Penta Forth Apparels Ltd.
2 LIMITATIONS
The information in this electrical safety inspection report was obtained during a visit to the facility and
during interviews with local factory management. It has not been possible to provide independent
verification for all the information and data collected, and, therefore, WEC cannot accept general
responsibility for omissions or errors arising from inaccuracies in this report from the information
obtained.
The findings and recommendations in this report are not intended to imply, guarantee, ensure or warrant
compliance with any government regulations. Additionally, the results do not imply in any way that
compliance with the findings or recommendations as stated in this report will eliminate all risks or
exposures not referred to in this report do not exist. Compliance with the findings and recommendations
stated in this report does not relieve the factory owner from obligation to comply with specific project
requirements, industry standards, or the provisions of any local government regulations.
3 DEFINITION
3.1 Time Frame
The amount of time being allocated based on the remediation work volume of the electrical issue
considering the feasibility and ideal status of materials, capital and working condition. Criticality and
priority level of the issue is not taken into consideration. It is bound only for the particular finding unless
mentioned typical, shall include the whole typical findings.
_________________________________________________________________________________________
Rezaul Karim
Managing Director
Penta Forth Apparels Ltd.
880 1711560028
a2zbd@agni.com
____________________________________________________________________________________________
The factory was constructed in 2012, production started in 2014, and during the inspection the
number of workers was approximately 385.
Number of Area of
Building Height of Building
Floors Building
Main Building 6 5,016 sq. m 19.70 m
Utility Shed 1 46 sq. m 4.57 m
__________________________________________________________________________________________
Utility Shed
Ground floor: Generator, Substation
__________________________________________________________________________________________
________________________________________________________________________________________
Generator #1
Generator Type Diesel
Capacity 150 kVA
Rated Voltage 400 V
Number of hours/day 2
Backup or Main supply Backup power
________________________________________________________________________________________
________________________________________________________________________________________
________________________________________________________________________________________
A Usage of Structure 6
B Type of construction 4
C Contents or consequential effects 5
D Degree of isolation 5
E Type of area and terrain 2
F Height of structure 8
G Lightning prevalence 21
Total index figure 51
Recommendation:
The total risk index figure is more than 40; hence a lightning protection system is required. An LPS
drawing must be drawn up
____________________________________________________________________________________________
RECOMMENDATION:
Have a qualified engineer create an as-built electrical SLD mentioning all the required information, and get it
reviewed & approved by Accord.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Thermographic scanning for the entire electrical system must be performed on a bi-annual basis and
recorded.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 8 Weeks
RECOMMENDATION:
Check the transformer oil condition by performing oil test, this must be done twice a year and recorded.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 8 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Hang this first aid and CPR instructions near all electrical equipment (LT panel, MDB, FDB, DB, SDB) on a
visible location.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Record earth pit resistances for all the earth pits, and do it once a year.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Insulation resistance test of all power cables (up to Floor distribution board or SDB) must be performed in a
periodic manner and recorded.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Maintenance Manager or Safety Officer must keep accurate records and ensure that they reflect actual factory
day to day operations.
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Electrical safety training and awareness program for the electrical personnel and staff must be initiated and
recorded .
PRIORITY: P-2
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
HT cable bends shall be avoided such that no stress is
imposed on the terminating of the cable or insulation of
the cable. Rearrange the cables using cable tray/ladder
and latch the additional cable with the tray/ladder. Or lay
the cable coil underground as per standard cable laying
procedures.
PRIORITY: P-3
Excess HT coil in transformer room
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
The HT cable must be encased in steel/HDPE pipe
(conduit) when passed through the wall and seal the
unused openings after the passage of conduit by fire
rated materials.
PRIORITY: P-2
HT cable entering utility room
REMEDIATION TIMEFRAME: 2 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Install cable tray or steel conduit to support & protect HT
cable on wall. The cable must be firmly latched at
regular interval to the support provided.
PRIORITY: P-3
HT cable not protected
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Install a ladder/pipe adequately supported with pole for
supporting the service cables in order to protect the
cables insulation from any physical damage.
PRIORITY: P-2
HT cable not supported
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Maintain a sufficient working space (preferably 1.07
meters) around the transformer or assign a qualified
engineer to design a required transformer room
according to BNBC, Section-2.6.3.
PRIORITY: P-2
Congested transformer room
REMEDIATION TIMEFRAME: 12 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Replace silica gel by a new one; or dry it under sun and
reuse it, if colour regains and breather oil cup must be
filled with transformer oil to the required level as
instructed by the manufacturer.
PRIORITY: P-1
Deteriorated silica gel and empty oil cup
REMEDIATION TIMEFRAME: 1 Week
RECOMMENDATION:
Encase the generator batteries and its charger in
metallic acid proof stand and insulate the battery
terminals. Establish a routine maintenance checklist for
the generator where the battery maintenance checklist
should be included.
PRIORITY: P-2
Generator batteries open and on floor
REMEDIATION TIMEFRAME: 2 Weeks
RECOMMENDATION:
Neutral wires must be terminated one by one at busbar
with proper sized cable lug.
PRIORITY: P-2
Bunched neutral wire
REMEDIATION TIMEFRAME: 4 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Organize all the power cables or wires securely and
neatly. Install slotted PVC channels for routing wires and
cables inside the panel.
PRIORITY: P-2
Cables & wires not drawn swiftly
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Install cable trays or ladder to support the cables. The
cables must be drawn swiftly and securely latched at
regular interval on the support. Terminate the cables,
entering or exiting all panels and boards, with all the
supportive and protective accessories.
PRIORITY: P-2
Cables not supported
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Provide/hang circuit diagrams of panels/boards in every
panel. (Provide identification and warning notice in front
every electrical panel. Include voltage level on the notice
and any precautions if required for special case).
PRIORITY: P-2
Circuit diagram not hung on panels
REMEDIATION TIMEFRAME: 4 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Provide earth connection for body and doors of metallic
distribution boards using green cables preferably braid
so that the metallic door remains at zero potential all the
time.
PRIORITY: P-1
Door earth bond not provided
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Provide cable gland according to the respective cable
size for cable entry and exit so that the cables are not
stressed on the sharp edges of the hole of panels.
Provide covers (of non-combustible material) if any
additional gap remains after installing cable glands.
PRIORITY: P-2
Gland holes open
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Arrange periodic inspection & thermal scan to identify
the overloading, loose connection, unbalanced load,
faulty device which may cause the excessive heat-rise
and take action accordingly.
PRIORITY: P-1
High temperature in PFI panel devices
REMEDIATION TIMEFRAME: 2 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Unrated wires should not be used in place of fuse.
Replace the defective HRC fuse with appropriately rated
HRC fuse.
PRIORITY: P-1
HRC fuse bypassed by wire
REMEDIATION TIMEFRAME: 2 Weeks
RECOMMENDATION:
Provide electrical graded rubber mats with the
specifications of 650 V-protection and required area
(accommodating at least two people or depending on the
panels length.
PRIORITY: P-1
Inadequate insulation mat
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Panels/devices located below stairs must be relocated to
safe place. Existing device installed near exit may be
relocated as required by fire safety regulations.
PRIORITY: P-2
IPS below stairs
REMEDIATION TIMEFRAME: 4 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Install base plate of the panel and make hole into it then
fit cable gland (required sized) for cable entry and exit to
the panel and seal all the unused openings by suitable
means to make the panel dust and vermin proof.
PRIORITY: P-2
No base plate
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Phase barriers between different phases must be
installed to avoid arc flashing. Standard separators
provided by the MCCB manufacturer must be used.
PRIORITY: P-2
No phase separators
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Panel enclosure including its door must be connected to
earth using green cables preferably earth braid so that
the metallic door remains at zero potential all the time.
Practice earth continuity test to insure earth continuity to
panel and loads enclosure and keep record.
PRIORITY: P-1
Panel body not earthed
REMEDIATION TIMEFRAME: 2 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
The cables must be protected and supported by a
covered cable tray or ladder throughout its length. The
cables must be drawn, arranged swiftly & latched firmly
at a regular interval on the support provided.
PRIORITY: P-2
Cables laid directly on floor
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
The cables must be protected and supported by a
covered cable tray or ladder throughout its length. The
cables must be latched firmly on the support provided.
PRIORITY: P-3
Generator cables not supported/protected.
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Wires installed near/attached to boiler/generator body
must be protected from external heat & moisture by
metallic heat resistant conduit
PRIORITY: P-1
Wire in flexible PVC conduit attached to boiler
REMEDIATION TIMEFRAME: 2 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Large exhaust fans must be connected through control
device such that it will not restart automatically when
power is restored.
PRIORITY: P-2
Large exhaust fans controlled by MCB
REMEDIATION TIMEFRAME: 4 Weeks
RECOMMENDATION:
Ensure dedicated earthing connection for the body of
boiler (consult with your boiler supplier).
PRIORITY: P-1
Boiler body not earthed
REMEDIATION TIMEFRAME: 2 Weeks
RECOMMENDATION:
Clearly identify each earth pit, and mark it for periodic
maintenance purposes.
PRIORITY: P-2
Earth pit near substation
REMEDIATION TIMEFRAME: 2 Weeks
__________________________________________________________________________________________
RECOMMENDATION:
Ensure minimum two earthing connection for generator
body (consult with your generator supplier).
PRIORITY: P-1
Generator body not earthed
REMEDIATION TIMEFRAME: 2 Weeks
RECOMMENDATION:
Design and Install LPS for your factory. Factory have to
submit LPS design to Accord before starting installation.
PRIORITY: P-1
Lightning Protection system missing
REMEDIATION TIMEFRAME: 8 Weeks
__________________________________________________________________________________________