GUGLER does not take any responsibility for workers of 3rd parties, such as civil
workers or suppliers outside of the scope of GUGLERS supply.
Before the final assembly at site can be started following requirements have to
be fulfilled:
All construction works at the powerhouse (including the roof, windows and
doors) have to be completely finished and cleaned and free access to the
powerhouse has to be available.
Sufficient illumination, heating and power supply has to be available
(230V/400C; 16A)
All recesses have to be finished according to the installation plan and agreed
with any 3rd parties (such as cable-channels for an electrical supplier outside
GUGLERS scope of supply).
The penstock has to be finished but the end-section must not be attached
before the turbine is in its final position.
This drawing is the property of GUGLER Water Turbines GmbH and must neither be copied nor used in other way without the consent of GUGLER
Water Turbines GmbH. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution.
The overhead crane for component positioning including its entire equipment
has to be installed, tested and approved.
Der Inhalt dieser Zeichnung ist geistiges Eigentum der Firma GUGLER Water Turbines GmbH. Die Zeichnung ist dem Empfaenger nur
zum persoenlichem Gebrauch anvertraut. Ohne schriftliche Bewilligung durch die Firma GUGLER Water Turbines GmbH darf sie
995_0_02-201016
DATEIPFAD/NAME
+43 7234 83 902 http://www.gugler.com filepath/name R:\395_Lodagung\Konstruktion\CAD (3D) neu\0_Einbauplan\0.dft
Guglers scope of supply
4700 11000 (not included any concrete works)
11000
3500
+154,81m service bay
crane
18600
35
min. required crane
4700 hook height 4200
18000
5000
4500
4000
truck door
12000
+154,81m 1000 +154,81m
B B
manhole butterfly valve
+154,81m DN2000 / PN6
35
4500
+151,25m
A +149,81m
end of Gugler's
scope of supply
3540
2576
Section B-B
1:100
draft tube
A runner
runner O 1127
distributor 4960
+151,25m
3005
generator 1
350
control cabinet min. TWL +150,25m
1440
(1200x500x2000)
butterfly valve 1 +149,81m
end of Gugler's DN2000 / PN6
scope of supply hydraulic power unit 1
30
second concrete
second concrete
turbine 1 control cabinet draft tube
DN 2000
(800x300x1000)
draft tube
concreted with formwork +147,31m
18000
35
unit 1
generator 2
7000
inlet pipe
Section A-A
1:50
500
second concrete
weder vervielfaeltigt noch dritten Personen zugaenglich gemacht werden. Zuwiderhandeln wird von uns gerichtlich verfolgt.
should be installed(adapted) after the turbine is at the right position. rev. date name notice
0
362
371
30
0
93 6
tur
bine
o utle
t
10000
500
35
10
500
30410 28620
+154,81m
This drawing is the property of GUGLER Water Turbines GmbH and must neither be copied nor used in other way without the consent of GUGLER
Water Turbines GmbH. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution.