PT.

PLN (Persero)
UIP KITSUM
UPP KITSUM 2

KRONOLOGI KETERLAMBATAN SCHEDULE FYI


UNIT 1 & 2 PLTU PANGKALAN SUSU
No Tanggal Sumber Penjelasan Link
Surat no : GPEC/MDP/LT7/PLN-S/2154/GPEC
1 03 Januari 2016 GPEC Concerning the issue of unit first year inspection OK
maintenances planned time
Surat no : GPEC/MDP/LT7/PLN-S/2155/GPEC
2 12 Januari 2016 GPEC Submission of the Inspection and Test Plan (ITP) of OK
FYI
Surat no :0101/KON.01.02/UIP I/2016
3 03 Februari 2016 UIP I Jadwal Pelaksanaan FYI PLTU Pangkalan Susu
OK
2x200 MW
Surat no :0024/KIT.04.03/P3BS/2016
4 12 Februari 2016 P3BS OK
Pelaksanaan FYI PLTU Pangkalan Susu
Surat no : GPEC/MDP/LT7/PLN-S /1865/GPEC
5 21 Februari 2016 GPEC OK
About Shut down unit 2 for FYI
PLN Kantor Rapat di PLN Kantor Pusat, agenda Pembahasan FYI
6 25 Februari 2016 OK
Pusat PLTU Pangkalan Susu unit 1&2
Surat no : 0034/KON.01.02/KITSUM 2/2016
7 25 Februari 2016 PLN UPP OK
Schedule FYI
Surat no : GPEC/MDP/LT4/PLN /0288/GPEC
8 26 Februari 2016 GPEC OK
Reply on Schedule FYI for PLTU Pangkalan Susu
PLN Sektor Rapat di Kantor IP, agenda Pembahasan MOH FYI
9 13 April 2016 OK
Medan Pangkalan Susu Unit 1 & 2
Surat no : GPEC/MDP/LT7/PLN-S/2214/GPEC
10 15 April 2016 GPEC OK
Concerning the issue of FYI of some area
Rapat di PLN UPP, agenda Special Meeting about
11 19 April 2016 PLN UPP OK
First Year Inspection
Surat no :0321/KON.01.02/UIP I/2016
12 21 April 2016 UIP I Penyampaian Draft SK tim Pengawas Pelaksanaan OK
FYI
Surat no : 0017/KIT.01.02/KITSBU/2016
PLN Sektor
13 19 Mei 2016 Tim Pendampingan Pelaksanaan FYI PLTU OK
Medan
Pangkalan Susu
PLN Kantor Rapat di PLN Kantor Pusat, agenda Kordinasi
14 01 Juni 2016 OK
Pusat Rencana Pelaksanaan FYI
Surat no : 0474/KON.01.02/UIP KITSUM/2016
15 16 Juni 2016 UIP I Persetujuan Tim Pendampingan Pelaksanaan FYI OK
PLTU Pangkalan Susu
Rapat di PLN P3B Sumatera, agenda Jadwal FYI
16 23 Juni 2016 P3BS OK
PLTU Pangkalan Susu unit 1&2

[Title] 1
PT. PLN (Persero)
UIP KITSUM
UPP KITSUM 2

Surat no : GPEC/MDP/LT4/PLN/0297/GPEC
17 27 Juni 2016 GPEC Issue about First Year Inspection (FYI) OK
Menindaklanjuti surat di point
Surat no : 0532/KON.01.02/UIP KITSUM/2016
18 29 Juni 2016 UIP I OK
FYI Schedule
Surat no : GPEC/MDP/LT4/PLN/0299/GPEC
19 02 July 2016 GPEC Reply on Adjusting Schedule of First Year Inspection OK
(FYI)
Rapat di kantor UIP I, agenda Adjusting Schedule of
20 14 July 2016 UIP I OK
First Year Inspection (FYI)
Surat no : GPEC/MDP/LT4/PLN/0301/GPEC
21 04 Agustus 2016 GPEC Proposal of Additional Cost Due to Adjusting Schedule OK
of First Year Inspection (FYI)
PLN Sektor
22 08 Agustus 2016 Notulen Rapat Evaluasi System Kelistrikan Sumbagut OK
Medan
Rapat Alokasi Energi bulan September 2016, salah
23 15 Agustus 2016 PLN P3BS satu point-nya tentang pengunduran Jadwal FYI unit 1 OK
dan 2
Surat no : GPEC/MDP/LT4/PLN/0303/GPEC
24 22 Agustus 2016 GPEG Issue about FYI and Proposal of Additional Cost Due OK
to the Delay of First Year Inspection (FYI)
Surat no : 0130/KIT.01.03/SMDN/2016
PLN Sektor
25 23 Agustus 2016 Pemberitahuan Notulen Rapat Evaluasi System OK
Medan
Kelistrikan Sumbagut
Surat no : 0668/KON.01.02/UIP KITSUM/2016
26 25 Agustus 2016 UIP I OK
FYI Schedule
Rapat di kantor UIP I, agenda Additional Cost Due to
27 1 September 2016 UIP I OK
Adjusting Schedule of First Year Inspection (FYI)
Surat no : 0726/KON.01.02/UIP I/2016
28 9 September 2016 UIP I OK
FYI PLTU Pangkalan Susu 1&2
Surat no : 0115/KON.01.02/KITSUM 2/2016
29 13 September 2016 PLN UPP OK
Document for FYI
Surat no : GPEC/MDP/LT7/PLN-S/2280/GPEC
30 14 September 2016 GPEC Submission of the First Year Inspection (FYI) OK
Maintenance Schedule and Manpower List
Surat no : 0142/KIT 01.92/P3BS/2016 First Year
31 16 September 2016 PLN P3BS OK
Inspection (FYI)
Notulen Rapat Pembahasan First Years Inspection
32 21 September 2016 PLN Pusat OK
PLTU Pangkalan Susu

[Title] 2
PT. PLN (Persero)
UIP KITSUM
UPP KITSUM 2

Historical Contractors ( GPEG )

Historical Project Owner ( PLN )

Historical Power Plant Owner ( PLN KIT )