ACTIVITY DURATION MANPOWER

A 1 8
B 2 8
C 7 3
D 11 4
E 7 6

F 3 4
G 9 4
H 9 8
I 5 6
J 1 4
K 1 4
L 15 6
M 2 3
N 1 2
O 4 4
P 2 6
Q 2 6
R 1 4
S 3 6
T 11 6
U 3 6
V 2 3
W 5 4
X 2 2
Y 6 6
Z 6 3
AA 3 6
BB 1 6
CC 2 6
DD 1 6
EE 11 6
FF 3 6
GG 3 5
HH 2 2
II 5 6
JJ 2 6
KK 4 6
LL 1 6
MM 2 6
NN 3 5
OO 5 4
PP 5 6
QQ 2 6
RR 3 6
SS 3 6
TT 3 4
UU 2 7
VV 13 2
WW 5 2
XX 6 4
YY 7 5
ZZ 3 4
AAA 1 8
BBB 2 6
CCC 1 4

A. SITE CLEARING
B. DEMOLITION & CLEARING
C. EXCAVATION (TO BE DONE PER AREA)
D. FACBRICATION OF STEELWORKS FOR 1ST FLOOR
a. FOOTING
b. COLUMNS
c. GRADE BEAMS
d. SPETIC VAULT
e. PARKING AREA
f. STRAP BEAM
E. FABRICATION FORMS AND SCAFFOLDS
a. FOOTING
b. GRADE BEAM
c. STRAP BEAM
d.
F. INSTALLATION OF FOOTING REINFORCEMENTS (TO BE DONE PER AREA)
G. INSTALLATION OF FORMS & SCAFFOLDINGS
H. CONCRETE POURING FOR FOOTING (PER AREA)
I. INSTALLATION OF COLUMNS AND GRADE BEAMS (PER AREA)
J. INSTALLATION OF STRAP BEAM ON LEFT EXTERIOR SIDE OF 4 & 5
K. POURING OF CONCRETE ON STRAP BEAM
L. REMOVING OF FORMS AND SCAFFOLDS
M. PUTTING OF BACKFILL (PER EXCAVATED AREA)
N. GRAVEL BEDDING & INSTALLMENT OF SLAB ON FILL REINFORCEMENT (PER AREA)
O. INSTALLATION OF PLUMBING PIPE LINES
P. POURING OF CONCRETE ON GRADE BEAMS AND SLAB ON FILL (PER AREA)
Q. INSTALLATION OF SCAFFOLDS AND FORMS FOR COLUMN (PER AREA)
R. CONCRETE POURING OF COLUMNS (PER AREA)
S. REMOVAL OF FORMWOKS AND SCAFFOLDS ON COLUMNS
T. INSTALLATION OF FORMWORKS & SCAFFOLDS FOR 2ND FLOOR BEAMS AND SLAB
U. INSTALLATION OF 2ND FLOOR BEAM REINFORCEMENT AND SLAB REINFORCEMENT
V. CONCRETE POURING OF 2ND FLOOR BEAM & SLAB
W. REMOVAL OF SCAFFOLDS OF BEAM
X. CHB LAYING ON 1ST FLOOR EXTERIOR WALLS
Y. INSTALLATION OF ELECTRICAL PIPE CONNECTIONS ON 1ST FLOOR
Z. PLASTERING ON 1ST FLOOR WALL
AA. FABRICATION OF STEEL FOR 2ND TO 3RD FLOOR
BB. INSTALLATION OF REINFORCEMENT FOR 2ND FLOOR COLUMN
CC. INSTALLTION OF FORMWORK & SCAFFOLDING FOR 2ND FLOOR COLUMN
DD. CONCRETE POURING FOR 2ND FLOOR COLUMN
EE. REMOVAL OF FORMS AND SCAFFOLD FOR 2ND FLOOR COLUMN
FF. INSTALLATION OF BEAM & SLAB REINFORCEMENT FOR 3RD FLOOR
GG. INSTALLATION OF FORMWORKS AND SCAFFOLDS FOR 3RD FLOOR BEAM AND SLAB
HH. CHB LAYING FOR 2ND FLOOR WALLS
II. INSTALLATION OF PIPES (ELECRICAL, PLIMBING & WATER SUPPLY) AT 2ND FLOOR
JJ. PLASTERING OF 2ND FLOOR WALLS
KK. POURING OF CONCRETE FOR 3RD FLOOR SLAB
LL. INSTALLATION OF FORMS AND SCAFFOLDS FOR 3RD FLOOR COLUMN AND SUSPENDED SLAB
DECK
MM. INSTALLATION OF 3RD FLOOR COLUMN & SUSPENDED SLAB DECK REINFORCEMENTS
NN. CONCRETE POURING ON 3RD FLOOR COLUMN
OO. CHB LAYING FOR 3RD FLOOR WALLS
PP. INSTALLATION OF PIPES (ELECTRICAL, PLUMBING & WATER SUPPLY) AT 3RD FLOOR
QQ. PLASTERING AT 3RD FLOOR WALLS
RR. CONCRETE POURING OF SUSPENDED SLAB DECK
SS. STEELWORKS FOR ROOF TRUSS
TT. INSTALLATION OF ROOF TRUSS
UU. INSTALLATION OF ROOF ACCESSORIES
VV. INSTALLATION OF CEILING BOARDS
WW. CONSTRUCTION OF SEPTIC TANK
a. EXCAVATION
b. GRAVEL BEDDING AND CONCRETE POURING
c. INSTALLATION OF STEEL REINFORCEMENTS
XX. CONSTRUCTION OF PARKING AREA
YY. CONSTRUCTION OF STAIRDS
a. FROM 1ST FLOOR TO 2ND FLOOR
b. FROM 2ND FLOOR TO 3RD FLOOR
ZZ. PAINTING & TILE WORKS
AAA. INSTALLATION OF DOORS & WINDOWS
BBB. REMOVING OF FORMS AND SCAFFOLDS
CCC. FINAL WORK AND CLEANING
DDD. ELECTRICAL WORKS