3rd floor
Columns 3007.6 kg Site Cut & 3 Bar cutters .16 mh/kg 9 Benders 4 Days
Reinforcement Bent 9 Installer
Column Forms 96 sq.m. Site 7 mh/sq.m. 20 Carpenters 3 Days
Fabricated 10 Laborers
Concrete 9.6 cu.m Site Mixed 3 Bagger man 17 mh/cu.m 4 Mason 2 Days
column 1 Portalift 8 Laborers
Beams & slabs 7676.98 kg 3 Bar cutters .16 mh/kg 9 Benders 9 Days
Stairs 9 Installer
Reinforcement
Forms 342.6 sq.m. 7 mh/sq.m. 20 Carpenters 10 Days
10 Laborers
Concrete 40.68 cu.m. 3 Bagger man 17 mh/cu.m 4 Mason 8 Days
1 Portalift 8 Laborers
Masonry 528 sq.m. -Site 3 mh/sq.m. 4 Mason 25 Days
Ground Floor Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
2nd Floor 337.5 sq.m. -Site 3 mh/sq.m. 4 Mason 16 Days
Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
3rd Floor 337.5 sq.m. -Site 3 mh/sq.m. 4 Mason 16 Days
Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
Thermal 150 sq.m. Membrane Subcontract 14 Days
Protection Topping
Waterproofing
Doors & 1 Lot Glass Doors & Subcontract 45 Days
Windows Curtain Walls
Except at T&B
Finishes
Wall Finishes 792 sq.m. 3 bagger 1.5 mh/sq.m. 4 Mason 25 Days
Plastering 1st mixer 2 Laborers
Floor
2nd Floor 675 sq.m. 3 Bagger man 1.5 mh/sq.m. 4 Mason 21 Days
1 Portalift 2 Laborers
3rd Floor 675 sq.m. 3 Bagger man 1.5 mh/sq.m. 4 Mason 21 Days
1 Portalift 2 Laborers
2nd Floor CR 6 sq.m. 8 mh/sq.m. 1 Mason 3 Days
TILES 1 Laborer
3rd Floor CR 6 sq.m. 8 mh/sq.m. 1 Mason 3 Days
TILES 1 Laborer
Floor Finishes Ceramic Tiles
1st Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
2nd Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
3rd Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
Painting Interior 1 Lot Subcontract 20 Days
Exterior 1 Lot Subcontract 20 Days
Electricals 1 Lot Subcontract 80 Days
Rough-in
Fixtures 1 Lot Subcontract 30 Days