PRESUPUESTO

Obra: CONSTRUCCION DE ESCALERA DE ACCESO A AZOTEA


Item Descripcin Unidad Metrado Precio Parcial Sub Total RENDIMIENTO N DIAS
1 TRABAJOS PRELIMINARES 1,204.13
1.01 DESMONTAJE DIVERSO GBL 1.00 250.00 250.00 16.00 0.06 1
1.02 DEMOLICION DE MUROS M2 3.60 16.94 60.98 16.00 0.23 1
1.03 DEMOLICION DE TECHO M2 4.62 24.75 114.35 16.00 0.29 1
1.04 ELIMINANCION DE DESMONTE M3 8.22 40.00 328.80 6.00 1.37 2
1.05 RESANES DIVERSOS GBL 1.00 450.00 450.00 7.00 0.14 1
2 ESCALERA DE CONCRETO 1,105.86
2.01 CONCRETO M3 1.16 313.09 361.62 12.00 0.10 1
2.02 ACERO KG 20.00 4.10 82.00 250.00 0.08 1
2.03 ENCOFRADO Y DESENCOFRADO M2 4.62 48.83 225.59 24.00 0.19 1
2.04 PISO EN ESCALERA M2 8.22 53.12 436.65 100.00 0.08 1
3 COLUMNAS DE AMARRE EN AZOTEA 476.36
3.01 CONCRETO F'C= 210 KG/CM2 EN COLUMNAS M3 0.35 313.09 109.58 10.00 0.04 1
3.02 ACERO DE REFUERZO FY 4200 KG/CM2 EN COLUMNAS KG 18.00 4.10 73.80 250.00 0.07 1
3.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 6.00 48.83 292.98 50.00 0.12 1
4 TABIQUERIA 2,233.92
4.01 MURO DE LADRILLO M2 39.00 57.28 2,233.92 6.92 5.64 1
5 VIGA DE AMARRE 530.81
5.01 CONCRETO M3 0.38 313.09 118.58 20.00 0.02 1
5.02 ACERO KG 40.40 4.10 165.64 250.00 0.16 1
5.03 ENCOFRADO Y DESENCOFRADO M2 5.05 48.83 246.59 45.00 0.11 1
6 CARPINTERIA METALICA 555.06
6.01 PUERTA METALICA UND 1.00 455.00 455.00 2.00 0.50 1
6.02 BISAGRAS UND 4.00 13.08 52.32 20.00 0.20 1
6.03 CERRADURA UND 1.00 47.74 47.74 5.00 0.20 1
7 COBERTURA 186.49
7.01 CALAMINA UND 5.78 24.50 141.49 40.00 0.14 1
7.02 CORREAS DE MADERA UND 10.00 4.50 45.00 5.00 2.00 2
8 ACABADOS Y PINTURAS 2,281.71
8.01 TARRAJEO DE MUROS M2 78.00 17.12 1,335.36 20.00 3.90 4
8.02 TARRAJEO DE FONDO ESCALERA M2 4.62 31.55 145.76 1.00 4.62 5
8.03 PINTADO DE MUROS M2 78.00 9.69 755.82 40.00 1.95 2
8.04 PINTADO DE FONDO DE ESCALERA M2 4.62 9.69 44.77 40.00 0.12 1
9 INSTALACIONES ELECTRICAS 333.76
9.01 SALIDA PARA ILUMINACION PTO 1.00 113.76 113.76 4.00 0.25 1
9.02 FLUORESCENTE UND 1.00 220.00 220.00 4.00 0.25 1
COSTO DIRECTO 8,908.10
GASTOS GENERALES (18%) 1,336.22
UTILIDAD (5%) 445.41
TOTAL PRESUPUESTO 10,689.72

SON: DIEZ MIL SEISCIENTOS OCHENTA Y NUEVE Y 72/100 NUEVOS SOLES