REPORT Pages :2
1-Identification:
Originator Name: Esmail Ahmed Morgan Date: 29/11/2017 Code:
Supplier: PR.NO: N.A NCR NO.: 43 /2017
Part Description: Oil cooler +
W.O NO: N/A
Heat exchanger
Part NO: N/A Drawing :N/A
Quantity:
Incoming
In- Process Inspection
Found in What Activity?
Final Inspection
Other
2- Description of non-conformity
Hydrotest is done for incoming 3 oil cooler (coded C1, C2, C3) and 2 heat exchanger (coded H1, H2) .
Results:
1. Oil coolers (C2 &C3) are rejected and cooler (C1) is accepted (Pressure test = 8 bar)
2. Heat exchanger (H1 & H2) is rejected ( Pressure test = 5 bar )
3- Recommended Action:
Disposition: Date:21/11/2017
Page 1 of 2
2
4- Correction Action
5- Approval of correction
6- Closing of non-conformity
Page 2 of 2