DAILY ACTIVITY REPORT (MECHANICAL- CP

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP CONVEYOR 2A &2B


CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE

BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART
2 BOILER & ESP

ROTATING EQUIPMENTS
HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP
RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM
PIPE RACK

FABRICATION &ERECTION OF
PIPING

FANS ,GEAR BOXES,PROPELLER


SHAFT & STRUCTURALS

COOLING
4 DISTRIBUTION PIPE LINES
TOWER
DRIFT ELIMINATORS & SPLASH
GUARDS

DECK RAILING WORK.

STRUCTURAL

TURBINE

TURBOGENERATOR
CONDENSER

AUXILLARIES
5 TG BUILDING

FABRICATION &ERECTION OF
PIPING

LUBE OIL SYSTEM

AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES &


OPENING
6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE


STRUCTURAL

EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
FABRICATION &ERECTION OF
PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 22
(HAZEMAG)
2 THERMAX 240
3 GPR 19
4 APT 16
5 SUVENDU SAHU 3
JOSEPH
6 7
CONSTRUCTIONS
PORT (MECHANICAL- CPP) DATE-29.08.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW

Vertical bracing erection & welding in Same to continue


progress.

Side Sheeting work & final welding in


progress Same to continue

Structural materials received &


unloading is under progress.

Bracket & Idler erection work in Same to continue


progress

Alignment & Welding of walkway is in


progress. Erection of gallery completed. Same to continue
Alignment of Gallery is in progress.
No activity

Approach of road to be
Levelling of ramp for trussel erection is made for Marching the
in progress. Final welding of trussel TR-6 Crane for erection of
is under progress. Trussel.Already made
passage to be widened.

No activity

No activity

All fabrication scraps being


cut for use &house keeping
Final painting work in progress. work to continue. Painting
work to continue.

No activity Same to continue


Completed

Completed

Completed
Controlled Cooling of Refractory to Controlled Cooling of
continue Refractory to continue

Completed

Insulation work of outlet nozzle of ESP- Same to continue


1 & MDC is in progress.

No activity

Final painting work taken up. Final


welding of connecting beams between Same to continue
Boiler-1 & Boiler-2 is in progress.

Internal Hydro test in progress. Erection


of non integral piping support in Same to continue
progress.

Erection of ID Fan taken up. ID fan


foundation modification in progress & Same to continue
foundation work for PA & SA FAN in
progress.
Bed ash cooler outlet duct pre assembly
taken up. Fabrication work of SA fan Same to continue
delivery line in progress

Erection & welding of secondary air duct Same to continue


fitting work in progress .

Welding work at ID FAN ducting in


progress. Welding & Erection of
economiser casing in Same to continue
progress.Connecting duct from boiler to
economiser work in progress.

MDC welding in progress. Erection of


MDC Bypass to ash seperator is in Same to continue
progress.

No activity

Emitting electrode erection in progress.


Hopper erection completed & welding is Same to continue
in progress.
clearing of raw water pump
Pipe assembly & welding is in progress. house area for starting of
vertical pump erection.

Erection of purlin is in progress. Same to continue

Roof sheeting work & Erection of side Same to continue


runner is in progress.

No activity as monitoring basin work yet


to start.

No activity

No activity No activity

Clearing of the Cooling


No activity Tower materials for
foundation layout to start.
Fabrication of remaining pipe racks is Same to continue
under progress.

1400mm CW bend painting in


progress. Fabrication of pipe supports
for CW Pump inlet is in progress. Same to continue
Erection of 1400mm bend to be taken
up near CW Pump house.

No activity No activity

No activity No activity

No activity No activity

Fixing of hand railing work in progress. Same to continue

Erection & welding of supporting beams Same to continue


for staircase in progress.

No activity

No activity
Balance condenser tubes received at Insertion of condenser tubes
site & cutting to required length is under to be taken up.
progress.

Positioning & alignment of


Condensate float tank has been erected condensate float tank to be
&kept in 15.5M floor. completed.

Fabrication of boiler feed pump delivery Same to continue


line in progress.

Fabrication &erection of lube oil pipe


line is in progress. Same to continue

Insulation work of 10.5 M control room


roof completed.Erection of AC duct & Same to continue
rapping of insulation is in progress.

Final welding work is in progress. Same to continue

All insert plates & edge angles for No activity


openings have been fixed in position.

No activity

No activity
Completed

No activity No activity

DM Water production for Boiler -2 Same to continue


internal hydro test.

No activity No activity

Hand railing work in progress. Same to continue


-29.08.13
REMARK

Hoppers, railings & chutes for


feeder breaker awaited at site.
Party has been followed up.

All matreials received at site

16 TON materials not despatched


by party despite of repeated
reminders. HAZEMAG has been
chased up to despatch the rework
materials post release of
payment.
Civil foundation work yet to be
completed

Trussel fabrication completed &


gallery to be received.party not
despatching further materials
despite of repeated reminders.
Rigorous followup required as
party is not able to provide any
evidence of work in progress.

Material not received at site

Civil work yet to be completed


Balance Erection work awaiting
completion of fan foundation.

Insulation work to start after


hydro test.
Follow up on for cables & conduits
of fire sensors at TG Building
10.5M control room roof.

Civil foundation work to


start.fabricated tank awaited at
site
Civil work yet to be completed &
mobilisation to be started by
Paltech

same as above

same as above
All other available equipments
have been placed in position.
Erection of remaining small pumps
to be taken up during erection of
panels

Purlin erection to start after gable


wall completion.