DAILY ACTIVITY REPORT (MECHANICAL

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
1 CHP

CONVEYOR 2A &2B

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE

BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS
HOT AIR PATH

COLD AIR PATH

2 BOILER & ESP


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART

2 BOILER & ESP

ROTATING EQUIPMENTS
HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP

TG TO BOILER INTERCONNECTION
RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM
PIPE RACK

FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT


& STRUCTURALS

DISTRIBUTION PIPE LINES


COOLING
4 TOWER DRIFT ELIMINATORS & SPLASH
GUARDS

DECK RAILING WORK.


STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER

AUXILLARIES
5 TG BUILDING

FABRICATION &ERECTION OF PIPING

LUBE OIL SYSTEM

AC DUCTING WORK
STRUCTURAL

ERECTION OF EMBEDED PLATES &


OPENING
6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL

EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT FABRICATION &ERECTION OF PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 29
(HAZEMAG)
2 THERMAX 226
3 GPR 23
4 APT 12
5 SUVENDU SAHU 6
JOSEPH
6 8
CONSTRUCTIONS
REPORT (MECHANICAL- CPP) DATE-11.09.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW

Final welding of Vertical bracing in


progress. Erection of feeder breaker Same to continue
platform assembly is in progress.

Side Sheeting work & final welding in


progress Same to continue

Dismantling work is in progress with proper


precautions.One no.bent Column of Rework to continue
staircase removed and tie bracings being
removed.

Column grouting work completed. Same to continue


Alignment & Welding of walkway
completed. Erection of gallery completed. Same to continue
Alignment of Gallery is in progress.

No activity

Levelling of ramp for trussel erection


completed. Final welding of trussel TR-6 is Erection process to be taken
up.
under progress.

Assembly work of Structures started. same to continue

Pipe inserts at 17.5m level fabricated and same to continue


inserted

All fabrication scraps being


cut for use & house keeping
Final painting work in progress. work to continue. Painting
work to continue.

No activity
Completed
Completed

Completed
No activity

Completed

Insulation work at outlet nozzle of ESP


completed.Insulation of PA duct ,pipes & Same to continue
bottom portion of economiser casing
connecting to MDC is in progress.

No activity

Final painting work in progress.Erection of


monorail support structure & monorail for Same to continue
ID FAN is in progress.

External hydrotest completed sucessfully in


presence of Deputy Director of Factories welding of supporting
and Boilers. Welding of supporting structures for pipes to
structures in progress.Erection of steam continue.
vent support taken up.

Erection of ID Fan completed & alignment is


in progress. ID fan foundation modification
in progress & foundation work for PA FAN Same to continue
completed & SA FAN in progress. Erection of
base frame of PA FAN is in progress.
Bed ash cooler outlet duct pre assembly is
in progress. Fabrication work of SA fan
delivery line in progress. Pre assembly of Same to continue
wind box completed & erection is in
progress.

Erection & welding of secondary air duct Same to continue


fitting work in progress .

Welding work at ID FAN ducting in progress.


Welding & Erection of economiser casing in Same to continue
progress.Connecting duct from boiler to
economiser work in progress.

MDC welding in progress. Erection &


welding of MDC Bypass to ash seperator is Same to continue
in progress. Fixing of ceramic cyclones pipes
in MDC is in progress.

Insulation work to be taken up.

Assembly of pent house structure taken


up .Emitting electrode erection in progress. Same to continue
Pre assembly & welding of 1st,3rd fields
Hopper about to be completed.

Fabrication work taken up after arranging


for steel from various places same to continue
Both Raw water pump sole plates Assembly work to be taken
positioned,levelled,grouted & curing is up.
under progress.

Erection &welding of longitudinal tie is in same to continue


progress.

Erection of cooling water pump(CW) base No activity


frame completed.

No activity as monitoring basin work yet to


start.

No activity

Fire fighting pumps have reached Fixing of Fire Sensor Cables


transporters Godown.GPR informed and and Conduits to start.
freight clearance by GPR is awaited

Clearing of the Cooling Tower materials for Foundation layout to start.


foundation layout is completed.
Fabrication of remaining pipe racks
completed & painting work is in progress.
Erection of pipe rack supporting column
near boiler is in progress.alignment of pipe Same to continue
rack near clarified water pump house
completed. Fabrication of remaining cable
rack is in progress.Painting of cable rack
started.

Welding of bend at cooling tower puddle


pipe started. Assembly of suction line of CW
inlet started. Fabrication of reducers for CW
Same to continue
line completed & painting is in progress.
Welding of flanges to puddle pipes in
cooling tower to be taken up.

All materials shited close to Cooling Tower Same to continue

No activity Shifting to continue

No activity Shifting to continue

Railing work at deck nearing completion.


Final welding of staircase & Fixing of
chequered plates for steps completed.Fixing
of handrailing to be taken up.

TG Floor being Cleaned to start Erection Same to Continue


Activities of Turbine
No activity

Expansion work of tube end is in progress &


welding of vaccum pipes to condenser is in Same to continue
progress.

Positioning & alignment of condensate Same to continue


float tank is under progress.

Fabrication of boiler feed pump delivery No activity


line in progress.

Fabrication & erection of lube oil pipe line


& pipe supports is in progress. Same to continue

Insulation work of 10.5 M control room roof


completed.Erection of AC duct & rapping of Same to continue
insulation is in progress.
Final welding & fixing of gratings work is in Same to continue
progress.

No activity No activity

No activity

No activity

Completed

No activity

No activity

Erection of purlins completed & levelling in Same to continue


progress.

No activity
11.09.13
REMARK

Hoppers, railings & chutes for feeder


breaker awaited at site. Party has been
followed up.

All materials received at site

Follow up on for Short Post and


stringers for inclined ramp.
Civil foundation work yet to be
completed

Trussel fabrication completed & gallery


to be received.party not despatching
further materials despite of repeated
reminders. Rigorous followup required
as party is not able to provide any
evidence of work in progress.

Civil work yet to be completed


Refractory work to be taken up during
the next week.
Balance Erection work awaiting
completion of fan foundation.

Erection work could not be started due


to civil clearance.
Plastering work of Raw water pump
house is in progress which will be
completed and pump erection work
shall start.

Alignment of base frame to be taken


after erection of suction line to pump.

Pipe fittings awaited at site.

Cables & conduits of fire sensors at TG


Building 10.5M control room roof have
reached Site

Civil foundation work to


start.fabricated tank awaited at site
Three nos. of vehicle containing 1400
dia & 1000 dia Pipes received at site &
unloading is in progress.

Civil work yet to be completed &


mobilisation to be started by
Paltech.Paltech to mobilise site by
15/9/13.

same as above

same as above

West side railing work of cooling tower


staircase to be taken up after
completion of deck railing.
Work stopped to give way for
completion of civil work.

Erection Work to start by 16/9/13

All other available equipments have


been placed in position.

IBR Approval awaited

Materials indented for supply of


cooling water to A.C.Units
Erection of remaining small pumps to
be taken up during erection of panels

Sheeting work to be done after


completion of purlin Erection