Академический Документы
Профессиональный Документы
Культура Документы
Engineering characteristic of the soil structure and mechanism to lead to the failure.
A number of possible failure mechanics were considered prior to determining the
most probable cause of the collapse. These mechanisms are discussed and the basic for
considering them unlikely cause of the failure and the sequence of the failure events are
presented.
The following failure mechanism leading to collapse of the building were considered,
lateral instability, column instability, floor slab failure, foundation failure, failure due to lateral
soil pressure and loss at floor slab. Each of this are discussed in turn.
The potential contributions of the problems that occurred with respect to the floor
slabs during construction and lifting as causes of the collapse were also considered. The
problem included exposure of post-tensioning tendon during casting of a slab, accidently lifting
of an extra slab and misplaced of a lifting nut while lifting a slab. Information obtained from
representatives of the lifting contractor indicated that concrete was placed over the exposed
post-tensioning tendon, damaged concrete in the floor slab due accidental lifting on an extra
slab was repaired using pressure injected epoxy and the damage to shear head causes by
misplacement of a lifting nut was not serious. It was therefore considered unlikely any these
problems were the cause of the collapse.
Lateral Instability
The lack of external lateral bracing and the fact of construction of the shear wall was
behind the schedule called for on the erection drawings raised the question of instability of the
structure under lateral loads. The west tower had no essentially no reserve capacity against
sideways buckling. When finite member size are accounted for in an approximate ways, the
reserve buckling increased to around 6. Lateral bracing provided by the shear wall constructed
in accordance with the plans and specifications or other lateral supports would have been
consistent with good practice. It was not likely, therefore, that lateral instability was the main
cause of the collapse. Evidence supports this conclusion. Eyewitness did not reported seeing
the building move laterally but rather collapse vertically towards the center of each tower. They
also did not report any perceptible lateral movement at the time of collapse. Observations of
the debris reported also did not indicate any evidence of significant lateral displacement of the
structure.
The displacements produced by the horizontal jack used to plumb the building were
small. The analysis indicated that the lateral load required to reduce the effect of the restoring
moment associated with load transfer between the wedges exceeded the capacity of the
horizontal jack. It is therefore not likely that the use of this jack to plumb the building initiated
the collapse of the west tower.
Column Instability
The result indicate that instability of the individual columns was not a problem. For
the conditions prevaling at the time of collapse in the west tower, the reserved capacity or ratio
of the bulking loads for columns in stage IV (unsupported length = 30 ft 5 in) to the dead weight
of the roof and level 12 and level 9/10/11 ranged from 2.2 to 7.8. using the capacity reduction
factor of 0.85 in the LRFD design procedure reduce these to the range of 1.9 to 6.6. The
unsupported length required for column bulking could have occurred as the floor slabs moved
down the columns of separated from the column, thus increasing the unsupported length. As
this occurs however, the slab dead load is removed, thereby reducing the probability of column
buckling.
Stage of the construction.
Weld Failure
The laboratory tests and metallographic examination raise questions regarding the
quality of some of the welds in the structure, both shop welds and field welds. A detailed
inspection was made at the landfill of the shop welds on the weld blocks and the tack welds on
the wedges supporting the roof and level 12 slabs on the west tower. Very few failures were
observed of any of the welds on the weld blocks. Those that were found were located in the
lower levels and were caused by extreme loads. The tack welds on the wedges obviously had
failed since the roof and level 12 slabs failed as the building collapse. The failure of these tack
welds was considered a consequence of the overall failure of the building rather than the initial
cause of the collapse. Failure of a tack weld alone also would not cause the wedge to fall out.
The noise one would expected to be associated with failure of the tack weld is much less than
reported by the eyewitness as occurring at the initiation of the collapse. Other weld failures
including failure of the column splice at the ground level in column E4.8 were considered a
result of the collapse and not the cause.
Figure 2
A different mechanism is believed to have been involved with the progression of the
failure along G line and south to column line H. Neither column lines G or H involved the
failure of jacks as slabs 9/10/11 had been temporarily wedged and the lifting nuts had been
removed from the jack rods in preparation for the next lift. An inspection of the column tops
(stage IV) from these two lines revealed that very little scraping or gouging occurred during
the collapse and, with the exception of the columns in lines 1 and 6, the shear heads released
cleanly and slid straight down. At columns G6 , HI and H6 the shear heads at the upper levels
did not release cleanly and some local bending of columns resulted. To a lesser degree, this
also happened at column H2. The bending moment about G line, and eventually about H line,
would have led to progressive loss of the wedges under floor slab 9. This action would have
been augmented by the racking forces produced by the transverse (north- south) tendons with
the effect that wedges also were lost under floor slab 12 along column lines G and H. The
analysis also indicated that' the slab would lift off one wedge at each column at small lateral
displacements This lift off could be followed by the wedges being lost.
Groundwater
Water levels were not initially noted for borings at footing locations because the water
circulated during coring would have caused a superficial level. Follow up readings are noted
on the boring logs, but indicate the borings were dry to cave depths of about 4.0 to 4.4 ft (1.2
to 1.3 m) up to 16 days after completion. In Borings B-l and B-2, water was not encountered
and the holes were dry upon completion to depths of caving at 10 to 12 ft.
An apparent water level was observed as noted in test pits adjacent to footings 2H and
10F. The water levels at these locations were comparable and relatively constant over a 16 day
period. In the excavation at Footing 2H a flow was observed through fissures in the bedrock.
The water levels indicated by this data is about EL -32.2 to -32.7.
Water level readings which were obtained in the field investigation are noted on the
boring and test pit logs. The water table should be expected to fluctuate with variations in
precipitation, surface runoff, leaking nearby utilities, pumping, and evaporation.
a) Calculations showed that these supports (hydraulic jacks at the time of collapse)
were the most heavily loaded in the west tower.
b) An eyewitness account of the slab behavior at this location at the time of failure is
consistent with loss of support.
c) This failure mechanism occurred in laboratory tests simulating the conditions
existing in the structure at the time of collapse. The failure resulted in a loud noise
in the laboratory tests which is consistent with the eyewitness reports.
d) The computed reserve capacity for this failure mechanism is one of the lowest of
the possible mechanisms analyzed.
2. The quality of materials in the structure was generally in accordance with the project
plans and specifications and did not play a significant role in initiating the collapse.
a) Tensile properties and chemical composition of the column steel satisfied the
ASTM requirements for A 36 and A 572 Grade 50 steel.
b) The results of tests of cores from the floor slabs and shear walls indicated the
compressive strengths of the concrete met the project plans and specifications.
c) Yield strength and breaking strength values of the post -tensioning strand generally
satisfied the ASTM requirements for steel strand.
3. There were a number of deviations from the project plans and specifications in the
structure as built, but the investigation indicated these deviations did not play a
significant role in initiating the collapse.
a) Data from borings and test pits indicated a number of footings rest on layers of
fill and disintegrated rock rather than "rock of suitable quality" or lean concrete.
b) The strength of some of the welds was less than the strength implied in the
structural drawings.
c) Column splice details shown on the plans do not meet the requirements of the
AISC Specification or of the AWS Structural Welding Code for prequalified
complete-penetration groove-welds.
d) Lack of joint penetration and large amounts of porosity were observed in some
of the field welds.
4. It is unlikely that the horizontal jack used to plumb the structure initiated the collapse.
a) Displacements produced by the jack in plumbing the building were small.
b) The maximum load the jack could apply to the structure was not sufficient to
cause inelastic action.
5. The reserve capacity against lateral instability was small. It does not appear, however,
that lateral instability was the initial cause of the collapse. Inadequate resistance to
lateral instability may have caused the collapse of the east tower.
a) Deadmen and guy cables whose purpose would have been to plumb the building
and provide lateral bracing were not used in the construction.
b) The height of the structure above the cast top of the shear walls at the time of
collapse was greater than three equivalent floors of height.
c) Eyewitnesses did not report seeing or feeling any lateral movement at initiation of
the collapse.
d) Observations of the debris did not indicate any overall lateral displacements or drift
in the collapse.
6. It is unlikely that lateral earth pressure acting against the basement wall on the north
side of the structure caused the building to collapse.