Work Resource
.
1. Enter a name in the Resource Name column
thinking
2. Enter an abbreviated version of resource name in the Initials column if required (you can
add Initials to the Gantt Chart view later as it takes up less space)
3. Add a group if appropriate (Full Time or Part Time for example)
4. Change the Max Units
5. Press Enter to complete
360
thinking . 360
thinking .
Discover the truth at www.deloitte.ca/careers Dis
Discover the truth at www.deloitte.ca/careers Deloitte & Touche LLP and affiliated entities.
Max units mean the amount of that resources available time that is available to the project.
For example if Jenny works 2 days a week she is available for 100% of her two days and will be able
to work between the hours of 9 am and 5 pm.
You can set her Max Units to 100% and change her working times to show which days she is working.
For example she only works on Tuesday and Thursday. So by setting her Max Units at 100% you are
indicating that Jenny is available all day on Tuesday and Thursday to work on the project.
You can also use Max Units to indicate that you have a team. For example:
We have three decorators on the project. We dont mind which decorator turns up to paint the walls,
so long as one does. We set the Max Units to 300% which tells us there are three in total and to assign
just one decorator we assign just 100% of the decorators. More on this shortly when we learn how to
assign resources.
Each time a resource is created a resource calendar is automatically created that determines individual
working times. This enables you to specify which hours a person works if they are part time, or on which
days they are available. You can also allocate individual holidays here.
61
Microsoft Project 2013 Essentials Creating and Assigning Resources
Do you like cars? Would you like to be a part of a successful brand? Send us your CV on
We will appreciate and reward both your enthusiasm and talent. www.employerforlife.com
Send us your CV. You will be surprised where it can take you.
When a task is Effort Driven Microsoft Project keeps the total work at its current level no matter how
many resources are allocated to it. When you add further resources, the remaining work is distributed
to them.
For example you have a huge report which will take one person a week to write, and you allocate your
writer to that task Project will schedule the task to take one week. If the task is Effort Driven and you
now add another writer to the task, Microsoft Project will reduce the length of time it takes to finish
the report to 2.5 days.
Download free eBooks at bookboon.com
63
Microsoft Project 2013 Essentials Creating and Assigning Resources
A Non Effort Driven task allows you to add lots of resources without affecting the duration of the task.
In our example above if the Report task is not effort driven then when I add the second writer to the
task the overall duration will stay the same.
The default option for Effort Driven Settings is that they are switched on. This means that Microsoft
Project will treat all tasks as Effort Driven.
If the majority of the tasks in your projects are Effort Driven the duration is dependant of the number
of resources assigned, then leave well alone.
If however most of your tasks are not Effort Driven you may wish to turn this off.
1. Click File
2. Click Options
3. Click Schedule
4. In the list deselect the check box next to All Tasks are Effort Driven
64
Microsoft Project 2013 Essentials Creating and Assigning Resources
AXA Global
Graduate Program
Find out more and apply
5. Click Assign
Repeat this process for all tasks that you wish to assign resources to.
66
Microsoft Project 2013 Essentials Creating and Assigning Resources
13.7.2 The initial assignment of resources using the Resource Column NEW
You can now add more than one resource using the resource column. In previous versions you could
only select one resource at a time this way.
,QFUHDVHWKHSHUFHQWDJHRI
UHVRXUFHKHUH
Download free eBooks at bookboon.com
67
Microsoft Project 2013 Essentials Creating and Assigning Resources
1RWHWKDWWKHSDSHUVKRZVXSKHUHZLWKWKH
QXPEHURIUHDPVDVWKDWLVWKHODEHOZHFKRVH
ZKHQFUHDWLQJWKHUHVRXUFH
e Graduate Programme
I joined MITAS because for Engineers and Geoscientists
I wanted real responsibili www.discovermitas.com
Maersk.com/Mitas e G
I joined MITAS because for Engine
I wanted real responsibili Ma
Month 16
I was a construction Mo
supervisor ina const
I was
the North Sea super
advising and the No
Real work he
helping foremen advis
International
al opportunities
Internationa
ree wo
work
or placements ssolve problems
Real work he
helping fo
International
Internationaal opportunities
ree wo
work
or placements ssolve pr
Download free eBooks at bookboon.com
You may decide to add or remove resource assignments in order to shorten the project, resolve over
working or simply because the wrong person is on the task.
69
Microsoft Project 2013 Essentials Creating and Assigning Resources
The Team Planner View is made up of two sections. The top shows a combined view of the resources
from the resource sheet together with a Gantt bar for the tasks allocated to that person in the timeline.
The bottom portion shows tasks which have not yet been assigned.
You can also see non-working time which is shaded in very light grey on the timeline. Non-working
time includes weekends and holidays based on the shared companywide calendar.
Also displayed is the non-working time, such as personal holidays and sick days which have been added
to individual calendars.
You can customise the way that the Formatting looks in Team Planner view.
Use the icons to set the formatting for each different type of task, from Auto or Manually Scheduled, to
showing the actual work or external or late tasks. Each one can have different fill colours and/or borders.
Download free eBooks at bookboon.com
70
Microsoft Project 2013 Essentials Creating and Assigning Resources
Reschedule a task if the person you want to perform that task is over worked.
You can allocate previously unallocated tasks by dragging.
Reassign a task to a different resource by dragging it around.
To reschedule a task to a different time, if you realise that you need to reschedule due to other issues
cropping up, simply drag the tasks Gantt bar to the new time period.
When you reschedule a task in The Team Planner, Project sets a Start No Earlier Than (SNET) constraint
on the task.
To reassign a task to a different resource drag the tasks Gantt bar from the assigned resource to the
new one and drop it on the desired time period.
93%
OF MIM STUDENTS ARE
WORKING IN THEIR SECTOR 3 MONTHS
FOLLOWING GRADUATION
MASTER IN MANAGEMENT
STUDY IN THE CENTER OF MADRID AND TAKE ADVANTAGE OF THE UNIQUE OPPORTUNITIES
Length: 1O MONTHS
THAT THE CAPITAL OF SPAIN OFFERS
Av. Experience: 1 YEAR
PROPEL YOUR EDUCATION BY EARNING A DOUBLE DEGREE THAT BEST SUITS YOUR
Language: ENGLISH / SPANISH
PROFESSIONAL GOALS
Format: FULL-TIME
STUDY A SEMESTER ABROAD AND BECOME A GLOBAL CITIZEN WITH THE BEYOND BORDERS
Intakes: SEPT / FEB
EXPERIENCE
To assign an unassigned task to any resource drag the tasks Gantt bar from the bottom pane to the top
pane and drop it in the time period where you wish to schedule it.
100% Allocation
When you assign a task to a resource this way, Microsoft Project 2013
assumes 100% availability on the task and assigns it accordingly.
You can reassign or reschedule multiple tasks in Team Planner view by holding down the control key
and clicking on each task. Then drag and drop the group of selected tasks.
The Team Planner View does not allow you to make multiple first assignments this way.
Over Allocation is when a resource has been given work that totals more hours than there are in the
day! I know that is normal procedure for many but not good for getting your project done in time and
on budget.
A resource can work on two or more tasks at the same time without any issues so long as none of the
tasks are full time. In this case each task appears on its own row. If however concurrent tasks take up
more time than that resource has available red stripes appear at the top or bottom of overlapping bars.
The Resource name appears in Red too.
72
Microsoft Project 2013 Essentials Creating and Assigning Resources
7KHVHOLQHVDUHUHGLQ
3URMHFW
You can set Team Planner to prevent Over Allocation automatically. This means that if you reassign a
task to a resource that is fully allocated, Microsoft Project will push the task off to when the resource
is available.
The status bar now displays the message that Prevent Over allocations is switched on.
73
Microsoft Project 2013 Essentials Creating and Assigning Resources
$OLVWRIILOWHUV
DSSHDUVKHUH<RX
FDQDOVRFUHDWH\RXU
RZQFXVWRPILOWHUV
WRR
To group Tasks:
75
Microsoft Project 2013 Essentials Creating and Assigning Resources
You can see that an extra row containing the group heading has been added and is shaded to differentiate
from the regular tasks.
76
Microsoft Project 2013 Essentials Creating and Assigning Resources
CLICK HERE
to discover why both socially
and academically the University
of Groningen is one of the best
places for a student to be
www.rug.nl/feb/education
You can now use Auto filter to pull out all those resources in a particular group or you can:
1. Right click on the resource you wish to create a hyperlink for in the Resource Sheet
2. Select Hyperlink
3. Select Create Hyperlink
4. Click on the Email Address button
5. Type the email address
6. Type a subject line
7. Click OK
78
Microsoft Project 2013 Essentials Creating and Assigning Resources
American online
LIGS University
is currently enrolling in the
Interactive Online BBA, MBA, MSc,
DBA and PhD programs:
6. Click OK
80
Microsoft Project 2013 Essentials Creating and Assigning Resources
7. Now set up the Work Weeks for your new calendar Follow the procedure earlier in the manual.
8. Click OK
If you choose to create a brand new base calendar you will have to set
the standard working times and all the public holidays too!
Sometimes you may have a task that is worked on at a particular time that is not in the standard calendar.
You may be testing equipment and this must be done at weekends instead of when all the staff are at work.
81
Microsoft Project 2013 Essentials Creating and Assigning Resources
In this case you can assign the Weekend Work calendar to the task.
83
Microsoft Project 2013 Essentials The Calendar View
84
Microsoft Project 2013 Essentials The Calendar View
Initially all your tasks may run into each other and look very strange. To get around this change the layout.
Maastricht
University is
the best specialist
university in the
Visit us and find out why we are the best! Netherlands
(Elsevier)
Masters Open Day: 22 February 2014
www.mastersopenday.nl
1. Click on the Filter Drop down in the Data Group on the View Ribbon
86
Microsoft Project 2013 Essentials The Calendar View
4. Click OK
6WHS2QH 6WHS)LYH$VVLJQUHVRXUFHV
3ODQ\RXUSURMHFW x 'HFLGHZKHWKHUDWDVNLVHIIRUW
GULYHQRUQRQHIIRUWGULYHQ
x $VVLJQUHVRXUFHVWRWDVNV
6WHSWZR6HWXSWKHSURJUDPPH
x 'HFLGHZKHWKHUWRVFKHGXOHIURPVWDUW
GDWHRUHQGGDWH
x 6HW&DOHQGDUZRUNLQJWLPHV 6WHS6L[(YDOXDWHWKHVFKHGXOH
x 6HWFDOHQGDURSWLRQV x ,IQHFHVVDU\FKHFNKRZ\RXFDQ
WLJKWHQWKHVFKHGXOHWRDFKLHYHD
UHTXLUHGILQLVKGDWH
x 5HVROYHRYHUDOORFDWLRQV
x (QWHUGHDGOLQHVDQGFRQVWUDLQWV
6WHSWKUHH&UHDWHWKHVFKHGXOH
x (QWHUWDVNVDQGPLOHVWRQHVJHWWDVNV
LQDORJLFDORUGHU
x (QWHUWDVNGXUDWLRQV
x 2XWOLQLQJRUJDQLVH\RXUVFKHGXOH 6WHS6HYHQ7UDFNLQJWKH3URMHFW
LQWRVXPPDU\WDVNVDQGVXEWDVNV x 6DYHDEDVHOLQH
x /LQNWDVNVWRJHWKHU x 8SGDWHSURJUHVV
x (QWHUODJRUOHDG x 5HVFKHGXOHXQFRPSOHWHGRU
x (QWHUQRQGHIDXOWUHODWLRQVKLSV6WDUW SDUWLDOO\FRPSOHWHGZRUN
6WDUW)LQLVK)LQLVK
x
6WHS(LJKW)RUPDW\RXUSURMHFW
x &KDQJHWKHIRUPDWRIWDVNV
6WHS)RXU(QWHUUHVRXUFHV
x &KDQJHWKHIRUPDWRI*DQWWEDUV
x (QWHUUHVRXUFHV
x )RUPDWWKH*DQWWFKDUW
x 6HW5HVRXUFH&DOHQGDUV
x 6DYHDVDWHPSODWH
x 6HW5HVRXUFHDYDLODELOLW\
88
Microsoft Project 2013 Essentials Evaluate your Schedule
You can still adjust the project once it has gone live, but it is best to go live with the best possible project.
89
Microsoft Project 2013 Essentials The Critical Path
For example:
You arrange to meet your best friend Jan for coffee at a swanky coffee shop in Central London. Jan lives
outside of London and is coming in for a day of shopping. It will take Jan 2 hours to get to the Coffee
Shop but as you live in London it will only take you one hour. You have one hour of leeway (slack)
before you have to start out to meet Jan. Once you set out, every part of your journey is now critical.
t
t t d D:
,IDQ\RIWKHVHVWDJHVDUHGHOD\HG\RXZLOOEH
ODWHIRUFRIIHH
The Critical Path is not a static object, it may change throughout the lifetime of the project based on
how tasks are performed as you begin to track progress.
7KHVHDUH5HGRQWKHVFUHHQ,
KDGWRPDNHWKHPVKRZXS
GLIIHUHQWO\KHUH
91
Microsoft Project 2013 Essentials The Critical Path
92
Microsoft Project 2013 Essentials The Critical Path
5. Click OK
17.8 Slack
17.8.1 What is slack?
Slack is the amount of time a task can slip behind before it begins to affect your schedule. Tasks on the
Critical path have no slack, as they cannot get behind without affecting the scheduled finish.
94
Microsoft Project 2013 Essentials The Critical Path
View how late you can allow non-critical tasks with slack to start without affecting the schedule
Identify which tasks you can divert resources from if tasks on the critical path are getting behind.
Free Slack the amount of time a task can slip before it delays another task
Total Slack the amount of time a task can slip before it delays the project finish date.
To see Slack in a visual way it can be displayed on the Gantt chart. It shows up as a dark blue thin line
coming out of the right hand side of the task bar.
6ODFN
95
Microsoft Project 2013 Essentials The Critical Path
You can now see the Schedule Table showing the Free Slack and Total Slack columns
Right click the grey square to the left of the first column and
above the first row choose the table from the list
6HOHFWDOO
You could:
97
Microsoft Project 2013 Essentials The Critical Path
The quickest way to display the Task Entry View is to split the screen so that the Gantt chart is at the
top and a form is at the bottom.
*DQWW&KDUW
)RUP
You can change which form appears in the bottom of the screen by right clicking and selecting the form
you wish to use.
98
Microsoft Project 2013 Essentials The Critical Path
1. To ensure that overtime costs are calculated correctly (if you are using Project to calculate costs)
2. To ensure that you approve the overtime work.
When overtime is added to a task, it reduces the duration of the task but it increases the cost of the task.
Example:
Sam is setting up an exhibition. Normally this will take a full day which equals 7 hours in working hours.
However this time there have been some snags and Sam needs an extra two hours. If Sam comes back
in the morning to do the extra bits, the exhibition will be delayed. The Solution is for Sam to work an
extra 2 hours at the end of the day. This means he will have worked a total of 9 hours.
7 hours at his regular hourly rate and 2 hours at his overtime rate.
By adding overtime the task is not delayed and so the exhibition is ready on time.
100
Microsoft Project 2013 Essentials The Critical Path
1. Make sure you have the Work pane in the bottom half of the window
2. Click into the overtime column
3. Adjust the hours
4. Click OK
Over allocation is the result of assigning more tasks to a resource than the resource can accomplish in
the working time available.
Microsoft Project determines which resources are over allocated based on:
The work and duration values for tasks that the resource is involved in.
The maximum number of units available for the resource.
The calendar used by the resource.
101
Microsoft Project 2013 Essentials The Critical Path
A small red person icon will appear in the Information column on the Gantt chart
17.11.3 How do I know when and which tasks are causing the over allocation?
1. Click View
2. Click on Resource Usage
On the left is the list of resources with the tasks they are involved in inset below. On the right is the
number of hours being worked on each task.
Over allocated resources will be shown in red and the over allocated hours will be in red too.
As you can see there is a timeline and it is possible to see exactly which tasks are causing problems.
103
Microsoft Project 2013 Essentials The Critical Path
Once you know where the over allocation is happening you can make informed choices about how to
deal with it.
If you realize when analyzing your project that a task is over allocated and happening at the wrong
time, you can move the task quite easily however bear in mind that one of the flexible constraints will
be added to the task.
104
Microsoft Project 2013 Essentials The Critical Path
We will examine Incomplete Parts to Status Date and Completed Parts to Status Date later on. (See:
What is meant by rescheduling? Page 121)
RUN FASTER.
RUN LONGER.. READ MORE & PRE-ORDER TODAY
RUN EASIER WWW.GAITEYE.COM
Drag the task in the Team Planner to the resource you wish to allocate it to
Reallocate using the Assign Resources Dialogue
Reallocate by changing the resource in the resource column
Drag the task you wish to reallocate to another resource and drop it in the correct timeframe.
In this example I dragged the Write Exercises task from Jenny to Ann as Jenny was over allocated.
106
Microsoft Project 2013 Essentials The Critical Path
You will not see the correct assignments in the dialogue box at this point.
Thats OK, Microsoft Project will have made the replacement and the next time
you click the Assign Resources icon you will see your new assignments.
Date constraints are restrictions to a task when they must start or finish in a particular time frame.
In Microsoft Project a constraint will fix a tasks date at one end or the other. This can have a negative
impact on any tasks that are connected or dependent on the constrained task.
Unless you absolutely must perform the task on the specific date, it is best to leave well alone and allow
Microsoft Project to schedule the tasks automatically using the most flexible constraints.
107
Microsoft Project 2013 Essentials The Critical Path
As Soon As Possible The default flexible constraint when scheduling your project from a Start Date.
It means that every task will start as soon as possible given the dependencies,
duration, resources and work time.
As Late As Possible This automatically applies to every task when you are scheduling from a Finish
Date. It is just as flexible as the Start As Soon As Possible constraint.
However there is not room for delay when using this kind of constraint and
if things get delayed then successor tasks and the end of the project will be
delayed too.
Start No Earlier Than (SNET) This is a partially flexible constraint and is used when tasks can only start after
a certain date. For example, you cannot book tickets for a football match until
they go on sale, but you can continue to book them right up to the match time
(unless they sell out!)
If you type a Start Date into the Start Date column, Microsoft Project will change
the constraint to a SNET!
Finish No Earlier Than This is a semi flexible constraint too. Great for tasks that must continue until
a specified date. So you could buy tickets up until the day before the football
match for example.
If you type a Finish date in the Finish Date column then Microsoft Project
changes the constraint type to Finish No Earlier Than.
Start No Later Than This is the latest date that the task can start. If you are scheduling from a Finish
Date then Microsoft Project uses this constraint type if you type a date in to
the Start Date Column.
For example, the course is being delivered in six weeks time, so you have to start
writing it at least three weeks beforehand, however if you could start earlier.
Finish No Later Than This is the latest date that a task can finish. If you schedule from a Finish
Date then Project uses this constraint type when you type into the Finish
Date column.
For example your design needs to be submitted to the client by a specific
date, so you set a Finish No Later Than constraint a couple of days earlier to
allow for tweaking and communicating with the client.
Must Start On This is completely fixed. This constraint overrides any dependencies that you
may have set and should be used only if absolutely necessary.
Must Finish On This completely fixes on the Finish Date. This specifies the exact date when the
task must end and is completely inflexible. It also overrides any dependencies
you have and should not be used unless you absolutely must.
Like with anything else that you want to do in Microsoft Project there are a few ways in which to
set constraints.
108
Microsoft Project 2013 Essentials The Critical Path
When you want to change the constraint type for many tasks at once the table area is very handy.
110
Microsoft Project 2013 Essentials The Critical Path
4. Click OK
111
Microsoft Project 2013 Essentials Your Project is now ready to go
What next?
Well firstly this is the point at which you need to get sign off from the stakeholders in your project. You
need to make sure that everyone involved is aware of how the project is shaping up and what is going
to happen. Once you have agreement, you will move on to the execution part of the project.
Set the Baseline this is a snapshot of your project at the sign off point. You will be comparing your
progress to this point.
Track progress gather information from each of the people involved in executing the tasks as to how
much they have done.
www.sylvania.com
We do not reinvent
the wheel we reinvent
light.
Fascinating lighting offers an infinite spectrum of
possibilities: Innovative technologies and new
markets provide both opportunities and challenges.
An environment in which your expertise is in high
demand. Enjoy the supportive working atmosphere
within our global group and benefit from international
career paths. Implement sustainable ideas in close
cooperation with other specialists and contribute to
influencing our future. Come and join us in reinventing
light every day.
Light is OSRAM
Update the project update Microsoft Project with the information you have received from the
individuals involved in doing the tasks so that you can keep on top of how the project is getting on and
spot any problems before they arise or at least as early as possible.
As this is the first time you are setting the baseline you will leave everything as it is and click OK.
At a later stage, you can set further baselines so that you can compare your progress and you can set
interim plans if you run out of baselines to set.
When you have set the baseline, nothing visible happens so where can you see that the baseline has
been set?
113
Microsoft Project 2013 Essentials Your Project is now ready to go
A snapshot of the project can be seen including the baseline in the project statistics box.
3. Click Statistics
Variance Shows the difference between the baseline and the actual
To see the Baseline on the Gantt chart you can display the Tracking Gantt
114
Microsoft Project 2013 Essentials Your Project is now ready to go
7KHJUH\OLQHVXQGHUQHDWK
DUHWKHEDVHOLQHDQGWKH
UHGRUEOXHOLQHVDERYH
DUHWKHFXUUHQWSRVLWLRQ
9LHZLQJWKH%DVHOLQH7DEOH
,I\RXVHHRQO\RQHEDU
,QIRUPDWLRQLQ0LFURVRIW3URMHFWLVVWRUHGLQWDEOHV7DEOHVDUHFROOHFWLRQVRILQIRUPDWLRQWKDWJRWRJHWKHU
WKHQ\RXKDYHQRW\HW
VRWKH(QWU\7DEOHLVWKHGHIDXOWWDEOHZKHUHLQIRUPDWLRQDERXWWDVNVLVHQWHUHG7KH&RVW7DEOHZLOOKROG
VDYHGWKHEDVHOLQH
PRUHGHWDLOHGLQIRUPDWLRQDERXWFRVWVDQGWKH%DVHOLQH7DEOHZLOOVKRZWKH%DVHOLQHYDOXHVIRUWKHPRVW
FRPPRQILHOGV
360
thinking .
360
thinking . 360
thinking .
Discover the truth at www.deloitte.ca/careers Dis
Discover the truth at www.deloitte.ca/careers Deloitte & Touche LLP and affiliated entities.
1. Click View
2. Click the drop down arrow under Tables
4. Select Baseline
5. Click Apply
The Baseline Table shows the baseline values for Baseline Start Baseline Finish Baseline Work and
Baseline Cost
116
Microsoft Project 2013 Essentials Your Project is now ready to go
After setting the baseline you can still make changes and then reset the plan. This could happen if the
stakeholders change their mind about something or your project gets put on hold for a time and when
you come back to it, the original dates are not relevant.
If you collected tracking information and did not have time to enter it into the project until the following
week, you can still enter the information that was correct up to that date by changing the Project Status
Date to the date you collected the information. When you close Microsoft Project the current date is
lost and next time you open it, the date will be whatever the date is when you open it.
117
Microsoft Project 2013 Essentials Your Project is now ready to go
5. Click OK
There are several ways to enter the information about how much of a task has been completed.
Mark on Track
Update Task dialogue box
The Percent Complete Icons
The Tracking Table
There are also different scenarios for Updating the Project to reflect progress.
Do you like cars? Would you like to be a part of a successful brand? Send us your CV on
We will appreciate and reward both your enthusiasm and talent. www.employerforlife.com
Send us your CV. You will be surprised where it can take you.
This command marks a task as 100% complete and sets the actual start and finish dates to the scheduled
start and finish dates. This is only useful if the task has been completed exactly according to plan!
1. Click Task
2. In the Schedule group click Mark on Track
This box includes all the fields that you may wish to update in one place. If several tasks have the same
values you can select them all before launching the dialogue box.
If each task has different and unique values then you will need to update each one separately.
1. Click Task
2. Click the drop down arrow next to Mark on Track
3. Click Update Task
4. Enter the information
5. Click OK
Here you can enter a percentage complete and the actual duration together with actual start and finish
date information. This will help to build a good picture of how the project progresses and can be used as
information to base future projects upon.
119
Microsoft Project 2013 Essentials Your Project is now ready to go
If a task has taken longer than expected or happened late, you may wish to specify this information.
When entering a percentage complete and an actual duration, Microsoft Project will calculate the
remaining duration.
J
This view allows you to enter information for each task one after the other and to see how Project
calculates the other progress fields based on your input.
1. Click View
2. Click Tables
3. Click Tracking
If you enter the percent complete the actual fields are populated in front of you so that you can keep
track of what is going on.
These icons live on the Task Ribbon and can be used quickly and easily.
120
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
In this instance you need to make sure that you dont allow your tasks to fall too far behind and you can
reschedule the work to start/resume on the status date or at a specified date of your choosing.
This then allows you to communicate with your resources to make sure that the project as a whole comes
in on time. (Or at least not too late)
AXA Global
Graduate Program
Find out more and apply
When rescheduling tasks the completed portion will be to the left of the status/project date and the
incomplete part will be to the right. You can specify what Project should do with the incomplete part
and if you tell Project to move it beyond the status/project date, then the task will be split as in the
picture below.
Or
Incomplete Parts to Status Date: moves the part of the task that has not been completed past the
Status Date.
As you can see, the Proof Read task has been completed by 25%. By rescheduling the incomplete work
past the status date, the remaining 75% and any subsequent tasks which are dependent on the Proof
Read task are moved forwards in time resulting in a split task.
122
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
If your Status Date is in the past and you wish to show what happened you can use Completed Parts to
Status date instead.
When rescheduling work in Project 2013 there are more choices on the drop down menu than in prior
versions. You can now select a specific way to reschedule as well as the original Incomplete Parts to
Status Date or Completed Parts to Status Date.
Sometimes you need to stop work on a project for a while due to other factors. When work finally
resumes all of your date information is no longer valid and Microsoft Project will be assuming that as
time moves on work that has been scheduled should get done.
If your project was interrupted in the middle and is now set to resume then you will have quite a lot of
schedule dates to reset manually. You can make Project reschedule any uncompleted work as follows:
123
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
Project will reschedule all incomplete work to start after the date you specified. You now need to look
at your project carefully and check for any issues that may need to be addressed.
Any date constraints that you had previously set will need to be reset manually. You will also need to
check for conflicts between constraints and predecessor tasks and look at milestone dates and the project
finish date to see if they should be adjusted because of the delay.
e Graduate Programme
I joined MITAS because for Engineers and Geoscientists
I wanted real responsibili www.discovermitas.com
Maersk.com/Mitas e G
I joined MITAS because for Engine
I wanted real responsibili Ma
Month 16
I was a construction Mo
supervisor ina const
I was
the North Sea super
advising and the No
Real work he
helping foremen advis
International
al opportunities
Internationa
ree wo
work
or placements ssolve problems
Real work he
helping fo
International
Internationaal opportunities
ree wo
work
or placements ssolve pr
Download free eBooks at bookboon.com
Sometimes there is a delay and the project continues to chug along and things do in fact get done. To
update the project in its entirety:
If you want Project to update tasks with partial percent complete you can select the Set 0%100%
complete option. This means that some tasks may update to 50% or 75% complete if that is the portion
that should have been comp.
If you want tasks to be updated as either completely finished or not done at all then select the Set 0%
OR 100% option.
125
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
3. Click Statistics
#27&$15((6+$66+,5
6$5.+$55/,33('
+(/29(4%$454(34(5(166+(
+(733(4%$454(34(5(16
%$5(/,1(3/$1
6+(&744(163/$1
126
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
93%
OF MIM STUDENTS ARE
WORKING IN THEIR SECTOR 3 MONTHS
FOLLOWING GRADUATION
MASTER IN MANAGEMENT
STUDY IN THE CENTER OF MADRID AND TAKE ADVANTAGE OF THE UNIQUE OPPORTUNITIES
Length: 1O MONTHS
THAT THE CAPITAL OF SPAIN OFFERS
Av. Experience: 1 YEAR
PROPEL YOUR EDUCATION BY EARNING A DOUBLE DEGREE THAT BEST SUITS YOUR
Language: ENGLISH / SPANISH
PROFESSIONAL GOALS
Format: FULL-TIME
STUDY A SEMESTER ABROAD AND BECOME A GLOBAL CITIZEN WITH THE BEYOND BORDERS
Intakes: SEPT / FEB
EXPERIENCE
Once you have set the baseline on a project and begun the tracking process you may find out that some
of your tasks are no longer needed. You could delete them, however if you do then you will lose any
baseline data that already exists with relation to the deleted task. It would be much better to cancel them
so that they stay in the project for reference but do not affect the project any more.
This could be done in Project 2007 however it required a fair bit of work. There is a new feature in
Microsoft Project 2013 which allows you to set a task to Inactive quickly and painlessly.
An Inactive Task is crossed out and the task bar turns white.
128
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
If you find later on that you need to reinstate an inactive task, you can do the following:
6. In the Into box select the fields to copy the data into
7. Click OK
You can save interim data for the entire project or just for selected tasks.
130
Microsoft Project 2013 Essentials Rescheduling Incomplete Work
To view your interim data you need to add the columns to the table so that you can see the data.
1. Right Click on the column heading to the right of where you wish the column to appear
2. Select Insert Column
3. Select Start2 (or Finish2)
CLICK HERE
to discover why both socially
and academically the University
of Groningen is one of the best
places for a student to be
www.rug.nl/feb/education
To change the colours simply select one of the Gantt Chart Styles from the ribbon.
132
Microsoft Project 2013 Essentials Formatting the Gantt chart
:LWK5HVRXUFH1DPHV :LWK5VRXUFH,QLWLDOV
To apply the same formatting to all tasks, select all the tasks first then follow the steps below.
133
Microsoft Project 2013 Essentials Formatting the Gantt chart
American online
LIGS University
is currently enrolling in the
Interactive Online BBA, MBA, MSc,
DBA and PhD programs:
To show Outline Numbers tick the check box in the Show/Hide Group
2XWOLQH1XPEHUVDUHDSSOLHG
Download free eBooks at bookboon.com
135
Microsoft Project 2013 Essentials Formatting the Gantt chart
Non-working time set in the standard calendar weekends and public holidays
Non-working time for a particular Resource
136
Microsoft Project 2013 Essentials Formatting the Gantt chart
4. Select Gridlines
5. Select Current Date
6. Choose a colour (red or orange work well)
7. Click OK
4. Select Gridlines
5. Select Status Date
6. Choose a colour (red or orange work well)
Click OK
138
Microsoft Project 2013 Essentials Formatting the Gantt chart
Formatting the table can make important elements stand out. We have already seen earlier how to format
Critical Tasks in the table, there are other ways to format it too.
5. Click OK
139
Microsoft Project 2013 Essentials Templates
21 Templates
21.1 What advantages are there to creating a template?
Templates allow you to base new projects on prior ones that have been successful! When you have a
project that works and you know that you will be doing more of the same type of project, starting from
a template saves time.
Task List
Task Dependencies
Resource Information
Calendar Settings
Formatting
Maastricht
University is
the best specialist
university in the
Visit us and find out why we are the best! Netherlands
(Elsevier)
Masters Open Day: 22 February 2014
www.mastersopenday.nl
Select which folder to save your template into and then click save.
You are now prompted to keep or remove various bits of information make your choice and click Save.
141
Microsoft Project 2013 Essentials Templates
21.1.2 Creating a new project based on a template first set the location where Project will
find templates.
First you will need to have set the default location for your personal project templates or your IT
department will need to set the location for the organisations templates.
To do this:
1. Click File
2. Click Options
3. Click Save
4. Browse to the Custom Office Templates folder (or create this folder in your Documents folder)
1. Click File
2. Click New
3. From the Enterprise short cut select the template you need.
143
Microsoft Project 2013 Essentials Templates
When printing the Gantt chart what you see on screen is what you get
This means the level of zoom you are on, the balance between the Gantt chart and
the table, and whatever filters you may have applied will all affect your printout.
145
Microsoft Project 2013 Essentials Printing and Reports
&OLFNKHUHWRSULQW
$QGWRVHWWKHQXPEHURI
FRSLHV
6HOHFW\RXUSULQWHUKHUH
6HOHFWH[DFWO\ZKLFKSDUW
RIWKHSURMHFW\RXZLVKWR
SULQW
$QGKRZPDQ\SDJHV
146
Microsoft Project 2013 Essentials Printing and Reports
You can select any of the Project Fields to be added to the legend and you can also select general fields
which are updated via the Project Properties.
1. Click File
2. Click Info
148
Microsoft Project 2013 Essentials Printing and Reports
149
Microsoft Project 2013 Essentials Printing and Reports
22.4.2 Headers
You can add headers to both the Gantt chart and the Calendar views
22.4.3 Footers
Footers can also be added following the same procedure as Headers. However when there is a Legend
on every page, the text will be left, centre or right aligned in the box underneath the legend.
Page breaks force certain tasks to always print on a new page. They appear as dashed lines above the
task with the break on it.
In Microsoft Project 2013 the Insert Page Break command is not on the Ribbon as you would expect.
You will need to customise the Ribbon to add it in.
151
Microsoft Project 2013 Essentials Printing and Reports
6. On the right hand side you will need to create a Custom Group
7. Click New Group
8. Type a name for your group at the bottom
9. Click OK
10. Click Add
11. Your new icon should now appear in your new group
12. Click OK
A page break will be inserted forcing tasks below the page break to print on a separate page.
Download free eBooks at bookboon.com
153
Microsoft Project 2013 Essentials Reports
23 Reports
In Project 2013 there is a brand new reporting engine and you can now create many more varied reports
than in previous versions.
In Microsoft Project 2013 the reports are set out on the page and can be edited directly. There are a
number of new reports that show you anything from over allocated resources to your cash flow.
Experiment with the different reports and find the ones that work for you.
154
Microsoft Project 2013 Essentials Appendices
24 Appendices
24.1 Working with more than one project
You can create a master project that contains several small projects within it or houses several different
projects so that you can see the links between them and how they sit in the timeline.
You may need to expand the inserted project to see all of its tasks.
The duration of some tasks is based not on the Working Time Calendar (i.e. 9:00am to 17:00pm and
no work on weekends) but on a 24hr day and a 7 day week, including holidays and non-working days.
Example
Someone is carrying a package by air. The time it takes to get from departure to arrival is 18hrs. This
can be represented by typing 18eh in the duration field.
156
Microsoft Project 2013 Essentials Appendices
You can adjust the timescale to view the project at the level of detail you require./ here are three tiers to
the timescale, two of which are shown as default.
4. Click OK
24.3 Costs
24.3.1 Assigning a Fixed Cost to a task
You can assign a fixed cost to a resource or a task. So for example if you know that there is a shipping
charge to add on to the cost of printing your banners you can add this as a fixed cost.
157
Microsoft Project 2013 Essentials Appendices
RUN FASTER.
RUN LONGER.. READ MORE & PRE-ORDER TODAY
RUN EASIER WWW.GAITEYE.COM
1. Click Resource
2. Click on the drop down next to Team Planner and then
3. Click Resource Sheet
Type costs for each resource in the Standard, Overtime and Cost per use columns.
Standard Rate Shows the rate of pay for regular non overtime
work performed by the resource
Overtime is only calculated at the overtime rate when you allocate the work as overtime.
Cost per Use Applies to any flat rate that must be paid
every time that resource is used
Examples
It may cost 100 to hire a crane driver, and you may have to pay 6 an hour on top of that. This would
be entered as a standard rate cost of 6 per hour and a cost per use of 100.
Resource costs can also be entered per day per week or per year.
20/day
2000/week
20000/year
159
Microsoft Project 2013 Essentials Appendices
The way resource costs are to be accrued to a project can be set individually for each resource.
25 Glossary
Project A connected series of task generally summary tasks to be completed in a given time
Summary Task A type of task that is made up of several smaller tasks and can be considered as a
phase of a project
Task A piece of work with a certain duration
Recurring task A task which takes place at the same time on a regular basis eg daily, weekly, monthly
and lasts for exactly the same amount of time.
NB this is a special kind of summary task.
Duration The amount of standard working time that a task is expected to take measured in
minutes, hours, days or months.
Elapsed Time Elapsed time takes no account of working hours and is the time from the very
beginning of a task to its end including non working time
Resources People or things that you need to get the project done that generally accrue a cost.
Effort Driven The more resources assigned to a task the shorter its duration becomes
Links (Dependencies) A method of determining when a task begins in relation to its predecessor or successor
Leveling Resource leveling is a way to fix over allocation by delaying a task until the assigned
resource has time to work on it or by splitting the task so that part is done when
planned and the rest is done later when the assigned resource has time.
Lag Time A delay between the end of one task and the start of another
Lead Time An overlap between two tasks
Schedule The duration and sequence of tasks within a project. A schedule consists mainly of
tasks, links, durations and constraints.
Critical Tasks Tasks that will delay the end of the project if they are delayed
Critical Path The sequence of tasks that must be performed in order not to delay delivery of
the project
Slack The amount of time non-critical tasks can be delayed without delaying the finish
date of the project
Slippage The amount of time by which a project will be late because a critical task has been
delayed.
Baseline The final draft of a project schedule. Your best guess at how long the project will
take and the point at which you get sign off from the stakeholders in the project.
Tracking Recording how much progress has been made on a regular basis and comparing
this to the baseline.
161
Microsoft Project 2013 Essentials Index
Index
A G
Appendices 153 Gantt Chart
Assigning formatting 131
overtime work 99 Glossary 159
Assigning resources 66 Grouping
resources 77
B
tasks 76
Backstage 18
Baseline H
comparing 125 Headers 149
set 112 Hyperlinks
view 113 create 42
Breaking Links 47 delete 43
C I
Constraint Inactive
entering 108 tasks 127
removing 109 Individual Resource Holidays 62
Constraints 106 Interim Plans 129
Costs 155
L
Current Date
Legend 144
formatting 135
Link
Customise the Ribbon 149
changing the type 48
D Linking tasks 45
Dates Linking Tasks
formatting 57 deleting 47
Deadline Links
adding 110 between manually scheduled tasks 49
Deadlines 106
N
Durations
Non Working Time
resources 64
formatting 135
E Notes
Effort Driven 64 adding 40
Elapsed Time 154 viewing 42
F O
Finish Date Over Allocation 101
project 21 Overtime Work
Footers 149 assigning 99
162
Microsoft Project 2013 Essentials Index
P Start Date
Page Break project 21
inserting 149 Status Date
Picture of a Project 142 formatting 137
Printing 143 Sub Project
calendar 147 inserting 153
Project
T
finish date 21
Task Dependency 44
start date 21 Tasks
working with more than one 153 adding 48
Public Holidays grouping 76
set 25 inactive 127
R reactivate an inactive task 129
Reports 143 recurring 54
S Z
Saving Projects 40 Zooming 50
163