Академический Документы
Профессиональный Документы
Культура Документы
Estimated Amount
No. Work Item Unit Remark
Quantity (Rp.)
1 Preparation Work
1.1 Mobilization Ls. 1.00
1.2 Demobilization Ls. 1.00 #REF!
1.3 Temporary facility Ls. 1.00
400,000
2 Ls. 1.00 #REF!
3 #REF! Ls. 1.00 #REF!
4 #REF! Ls. 1.00 #REF!
5 #REF! Ls. 1.00 #REF!
6 #REF! Ls. 1.00 #REF!
7 #REF! Ls. 1.00 #REF!
8 Chemical Building Foundation Civil Construction Ls. 1.00 #REF!
9 #REF! Ls. 1.00 #REF!
The quantity in the above items mentioned is only an estimated figure which shall not be regarded as basis for final claim.
Estimated
No. Work Item Unit -RMB Direction Measurement
Quantity
1 Preparation Work
Including all survey and setting
1.1 Survey and Setting Out Ls. 1.00 - out works lump sum price
Including draining works, sloping
2 Earth Work - supporting and others
construction measurement.
Calculated base on
Disposal area within 1 km Radius,
2.1 Soil Excavation and Disposal m3 9,000 - confirmedcontractor
the subcontractor shall level the
survey data
Calculated base on
disposal material.
Incl. material and Compaction
confirmed survey
2.2 Backfill Gravel() m3 1 - 1 dataafter compacted)
Test
Calculated
base on
2.3 Backfill soil m3 1 - Incl. material and Test,
Compaction Compaction
the Test confirmed survey
materials shall excavated and dataafter compacted)
Calculated base on
2.4 Backfill soilMaterial supply by contractor m3 4 - transported from storage area confirmed survey
within 1KM Radius
dataafter compacted)
1
3 Concrete Work - Including
foundation cleaning,
form works, concrete pouring,
Plain concrete layer construction(C15) concrete curing etc. Concrete according to the detail
3.1 m3 191.00 - shall submit
Including formbyworks,
contractor
concrete design drawing
C15
pouring, concrete curing etc,
Raft foundation concrete Boiler foundation
concrete shall submit by according to the detail
3.2 m3 3700.00 -
contractor design drawing
Independent foundation, cushion cap Including form works, concrete
foundation, continuous beam including
pouring, concrete curing etc, according to the detail
3.3 m3 250.00 -
columns, etc.) concrete shall submit by design drawing
contractorform works, concrete
Including
pouring, concrete curing etc, according to the detail
3.4 m3 50.00 -
Ponds structure concrete construction concrete shall submit by design drawing
Including
contractorform works, concrete
pouring, concrete curing etc, according to the detail
3.5 Ditch concrete construction m3 30.00 -
concrete shall submit by design drawing
contractor
Material supplied by
according to the detail
3.6 Asphalt coatingIf required
3000.00 - subcontractor design drawing
Estimated
No. Work Item Unit -RMB Direction Measurement
Quantity PHC600 Pile cutting, the cut pipe
will remove to storage area
3.7 PHC Pile Cutting PHC pcs 277.00 - within 1KM
Piles hole Radius.phc600
cleaning, pile's hole
1
covered plate and rebar
fabrication, installation. The plate
3.8 PHC Pile Cap Fabrication PHC pcs 277.00 -
supply by subcontractor.
Including
material and others according to the detail
3.9 Grouting m3 10.00 -
works design drawing
1 Preparation Work
Including all survey and setting
1.1 Survey and Setting Out Ls. 1.00 - out works
Including draining works, sloping
2 Earth Work - supporting and others
construction measurement.
Calculated base on
Disposal area within 1 km Radius,
2.1 Soil Excavation and Disposal m3 15,797 - confirmed survey data
the subcontractor shall level the
Calculated base on
disposal material.
Incl. material and Compaction
confirmed survey
2.2 Backfill Gravel m3 2,500 - 1 dataafter compacted)
Test
Calculated
base on
2.3 Backfill soil m3 1,500 - Incl. material and Test,
Compaction Compaction
the Test confirmed survey
materials shall excavated and dataafter compacted)
Calculated base on
Backfill soilMaterial supply by contractor transported from storage area
2.4 m3 5,000 - confirmed survey
within 1KM Radius dataafter compacted)
1
Estimated
No. Work Item Unit -RMB Direction Measurement
Quantity
m3 457.07
Including form works, concrete
pouring, concrete curing etc, according to the detail
3.7 Ditch concrete construction m3 100.00 -
concrete shall submit by design drawing
contractor
according to the detail
3.8 Asphalt coating 2500.00 - Material supplied by subcontrac design drawing
PHC600 Pile cutting, the cut pipe
will remove to storage area
3.9 PHC Pile Cutting PHC pc 400.00 - within 1KM
Piles hole Radius.phc600
cleaning, pile's hole
1
covered plate and rebar
fabrication, installation. The plate
3.10 PHC Pile Cap FabricationPHC pcs 400.00 -
supply by subcontractor.
Including
material and others according to the detail
3.11 Grouting m3 10.00 -
works design drawing
Estimated
No. Work Item Unit -RMB Direction Measurement
Quantity
1.00 -
1.00 -
Totalexcluding VAT -
10% VAT -
Totalincluding VAT -
Total