0.05
3 Switchgear Room
(50 Pa)
0.03
4 AHU Room
(30 Pa)
0.03
5 Battery Room
(30 Pa)
Note: The building pressure test was carried out on 29.08.2017 at 21C.
ZAULIYAH GAS PLANT PROJECT
Building Pressure Test Record Date: 28.08.2017
Measured Value AHEC PDO-CSU
S.No. Description
(kPa) Signature Signature
Note: The battery room pressure were fluctuating in between 0.01kPa to 0.02kPa. The building pressure tes
GAS PLANT PROJECT
e Test Record Date: 28.08.2017
Evidence
0.01kPa to 0.02kPa. The building pressure test was carried out on 28.08.2017
ZAULIYAH GAS PLANT PROJECT
Initial Operation Period Activities / Support Record
AHEC PDO-CSU PDO-Operation
S.No. Activities & Support
Signature Signature Signature
10 Completion of trainings.
Note:
S PLANT PROJECT
d Activities / Support Record
Justification
The test was carried out successfully on
14/08/2017 from 10:15AM to 10:30AM in
presence of PDO-CSU, PDO-Operation and
coordination with Marmul CCR and MAF. Refer
attachements.