Академический Документы
Профессиональный Документы
Культура Документы
A. General Information
PU: Rudrapur
Date of Reg.: Registration No.:
Division: Rudrapur (To be filled by BE PU) (To be filled by BE PU)
B. Problem
Description of Problem / Issue / Opprotunity:
(Pl. briefly mention consequences in terms of Cost, Rework / Rejection, Customer dissatisfaction etc.)
To eliminate AFB issue in tractors.
Current Status of the Problem / Issue (Quantified):
Pareto Chart of Defects
20 100
15 80
Percent
60
RPH
10
3.49650
3.49650
3.32168
2.27273
2.09790
1.39860 40
1.22378
0.87413
0.52448
0.52448
5 20
0 0
Defects
12
0
Benefits projected / Impact of Project - In terms of Cost, Quality, Revenue, delivery, CSI etc.
VP Customer Care (In case of field quality) VP Quality Assurance (In case of all quality related projects) Respective EL
For innovative problem solving project, only MYB certification is applicable
For MGB, One project in High impact category' or 2 projects in the 'Other' category of impact are required to be completed in a financial year
For Field Quality related problem, approval should be taken from VP-Customer Care & VP-Quality Assurance
For Inhouse & Supplier Quality, approvals should be taken from VP-Quality Assurance