Commissioning Service Department

Commissioning Standard Test


Formats
Description: DEW POINT TEST Record No. :
Equip. No. Drawing ref.: Sheet :
Contractor : Contract no.: Substation No :

Dew point Test

Gas Pressure
Compartment no. Dew Point C ppmmass ppmvol
(k Pa)

Acceptance Criteria: -35C for C.B. , -30C for other Compartment

Tested by Witnessed by
Name: Eng.
Signature:
Date: