Академический Документы
Профессиональный Документы
Культура Документы
AFS
AYS
AMJ
AMJ AMJ
AMJ
TAA
ENGG CERT
AYS
SAG
SAG
ISSUED FOR CONSTRUCTION
DESCRIPTION
AS-BUILT
AS-BUILT
BI-10-01382
JO/EWO
10-01382
10-01382
09/21/17 10-01382
00
01
02
DISCIPLINE
ENGINEER
SAG
09/21/17
DATE:
PROJECT
ENGINEER
JZM
ETAP STUDY REPORT
09/21/17
DATE:
CERTIFIED
AMJ
09/21/17
DATE:
CONSTRUCTION
AGENCY
AMJ
09/21/17
DATE:
OPERATIONS
AFS
09/21/17
DATE:
Prepared by
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
SEPTEMBER 2017
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
AMJ
TABLE OF CONTENTS
AMJ AMJ
AMJ
TAA
ENGG CERT
AYS
SAG
SAG
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
07/24/17
06/28/15
NO. DATE
REV
00
01
02
DISCIPLINE
ENGINEER
SAG
09/21/17
DATE:
PROJECT
ENGINEER
JZM
09/21/17
DATE:
CERTIFIED
AMJ
09/21/17
DATE:
CONSTRUCTION
AGENCY
AMJ
09/21/17
DATE:
OPERATIONS
AFS
09/21/17
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
1.0 OBJECTIVE
AMJ
AMJ AMJ
The objective of this study is to verify the performance of the proposed electrical system
AMJ
TAA
ENGG CERT
and the sizes and ratings of the electrical equipment that will be installed under this
AYS
SAG
SAG
Budget Item (BI). This is accomplished by conducting the studies listed below using the
Electrical Transient Analyzer Program (ETAP) version 12.5.0:
I. Load flow
ISSUED FOR CONSTRUCTION
AS-BUILT
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
system.
Controlgear: Equipment manufactured to either 16-SAMSS-503 (LV Controlgear), 16-
07/24/17
06/28/15
DATE
00
01
02
DATE:
09/21/17
other distribution equipment. For example switchgear, controlgear, panel boards,
PROJECT
ENGINEER
switchracks, switchboards, etc.
JZM
DATE:
09/21/17 ESP: Electrical Submersible Pump
CERTIFIED
AMJ GIS: Gas Insulated Switchgear
09/21/17
DATE: High Voltage: Voltages 1000 V or greater unless otherwise designated in a specific
CONSTRUCTION
AGENCY
AMJ
MSAER or referenced international standard.
09/21/17
DATE: Low Voltage: Voltages less than 1000 V, unless otherwise designated in a specific
OPERATIONS
AFS
MSAER or referenced international standard.
09/21/17
DATE: MSAER: Mandatory Saudi Aramco Engineering Requirements.
CONTROL NUMBER
VERIFICATION
Operating Load:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
For new facilities: Anticipated one-hour demand based on plant or facility design
_____________________
conditions.
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
For existing facilities: When data from metering equipment is available: Maximum
AYS
AMJ
AMJ AMJ
SAG
SAG
single bus tie breaker. Each bus has one breaker to receive incoming power. (i.e., power
flow into and between the two busses is controlled with three breakers). These schemes
DESCRIPTION
AS-BUILT
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
00
01
02
energy to another form or store electrical energy. Examples of utilization equipment would
DISCIPLINE
ENGINEER be motors, heaters, lamps, batteries, etc. Equipment directly feeding/controlling the
SAG
DATE:
09/21/17 utilization equipment is considered part of the utilization equipment (e.g., AFDs, reduced
PROJECT
ENGINEER voltage starters, battery chargers, etc.).
JZM
DATE:
09/21/17 3.0 REFERENCES
CERTIFIED
AMJ 3.1 Saudi Aramco Engineering Standard SAES-P-100 (Electrical Design Criteria).
09/21/17
DATE: 3.2 Saudi Aramco Engineering Standard SAES-P-104 (Wiring Methods and Materials).
CONSTRUCTION
AGENCY
AMJ
3.3 Saudi Aramco Engineering Standard SAES-P-121 (Transformers and Reactors).
09/21/17
DATE: 3.4 Design Documents And Drawings
OPERATIONS
AFS
3.4.1 Electrical One Line Diagram, Loop-01 & Loop-02, feeder-4 S/S-46, AYC-E-
DATE:
09/21/17 107-sht.074 rev. 01
CONTROL NUMBER
VERIFICATION
3.4.2 Electrical One Line Diagram, Loop-04 & Loop-05, feeder-2 S/S-46, AYC-E-
EDSD
107-sht.075 rev. 01
DATE:
3.4.3 Electrical One Line Diagram, Sewage Lift Station-1 Package-2, AYC-E-107-
BY:
REVISIONCERTIFICATION
sht.288 rev.01
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
rev.01- as-built.
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
mission and accommodate manpower projected in the future. Under this BI, it is required
AYS
SAG
SAG
to construct new residential villas, apartment buildings, schools, community facilities, and
support facilities to achieve Saudi Aramco residential program.
In addition, it is requested to design new electrical power distribution system. It is planned
ISSUED FOR CONSTRUCTION
to design a new 115 kV gas insulated switchgear (GIS) substation that will interface with
National Grid 115 kV substation located at Half-moon bay via 2 underground cables.
DESCRIPTION
AS-BUILT
AS-BUILT
Moreover, the residential primary distribution system will operate at 13.8 kV through
looped pad-mounted SF6 switchgears, underground cables, and looped package
substations. A new double-ended 13.8 kV substations will be constructed to feed the
residential pad-mounted SF6 loops and all other facilities requires a 13.8 kV distribution
system such as the existing substation no. 16.
5.0 PROPOSED ELECTRICAL SYSTEM DESCRIPTION
JO/EWO
10-01382
10-01382
09/21/17 10-01382
This project will add substation no. 46 which consist of two buildings accommodating the
115 kV GIS switchgear and 13.8 kV substation feeding six 13.8 kV distribution loops.
07/24/17
06/28/15
DATE
The new electrical system will receive power via two (2) 115 kV underground cables from
NO.
REV
00
01
02
SEC. The 115 kV will be stepped down to the 13.8 kV via two (2) 115/13.8 kV transform-
DISCIPLINE
ENGINEER ers. The two transformers will supply power to the new 13.8 kV switchgear, at substation
SAG
DATE:
09/21/17 no. 46, which will be used to feed the power distribution loops next to the substation
PROJECT
ENGINEER services transformers.
JZM
DATE:
09/21/17 The scope of this job order, Package 2, is to supply and install the new 115 kV and 13.8
CERTIFIED
AMJ kV substations. The following equipment is related to ETAP study:
DATE:
09/21/17
One (1) 115 kV substation building and its service equipment.
CONSTRUCTION
AGENCY
AMJ
115 kV indoor GIS consisting of double bus, single breaker in Z shape configuration.
DATE:
09/21/17
Two (2) 115/13.8 kV, 50/67 MVA (ONAN/ONAF), 60Hz power transformers
OPERATIONS
AFS One (1) 13.8 kV substation building and its service equipment.
Four (4) 13.8 kV, 3000 A cable busses.
09/21/17
DATE:
CONTROL NUMBER
VERIFICATION
One (1) 13.8 kV, 3000 A, 40 kA for 2 sec double ended indoor metal clad switchgear.
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
15 kV power cables
AYS
AMJ
AMJ AMJ
Other packages, under different job orders, will be responsible for supplying and installing
AMJ
TAA
ENGG CERT
SAG
SAG
AS-BUILT
AS-BUILT
3-Phase Single-Line-Ground
JO/EWO
10-01382
10-01382
09/21/17 10-01382
Type Reference
I sym I asym I sym I asym
X/R X/R
07/24/17
06/28/15
DATE
00
01
02
DISCIPLINE
ENGINEER Maximum 15.5 20.0 19.4 17.5 6.2 17.8 Attachment 1A
SAG
DATE:
09/21/17
Ultimate 16.5 12.6 18.6 11.8 6.7 12.1 Attachment 1B
PROJECT
ENGINEER
All new electrical equipment such as switchgear, transformers, cables, and loads
JZM
09/21/17
DATE:
CERTIFIED data are based on NMR Data.
AMJ
DATE:
09/21/17 Cable lengths are based on the project cable and conduit schedule.
115 KV Incoming power cables to the GIS are assumed as 1/C 400 mm2, 1 km.
CONSTRUCTION
AGENCY
AMJ
DATE:
09/21/17 All tap changers of the transformer at all packaged substation are set one point
OPERATIONS
below the neutral point (at -2.5%).
AFS
09/21/17 7.0 ELECTRICAL SYSTEM STUDIES FOR BASE CASE
DATE:
CONTROL NUMBER
All power distribution loops are in the normal configuration and being fed from two
_____________________
ends. The loop is normally open at the package substation in the center for each of
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
Configuration
Revision Study case Output report
AYS
SAG
SAG
status
Base LF_NOR LF-NORMAL LF_NOR
Results
ISSUED FOR CONSTRUCTION
The study revealed that the system is healthy and confirming to SAES-P-100
requirements. For the generated ETAP study summary, one line diagram and study
DESCRIPTION
AS-BUILT
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
00
01
02
status
DISCIPLINE
ENGINEER Base LF_MIN_END A LF-MIN-END A LF_MIN END A
SAG
09/21/17
DATE:
PROJECT
Base LF_MIN_END B LF-MIN-END B LF_MIN END B
ENGINEER
JZM
Results
09/21/17
DATE:
CERTIFIED The study revealed that the system is healthy and confirming to SAES-P-100
AMJ
09/21/17 requirements.
DATE:
CONSTRUCTION
AGENCY
For the generated ETAP study summary, one line diagram and study alert, refer to
AMJ
09/21/17
Table 5, Attachment 2, 5, 6, 7 and 8 respectively.
DATE:
OPERATIONS 7.3 Load Flow Maximum Voltage Configuration
AFS
09/21/17
The utility is set at ultimate short circuit configuration.
DATE:
Network in normal configuration with all motors are disconnected.
CONTROL NUMBER
VERIFICATION
All power distribution loops are in the normal configuration and being fed from two
DATE:
BY:
ends.
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
Configuration
AMJ
TAA
ENGG CERT
SAG
SAG
Results
The study revealed that the system is healthy and confirming to SAES-P-100
ISSUED FOR CONSTRUCTION
requirements.
For the generated ETAP study summary, one line diagram and study alert, refer to
DESCRIPTION
AS-BUILT
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
00
01
02
DATE:
09/21/17 Loop 4A L86-PS301 13.8 99.98 98.57 98.41 99.98
CONSTRUCTION
AGENCY
AMJ
Loop 4A L86-PS308 13.8 99.95 98.46 98.45 99.95
09/21/17
DATE:
Loop 4A L86-PS309 13.8 99.95 98.45 98.46 99.95
OPERATIONS
AFS Loop 4A L86-PS315 13.8 99.98 98.4 98.58 99.99
09/21/17
DATE:
Loop 4B L86-PS316 13.8 99.99 98.59 98.4 99.99
CONTROL NUMBER
VERIFICATION
EDSD
APPROVAL/CERTIFICATION REQUIREMENTS,
_____________________
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
AMJ
AMJ AMJ
SAG
SAG
AS-BUILT
AS-BUILT
10-01382
10-01382
09/21/17 10-01382
00
01
02
DISCIPLINE
ENGINEER
o All power distribution loops are being fed from one end that is connected to bus
SAG
09/21/17 A of the main 13.8 kV switchgear at substation no. 46.
DATE:
PROJECT
ENGINEER
JZM Table 6: ETAP Model Setting-SC Ultimate (End A)
09/21/17
DATE: Configuration
CERTIFIED Revision Study case Output report
AMJ status
09/21/17
DATE: Base SC_ULT_END A SC.Ult SC_ULT_ENDA
CONSTRUCTION
AGENCY
AMJ Results
09/21/17
DATE:
OPERATIONS The study revealed that the system is healthy and confirming to SAES-P-100
AFS requirements.
09/21/17
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
Device
AMJ
TAA
ENGG CERT
SAG
SAG
208-046-SG-
2 13.8 30 48 31.5 40 64 Acceptable
301B
DESCRIPTION
AS-BUILT
AS-BUILT
For one line diagram and result summary refer to Attachment 11 and 12 respectively.
10-01382
10-01382
09/21/17 10-01382
00
01
02
301A
EDSD
208-046-SG-
2 13.8 30 48 31.5 40 64 Acceptable
301B
DATE:
BY:
For one line diagram and result summary refer to Attachment 13 and 14 respectively.
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
AFS
AYS
SAG
SAG
AS-BUILT
AS-BUILT
9.0 ATTACHMENTS
10-01382
09/21/17 10-01382
00
01
02
DATE:
09/21/17 Attachment 11 ETAP One Line Diagram for SC_ULT_END A
CONSTRUCTION
AGENCY
AMJ
Attachment 12 Short Circuit Summary Report for SC_ULT_END A
09/21/17
DATE:
OPERATIONS
Attachment 13 ETAP One Line Diagram for SC_ULT_END B
AFS
09/21/17
Attachment 14 Short Circuit Summary Report for SC_ULT_END B
DATE:
CONTROL NUMBER
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
_____________________
(DCC) NO. 10-01382-0004
o ETAP STUDY REPORT DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION