Software requirements:
Hardware requirements:
PC
A further requirement is that a properly functioning STEP 7 Micro/WIN project is available and
loaded into S7-200 CPU.
Start S7-200 PC Access via Start > SIMATIC > S7-200 PC Access V1.0.0.56 > S7-
200 PC Access.
Create a new project.
Fig. 01
Mark controller, e.g. "MicroWIN (CP5611(PPI))", and open the dialog Status > PG/PC
Interface....
As access point of the application you must set "Micro/WIN" with the existing
communications connection to the S7-200, e.g. "-->CP5611(PPI)".
Note:
If the access point is not "Micro/WIN", first close the dialog and set the access point via Control
Panel > Set PG/PC Interface.
Via File > Import Symbols you import the symbol of the selected STEP 7 Micro/WIN
project.
Then save the configuration you have created.
In S7-200 PC Access you can now access the symbol of the STEP 7 Micro/WIN project.
Fig. 03
If you mark the project folder "Project1", for example, you can check the address of the
PLC via Edit > Properties.
Fig. 04
Fig. 06
Note:
If the S7-200 OPC server has not been started on the local PC, you must specify the computer
name or the IP address of the remote PC on which the S7-200 OPC server is located. When
accessing the OPC server via network, please refer to the DCOM settings in the WinCC flexible
Online Help under "Communication > OPC > Commissioning the OPC > DCOM".
Fig. 07
You can display this variable via an input/output field in the Start picture.
Save the configuration.
Fig. 09