Draft Cost Estimate For Geo Technical Investigation

14 Bore Holes
Sl.N Considered
Particulars Unit
o.
Alcon Qty Amount

MOBILISATION: Mobilisation of boring rig,


1 personal etc., for carrying out investigations LS/Site 30000 1 30,000
including demobilisation on completion of work.

BY ROTARY DRILLING METHOD: Drilling in soil


2 Rmt 750 140 105,000
all kinds of soils
Conducting standard penetration tests (SPT) as per IS
3 No's 500 140 70,000
2131 1981 at 1.50m or 2.0m depth intervals,
Collection of undisturbed samples (UDS) from the
4 No's 500 140 70,000
bore holes
Drilling in soft disintegrated rock strata using TC Bit
5 Rmt 1650 70 115,500
with core recover less than 10%
Drilling in hard rock using NX size Diamond bit with
6 Rmt 3500 70 245,000
core recover more than 10%.
Per
7 Shifting equipment from one bore location to another 1500 13 19,500
Location
8 Laboratory Tests for Soils:

Carrying out the following laboratory tests on the


samples collected from the site as per IS 2720 :
Per Bore
a. Grain size analysis 3000 14 42,000
Hole
b. Consistency limits
c. Natural Density.
d. Natural Moisture Content
e. Triaxial / Direct shear tests- NOT NECESSARY
9 Laboratory tests for Rock
a. Unconfined Compressive strength for rock. Per Sample 1500 14 21,000
b. Water content & Density of rock
Preparation and submission of detailed report
11 regarding SBC in triplicate along with Per Site 10000 1 10,000
recommendations regarding type of foundation
Supplying rock core samples in wooden boxes. (If
10 Each Bore 1500 14 21,000
Required)

TOTAL 749,000.00
TUSPL

RATE AMOUNT

3000 3000

750 105000

500 70000

500 70000

1500 105000

2500 175000

1500 19500

1500 21000

1500 21000

10000 10000

1500 21000

620,500.00