The UPS System located normally in the LV rooms supports critical telephone & data room sockets,
central equipment in the BMS, Server and security rooms etc. for a period of 30 minutes until power is
restored. The UPS system provides continuous, regulated AC power to the loads under normal and
abnormal conditions, including loss of the utility AC power.

The purpose of this procedure is to define the step by step method to implement the correct practices for
the precommissioning & commissioning of UPS Systemthrough the guidelines contained herein so as to
ensure that the job execution complies with the project requirements and serves the intended function to
satisfactory level.

Required Tools

Portable Hand tools


Advertisement
Step Ladder

ac

variable Multimeter

speed drive
Megger

Leading manufacturer in Precommissioning Procedure


industrial automation&electric for UPS System
power. Go to invt.com/Inverter
1. Ensure that the UPS System installation is

Current complete and mechanical completion is


approved & all comments on the installation are
Transformers incorporated.
HOBUT Current transformer
2. Ensure that no damage has occurred between
range manufactured in the UK. mechanical completion & precommissioning.
Go to hobut.co.uk
3. Replace damaged components, if any
4. Ensure the installation is in line with the
approved shop drawings, local authority codes & manufacturers recommendations.
5. Verify the following as regards to wiring & installation:
Check ground connection
Check tightness of power parts
Check the setting of electronic board
Check all power fuses for continuity
Check all switches / breakers are in open position
Check the system is interfaced with the BMS

Commissioning Procedure for UPS System


1. Ensure that all the precommissioning checks are carried out successfully.
2. Ensure that the customer support representative from the equipment manufacturer is present to
check & start the UPS units.

Pre-Power checks:
Verify that all UPS isolators & battery breaker are open
Verify that correct voltage (415 VAC) is selected on power supply transformers T2 & T3.
Check & verify the UPS voltage output.
Verify that control switches (Q1,Q2 & Q3) on UPS logic board are open.

Rectifier Section
Apply mains voltage to input & record.
Close input isolator
Set Q3 on UPS logic board to ON position
Check the rectifier output & record VDC (if necessary adjust by R21 on rectifier logic board)
Check battery voltage & polarity
Check battery breaker

Inverter Section

Set the inverter switch Q2 on UPS logic board to ON position, the inverter will ramp-up to nominal
voltage.
Record the output voltage & frequency Output switch section
Close by-pass isolator
Set Q1 on UPS logic board to ON position
Close output isolator
Measure & record the output voltage

UPS function test

1. Simulate a power black-out by switching off the input isolator, the inverter will run on batteries &
following messages will be displayed: Battery on load
2. Close the input isolator
3. Turn off the inverter, the load will be transferred to by-pass.
4. Turn ON the inverter & verify that the load will be transferred automatically to the inverter.
5. Ensure that proper cooling is taking place

Alarms Test

The following alarms shall be checked


Inverter OFF / load on by pass
Battery CB open
Output switch open
By-pass switch open
Rectifier OFF
UPS on maintenance by-pass

Check & verify the mimic diagram functions finally.

Attachments:

Precommissioning of UPS System


Commissioning of UPS System
Pre-Commissiong & Commissioning plan for Electrical System
Risk Assesment
Advertisement

ac variable
speed drive
Leading manufacturer in
industrial
automation&electric power.
invt.com

Like Share Sign Up to see what your friends like.

Related Method Statements:



Method Statement For the Installation of UPS System

Uninterrupted UPS Power Supply Systems

METHOD STATEMENT FOR PRECOMMISSIONING & COMMISSIONING

PRECOMMISSIONING & COMMISSIONING PROCEDURE FOR BUILDING