SL.No. DESCRIPTION
C. ELECTRICAL WORKS
I Transformer.
II Motor.
III Generator.
HP : HOLD POINT.
A point which requires inspection/verification and acceptance by Owner/ Consultant
before any further processing is permitted. Contractor shall not process the activity
beyond a Hold Point without written approval by Owner/ Consultant.
W : WITNESS POINT.
An activity which requires witnessing by Owner/ Consultant when activity is performed.
Suppose, after proper notification has been provided, the contractor not obliged to
hold further processing, if Owner/ Consultant is not available to witness the activity or
does not provide the comments before the date notified.
NOTE :-
Contractor to submit required formats and job procedures for each activity listed in
ITPs and submit to Owner/ Consultant for approval. Responsibility for execution of the
inspection/ testing is with the contractor. Owner/ Consultant only verify examination or
testing done by the Contractor at important stages. Activities for which ITPs are not
given, contractor to develop and get the same approved by Owner/ Consultant well
before start of the work.
INDICATIVE INSPECTION &
HPCL, Visakh TEST PLAN
TOYO ENGINEERING INDIA LTD.
ISSUED :29.12.2008 JOB NO. : 6261
DOC.No. 6261-CD-303 DHT PROJECT Sheet 3
SL.
NO. ACTIVITY CONTRACTOR PMC
I POWER TRANSFORMER
8 Check oil filling of tank and OLTC, prior to filling, oil from WC Rw
each drum to be tested against di-electric strength for
minimum value of 50 KV - no breaking (2mm gap)
10 Check oil (tested) filling to the cable end box and ensure WC S
oil levels.
26 Mechanical acceptance. WC HP
SL.
NO. ACTIVITY CONTRACTOR PMC
II MOTOR.
SL.
NO. ACTIVITY CONTRACTOR PMC
III GENERATOR.
20 Perform Earth fault test & see the operation of E/F relay. WC W
21 Perform open circuit test & draw the open CRT curve for WC W
comparison.
INDICATIVE INSPECTION &
HPCL, Visakh TEST PLAN
TOYO ENGINEERING INDIA LTD.
ISSUED :29.12.2008 JOB NO. : 6261
DOC.No. 6261-CD-303 DHT PROJECT Sheet 10
NOTE:- Activities pertaining to SI. No. 5 and 15 will be checked by Mechanical Group.
INDICATIVE INSPECTION &
HPCL, Visakh TEST PLAN
TOYO ENGINEERING INDIA LTD.
ISSUED :29.12.2008 JOB NO. : 6261
DOC.No. 6261-CD-303 DHT PROJECT Sheet 11
SL.
NO. ACTIVITY CONTRACTOR PMC
13 Check name plate for each breaker, inspect and test the WC S
operating mechanics (Mechanically), interlocks, contacts,
arc chutes, auxiliary devices and adjustments as
required.
16 Test and witness I.R value of the power and control bus. WC W
23 Mechanical acceptance. WC W
11 Mechanical acceptance. WC W