Introduction
Craft Production
Mass Production
Lean Production
Mass Production - After the World War I, Henry Ford and General Motor’s Alfred Sloan
moved world manufacturing from centuries of craft production into the age of mass
production. Mass production started in 1915 was matured by 1920; requires highly
mechanized machines, less skilled labor and high capital for production. Mass
production offers low design and volume flexibility at good price1.
Lean Production – After the World War II, Eiji Toyota and Taiichi Ohno formed a
production system called Toyota Production System that was termed as lean
manufacturing system later on. It was started in 1950; requires simple machines, skilled
labor and moderate capital for production. Lean manufacturing offers high design and
volume flexibility at best price1.
Lean thinking got it name from a 1990’s best seller called “The Machine That Changed
the World: The story of lean production by Womack and Jones. They introduces five
core concepts of lean manufacturing5–
Lean Manufacturing:
Lean is about doing more with less: Less time, inventory, space, people, and money.
Lean is about speed and getting it right the first time. Its characteristics are Zero waiting
time, Zero Inventory, Scheduling - internal customer pull instead of push system, Batch
to Flow -- cut batch sizes, Line Balancing and Cutting actual process times.
1. Continuous improvement
2. Doing everything more efficiently
3. Reducing operating cost
4. Fulfilling customers desire for max value at the lowest
5. Price
Waste elimination is one of the most effective ways to increase the profitability in
manufacturing business. In order to eliminate waste, it is important to understand exactly
what waste is and where it exists in the factory, the typical wastes found in
manufacturing environments are quite similar. To eliminate waste, Originally 7 main
types of waste were identified as part of the Toyota Production System. However, this
list has been modified and expanded by various practitioners of lean manufacturing and
generally includes the following
1. Over-production
2. Waiting
3. Transportation
4. Over-processing
5. Inventory
6. Motion
7. Defects
8. Correction
9. Knowledge Disconnection
7. Defects – In addition to physical defects which directly add to the costs of goods
sold, this may include errors in paperwork, provision of incorrect information about the
product, late delivery, production to incorrect specifications, use of too much raw
materials or generation of unnecessary scrap.
Standard Work
1. Standard work sequence - This is the order in which a worker must perform
tasks, including motions and processes.
2. Standard timing – Standard time is the frequency with which a single piece is
produced. Standard time is used to clearly specify and monitor the rate at which
a process should be occurring at various production stages.
3. Standard in-process inventory – This is the minimum unit of materials,
consisting primarily of units undergoing processing, which are required to keep a
cell or process moving at the desired rate.
4. Communication of Standard Work to employees - Standard work guidelines
shouldn’t only be textual manuals but should include pictures, visual displays and
even samples. Employees are unlikely to read boring textual production manuals
so visual displays and actual samples, including pictures, should be used as
much as possible.
5. Visual Management - Visual Management systems enable factory workers to
be well informed about production procedures, status and other important
information for them to do their jobs as effectively as possible. Large visual
displays are generally much more effective means of communication to workers
on the factory floor than written reports and guidelines and therefore should be
used as much as possible.
6. Quality at the Source (or “Do It Right the First Time”) - Quality at the Source,
also called “Do It Right the First Time”, means that quality should be built into the
production process in such a way that defects are unlikely to occur in the first
place.
7. Value Stream Mapping - Value stream mapping is a set of methods to visually
display the flow of materials and information through the production process. The
objective of value stream mapping is to identify value-added activities and non
value-added activities.
8. The Five S’s - The Five S’s are some rules for workplace organization which aim
to organize each worker’s work area for maximum efficiency.
9. Preventative Maintenance - Preventative Maintenance is a series of routines,
procedures and steps that are taken in order to try to identify and resolve
potential problems before they happen.
10. Total Productive Maintenance - Total Productive Maintenance (TPM) assigns
basic preventative maintenance work including inspection, cleaning, lubricating,
tightening and calibration to the production workers who operate the equipment.
TPM clearly assigns responsibility to workers to proactively identify, monitor and
correct the causes of problems leading to unnecessary machine downtime.
11. Cause and effect diagram - A Cause-and-Effect Diagram is a tool that helps
identify, sort, and display possible causes of a specific problem or quality
characteristic. It graphically illustrates the relationship between a given outcome
and all the factors that influence the outcome.
METHODOLOGY
Data Collection
For the collection of primary data metrics will be fixed and would be filled and monitored
in specific data collection formats.
Different variables are identified in framework of category of waste i.e. waiting time,
defects, inventory, transportation, motion and processing. Identify the unnecessary
activities and analyze the collected data for the implementation phase.
Reduction of wastes
Working with on site supervisory team, plan would be decided through work practice and
workplace changes, method improvement studies and stringent material utilization
norms. Necessary and logical changes will be suggested to reduce the wastes for
sewing production floor.
Sewing line Inspection: As there are no spreading and cutting facilities available in the
unit, so the concerned area for the study of defect is only sewing production line. There
are approximately 280 machines on the floor arranged in 6 lines, which are responsible
for the production. There are two check points in the line-
• In-line inspection
• Final inspection
Inline inspection is on the critical operation only some selected check points are
there to be checked and it is responsible to prevent the flow of defective pieces for the
next operations, because if it will be caught in the end than the garment may get
damage in making alteration of the defect which are generated in initial operations. Final
inspection is responsible for checking the whole garment.
Finishing inspection: Some defects are not easily visible in sewing line checking they
can be viewed easily after the thread cutting and pressing which is done in the finishing.
There are also two check points in the finishing-
1. Initial inspection
2. Final inspection
In the initial inspection the garment is being checked from the inside i.e. no
broken stitch, raw edges or spotting etc should remain inside, than only it forwarded to
final inspection. In the final inspection whole garment is checked.
Tool for measuring the Defects:
Defective per hundred units is the no. of defective pieces occurring per hundred
pieces. This is very useful tool to measure the percentage of alteration occurring in the
sewing production.
For calculating the waste due to defect, DHU level will have to calculate. If the
DHU level is more than the company norms than definitely there is something wrong
which is increasing the cost of quality. All the processes which are happening on the
floor i.e. alteration but they are not required are waste. So if the DHU level is more than
it is necessary to monitor each alteration on every stage to minimize the waste.
Data collection:
The process of data collection for DHU starts from listing down all kinds of defects which
are coming during sewing noted the alteration of whole day on every check point
including finishing also and collected this data for the 8 days/check point.
40
Waist patti width variation, 12.24
35
30
25
Open stitch, 11.56
%
20
Missing operation, 3.06
15
Puckering, 4.08
10 Run off, 4.42
5 Cut, 2.38
Type of Defects
Data had been collected for eight days on initial check point and it was found that major
alterations coming at initial inspection were:
• Raw edges
• Pinch sew
• Waist patti width variation
• Open stitches
These defects kept more than 70% share among all the defects, so all these four defects
were needed to analyze very closely to minimize the waste due to these defects.
Final Inspection: All points are checked Garment
Date Checked Pcs Passed Pcs Altered % Defective
Day 1 180 143 37 20.55
Day 2 109 56 53 48.62
Day 3 103 68 35 34.00
Day 4 113 82 31 27.67
Day 5 93 82 11 12.00
Day 6 101 50 51 50.50
Day 7 124 92 32 25.80
Day 8 120 87 33 27.50
Total 943 660 283 30.00
Fabric fault, 30
35
30
25
Waist patti width variation, 2.5
Run off, 11
15
10
Pinch, 3.53
Cut, 1.41
5
0
Type of Defects
The final inspection the whole garment is checked very carefully, in the chart it can be
seen that the defects which keep the max percentage among all the defects are -
Raw edge
Run-off
Fabric fault
Color variation
So these are the main area of concern in the favor of minimizing the waste.
Similarly initial and Final Inspection at finishing were done and analysed with the help of
cause and effect diagram. The results are as follows
1. Alteration percentage in sewing in-line inspection = 33.91%
2. Alteration percentage in sewing final inspection = 30.00%
3. Alteration percentage in finishing initial inspection = 21.95%
4. Alteration percentage in finishing final inspection = 23.36%
Sewing floor average alteration = 72%
Contribution of manual error to total defect is = 43%
Contribution of machine error to total defect is = 8%
Contribution of method error to total defect is = 20%
Contribution of material error to total defect is = 29%
Material flow:
The specific area where to focus work was right from receiving of cut parts to
bundling, bundling to production floor, and production to finishing department. There was
no spreading and cutting in the unit A-5. All the cut components had to come from the
Faridabad unit in the poly-bags by the road transportation to the Noida unit. Cutting
department was on 1st floor, so all the cut parts were brought to 1st floor from the ground
floor by the labor itself because there was no lift. In the cutting department the bundle
sorting was done by the labor i.e. fusing, straightening the cut parts and tag preparation
was done then final bundling was done, than all the prepared bundles were sent to the
production floor by the labor in the poly-bags by loading on their back.
There were 6 lines of sewing machines which were responsible for the garment
production. Feeding in all of the 6 lines was being given from the front but the final out
put was coming in the end only from 2 lines. In other four lines the final out put was
coming from the middle end. These 4 lines were divided in two parts, when the garment
was half finished and reached in the middle of line, it was brought back by the helper,
who fed that half finished garment in the end of line, it started to flow towards the starting
point and was being finished in the middle end. Here the transportation was increasing;
this process consumed more manpower and more time compare to the other two lines.
Bundle sorting
Final garment
1st floor
Bundle loading
Ground floor
Basement
All the loading right from cut part delivery to loading on all the relevant floors, the
material is loaded by labor putting on their back and carrying to the destination. This may
the cause of health injury of the employed worker and material damage as it is the
routine work and many a times in a day worker have to carry the good amount of raw
material and finished pieces from one floor to another floor.
Pie chart for the cause of defect:
Method
19%
Man
45%
Material
28%
Machine
8%
I. All the transportation of cut parts and finished pieces, from one floor to other floor
was done by the labor carrying on its back.
II. Transportation within the 4 sewing line was more than the other two lines because
the line was divided in two parts, output from the 1st half line were being fed from the
back of 2nd half line, means in the line the flow material was reversing back and it
takes time and extra manpower in transporting the material in the comparison of the
other two lines.
III. Flow of the material in the line was carrying on the table, which had the lesser width
because the material flow on the table was not smooth; the result was missing
operation in the garment.
IV. Baskets were missing on some workstations, so the pieces were put on the floor.
Resultantly, the percentage of spotted and dusted pieces was increasing.
V. The other disadvantages of putting down the pieces on floor were:
(Percentage of defectives due to spotting was 32% in initial inspection and 26% in
final inspection)
• Operator fatigue in picking up and dropping down the material
• Percentage of dusted and spotted pieces 10.66%.
• Loss of manpower engaged in dust removing.
• Consumption of stain removing solvent engaged in removing dust is 70 to
80 liters per day.
• Ring formation in dark shade pieces due to the spray gun
• Checker’s time consumed in removing dust is –
No. of pieces checked/hour = 30 pieces/checker
Total no. of checkers = 12
Time consumed in removing dust = 16.25 seconds/checker
Percentage of pieces treated by solvent = 100 %
Time consumed in dust removing/shift (in seconds) = 8*30*12*16.25
= 46800 seconds
= 13 hours
Available hours = 8*12 = 96 hours
Time consumed in dust removing (in percentage) = 13.54%
• Time consumption of the operator engaged in removing major stains-
Percentage of pieces having major stains = 13.16 %
Average daily production from 4 lines = 560*4 = 2240
Total average stained pieces/shift = 2240*13.16/100
= 295 pieces
Average time consumed in stain removing is = 63.46 secs/piece
So total time consumed in removing major spots =312 minutes
As a part of project was able to design implementation approach for an apparel factory,
do technical audit and value stream mapping and corresponding cost benefit analysis of
implementing lean manufacturing in the factory cam be audited. The study remains more
or less of an analysis along with primary data collection. Hence suggesting someone to
implement in various areas such as Unnecessary inventory, Over production, Non Value
adding motions, Over-processing by using modules i.e. lean foundation, shop floor
implementation, performance improvement and follow up and corresponding sub
modules on a shop floor and feel the real benefits.
Bibliography:
1. Saurabh Govind & Inderneel Kr Das, Identification, analysis & minimization of
process wastes; A DP 2002-2004
2. Ohno, Taiichi, Toyota production system: Beyond large scale production.
3. www.mekongcapital.com/Introduction%20to%20Lean%20manufacturing%
4. www.balancedscorecard.org/files/c-ediag.pdf
5. www.google.co.in
6. www.wikipedia.org
7. http://en.wikipedia.org/wiki/Lean_manufacturing
8. http://www.leanadvisors.com/Lean/
9. http://www.microsoft.com/industry/manufacturing/solutions/lean.mspx
10. http://www.simpler.com
11. www.leanbeyond.com
12. http://qualitytrainingportal.com
13. www.mckinsey.com/practice/psdc/ourwork/howwework/
14. www.se.cuhk.edu.hk/~yang/pubs.html