PROGRESS REPORT DAILY WEEKLY No. PO No.

Project Name : 1 ry RH Replacement Project 2017 Plant : Boiler Unit1 Order/PR No. : Date. Page. 1/1
WEATHER

Activities Description Next Action Plan Problems and Difficulties. ()

Solved and How ()

Tool & Equipment use perday

% Progress : Plan today Actual today Consumablet use perday


Plan Tomorrow =
Manpower :
1. Project Mgr. Person Hrs. Fuel use perday
2. Project Planner Person Hrs.
3. Admin Person Hrs.
4. Lead team inspector Person Hrs. Project Status and Result of Solved ()
5. Inspector Person Hrs.
6. Safety technician Person Hrs. DELAY /
7. Hole Watch Man Person Hrs. EQUAL /
8. Fire watch man Person Hrs. FAST /
9. Driver Person Hrs.
Total Hrs.
Contractor Company : Prepared By PAE Approved By BLCP Date :
PAE Technical Service Public Company Limited.
FP-12-03 Eff. Date 01/10/56