WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.1
POUR-1 10-Oct-10 11-Nov-10 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1140 Column Starter Marking 10-Oct-10 A 11-Oct-10 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.2
POUR-2 30-Oct-10 28-Nov-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1270 Column Starter Marking 30-Oct-10 A 31-Oct-10 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.3
POUR-3 25-Oct-10 23-Nov-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1400 Column Starter Marking 25-Oct-10 A 26-Oct-10 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.4
POUR-4 17-Nov-10 16-Dec-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1530 Column Starter Marking 17-Nov-10 18-Nov-10 2
A A
A1540 Columns - Re-Bar 19-Nov-10 25-Nov-10 7
A A
A1550 Columns - Formwork 21-Nov-10 30-Nov-10 10
A A
A1560 Columns - Casting 23-Nov-10 29-Nov-10 7
A A
A1570 Shear Wall / Core Wall / Ret. 19-Nov-10 28-Nov-10 10
Wall Re-Bar A A
A1580 Shear Wall / Core Wall / Ret. 22-Nov-10 01-Dec-10 10
Wall Formwork A A
A1590 Shear Wall / Core Wall / Ret. 25-Nov-10 01-Dec-10 7
Wall Casting A A
A1600 Staircase - Formwork 30-Nov-10 01-Dec-10 2
A A
A1610 Staircase - Re-Bar 02-Dec-10 03-Dec-10 2
A A
A1620 Staircase - Casting 04-Dec-10 04-Dec-10 1
A A
A1630 Slab / Beams - Formwork 27-Nov-10 11-Dec-10 15
A A
A1640 Slab / Beams - Re-Bar 05-Dec-10 14-Dec-10 10
A A
A1650 Slab / Beams Checking & 15-Dec-10 16-Dec-10 2
Casting A A
sujmall-1.1.2.1.1.5
POUR-5 27-Dec-10 25-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1660 Column Starter Marking 27-Dec-10 28-Dec-10 2
A A
(c) Primavera Systems, Inc. Page 5 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.6
POUR-6 30-Dec-10 28-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1790 Column Starter Marking 30-Dec-10 31-Dec-10 2
A A
A1800 Columns - Re-Bar 01-Jan-11 A 07-Jan-11 A 7
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.7
POUR-7 12-Mar-11 10-Apr-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1920 Column Starter Marking 12-Mar-11 13-Mar-11 2
A A
A1930 Columns - Re-Bar 14-Mar-11 20-Mar-11 7
A A
A1940 Columns - Formwork 16-Mar-11 25-Mar-11 10
A A
A1950 Columns - Casting 18-Mar-11 24-Mar-11 7
A A
A1960 Shear Wall / Core Wall / Ret. 14-Mar-11 23-Mar-11 10
Wall Re-Bar A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.1.8
POUR-8 23-Apr-11 22-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2050 Column Starter Marking 23-Apr-11 A 24-Apr-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.1
POUR-1 23-Nov-10 25-Dec-10 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2180 Column Starter Marking 23-Nov-10 24-Nov-10 2
A A
A2190 Columns - Re-Bar 25-Nov-10 01-Dec-10 7
A A
A2200 Columns - Formwork 27-Nov-10 06-Dec-10 10
A A
A2210 Columns - Casting 29-Nov-10 05-Dec-10 7
A A
A2220 Shear Wall / Core Wall / Ret. 25-Nov-10 04-Dec-10 10
Wall Re-Bar A A
A2230 Shear Wall / Core Wall / Ret. 28-Nov-10 07-Dec-10 10
Wall Formwork A A
A2240 Shear Wall / Core Wall / Ret. 01-Dec-10 07-Dec-10 7
Wall Casting A A
A2250 Staircase - Formwork 04-Dec-10 05-Dec-10 2
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.2
POUR-2 14-Dec-10 12-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2310 Column Starter Marking 14-Dec-10 15-Dec-10 2
A A
A2320 Columns - Re-Bar 16-Dec-10 22-Dec-10 7
A A
A2330 Columns - Formwork 18-Dec-10 27-Dec-10 10
A A
A2340 Columns - Casting 20-Dec-10 26-Dec-10 7
A A
A2350 Shear Wall / Core Wall / Ret. 16-Dec-10 25-Dec-10 10
Wall Re-Bar A A
A2360 Shear Wall / Core Wall / Ret. 19-Dec-10 28-Dec-10 10
Wall Formwork A A
A2370 Shear Wall / Core Wall / Ret. 22-Dec-10 28-Dec-10 7
Wall Casting A A
A2380 Staircase - Formwork 25-Dec-10 26-Dec-10 2
A A
A2390 Staircase - Re-Bar 27-Dec-10 28-Dec-10 2
A A
A2400 Staircase - Casting 29-Dec-10 29-Dec-10 1
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.3
POUR-3 13-Dec-10 11-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2440 Column Starter Marking 13-Dec-10 14-Dec-10 2
A A
A2450 Columns - Re-Bar 15-Dec-10 21-Dec-10 7
A A
A2460 Columns - Formwork 17-Dec-10 26-Dec-10 10
A A
A2470 Columns - Casting 19-Dec-10 25-Dec-10 7
A A
A2480 Shear Wall / Core Wall / Ret. 15-Dec-10 24-Dec-10 10
Wall Re-Bar A A
A2490 Shear Wall / Core Wall / Ret. 18-Dec-10 27-Dec-10 10
Wall Formwork A A
A2500 Shear Wall / Core Wall / Ret. 21-Dec-10 27-Dec-10 7
Wall Casting A A
A2510 Staircase - Formwork 26-Dec-10 27-Dec-10 2
A A
A2520 Staircase - Re-Bar 28-Dec-10 29-Dec-10 2
A A
A2530 Staircase - Casting 30-Dec-10 30-Dec-10 1
A A
A2540 Slab / Beams - Formwork 23-Dec-10 06-Jan-11 A 15
A
A2550 Slab / Beams - Re-Bar 31-Dec-10 09-Jan-11 A 10
A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.4
POUR-4 15-Jan-11 13-Feb-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2570 Column Starter Marking 15-Jan-11 A 16-Jan-11 A 2
sujmall-1.1.2.1.2.5
POUR-5 19-Feb-11 20-Mar-11 30 0
A A
(c) Primavera Systems, Inc. Page 12 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.6
POUR-6 19-Feb-11 20-Mar-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2830 Column Starter Marking 19-Feb-11 20-Feb-11 2
A A
A2840 Columns - Re-Bar 21-Feb-11 27-Feb-11 7
A A
(c) Primavera Systems, Inc. Page 13 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.7
POUR-7 10-May-11 08-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2960 Column Starter Marking 10-May-11 11-May-11 2
A A
A2970 Columns - Re-Bar 12-May-11 18-May-11 7
A A
A2980 Columns - Formwork 14-May-11 23-May-11 10
A A
A2990 Columns - Casting 16-May-11 22-May-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.1.2.8
POUR-8 21-May-11 19-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3090 Column Starter Marking 21-May-11 22-May-11 2
A A
A3100 Columns - Re-Bar 23-May-11 29-May-11 7
A A
A3110 Columns - Formwork 25-May-11 03-Jun-11 A 10
A
A3120 Columns - Casting 27-May-11 02-Jun-11 A 7
A
A3130 Shear Wall / Core Wall / Ret. 23-May-11 01-Jun-11 A 10
Wall Re-Bar A
A3140 Shear Wall / Core Wall / Ret. 26-May-11 04-Jun-11 A 10
Wall Formwork A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.1
POUR-1 25-Jan-11 26-Feb-11 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3220 Column Starter Marking 25-Jan-11 A 26-Jan-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.2
POUR-2 11-May-11 09-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3350 Column Starter Marking 11-May-11 12-May-11 2
A A
A3360 Columns - Re-Bar 13-May-11 19-May-11 7
A A
A3370 Columns - Formwork 15-May-11 24-May-11 10
A A
A3380 Columns - Casting 17-May-11 23-May-11 7
A A
A3390 Shear Wall / Core Wall / Ret. 13-May-11 22-May-11 10
Wall Re-Bar A A
A3400 Shear Wall / Core Wall / Ret. 16-May-11 25-May-11 10
Wall Formwork A A
A3410 Shear Wall / Core Wall / Ret. 19-May-11 25-May-11 7
Wall Casting A A
A3420 Staircase - Formwork 21-May-11 04-Jun-11 A 15
A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.3
POUR-3 04-Feb-11 05-Mar-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3480 Column Starter Marking 04-Feb-11 05-Feb-11 2
A A
A3490 Columns - Re-Bar 06-Feb-11 12-Feb-11 7
A A
A3500 Columns - Formwork 08-Feb-11 17-Feb-11 10
A A
A3510 Columns - Casting 10-Feb-11 16-Feb-11 7
A A
A3520 Shear Wall / Core Wall / Ret. 06-Feb-11 15-Feb-11 10
Wall Re-Bar A A
A3530 Shear Wall / Core Wall / Ret. 09-Feb-11 18-Feb-11 10
Wall Formwork A A
A3540 Shear Wall / Core Wall / Ret. 12-Feb-11 18-Feb-11 7
Wall Casting A A
A3550 Staircase - Formwork 17-Feb-11 18-Feb-11 2
A A
A3560 Staircase - Re-Bar 19-Feb-11 20-Feb-11 2
A A
A3570 Staircase - Casting 21-Feb-11 21-Feb-11 1
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.4
POUR-4 17-Apr-11 16-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3610 Column Starter Marking 17-Apr-11 A 18-Apr-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.5
POUR-5 06-Apr-11 05-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3740 Column Starter Marking 06-Apr-11 A 07-Apr-11 A 2
sujmall-1.1.2.2.1.6
POUR-6 13-Apr-11 12-May-11 30 0
A A
(c) Primavera Systems, Inc. Page 20 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.1.7
POUR-7 14-Jun-11 13-Jul-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4000 Column Starter Marking 14-Jun-11 A 15-Jun-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.2.1
POUR-A 26-Jun-11 28-Jul-11 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4260 Column Starter Marking 26-Jun-11 A 27-Jun-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.2.3
POUR-C 21-Jun-11 20-Jul-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4520 Column Starter Marking 21-Jun-11 A 22-Jun-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.2.5
POUR-E 28-Aug-11 26-Sep-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4780 Column Starter Marking 28-Aug-11 29-Aug-11 2
A A
A4790 Columns - Re-Bar 30-Aug-11 05-Sep-11 7
A A
A4800 Columns - Formwork 01-Sep-11 10-Sep-11 10
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.2.6
POUR-F 13-Aug-11 11-Sep-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4910 Column Starter Marking 13-Aug-11 14-Aug-11 2
A A
A4920 Columns - Re-Bar 15-Aug-11 21-Aug-11 7
A A
A4930 Columns - Formwork 17-Aug-11 26-Aug-11 10
A A
A4940 Columns - Casting 19-Aug-11 25-Aug-11 7
A A
A4950 Shear Wall / Core Wall / Ret. 15-Aug-11 24-Aug-11 10
Wall Re-Bar A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.2.7
POUR-G 25-Oct-11 23-Nov-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5040 Column Starter Marking 25-Oct-11 A 26-Oct-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.3.1
POUR-A 27-Aug-11 18-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5170 Column Starter Marking 27-Aug-11 28-Aug-11 2
A A
A5180 Columns - Re-Bar 29-Aug-11 04-Sep-11 7
A A
A5190 Columns - Formwork 30-Aug-11 08-Sep-11 10
A A
A5200 Columns - Casting 31-Aug-11 04-Sep-11 5
A A
A5210 Shear Wall / Core Wall Re-Bar 29-Aug-11 07-Sep-11 10
A A
A5220 Shear Wall / Core Wall 01-Sep-11 10-Sep-11 10
Formwork A A
A5230 Shear Wall / Core Wall Casting 04-Sep-11 10-Sep-11 7
A A
A5240 Slab / Beams - Formwork 03-Sep-11 14-Sep-11 12
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.3.2
POUR-B 03-Sep-11 25-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5270 Column Starter Marking 03-Sep-11 04-Sep-11 2
A A
A5280 Columns - Re-Bar 05-Sep-11 11-Sep-11 7
A A
A5290 Column Formwork 06-Sep-11 15-Sep-11 10
A A
A5300 Column Concreting 07-Sep-11 11-Sep-11 5
A A
A5310 Shear Wall / Core Wall Re-Bar 05-Sep-11 14-Sep-11 10
A A
A5320 Shear Wall / Core Wall 08-Sep-11 17-Sep-11 10
Formwork A A
A5330 Shear Wall / Core Wall Casting 11-Sep-11 17-Sep-11 7
A A
A5340 Slab / Beams Formwork 10-Sep-11 21-Sep-11 12
A A
A5350 Slab / Beams Re-Bar 17-Sep-11 23-Sep-11 7
A A
A5360 Slab / Beams Checking & 24-Sep-11 25-Sep-11 2
Casting A A
sujmall-1.1.2.2.3.3
POUR-C 04-Sep-11 26-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5370 Column Starter Marking 04-Sep-11 05-Sep-11 2
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.3.4
POUR-D 22-Sep-11 19-Oct-11 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5470 Column Starter Marking 22-Sep-11 23-Sep-11 2
A A
A5480 Column Re-Bar 24-Sep-11 30-Sep-11 7
A A
A5490 Column Formwork 25-Sep-11 04-Oct-11 A 10
A
A5500 Column Concreting 26-Sep-11 05-Oct-11 A 10
A
A5510 Shear Wall / Core Wall Re-Bar 24-Sep-11 03-Oct-11 A 10
A
A5520 Shear Wall / Core Wall 27-Sep-11 06-Oct-11 A 10
Formwork A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.3.5
POUR-E 28-Sep-11 20-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5570 Column Starter Marking 28-Sep-11 29-Sep-11 2
A A
A5580 Column Re-Bar 30-Sep-11 06-Oct-11 A 7
A
A5590 Column Formwork 01-Oct-11 A 10-Oct-11 A 10
sujmall-1.1.2.2.3.6
POUR-F 02-Oct-11 24-Oct-11 23 0
A A
(c) Primavera Systems, Inc. Page 32 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.3.7
POUR-G 09-Nov-11 01-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5770 Column Starter Marking 09-Nov-11 10-Nov-11 2
A A
A5780 Column Re-Bar 11-Nov-11 17-Nov-11 7
A A
A5790 Column Formwork 12-Nov-11 21-Nov-11 10
A A
A5800 Column Concreting 13-Nov-11 17-Nov-11 5
A A
A5810 Shear Wall / Core Wall Re-Bar 11-Nov-11 20-Nov-11 10
A A
(c) Primavera Systems, Inc. Page 33 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.4.1
POUR-A 04-Oct-11 26-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5870 Column Starter Marking 04-Oct-11 A 05-Oct-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.4.2
POUR-B 27-Sep-11 19-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5970 Column Starter Marking 27-Sep-11 28-Sep-11 2
A A
A5980 Columns - Re-Bar 29-Sep-11 05-Oct-11 A 7
A
A5990 Column Formwork 30-Sep-11 09-Oct-11 A 10
A
A6000 Column Concreting 01-Oct-11 A 05-Oct-11 A 5
sujmall-1.1.2.2.4.3
POUR-C 22-Oct-11 13-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6070 Column Starter Marking 22-Oct-11 A 23-Oct-11 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.4.4
POUR-D 04-Nov-11 01-Dec-11 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6170 Column Starter Marking 04-Nov-11 05-Nov-11 2
A A
A6180 Column Re-Bar 06-Nov-11 12-Nov-11 7
A A
A6190 Column Formwork 07-Nov-11 16-Nov-11 10
A A
A6200 Column Concreting 08-Nov-11 18-Nov-11 11
A A
A6210 Shear Wall / Core Wall Re-Bar 06-Nov-11 15-Nov-11 10
A A
A6220 Shear Wall / Core Wall 09-Nov-11 18-Nov-11 10
Formwork A A
A6230 Shear Wall / Core Wall Casting 12-Nov-11 18-Nov-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.4.5
POUR-E 22-Oct-11 13-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6270 Column Starter Marking 22-Oct-11 A 23-Oct-11 A 2
sujmall-1.1.2.2.4.6
POUR-F 26-Oct-11 17-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.4.7
POUR-G 03-Dec-11 25-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6470 Column Starter Marking 03-Dec-11 04-Dec-11 2
A A
A6480 Column Re-Bar 05-Dec-11 11-Dec-11 7
A A
A6490 Column Formwork 06-Dec-11 15-Dec-11 10
A A
A6500 Column Concreting 07-Dec-11 11-Dec-11 5
A A
A6510 Shear Wall / Core Wall Re-Bar 05-Dec-11 14-Dec-11 10
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.5.1
POUR-A 26-Nov-11 18-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6570 Column Starter Marking 26-Nov-11 27-Nov-11 2
A A
A6580 Columns - Re-Bar 28-Nov-11 04-Dec-11 7
A A
A6590 Columns - Formwork 29-Nov-11 08-Dec-11 10
A A
A6600 Columns - Casting 30-Nov-11 04-Dec-11 5
A A
A6610 Shear Wall / Core Wall Re-Bar 28-Nov-11 07-Dec-11 10
A A
A6620 Shear Wall / Core Wall 01-Dec-11 10-Dec-11 10
Formwork A A
A6630 Shear Wall / Core Wall Casting 04-Dec-11 10-Dec-11 7
A A
A6640 Slab / Beams - Formwork 03-Dec-11 14-Dec-11 12
A A
A6650 Slab / Beams - Re-Bar 10-Dec-11 16-Dec-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.5.2
POUR-B 21-Oct-11 12-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6670 Column Starter Marking 21-Oct-11 A 22-Oct-11 A 2
sujmall-1.1.2.2.5.3
POUR-C 15-Nov-11 07-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6770 Column Starter Marking 15-Nov-11 16-Nov-11 2
A A
A6780 Columns - Re-Bar 17-Nov-11 23-Nov-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.5.4
POUR-D 17-Dec-11 13-Jan-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6870 Column Starter Marking 17-Dec-11 18-Dec-11 2
A A
A6880 Column Re-Bar 19-Dec-11 25-Dec-11 7
A A
A6890 Column Formwork 20-Dec-11 29-Dec-11 10
A A
A6900 Column Concreting 21-Dec-11 30-Dec-11 10
A A
A6910 Shear Wall / Core Wall Re-Bar 19-Dec-11 28-Dec-11 10
A A
A6920 Shear Wall / Core Wall 22-Dec-11 31-Dec-11 10
Formwork A A
A6930 Shear Wall / Core Wall Casting 25-Dec-11 31-Dec-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.5.5
POUR-E 15-Nov-11 07-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6970 Column Starter Marking 15-Nov-11 16-Nov-11 2
A A
A6980 Column Re-Bar 17-Nov-11 23-Nov-11 7
A A
A6990 Column Formwork 18-Nov-11 27-Nov-11 10
A A
A7000 Column Concreting 19-Nov-11 23-Nov-11 5
A A
A7010 Shear Wall / Core Wall Re-Bar 17-Nov-11 26-Nov-11 10
A A
A7020 Shear Wall / Core Wall 20-Nov-11 29-Nov-11 10
Formwork A A
A7030 Shear Wall / Core Wall Casting 23-Nov-11 29-Nov-11 7
A A
A7040 Slab / Beams Formwork 22-Nov-11 03-Dec-11 12
A A
A7050 Slab / Beams Re-Bar 29-Nov-11 05-Dec-11 7
A A
A7060 Slab / Beams Checking & 06-Dec-11 07-Dec-11 2
Casting A A
sujmall-1.1.2.2.5.6
POUR-F 19-Nov-11 11-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.2.5.7
POUR-G 27-Dec-11 18-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7170 Column Starter Marking 27-Dec-11 28-Dec-11 2
A A
A7180 Column Re-Bar 29-Dec-11 04-Jan-12 A 7
A
A7190 Column Formwork 30-Dec-11 08-Jan-12 A 10
A
A7200 Column Concreting 31-Dec-11 04-Jan-12 A 5
A
A7210 Shear Wall / Core Wall Re-Bar 29-Dec-11 07-Jan-12 A 10
A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.3.2.1
POUR-A 20-Dec-11 11-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7270 Column Starter Marking 20-Dec-11 21-Dec-11 2
A A
A7280 Columns - Re-Bar 22-Dec-11 28-Dec-11 7
A A
A7290 Columns - Formwork 23-Dec-11 01-Jan-12 A 10
A
A7300 Columns - Casting 24-Dec-11 28-Dec-11 5
A A
A7310 Shear Wall / Core Wall Re-Bar 22-Dec-11 31-Dec-11 10
A A
A7320 Shear Wall / Core Wall 25-Dec-11 03-Jan-12 A 10
Formwork A
A7330 Shear Wall / Core Wall Casting 28-Dec-11 03-Jan-12 A 7
A
A7340 Slab / Beams - Formwork 27-Dec-11 07-Jan-12 A 12
A
A7350 Slab / Beams - Re-Bar 03-Jan-12 A 09-Jan-12 A 7
sujmall-1.1.2.3.2.2
POUR-B 14-Nov-11 06-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7370 Column Starter Marking 14-Nov-11 15-Nov-11 2
A A
(c) Primavera Systems, Inc. Page 45 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.3.2.3
POUR-C 09-Dec-11 31-Jan-12 54 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7470 Column Starter Marking 09-Dec-11 10-Dec-11 2
A A
A7480 Columns - Re-Bar 11-Dec-11 17-Dec-11 7
A A
A7490 Column Formwork 12-Dec-11 21-Dec-11 10
A A
A7500 Column Concreting 13-Dec-11 17-Dec-11 5
A A
A7510 Shear Wall / Core Wall Re-Bar 11-Dec-11 20-Dec-11 10
A A
A7520 Shear Wall / Core Wall 14-Dec-11 23-Dec-11 10
Formwork A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.3.2.4
POUR-D 29-Jan-12 25-Feb-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7570 Column Starter Marking 29-Jan-12 A 30-Jan-12 A 2
sujmall-1.1.2.3.2.5
POUR-E 09-Dec-11 05-Jan-12 28 0
A A
(c) Primavera Systems, Inc. Page 47 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.3.2.6
POUR-F 13-Dec-11 09-Jan-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7770 Column Starter Marking 13-Dec-11 14-Dec-11 2
A A
A7780 Column Re-Bar 15-Dec-11 21-Dec-11 7
A A
A7790 Column Formwork 16-Dec-11 25-Dec-11 10
A A
A7800 Column Concreting 17-Dec-11 26-Dec-11 10
A A
A7810 Shear Wall / Core Wall Re-Bar 15-Dec-11 24-Dec-11 10
A A
(c) Primavera Systems, Inc. Page 48 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.3.2.7
POUR-G 20-Jan-12 16-Feb-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7870 Column Starter Marking 20-Jan-12 A 21-Jan-12 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.1
POUR-A 13-Jan-12 04-Feb-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13910 Shear Wall / Core Wall Re-Bar 15-Jan-12 A 24-Jan-12 A 10
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.2
POUR-B 06-Jan-12 28-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8150 Column Starter Marking 06-Jan-12 A 07-Jan-12 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.3
POUR-C 02-Jan-12 24-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8250 Column Starter Marking 02-Jan-12 A 03-Jan-12 A 2
sujmall-1.1.2.4.1.4
POUR-D 27-Feb-12 20-Mar-12 23 0
A A
(c) Primavera Systems, Inc. Page 52 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.5
POUR-E 07-Jan-12 29-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8450 Column Starter Marking 07-Jan-12 A 08-Jan-12 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.6
POUR-F 11-Jan-12 02-Feb-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8550 Column Starter Marking 11-Jan-12 A 12-Jan-12 A 2
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.4.1.7
POUR-G 18-Feb-12 11-May-12 84 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8650 Column Starter Marking 18-Feb-12 19-Feb-12 2
A A
A8660 Column Re-Bar 20-Feb-12 26-Feb-12 7
A A
A8670 Column Formwork 21-Feb-12 01-Mar-12 10
A A
A8680 Column Concreting 22-Feb-12 26-Feb-12 5
A A
A8690 Shear Wall / Core Wall Re-Bar 20-Feb-12 29-Feb-12 10
A A
A8700 Shear Wall / Core Wall 23-Feb-12 03-Mar-12 10
Formwork A A
A8710 Shear Wall / Core Wall Casting 26-Feb-12 03-Mar-12 7
A A
A8720 Slab / Beams Formwork 25-Feb-12 07-Mar-12 12
A A
A8730 Slab / Beams Re-Bar 03-Mar-12 09-Mar-12 7
A A
A8740 Slab / Beams Checking & 10-May-12 11-May-12 2
Casting A A
sujmall-1.1.2.5.1.1
POUR-A 23-Oct-11 07-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8750 Column Starter Marking 23-Oct-11 A 23-Oct-11 A 1
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.1.2
POUR-B 26-Oct-11 10-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8820 Column Starter Marking 26-Oct-11 A 26-Oct-11 A 1
sujmall-1.1.2.5.2.1
POUR-A 09-Nov-11 24-Nov-11 16 0
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.2.2
POUR-B 12-Nov-11 27-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8960 Column Starter Marking 12-Nov-11 12-Nov-11 1
A A
A8970 Columns - Re-Bar 13-Nov-11 14-Nov-11 2
A A
A8980 Columns - Formwork 14-Nov-11 16-Nov-11 3
A A
A8990 Columns - Casting 15-Nov-11 18-Nov-11 4
A A
A9000 Slab / Beams - Formwork 18-Nov-11 24-Nov-11 7
A A
A9010 Slab / Beams - Re-Bar 21-Nov-11 25-Nov-11 5
A A
A9020 Slab / Beams Checking & 26-Nov-11 27-Nov-11 2
Casting A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.3.1
POUR-A 26-Nov-11 11-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9030 Column Starter Marking 26-Nov-11 26-Nov-11 1
A A
A9040 Columns - Re-Bar 27-Nov-11 28-Nov-11 2
A A
A9050 Columns - Formwork 28-Nov-11 30-Nov-11 3
A A
A9060 Columns - Casting 29-Nov-11 02-Dec-11 4
A A
A9070 Slab / Beams - Formwork 02-Dec-11 08-Dec-11 7
A A
A9080 Slab / Beams - Re-Bar 05-Dec-11 09-Dec-11 5
A A
A9090 Slab / Beams Checking & 10-Dec-11 11-Dec-11 2
Casting A A
sujmall-1.1.2.5.3.2
POUR-B 29-Nov-11 14-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9100 Column Starter Marking 29-Nov-11 29-Nov-11 1
A A
A9110 Columns - Re-Bar 30-Nov-11 01-Dec-11 2
A A
A9120 Columns - Formwork 01-Dec-11 03-Dec-11 3
A A
A9130 Columns - Casting 02-Dec-11 05-Dec-11 4
A A
A9140 Slab / Beams - Formwork 05-Dec-11 11-Dec-11 7
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.4.1
POUR-A 13-Dec-11 28-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9170 Column Starter Marking 13-Dec-11 13-Dec-11 1
A A
A9180 Columns - Re-Bar 14-Dec-11 15-Dec-11 2
A A
A9190 Columns - Formwork 15-Dec-11 17-Dec-11 3
A A
A9200 Columns - Casting 16-Dec-11 19-Dec-11 4
A A
A9210 Slab / Beams - Formwork 19-Dec-11 25-Dec-11 7
A A
A9220 Slab / Beams - Re-Bar 22-Dec-11 26-Dec-11 5
A A
A9230 Slab / Beams Checking & 27-Dec-11 28-Dec-11 2
Casting A A
sujmall-1.1.2.5.4.2
POUR-B 16-Dec-11 31-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9240 Column Starter Marking 16-Dec-11 16-Dec-11 1
A A
A9250 Columns - Re-Bar 17-Dec-11 18-Dec-11 2
A A
A9260 Columns - Formwork 18-Dec-11 20-Dec-11 3
A A
(c) Primavera Systems, Inc. Page 59 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.5.1
POUR-A 30-Dec-11 14-Jan-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9310 Column Starter Marking 30-Dec-11 30-Dec-11 1
A A
A9320 Columns - Re-Bar 31-Dec-11 01-Jan-12 A 2
A
A9330 Columns - Formwork 01-Jan-12 A 03-Jan-12 A 3
sujmall-1.1.2.5.5.2
POUR-B 02-Jan-12 17-Jan-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9380 Column Starter Marking 02-Jan-12 A 02-Jan-12 A 1
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.6.1
POUR-A 30-Jan-11 29-Jan-12 365 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9450 Column Starter Marking 16-Jan-12 A 16-Jan-12 A 1
sujmall-1.1.2.5.6.2
POUR-B 19-Jan-12 03-Feb-12 16 0
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.7.1
POUR-A 02-Feb-12 17-Feb-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9590 Column Starter Marking 02-Feb-12 02-Feb-12 1
A A
A9600 Columns - Re-Bar 03-Feb-12 04-Feb-12 2
A A
A9610 Columns - Formwork 04-Feb-12 06-Feb-12 3
A A
A9620 Columns - Casting 05-Feb-12 08-Feb-12 4
A A
A9630 Slab / Beams - Formwork 08-Feb-12 14-Feb-12 7
A A
A9640 Slab / Beams - Re-Bar 11-Feb-12 15-Feb-12 5
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.7.2
POUR-B 05-Feb-12 20-Feb-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9660 Column Starter Marking 05-Feb-12 05-Feb-12 1
A A
A9670 Columns - Re-Bar 06-Feb-12 07-Feb-12 2
A A
A9680 Columns - Formwork 07-Feb-12 09-Feb-12 3
A A
A9690 Columns - Casting 08-Feb-12 11-Feb-12 4
A A
A9700 Slab / Beams - Formwork 11-Feb-12 17-Feb-12 7
A A
A9710 Slab / Beams - Re-Bar 14-Feb-12 18-Feb-12 5
A A
A9720 Slab / Beams Checking & 19-Feb-12 20-Feb-12 2
Casting A A
sujmall-1.1.2.5.8.1
POUR-A 19-Feb-12 05-Mar-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9730 Column Starter Marking 19-Feb-12 19-Feb-12 1
A A
A9740 Columns - Re-Bar 20-Feb-12 21-Feb-12 2
A A
A9750 Columns - Formwork 21-Feb-12 23-Feb-12 3
A A
A9760 Columns - Casting 22-Feb-12 25-Feb-12 4
A A
(c) Primavera Systems, Inc. Page 63 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.2.5.8.2
POUR-B 22-Feb-12 08-Mar-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9800 Column Starter Marking 22-Feb-12 22-Feb-12 1
A A
A9810 Columns - Re-Bar 23-Feb-12 24-Feb-12 2
A A
A9820 Columns - Formwork 24-Feb-12 26-Feb-12 3
A A
A9830 Columns - Casting 25-Feb-12 28-Feb-12 4
A A
A9840 Slab / Beams - Formwork 28-Feb-12 05-Mar-12 7
A A
A9850 Slab / Beams - Re-Bar 02-Mar-12 06-Mar-12 5
A A
A9860 Slab / Beams Checking & 07-Mar-12 08-Mar-12 2
Casting A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.2.3.1
SPRINKLER & HYDRANT SYSTEM 21-Nov-11 29-Jul-12 249 3 163
A
sujmall-1.1.5.2.3.1.1
BASEMENT-3 21-Nov-11 18-Feb-12 90 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.2.3.1.2
BASEMENT-2 01-Dec-11 28-Feb-12 90 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.3
BASEMENT-1 11-Dec-11 28-Feb-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.4
LOWER GROUND FLOOR 1 21-Dec-11 09-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.2.3.1.5
UPPER GROUND FLOOR 31-Dec-11 19-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.6
FIRST FLOOR 10-Jan-12 29-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.7
SECOND FLOOR 20-Jan-12 29-Jul-12 189 3 163
A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.2.3.1.8
THIRD FLOOR 30-Jan-12 03-Apr-12 65 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.9
THEATER EXIT FLOOR 09-Feb-12 29-Mar-12 50 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.10
FOURTH FLOOR 19-Feb-12 08-Apr-12 50 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
sujmall-1.1.5.2.3.1.11
FIFTH FLOOR 29-Feb-12 23-Apr-12 55 0
A A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.2.3.2
FIRE SHAFT 10-Jan-12 23-Apr-12 105 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12200 Fabrication of Sprinkler Pipes 10-Jan-12 A 23-Feb-12 45
A
A12210 Erection of Sprinkler Pipes 07-Feb-12 06-Apr-12 A 60
A
A12220 Testing of the Sprinkler Pipes 14-Apr-12 A 23-Apr-12 A 10
sujmall-1.1.5.2.3.3
MLCP 24-Feb-12 03-Jun-12 101 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12230 Fabrication of Sprinkler Pipes 24-Feb-12 23-Apr-12 A 60
A
A12240 Erection of Sprinkler Pipes 25-Mar-12 23-May-12 60
A A
A12250 Testing of the Sprinkler Pipes 20-May-12 03-Jun-12 A 15
A
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
sujmall-1.1.5.8 DG Equipment & Low Side Works 19-Dec-11 04-Nov-12 221 101 65
A
Activity ID Activity Name Start Finish Original Duration Total Float
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration
WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration