Академический Документы
Профессиональный Документы
Культура Документы
TRANSFER HOUSE 1
TRANSFER TOWER 2
CONVEYOR 1A & 1B
CONVEYOR 4A & 4B
CONVEYOR 5A & 5B
BOILER -I
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
BOILER -II
STRUCTURAL
PRESSURE PART
2 BOILER & ESP
ROTATING EQUIPMENTS
HOT AIR DUCTING
FUEL PATH
INSULATION
ESP
RAW WATER PUMP HOUSE
COMPRESSOR HOUSE
3 LP PIPING
FIRE FIGHTING SYSTEM
LDO SYSTEM
PIPE RACK
FABRICATION &ERECTION OF
PIPING
COOLING
4 DISTRIBUTION PIPE LINES
TOWER
DRIFT ELIMINATORS & SPLASH
GUARDS
STRUCTURAL
TURBINE
TURBOGENERATOR
CONDENSER
AUXILLARIES
5 TG BUILDING
FABRICATION &ERECTION OF
PIPING
AC DUCTING WORK
STRUCTURAL
EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
FABRICATION &ERECTION OF
PIPING
CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 22
(HAZEMAG)
2 THERMAX 240
3 GPR 19
4 APT 16
5 SUVENDU SAHU 3
JOSEPH
6 7
CONSTRUCTIONS
PORT (MECHANICAL- CPP) DATE-29.08.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW
Approach of road to be
Levelling of ramp for trussel erection is made for Marching the
in progress. Final welding of trussel TR-6 Crane for erection of
is under progress. Trussel.Already made
passage to be widened.
No activity
No activity
Completed
Completed
Controlled Cooling of Refractory to Controlled Cooling of
continue Refractory to continue
Completed
No activity
No activity
No activity
No activity No activity
No activity No activity
No activity No activity
No activity No activity
No activity
No activity
Balance condenser tubes received at Insertion of condenser tubes
site & cutting to required length is under to be taken up.
progress.
No activity
No activity
Completed
No activity No activity
No activity No activity
same as above
same as above
All other available equipments
have been placed in position.
Erection of remaining small pumps
to be taken up during erection of
panels