Академический Документы
Профессиональный Документы
Культура Документы
1. Details of Project
a. Project / Site Name: Raw Material Store Building Column Strengthening by Fabrication & other
Fabrication Works.
b. Type of works: Fabrication Work for Column Strengthening by MS Fabrication Jacketing & other
Fabrication Works.
c. No. of Floor: All Floors.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 1
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
Substandard material will be rejected without giving any justification for which Contractor has to
supply the good quality material without affecting the progress of work.
In case any structural elements are not available in the approved brands mentioned above then
Contractor with adequate backups shall approach clients PM for the approval of alternate brand for
the particular member only.
Red oxide Asian Paint.
Shear Connectors, Specific nails and Bolting systems HILTI.
Rebaring works Specifications as per civil tender part or need to take approval prior starting of work.
Contractor shall get the approval of make of material for other works before starting the works.
4. SUFFICENCY OF TENDER
The Tenderer shall be deemed to have satisfied himself before tendering as to the correctness and
sufficiency of his tender for the works and about the rates and prices quoted by him, and except in so far as
it is otherwise provided in the contract, cover all his obligations under the contract and all matters and things
necessary for proper execution and maintenance of the works.
7. IDLE CHARGES
a. The Contractor shall not be paid any idle charges for any delays.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 2
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
a. The Contractor is bound to complete work stage wise; Milestones detailed in Contract programme or as
per the revised approved programme. Additional ten days may be considered prior to imposition for
stage wise penalty if approved by the Company, failing which intermediate compensation shall be
levied. In the event of the Contractor failing to comply with the condition here above the contract is
liable to be terminated at any stage and/or the Contractor shall be liable to pay as compensation such
amount as the PM in consultation of the Company may decide of the Contract, sum for the quantity of
Work that remains incomplete.
b. If the Contractor shall fail to achieve completion of the whole of the Works or, if applicable, any section
within the time prescribed by clause a hereof relating to time of Completion, then the Contractor shall
pay to the Company the sum of 0.5% per week as an amount of compensation for delays for every
week or part of which shall elapse between the time prescribed by clause 6 hereof and the date of
certified completion of whole of the Works or any section thereof, if applicable. The Company may,
without prejudice to any other method of recovery, deduct the amount of such damages from any
monies in his hands, due or which may become due to the Contractor as a debt. The payment or
deduction of such damages shall not relieve the Contractor from his obligation to complete whole of the
Works or any sections, or from any other of his obligations and liabilities under the Contract.
c. If, before the completion of the whole of the Works, any part or section of the Works has been certified
by the PM as completed, pursuant to clause a hereof, and occupied or used by the Company, the
amount of compensation for delay shall, for any period of delay after issue of such Completion
Certificate and in the absence of alternative provisions in the Contract be reduced in the proportion
which the value of the part or section so certified bears to the value of the whole of the Works.
9. SITE FACILITIES
i. Water supply
The Company will supply Water free at one point near site. Further Contractor shall make his own
arrangement for storage tank, laying all the pipe lines, making connections, distribution, maintaining the
same and dismantling on completion of work and making good any damage due to removal of such
piping work. No claims for hold up or delay in Work on this account of non-availability of water shall be
entertained.
ii. Electric supply
The Company will supply Electricity at one point near site location on chargeable basis and contractor
shall get sub meter installed as well as extension of wire / cable shall be done at his cost. In case the
client provides electricity at his cost then the contractor is entitled for deduction of 1.5% from each RA
bill.
The Contractor shall make his own arrangement for suitable standby power. Further he shall arrange at
his own cost the necessary switch board, and other switch gears, etc., and shall be responsible for their
maintenance.
a. Further distribution shall be done by the Contractor at his cost as per approved layout. He shall provide
required clearances for overhead lines to facilitate easy movement of machinery. These overhead lines
shall be shifted and rerouted at the Contractor's cost during execution of work if the same are found to
obstruct any other work of any agency working at site or requires to be shifted due to unforeseen
reasons.
b. On completion of the Work, the Contractor shall to the satisfaction of the PM, remove all wiring installed
by him and make good, any disturbance or damage done.
c. The Contractor shall employ a certified and licensed Electrician for carrying out this work.
d. For measuring the power usage of Contractor sub-meter is to be fixed by Contractor.
iii. Contractor's Offices, Go-downs, Workshop
The Company shall allow at his own discretion and convenience land for the construction of the
Contractor's site office, go downs, workshop assembly yard near the site at cost; the Contractor shall
include such expenses for project duration in contract rates. The Contractor shall construct and
maintain at his cost, all these temporary works which shall be well ventilated, lighted and provided with
water, electricity and sanitary arrangement to the approval of the PM.
The Contractor shall remove immediately on completion of the work such building and make good, to
the satisfaction of the PM, all the damages sustained. The Company through the PM may order, if so
required by the Company removal of such building or buildings and the Contractor shall carry out such
instructions at no additional cost to the Contract.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 3
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
The Architect, the Consultants (Structural & Services) through the PM shall make any variation in the
form, quality or quantity of the Works or any part thereof that may, in his opinion, be necessary and for
that purpose, or if for any other reason it shall, in his opinion, be desirable, he shall have the power to
order the Contractor through the PM with prior approval of the Company to do and the Contractor shall
do any of the followings
a. increase or decrease the Work (Area) included in the Contract,
b. change the character or quality or kind of any such Work,
c. change the levels, lines, position and dimensions of any part of the Works,
d. execute additional work of any kind necessary for the completion of the Works,
e. Change any specified sequence or timing of construction of any part of the Works.
And no such variation shall in any way vitiate or invalidate the Contract, but the value, if any, of all such
variations shall be taken into account in ascertaining the amount of the Contract Price.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 4
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
materials, then the materials shall in all respects comply with the relevant and current I.S.I. and for
measurements IS Codes. In such cases where I.S.I. do not exist, the specified approved manufacturers'
specification shall be followed; in absence of all these, the PM's instructions shall be followed.
The Contractor shall give the specific list of materials proposed to be used by him along with the tender
document under scope of contractor. The PM reserves the right to accept or reject the names proposed by
him in the list. Any cost implication due to this shall be at the cost of the Contractor. The Contractor cannot
claim extra costs due to changes made by the PM at the time of approval.
19. SUB-LETTING :
The Contractor shall not sub-let the whole or any part of the Works except where otherwise provided by the
Contract. The Contractor shall not sub-let any part of the Works without the prior written consent of the PM /
Company, which shall not be unreasonably withheld. However, such consent, if given, shall not relieve the
Contractor from any liability or obligation under the Contract and he shall be wholly responsible for,
i. Carrying out and completing the works in all respects in accordance with the Contract.
ii. Acts, defaults and neglects of any sub-Contractor, his agents, servants or workmen as fully as if they were
the acts, defaults or neglects of the Contractor, his agents, servants or workmen. Provided always that the
provision of labour on a piecework basis shall not be deemed to be a sub-letting under this Clause.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 5
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
i. Satisfy the Company that the appliance is in good condition and conform to relevant Indian Standards.
ii. Inform The Company of the maximum current rating, voltage and number of phases of the appliance.
iii. Obtain permission of The Company to deal with the appliance to which the socket may be connected.
iv. The Company will not grant permission to plug in until he satisfied that:
v. The appliance is in good condition and is fitted with a suitable plug.
vi. The appliance if fitted with a suitable cable having two earth conductors, one of which shall be on
earthed metal sheath surrounding the cores.
vii. No electrical cable in use by other Contractor / the Company will be disturbed without prior permission.
No weight of any description will be imposed on any such cable and no ladder or similar equipment will
rest against or be attached to it.
viii. The voltage for all portable equipment e.g. drilling, machines, temporary lighting, etc. will not exceed 24
(twenty-four) volts.
ix. No work must be carried out on any live equipment. Equipment must be made safe by the Contractor
and a Permit-to-Work issued by the Company before any work is carried out.
x. All electrical connections, installation shall be certified Safe by an approved Electrical Inspector before
connecting it to source.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 6
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
31. INSURANCES :
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 7
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
i. Workmen's Insurance
The Client/Company shall not be liable for any payment in respect of any damages or compensation
payable according to law in respect or in consequence of any accident or injury or loss of life to any
workman or other person in the employment of the Contractor or any sub-contractor, except an accident
or injury resulting from any act or default of the Client/Company, his agents or servants. The Contractor
shall insure against such liability with an insurer approved by the Client/Company for sum of the
established norms during the entire period till completion of Period of Maintenance (Defect Liability
Period). The Contractor shall also indemnify the Client/Company against all claims which may be made
upon the Client/Company, whether under the Workmens Compensation Act or any other statute in force,
during the currency of this contract or at common law in respect of any employee of the Contractor or of
sub-contractor and shall be at his own expense effect and maintain until the term of the Contract, with an
Insurance Company, approved by the Client/Company, a policy of Insurance against such risks and
deposit such policy or policies with the PM / Client/Company from time to time.
a. Without prejudice to the other rights of the Client/Company against the Contractor in respect of such
default, the Client/Company may so insure and shall be entitled to deduct the premiums paid along
with his service charges of 0.25% of the Contract Price and liquidated damages of 0.25% of the
Contract Price for noncompliance from any sums payable to the Contractor under this Contract or
such amount may be recoverable by the Client/Company from the Contractor as debt.
b. The Contractor shall be responsible for any liability which may not be covered by the insurance
Policies referred to above and also for all other damages to any person, animal or defective
workmanship in carrying out of this Contract, whatever, may be the reasons due to which the
damage shall have been caused.
c. The Contractor shall also indemnify and keep indemnified the Client/Company against all and any
costs charges or expenses arising out of any claim or proceedings relating to the Works and also in
respect of any award of damage or compensation arising there from.
d. The Contractor, in case of re-building or reinstatement after fire, shall be entitled to such extension of
time for completion as the PM may deem fit, but shall, however not be entitled to reimbursement by
the Client/Company or any shortfall or deficiency in the amount finally paid by the Insurer in
settlement of any claim arising as set out herein.
e. Insurance by Sub-contractor and Nominated Sub-contractor
f. Without prejudice to his liability under this clause the Contractor shall also cause all nominated Sub-
contractor to effect, for their respective portions of the works, similar policies of insurance in
accordance with the provisions of this clause and shall deposit or cause to deposit with the
Client/Company such policies. The Contractor shall not permit a nominated Sub-contractor to
commence work at the site unless the said insurance Policies are submitted. In the event of failure of
the Sub-contractor to take out such a policy of Insurance before commencing the works at the site,
the Contractor shall be responsible for any claim or damage attributable to the said Sub-contractor.
g. Period of Policies: All the insurance covers for full amount shall be kept in full force (alive) during
the entire period of the contract (till end of maintenance period).
h. Remedy on Contractor 's Failure to Insure : If the Contractor shall fail to effect and keep in force
the insurances referred to above, or any other insurance which he may be required to effect under
the terms of the Contract, then and in any such case the Client/Company on advice of the PM may
effect and keep in force any such insurance and pay such premium or premiums as may be
necessary for that purpose and from time to time deduct the amount so paid by the Client/Company
as aforesaid from any moneys due or which may become due to the Contractor, or recover the same
as debt due from the Contractor.
i. The Contractor shall also indemnify and keep indemnified the Client/Company against all and any
costs, charges or expenses arising out of any claims which may be made upon the Client/Company,
whether under the Workmens Compensation Act or any other statute in force, during the currency of
this contract or at Common Law in respect of any employee of the Contractor or of Sub-contractor
and shall be at his own expense effect and maintain until the completion of the contract (till end of
maintenance period) with an Insurance Company, approved by the Client/Company, a policy of
Insurance against such risks and deposit such policy or policies with the Client/Company from time to
time during the currency of this contract.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 8
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
Contractor shall submit all the above mentioned Legal compliances, in case of non-availability of any of
above stated compliances, Contractor shall submit undertaking document stating reason for non-availability
as well as if required in future its Contractors liability for any legal consequences arising due to non-
compliance of govt. norms, and client shall not be responsible for any non-compliance during WO period as
well as in future for this particular order.
C.) The Contractor shall abide by all the safety norms mentioned in Safety Manual and also shall duly obligate to
follow SOP and Labour Laws as per below.
Safety Manual
SOP
Labour Laws
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 9
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
a) GST means any tax imposed on the supply of goods or services or both under GST Law.
b) Cess means any applicable cess, existing or future on the supply of Goods and Services.
c) GST Law means IGST Act, GST (Compensation to the States for Loss of Revenue) Act, CGST Act,
UTGST Act and SGST Act, 2017 and all related ancillary legislations.
Change in Tax law: Sec. 171 of CGST/SGST Act contains provisions related to anti-profiteering. On
the basis of same on introduction of GST, the Vendor should pass on the tax benefit/savings, if any, on
account of tax credits or lowering of tax rates to us by way of adjustment in the contract price. Non-
compliance of the same may lead to levy of penalty by Government. Any increase in tax cost due to
change in the rates of tax shall be reimbursed by us.
Obligation of Vendor: The Vendor shall comply with all the compliance requirements under GST
Law. Further, the Vendor agrees to do all things that may be necessary to enable us to claim input tax
credit in relation to any GST payable under this Agreement/P.O./W.O. or in respect of any supply of
Goods or Services under this Agreement/P.O./W.O. This shall include (but not limited to):
a) Issuing Invoices/Debit Notes/Revised Invoices/Credit Notes as per the prescribed format, containing
all the information as is required for us to avail Input Tax Credit.
b) Submission of periodic statements/returns as per the GST laws within specified time lines with
complete and correct details as may be prescribed.
c) Issuance of Debit Note within the prescribed time limit to enable us to take the Credit.
d) Timely payment of tax liability by utilization of admissible credit or through cash.
Penal clause: If any amount of credit, refund or any other benefit is denied or delayed to us or any
penal charge or interest is imposed on the us due to any non-compliance by the Vendor (including but
not limited to the failure to upload or incorrect disclosure of details on the GSTIN portal or delay/failure
to deposit tax within due dates or due to non-furnishing or furnishing of incorrect/incomplete
documents by the Vendor, wrong determination of nature of supply), the Vendor shall be liable to
reimburse the loss which accrues to us on the aforesaid account. Alternatively we shall be entitled to
withhold the payment of all the subsequent bills issued by the Vendor and recover such loss from any
outstanding payment.
l) GST UNDERTAKING:
We understand that after the Goods and Services Tax (GST) becomes applicable, most of the indirect
taxes that are being levied separately shall be subsumed within GST. In such an eventuality, the terms
of the Contract shall be re-negotiated to align the same with the changes in the applicable laws
including availing and passing of the necessary Input Credit on goods and services. The Contractor
further agrees to share with the Client, the costing, taxation structure / mechanism, both pre and post
GST implementation.
The Contractor shall register themselves and ensure adherence to all the rules and regulations as may
become applicable under the GST Act. As and when GST comes into effect, the payment of GST
towards contractor shall be made subjected to fulfillment of all the following condition:
Tax Invoice shall be received by client / company
Goods / Services shall be received by client / company
Payment of GST to the government shall be made by contractor
Filing of GSTR-1 by contractor so that credit will flow in our GSTR-2
m) Income Tax and WCT (Tax deducted at source)
Each payment made from time to time to the Contractor, shall be subjected to WCT, TDS, VAT and
Income Tax TDS. Tax Deducted at Source as per the provisions of the relevant Act and Rules
prevailing at that time for which TDS certificate will be issued in accordance with the applicable
provisions.
n) The PF Liability in reference to order shall be as stated below.
The contractor should be PF registered. The contractor shall maintain attendance muster of staff as
well as labour. The contractor shall submit PF challans, with each Bill. If contractor is not having PF
registration, deduction shall be applicable.
PF liability shall be defined as below for the job works (Labour wages)
1 Contractor shall be bifurcated in following categories:
a. Contractor with PF registration or have applied for PF registration
b. Contractor without PF registration and are not interested to register (includes contractor who
are having less than 9 labours at site).
2 For Contractor falling under category 1a needs to submit PF challans & ECS monthly as per
government norms.
3 For Contractor falling under category 1b, client/principal Client/Company shall contract the rates
based on required PF deductions from RA bill as mentioned in point 4 below, as well as include
the same in contract condition considering it as an job work.
4 For non PF registered Contractor, it is deemed that from total amount of work order issued, 40%
of the amount is labor part and on such labor part the applicable PF deduction is of 25.61%.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 10
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
5 The deduction as mentioned in 4th point shall be deducted from each RA bill (Gross bill before
ST) of Contractor (incl. retention) and the summary page of RA bill certificate.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 11
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
3.2 100% of retention money shall be released on completion 12 months from the date completion
of defect liability period as defined herein.
3.3 The Contractor shall be obliged to pay from RA bill amount as mentioned in Clause no 3 as
retention money.
The Retention money shall not bear any interest. All compensation or other sums of money
payable by the Contractor to the Company under the terms of this contract may be deducted
from his retention money or from any sums which may be due or may become due by the
Company to the Contractor on any account whatsoever, and in the event of his retention money
being reduced by reason of any such deduction as aforesaid, the Contractor shall, within ten
days thereafter, make good in cash as aforesaid any sum or sums which may have been
deducted from the retention money or any part thereof..
4.0 Commencement of work and Mobilization: The contractor shall mobilize within 2 days from the date
of issue of LOI/WO/Mail confirmation.
6.0 Subcontract:
6.1 The contractor shall not sublet whole or part of work to any subcontractor or other contractor
without prior approval of client.
6.2 The subcontracting shall subject to approval of client only.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 12
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
7.1 LD shall be deducted for delay in work beyond the stipulated date of completion agreed by client.
7.2 LD equal to 1% of order value per week of delay shall be deducted from Bills, which shall be
limited to 5% of order value.
7.3 Extension of time shall not relieve contractor from liability of LD. However the client may approve
the time extension with or without LD. This would be solely on the discretion of client.
8.0 Termination:
8.1 The client reserves the right to terminate the order by giving 2 days notice, without giving any
reasons.
8.2 The contractor shall be paid only for the work certified by the project manager of client, till the
date of termination.
8.3 The contractor shall not be entitled for any further claim or compensation after termination.
8.4 The client reserves the right to execute the balance job on risk and cost of contractor.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 13
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
deemed to be a submission to arbitration within the meaning of the Arbitration and Conciliation Act,
1996 or any statutory modification thereof.
The work under the Contract shall continue during the arbitration proceedings and no payment due to
the Contractor shall be withheld on account of such proceeding under progress.
No award of the Arbitrators shall relieve the Contractor of his obligations to adhere strictly to the
Company's instructions with regard to the works.
The venue of the Arbitration shall be decided by the Arbitrators; which shall be within Vadodara
limits. The Arbitrator shall give his award separately on each item with reason and costs. The award
of the Arbitrators shall be final, conclusive and binding on all parties.
The Company and the Contractor hereby shall also agree that arbitration under this clause shall be a
condition precedent to any right of action under the contract. The provisions of this clause shall
survive the expiry or sooner termination of his Contract.
10.2 Interim Relief: Parties shall be free to avail interim relief / injunctive relief from court.
*****
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 14
SEAL OF TENDERER
RAW MATERIAL STORE BUILDING, VADODARA COLUMN STRENGTHENING & OTHER FABRICATION WORK
As per approved GST Invoice Format shared by the company to contractor from time to time.
VOLUME I COLUMN STRENGTHENING & OTHER FABRICATION WORK (GCC & SPCC) 15
SEAL OF TENDERER