EPC for Second New Overhead Line and Extension of the ex

Sequency of Shutdown Activity (FCS & PD


Sl. No Description
1 Modification of ATS function and interlock function and scheme checks in
33KV AIS SWGR at FCS Incomer-1/2 and Bus coupler (OGC)
2 Modification of 33KV AIS SWGR at FCS Incomer -1 panel for 2 out
of 3 scheme functionality.
3 Pre commissioning checks for Incomer -1/2 and bus section panel at FCS

4 Functional check & Simulation of ATS with 2 out of 3 schemes Shutdown


activity
5 Testing of Existing protection relay & scheme checks verification and interlock
checks in Fahud 33KV GIS panel L12 and R12.

6 HV power cable Hi-pot testing from Fahud SS- First Riser Pole, Black Top Road
crossing, Scrap Yard and FCS Substation up to Incomer -2.
7 Line Impedance and Megger testing of new 33KV OHL and Extension OHL
from Fahud PS
8 Commissioning of New OHL-2 from L12 GIS panel up to FCS incomer -2 panels

9 Commissioning of Incomer -2 with Bus 2 Right side after opening of Bus


coupler. (Ensure 415LV panel Bus is feeding from TX-1 incomer and B/C-1&2
closed)
10 Energizing of TX2 and TX3 transformer from Bus 2 with new OHL-2.
Changeover 415V Bus from TX1 supply to TX2 and 3 Transformer source.

11 Shutdown 33KV Incomer -1 and OHL-1, disconnection of existing Cable from


OGC Feeder at Airport Switch Rack,- Shutdown activity
12 Replacement of existing Vertical Disconnector at FCS end Terminal pole with
new Disconnector without FUSE holder. - Shutdown activity
13 Commissioning of New OHL-1 from R12 GIS panel up to FCS incomer -1 panels
d Extension of the existing Overhead-Line (OHL) at FCS
own Activity (FCS & PDO Substation)
Duration Start Finish Remarks Day Working Hours
11.03.2017 16.03.2017 OGC Operations support 7.00 AM to 06.00 PM
50 Hrs
required
11.03.2017 12.03.2017 OGC Operations team support 7.00 AM to 06.00 PM
20 Hrs
required.
16.03.2017 16.03.2017 OGC Operations support 7.00 AM to 06.00 PM
10 Hrs
required
26.03.2017 26.03.2017 OGC Operations support 7.00 AM to 13.00 PM
6 Hrs
required
18.03.2017 22.03.2017 PDO operations/OGC Support
50 Hrs required for Permit and testing 7.00 AM to 06.00 PM
Witness.
6 Hrs 20.02.2017 02.03.2017 OGC Project team support for 7.00 AM to 13.00 PM
witness activities.
20 Hrs 23.03.2017 24.03.2017 PDO/OGC team support for 7.00 AM to 06.00 PM
witness activities.
10 Hrs 26.03.2017 26.03.2017 PDO/OGC Operations team 7.00 AM to 06.00 PM
support required.
26.03.2017 26.03.2017 PDO/OGC Operations team
10 Hrs support required. 7.00 AM to 06.00 PM

27.03.2017 27.03.2017 OGC Operations team support


10 Hrs required. 7.00 AM to 06.00 PM

20 Hrs 02.04.2017 03.04.2017 PDO/OGC Operations team 7.00 AM to 06.00 PM


support required.
02.04.2017 03.04.2017 PDO/OGC Operations team 7.00 AM to 06.00 PM
20 Hrs
support required.
04.04.2017 04.04.2017 PDO/OGC Operations team
10 Hrs 7.00 AM to 06.00 PM
support required.