Вы находитесь на странице: 1из 97

SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1 SUJANA MALL - Hyderabad 10-Mar-10 08-Jan-13 870 166 0


A

sujmall-1.1 DELAY IN INITIAL START OF WORK 10-Mar-10 09-Sep-10 184 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1000 Blasting License 10-Mar-10 03-May-10 55
A A
A1010 Handing over of 2 acres of land 10-Apr-10 A 05-Jul-10 A 87

A1020 Collapse of Road/Rainfall 18-Jun-10 A 06-Sep-10 81


A
A1030 Local Problems 22-Jun-10 A 09-Sep-10 80
A

sujmall-1.1.1 FOUNDATION WORKS (B3) 10-Sep-10 19-Mar-11 191 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1040 Footing Exacavation 10-Sep-10 06-Feb-11 150
A A
A1050 P.C.C for Footing 22-Sep-10 19-Jan-11 A 120
A
A1060 R.W. Raft / Footings Rebar 23-Sep-10 20-Jan-11 A 120
Works A
A1070 R.W.Raft / Footings - Shuttering 24-Sep-10 20-Feb-11 150
A A
A1080 R.W.Raft / Footings - Concreting 26-Sep-10 23-Jan-11 A 120
A
A1090 Backfilling 06-Oct-10 A 04-Mar-11 150
A
A1100 P.C.C. for Grade Slab 13-Dec-10 12-Mar-11 90
A A
A1110 Drain Works 19-Jan-11 A 19-Mar-11 60
A

(c) Primavera Systems, Inc. Page 1 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1120 Reinforcement for Grade Slab 19-Jan-11 A 17-Feb-11 30


A
A1130 Concreting for Grade Slab 19-Jan-11 A 17-Feb-11 30
A

sujmall-1.1.2 STRUCTURAL WORKS 10-Oct-10 11-May-12 580 0


A A

sujmall-1.1.2.1 BASEMENT WORKS (B2 & B1) 10-Oct-10 19-Jun-11 253 0


A A

sujmall-1.1.2.1.1 BASEMENT 2 (86.70 LVL) 10-Oct-10 22-May-11 225 0


A A

sujmall-1.1.2.1.1.1
POUR-1 10-Oct-10 11-Nov-10 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1140 Column Starter Marking 10-Oct-10 A 11-Oct-10 A 2

A1150 Columns - Re-Bar 12-Oct-10 A 18-Oct-10 A 7

A1160 Columns - Formwork 14-Oct-10 A 23-Oct-10 A 10

A1170 Columns - Casting 16-Oct-10 A 22-Oct-10 A 7

A1180 Shear Wall / Core Wall / Ret. 12-Oct-10 A 21-Oct-10 A 10


Wall Re-Bar
A1190 Shear Wall / Core Wall / Ret. 15-Oct-10 A 24-Oct-10 A 10
Wall Formwork
A1200 Shear Wall / Core Wall / Ret. 18-Oct-10 A 24-Oct-10 A 7
Wall Casting
A1210 Staircase - Formwork 21-Oct-10 A 22-Oct-10 A 2

A1220 Staircase - Re-Bar 23-Oct-10 A 24-Oct-10 A 2

(c) Primavera Systems, Inc. Page 2 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1230 Staircase - Casting 25-Oct-10 A 25-Oct-10 A 1

A1240 Slab / Beams - Formwork 21-Oct-10 A 05-Nov-10 16


A
A1250 Slab / Beams - Re-Bar 29-Oct-10 A 09-Nov-10 12
A
A1260 Slab / Beams Checking & 10-Nov-10 11-Nov-10 2
Casting A A

sujmall-1.1.2.1.1.2
POUR-2 30-Oct-10 28-Nov-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1270 Column Starter Marking 30-Oct-10 A 31-Oct-10 A 2

A1280 Columns - Re-Bar 01-Nov-10 07-Nov-10 7


A A
A1290 Columns - Formwork 03-Nov-10 12-Nov-10 10
A A
A1300 Columns - Casting 05-Nov-10 11-Nov-10 7
A A
A1310 Shear Wall / Core Wall / Ret. 01-Nov-10 10-Nov-10 10
Wall Re-Bar A A
A1320 Shear Wall / Core Wall / Ret. 04-Nov-10 13-Nov-10 10
Wall Formwork A A
A1330 Shear Wall / Core Wall / Ret. 07-Nov-10 13-Nov-10 7
Wall Casting A A
A1340 Staircase - Formwork 10-Nov-10 11-Nov-10 2
A A
A1350 Staircase - Re-Bar 12-Nov-10 13-Nov-10 2
A A
A1360 Staircase - Casting 14-Nov-10 14-Nov-10 1
A A
A1370 Slab / Beams - Formwork 09-Nov-10 23-Nov-10 15
A A

(c) Primavera Systems, Inc. Page 3 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1380 Slab / Beams - Re-Bar 17-Nov-10 26-Nov-10 10


A A
A1390 Slab / Beams Checking & 27-Nov-10 28-Nov-10 2
Casting A A

sujmall-1.1.2.1.1.3
POUR-3 25-Oct-10 23-Nov-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1400 Column Starter Marking 25-Oct-10 A 26-Oct-10 A 2

A1410 Columns - Re-Bar 27-Oct-10 A 02-Nov-10 7


A
A1420 Columns - Formwork 29-Oct-10 A 07-Nov-10 10
A
A1430 Columns - Casting 31-Oct-10 A 06-Nov-10 7
A
A1440 Shear Wall / Core Wall / Ret. 27-Oct-10 A 05-Nov-10 10
Wall Re-Bar A
A1450 Shear Wall / Core Wall / Ret. 30-Oct-10 A 08-Nov-10 10
Wall Formwork A
A1460 Shear Wall / Core Wall / Ret. 02-Nov-10 08-Nov-10 7
Wall Casting A A
A1470 Staircase - Formwork 07-Nov-10 08-Nov-10 2
A A
A1480 Staircase - Re-Bar 09-Nov-10 10-Nov-10 2
A A
A1490 Staircase - Casting 11-Nov-10 11-Nov-10 1
A A
A1500 Slab / Beams - Formwork 04-Nov-10 18-Nov-10 15
A A
A1510 Slab / Beams - Re-Bar 12-Nov-10 21-Nov-10 10
A A
A1520 Slab / Beams Checking & 21-Nov-10 23-Nov-10 3
Casting A A

(c) Primavera Systems, Inc. Page 4 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.2.1.1.4
POUR-4 17-Nov-10 16-Dec-10 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1530 Column Starter Marking 17-Nov-10 18-Nov-10 2
A A
A1540 Columns - Re-Bar 19-Nov-10 25-Nov-10 7
A A
A1550 Columns - Formwork 21-Nov-10 30-Nov-10 10
A A
A1560 Columns - Casting 23-Nov-10 29-Nov-10 7
A A
A1570 Shear Wall / Core Wall / Ret. 19-Nov-10 28-Nov-10 10
Wall Re-Bar A A
A1580 Shear Wall / Core Wall / Ret. 22-Nov-10 01-Dec-10 10
Wall Formwork A A
A1590 Shear Wall / Core Wall / Ret. 25-Nov-10 01-Dec-10 7
Wall Casting A A
A1600 Staircase - Formwork 30-Nov-10 01-Dec-10 2
A A
A1610 Staircase - Re-Bar 02-Dec-10 03-Dec-10 2
A A
A1620 Staircase - Casting 04-Dec-10 04-Dec-10 1
A A
A1630 Slab / Beams - Formwork 27-Nov-10 11-Dec-10 15
A A
A1640 Slab / Beams - Re-Bar 05-Dec-10 14-Dec-10 10
A A
A1650 Slab / Beams Checking & 15-Dec-10 16-Dec-10 2
Casting A A

sujmall-1.1.2.1.1.5
POUR-5 27-Dec-10 25-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1660 Column Starter Marking 27-Dec-10 28-Dec-10 2
A A
(c) Primavera Systems, Inc. Page 5 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1670 Columns - Re-Bar 29-Dec-10 04-Jan-11 A 7


A
A1680 Columns - Formwork 31-Dec-10 09-Jan-11 A 10
A
A1690 Columns - Casting 02-Jan-11 A 08-Jan-11 A 7

A1700 Shear Wall / Core Wall / Ret. 29-Dec-10 07-Jan-11 A 10


Wall Re-Bar A
A1710 Shear Wall / Core Wall / Ret. 01-Jan-11 A 10-Jan-11 A 10
Wall Formwork
A1720 Shear Wall / Core Wall / Ret. 04-Jan-11 A 10-Jan-11 A 7
Wall Casting
A1730 Staircase - Formwork 09-Jan-11 A 10-Jan-11 A 2

A1740 Staircase - Re-Bar 11-Jan-11 A 12-Jan-11 A 2

A1750 Staircase - Casting 13-Jan-11 A 13-Jan-11 A 1

A1760 Slab / Beams - Formwork 06-Jan-11 A 20-Jan-11 A 15

A1770 Slab / Beams - Re-Bar 14-Jan-11 A 23-Jan-11 A 10

A1780 Slab / Beams Checking & 24-Jan-11 A 25-Jan-11 A 2


Casting

sujmall-1.1.2.1.1.6
POUR-6 30-Dec-10 28-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1790 Column Starter Marking 30-Dec-10 31-Dec-10 2
A A
A1800 Columns - Re-Bar 01-Jan-11 A 07-Jan-11 A 7

A1810 Columns - Formwork 03-Jan-11 A 12-Jan-11 A 10

(c) Primavera Systems, Inc. Page 6 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1820 Columns - Casting 05-Jan-11 A 11-Jan-11 A 7

A1830 Shear Wall / Core Wall / Ret. 01-Jan-11 A 10-Jan-11 A 10


Wall Re-Bar
A1840 Shear Wall / Core Wall / Ret. 04-Jan-11 A 13-Jan-11 A 10
Wall Formwork
A1850 Shear Wall / Core Wall / Ret. 07-Jan-11 A 13-Jan-11 A 7
Wall Casting
A1860 Staircase - Formwork 12-Jan-11 A 13-Jan-11 A 2

A1870 Staircase - Re-Bar 14-Jan-11 A 15-Jan-11 A 2

A1880 Staircase - Casting 16-Jan-11 A 16-Jan-11 A 1

A1890 Slab / Beams - Formwork 09-Jan-11 A 23-Jan-11 A 15

A1900 Slab / Beams - Re-Bar 17-Jan-11 A 26-Jan-11 A 10

A1910 Slab / Beams Checking & 27-Jan-11 A 28-Jan-11 A 2


Casting

sujmall-1.1.2.1.1.7
POUR-7 12-Mar-11 10-Apr-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A1920 Column Starter Marking 12-Mar-11 13-Mar-11 2
A A
A1930 Columns - Re-Bar 14-Mar-11 20-Mar-11 7
A A
A1940 Columns - Formwork 16-Mar-11 25-Mar-11 10
A A
A1950 Columns - Casting 18-Mar-11 24-Mar-11 7
A A
A1960 Shear Wall / Core Wall / Ret. 14-Mar-11 23-Mar-11 10
Wall Re-Bar A A

(c) Primavera Systems, Inc. Page 7 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A1970 Shear Wall / Core Wall / Ret. 17-Mar-11 26-Mar-11 10


Wall Formwork A A
A1980 Shear Wall / Core Wall / Ret. 20-Mar-11 26-Mar-11 7
Wall Casting A A
A1990 Staircase - Formwork 25-Mar-11 26-Mar-11 2
A A
A2000 Staircase - Re-Bar 27-Mar-11 28-Mar-11 2
A A
A2010 Staircase - Casting 29-Mar-11 29-Mar-11 1
A A
A2020 Slab / Beams - Formwork 22-Mar-11 05-Apr-11 A 15
A
A2030 Slab / Beams - Re-Bar 30-Mar-11 08-Apr-11 A 10
A
A2040 Slab / Beams Checking & 09-Apr-11 A 10-Apr-11 A 2
Casting

sujmall-1.1.2.1.1.8
POUR-8 23-Apr-11 22-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2050 Column Starter Marking 23-Apr-11 A 24-Apr-11 A 2

A2060 Columns - Re-Bar 25-Apr-11 A 01-May-11 7


A
A2070 Columns - Formwork 27-Apr-11 A 06-May-11 10
A
A2080 Columns - Casting 29-Apr-11 A 05-May-11 7
A
A2090 Shear Wall / Core Wall / Ret. 25-Apr-11 A 04-May-11 10
Wall Re-Bar A
A2100 Shear Wall / Core Wall / Ret. 28-Apr-11 A 07-May-11 10
Wall Formwork A
A2110 Shear Wall / Core Wall / Ret. 01-May-11 07-May-11 7
Wall Casting A A

(c) Primavera Systems, Inc. Page 8 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A2120 Staircase - Formwork 06-May-11 07-May-11 2


A A
A2130 Staircase - Re-Bar 08-May-11 09-May-11 2
A A
A2140 Staircase - Casting 10-May-11 10-May-11 1
A A
A2150 Slab / Beams - Formwork 03-May-11 17-May-11 15
A A
A2160 Slab / Beams - Re-Bar 11-May-11 20-May-11 10
A A
A2170 Slab / Beams Checking & 21-May-11 22-May-11 2
Casting A A

sujmall-1.1.2.1.2 BASEMENT 1 (90.30 LVL)) 23-Nov-10 19-Jun-11 209 0


A A

sujmall-1.1.2.1.2.1
POUR-1 23-Nov-10 25-Dec-10 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2180 Column Starter Marking 23-Nov-10 24-Nov-10 2
A A
A2190 Columns - Re-Bar 25-Nov-10 01-Dec-10 7
A A
A2200 Columns - Formwork 27-Nov-10 06-Dec-10 10
A A
A2210 Columns - Casting 29-Nov-10 05-Dec-10 7
A A
A2220 Shear Wall / Core Wall / Ret. 25-Nov-10 04-Dec-10 10
Wall Re-Bar A A
A2230 Shear Wall / Core Wall / Ret. 28-Nov-10 07-Dec-10 10
Wall Formwork A A
A2240 Shear Wall / Core Wall / Ret. 01-Dec-10 07-Dec-10 7
Wall Casting A A
A2250 Staircase - Formwork 04-Dec-10 05-Dec-10 2
A A

(c) Primavera Systems, Inc. Page 9 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A2260 Staircase - Re-Bar 06-Dec-10 07-Dec-10 2


A A
A2270 Staircase - Casting 08-Dec-10 08-Dec-10 1
A A
A2280 Slab / Beams - Formwork 04-Dec-10 19-Dec-10 16
A A
A2290 Slab / Beams - Re-Bar 12-Dec-10 23-Dec-10 12
A A
A2300 Slab / Beams Checking & 24-Dec-10 25-Dec-10 2
Casting A A

sujmall-1.1.2.1.2.2
POUR-2 14-Dec-10 12-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2310 Column Starter Marking 14-Dec-10 15-Dec-10 2
A A
A2320 Columns - Re-Bar 16-Dec-10 22-Dec-10 7
A A
A2330 Columns - Formwork 18-Dec-10 27-Dec-10 10
A A
A2340 Columns - Casting 20-Dec-10 26-Dec-10 7
A A
A2350 Shear Wall / Core Wall / Ret. 16-Dec-10 25-Dec-10 10
Wall Re-Bar A A
A2360 Shear Wall / Core Wall / Ret. 19-Dec-10 28-Dec-10 10
Wall Formwork A A
A2370 Shear Wall / Core Wall / Ret. 22-Dec-10 28-Dec-10 7
Wall Casting A A
A2380 Staircase - Formwork 25-Dec-10 26-Dec-10 2
A A
A2390 Staircase - Re-Bar 27-Dec-10 28-Dec-10 2
A A
A2400 Staircase - Casting 29-Dec-10 29-Dec-10 1
A A

(c) Primavera Systems, Inc. Page 10 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A2410 Slab / Beams - Formwork 24-Dec-10 07-Jan-11 A 15


A
A2420 Slab / Beams - Re-Bar 01-Jan-11 A 10-Jan-11 A 10

A2430 Slab / Beams Checking & 11-Jan-11 A 12-Jan-11 A 2


Casting

sujmall-1.1.2.1.2.3
POUR-3 13-Dec-10 11-Jan-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2440 Column Starter Marking 13-Dec-10 14-Dec-10 2
A A
A2450 Columns - Re-Bar 15-Dec-10 21-Dec-10 7
A A
A2460 Columns - Formwork 17-Dec-10 26-Dec-10 10
A A
A2470 Columns - Casting 19-Dec-10 25-Dec-10 7
A A
A2480 Shear Wall / Core Wall / Ret. 15-Dec-10 24-Dec-10 10
Wall Re-Bar A A
A2490 Shear Wall / Core Wall / Ret. 18-Dec-10 27-Dec-10 10
Wall Formwork A A
A2500 Shear Wall / Core Wall / Ret. 21-Dec-10 27-Dec-10 7
Wall Casting A A
A2510 Staircase - Formwork 26-Dec-10 27-Dec-10 2
A A
A2520 Staircase - Re-Bar 28-Dec-10 29-Dec-10 2
A A
A2530 Staircase - Casting 30-Dec-10 30-Dec-10 1
A A
A2540 Slab / Beams - Formwork 23-Dec-10 06-Jan-11 A 15
A
A2550 Slab / Beams - Re-Bar 31-Dec-10 09-Jan-11 A 10
A

(c) Primavera Systems, Inc. Page 11 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A2560 Slab / Beams Checking & 10-Jan-11 A 11-Jan-11 A 2


Casting

sujmall-1.1.2.1.2.4
POUR-4 15-Jan-11 13-Feb-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2570 Column Starter Marking 15-Jan-11 A 16-Jan-11 A 2

A2580 Columns - Re-Bar 17-Jan-11 A 23-Jan-11 A 7

A2590 Columns - Formwork 19-Jan-11 A 28-Jan-11 A 10

A2600 Columns - Casting 21-Jan-11 A 27-Jan-11 A 7

A2610 Shear Wall / Core Wall / Ret. 17-Jan-11 A 26-Jan-11 A 10


Wall Re-Bar
A2620 Shear Wall / Core Wall / Ret. 20-Jan-11 A 29-Jan-11 A 10
Wall Formwork
A2630 Shear Wall / Core Wall / Ret. 23-Jan-11 A 29-Jan-11 A 7
Wall Casting
A2640 Staircase - Formwork 28-Jan-11 A 29-Jan-11 A 2

A2650 Staircase - Re-Bar 30-Jan-11 A 31-Jan-11 A 2

A2660 Staircase - Casting 01-Feb-11 01-Feb-11 1


A A
A2670 Slab / Beams - Formwork 25-Jan-11 A 08-Feb-11 15
A
A2680 Slab / Beams - Re-Bar 02-Feb-11 11-Feb-11 10
A A
A2690 Slab / Beams Checking & 12-Feb-11 13-Feb-11 2
Casting A A

sujmall-1.1.2.1.2.5
POUR-5 19-Feb-11 20-Mar-11 30 0
A A
(c) Primavera Systems, Inc. Page 12 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A2700 Column Starter Marking 19-Feb-11 20-Feb-11 2
A A
A2710 Columns - Re-Bar 21-Feb-11 27-Feb-11 7
A A
A2720 Columns - Formwork 23-Feb-11 04-Mar-11 10
A A
A2730 Columns - Casting 25-Feb-11 03-Mar-11 7
A A
A2740 Shear Wall / Core Wall / Ret. 21-Feb-11 02-Mar-11 10
Wall Re-Bar A A
A2750 Shear Wall / Core Wall / Ret. 24-Feb-11 05-Mar-11 10
Wall Formwork A A
A2760 Shear Wall / Core Wall / Ret. 27-Feb-11 05-Mar-11 7
Wall Casting A A
A2770 Staircase - Formwork 04-Mar-11 05-Mar-11 2
A A
A2780 Staircase - Re-Bar 06-Mar-11 07-Mar-11 2
A A
A2790 Staircase - Casting 08-Mar-11 08-Mar-11 1
A A
A2800 Slab / Beams - Formwork 01-Mar-11 15-Mar-11 15
A A
A2810 Slab / Beams - Re-Bar 09-Mar-11 18-Mar-11 10
A A
A2820 Slab / Beams Checking & 19-Mar-11 20-Mar-11 2
Casting A A

sujmall-1.1.2.1.2.6
POUR-6 19-Feb-11 20-Mar-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2830 Column Starter Marking 19-Feb-11 20-Feb-11 2
A A
A2840 Columns - Re-Bar 21-Feb-11 27-Feb-11 7
A A
(c) Primavera Systems, Inc. Page 13 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A2850 Columns - Formwork 23-Feb-11 04-Mar-11 10


A A
A2860 Columns - Casting 25-Feb-11 03-Mar-11 7
A A
A2870 Shear Wall / Core Wall / Ret. 21-Feb-11 02-Mar-11 10
Wall Re-Bar A A
A2880 Shear Wall / Core Wall / Ret. 24-Feb-11 05-Mar-11 10
Wall Formwork A A
A2890 Shear Wall / Core Wall / Ret. 27-Feb-11 05-Mar-11 7
Wall Casting A A
A2900 Staircase - Formwork 04-Mar-11 05-Mar-11 2
A A
A2910 Staircase - Re-Bar 06-Mar-11 07-Mar-11 2
A A
A2920 Staircase - Casting 08-Mar-11 08-Mar-11 1
A A
A2930 Slab / Beams - Formwork 01-Mar-11 15-Mar-11 15
A A
A2940 Slab / Beams - Re-Bar 09-Mar-11 18-Mar-11 10
A A
A2950 Slab / Beams Checking & 19-Mar-11 20-Mar-11 2
Casting A A

sujmall-1.1.2.1.2.7
POUR-7 10-May-11 08-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A2960 Column Starter Marking 10-May-11 11-May-11 2
A A
A2970 Columns - Re-Bar 12-May-11 18-May-11 7
A A
A2980 Columns - Formwork 14-May-11 23-May-11 10
A A
A2990 Columns - Casting 16-May-11 22-May-11 7
A A

(c) Primavera Systems, Inc. Page 14 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3000 Shear Wall / Core Wall / Ret. 12-May-11 21-May-11 10


Wall Re-Bar A A
A3010 Shear Wall / Core Wall / Ret. 15-May-11 24-May-11 10
Wall Formwork A A
A3020 Shear Wall / Core Wall / Ret. 18-May-11 24-May-11 7
Wall Casting A A
A3030 Staircase - Formwork 23-May-11 24-May-11 2
A A
A3040 Staircase - Re-Bar 25-May-11 26-May-11 2
A A
A3050 Staircase - Casting 27-May-11 27-May-11 1
A A
A3060 Slab / Beams - Formwork 20-May-11 03-Jun-11 A 15
A
A3070 Slab / Beams - Re-Bar 28-May-11 06-Jun-11 A 10
A
A3080 Slab / Beams Checking & 07-Jun-11 A 08-Jun-11 A 2
Casting

sujmall-1.1.2.1.2.8
POUR-8 21-May-11 19-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3090 Column Starter Marking 21-May-11 22-May-11 2
A A
A3100 Columns - Re-Bar 23-May-11 29-May-11 7
A A
A3110 Columns - Formwork 25-May-11 03-Jun-11 A 10
A
A3120 Columns - Casting 27-May-11 02-Jun-11 A 7
A
A3130 Shear Wall / Core Wall / Ret. 23-May-11 01-Jun-11 A 10
Wall Re-Bar A
A3140 Shear Wall / Core Wall / Ret. 26-May-11 04-Jun-11 A 10
Wall Formwork A

(c) Primavera Systems, Inc. Page 15 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3150 Shear Wall / Core Wall / Ret. 29-May-11 04-Jun-11 A 7


Wall Casting A
A3160 Staircase - Formwork 03-Jun-11 A 04-Jun-11 A 2

A3170 Staircase - Re-Bar 05-Jun-11 A 06-Jun-11 A 2

A3180 Staircase - Casting 07-Jun-11 A 07-Jun-11 A 1

A3190 Slab / Beams - Formwork 31-May-11 14-Jun-11 A 15


A
A3200 Slab / Beams - Re-Bar 08-Jun-11 A 17-Jun-11 A 10

A3210 Slab / Beams Checking & 18-Jun-11 A 19-Jun-11 A 2


Casting

sujmall-1.1.2.2 "RETAIL FLOOR WORKS (LGF, 25-Jan-11 18-Jan-12 359 0


UGF, 1st, 2nd & 3rd)" A A

sujmall-1.1.2.2.1 LOWER GROUND FLOOR (94.5 25-Jan-11 18-Jul-11 175 0


LVL) A A

sujmall-1.1.2.2.1.1
POUR-1 25-Jan-11 26-Feb-11 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3220 Column Starter Marking 25-Jan-11 A 26-Jan-11 A 2

A3230 Columns - Re-Bar 27-Jan-11 A 02-Feb-11 7


A
A3240 Columns - Formwork 29-Jan-11 A 07-Feb-11 10
A
A3250 Columns - Casting 31-Jan-11 A 06-Feb-11 7
A
A3260 Shear Wall / Core Wall / Ret. 27-Jan-11 A 05-Feb-11 10
Wall Re-Bar A
A3270 Shear Wall / Core Wall / Ret. 30-Jan-11 A 08-Feb-11 10

(c) Primavera Systems, Inc. Page 16 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3280 Shear Wall / Core Wall / Ret. 02-Feb-11 08-Feb-11 7


Wall Casting A A
A3290 Staircase - Formwork 05-Feb-11 06-Feb-11 2
A A
A3300 Staircase - Re-Bar 07-Feb-11 08-Feb-11 2
A A
A3310 Staircase - Casting 09-Feb-11 09-Feb-11 1
A A
A3320 Slab / Beams - Formwork 05-Feb-11 20-Feb-11 16
A A
A3330 Slab / Beams - Re-Bar 13-Feb-11 24-Feb-11 12
A A
A3340 Slab / Beams Checking & 25-Feb-11 26-Feb-11 2
Casting A A

sujmall-1.1.2.2.1.2
POUR-2 11-May-11 09-Jun-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3350 Column Starter Marking 11-May-11 12-May-11 2
A A
A3360 Columns - Re-Bar 13-May-11 19-May-11 7
A A
A3370 Columns - Formwork 15-May-11 24-May-11 10
A A
A3380 Columns - Casting 17-May-11 23-May-11 7
A A
A3390 Shear Wall / Core Wall / Ret. 13-May-11 22-May-11 10
Wall Re-Bar A A
A3400 Shear Wall / Core Wall / Ret. 16-May-11 25-May-11 10
Wall Formwork A A
A3410 Shear Wall / Core Wall / Ret. 19-May-11 25-May-11 7
Wall Casting A A
A3420 Staircase - Formwork 21-May-11 04-Jun-11 A 15
A

(c) Primavera Systems, Inc. Page 17 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3430 Staircase - Re-Bar 24-May-11 25-May-11 2


A A
A3440 Staircase - Casting 26-May-11 26-May-11 1
A A
A3450 Slab / Beams - Formwork 21-May-11 04-Jun-11 A 15
A
A3460 Slab / Beams - Re-Bar 29-May-11 07-Jun-11 A 10
A
A3470 Slab / Beams Checking & 08-Jun-11 A 09-Jun-11 A 2
Casting

sujmall-1.1.2.2.1.3
POUR-3 04-Feb-11 05-Mar-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3480 Column Starter Marking 04-Feb-11 05-Feb-11 2
A A
A3490 Columns - Re-Bar 06-Feb-11 12-Feb-11 7
A A
A3500 Columns - Formwork 08-Feb-11 17-Feb-11 10
A A
A3510 Columns - Casting 10-Feb-11 16-Feb-11 7
A A
A3520 Shear Wall / Core Wall / Ret. 06-Feb-11 15-Feb-11 10
Wall Re-Bar A A
A3530 Shear Wall / Core Wall / Ret. 09-Feb-11 18-Feb-11 10
Wall Formwork A A
A3540 Shear Wall / Core Wall / Ret. 12-Feb-11 18-Feb-11 7
Wall Casting A A
A3550 Staircase - Formwork 17-Feb-11 18-Feb-11 2
A A
A3560 Staircase - Re-Bar 19-Feb-11 20-Feb-11 2
A A
A3570 Staircase - Casting 21-Feb-11 21-Feb-11 1
A A

(c) Primavera Systems, Inc. Page 18 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3580 Slab / Beams - Formwork 14-Feb-11 28-Feb-11 15


A A
A3590 Slab / Beams - Re-Bar 22-Feb-11 03-Mar-11 10
A A
A3600 Slab / Beams Checking & 04-Mar-11 05-Mar-11 2
Casting A A

sujmall-1.1.2.2.1.4
POUR-4 17-Apr-11 16-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3610 Column Starter Marking 17-Apr-11 A 18-Apr-11 A 2

A3620 Columns - Re-Bar 19-Apr-11 A 25-Apr-11 A 7

A3630 Columns - Formwork 21-Apr-11 A 30-Apr-11 A 10

A3640 Columns - Casting 23-Apr-11 A 29-Apr-11 A 7

A3650 Shear Wall / Core Wall / Ret. 19-Apr-11 A 28-Apr-11 A 10


Wall Re-Bar
A3660 Shear Wall / Core Wall / Ret. 22-Apr-11 A 01-May-11 10
Wall Formwork A
A3670 Shear Wall / Core Wall / Ret. 25-Apr-11 A 01-May-11 7
Wall Casting A
A3680 Staircase - Formwork 30-Apr-11 A 01-May-11 2
A
A3690 Staircase - Re-Bar 02-May-11 03-May-11 2
A A
A3700 Staircase - Casting 04-May-11 04-May-11 1
A A
A3710 Slab / Beams - Formwork 27-Apr-11 A 11-May-11 15
A
A3720 Slab / Beams - Re-Bar 05-May-11 14-May-11 10
A A

(c) Primavera Systems, Inc. Page 19 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A3730 Slab / Beams Checking & 15-May-11 16-May-11 2


Casting A A

sujmall-1.1.2.2.1.5
POUR-5 06-Apr-11 05-May-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A3740 Column Starter Marking 06-Apr-11 A 07-Apr-11 A 2

A3750 Columns - Re-Bar 08-Apr-11 A 14-Apr-11 A 7

A3760 Columns - Formwork 10-Apr-11 A 19-Apr-11 A 10

A3770 Columns - Casting 12-Apr-11 A 18-Apr-11 A 7

A3780 Shear Wall / Core Wall / Ret. 08-Apr-11 A 17-Apr-11 A 10


Wall Re-Bar
A3790 Shear Wall / Core Wall / Ret. 11-Apr-11 A 20-Apr-11 A 10
Wall Formwork
A3800 Shear Wall / Core Wall / Ret. 14-Apr-11 A 20-Apr-11 A 7
Wall Casting
A3810 Staircase - Formwork 19-Apr-11 A 20-Apr-11 A 2

A3820 Staircase - Re-Bar 21-Apr-11 A 22-Apr-11 A 2

A3830 Staircase - Casting 23-Apr-11 A 23-Apr-11 A 1

A3840 Slab / Beams - Formwork 16-Apr-11 A 30-Apr-11 A 15

A3850 Slab / Beams - Re-Bar 24-Apr-11 A 03-May-11 10


A
A3860 Slab / Beams Checking & 04-May-11 05-May-11 2
Casting A A

sujmall-1.1.2.2.1.6
POUR-6 13-Apr-11 12-May-11 30 0
A A
(c) Primavera Systems, Inc. Page 20 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A3870 Column Starter Marking 13-Apr-11 A 14-Apr-11 A 2

A3880 Columns - Re-Bar 15-Apr-11 A 21-Apr-11 A 7

A3890 Columns - Formwork 17-Apr-11 A 26-Apr-11 A 10

A3900 Columns - Casting 19-Apr-11 A 25-Apr-11 A 7

A3910 Shear Wall / Core Wall / Ret. 15-Apr-11 A 24-Apr-11 A 10


Wall Re-Bar
A3920 Shear Wall / Core Wall / Ret. 18-Apr-11 A 27-Apr-11 A 10
Wall Formwork
A3930 Shear Wall / Core Wall / Ret. 21-Apr-11 A 27-Apr-11 A 7
Wall Casting
A3940 Staircase - Formwork 26-Apr-11 A 27-Apr-11 A 2

A3950 Staircase - Re-Bar 28-Apr-11 A 29-Apr-11 A 2

A3960 Staircase - Casting 30-Apr-11 A 30-Apr-11 A 1

A3970 Slab / Beams - Formwork 23-Apr-11 A 07-May-11 15


A
A3980 Slab / Beams - Re-Bar 01-May-11 10-May-11 10
A A
A3990 Slab / Beams Checking & 11-May-11 12-May-11 2
Casting A A

sujmall-1.1.2.2.1.7
POUR-7 14-Jun-11 13-Jul-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4000 Column Starter Marking 14-Jun-11 A 15-Jun-11 A 2

A4010 Columns - Re-Bar 16-Jun-11 A 22-Jun-11 A 7

(c) Primavera Systems, Inc. Page 21 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4020 Columns - Formwork 18-Jun-11 A 27-Jun-11 A 10

A4030 Columns - Casting 20-Jun-11 A 26-Jun-11 A 7

A4040 Shear Wall / Core Wall / Ret. 16-Jun-11 A 25-Jun-11 A 10


Wall Re-Bar
A4050 Shear Wall / Core Wall / Ret. 19-Jun-11 A 28-Jun-11 A 10
Wall Formwork
A4060 Shear Wall / Core Wall / Ret. 22-Jun-11 A 28-Jun-11 A 7
Wall Casting
A4070 Staircase - Formwork 27-Jun-11 A 28-Jun-11 A 2

A4080 Staircase - Re-Bar 29-Jun-11 A 30-Jun-11 A 2

A4090 Staircase - Casting 01-Jul-11 A 01-Jul-11 A 1


A4100 Slab / Beams - Formwork 24-Jun-11 A 08-Jul-11 A 15

A4110 Slab / Beams - Re-Bar 02-Jul-11 A 11-Jul-11 A 10


A4120 Slab / Beams Checking & 12-Jul-11 A 13-Jul-11 A 2
Casting
sujmall-1.1.2.2.1.8
POUR-8 19-Jun-11 18-Jul-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4130 Column Starter Marking 19-Jun-11 A 20-Jun-11 A 2

A4140 Columns - Re-Bar 21-Jun-11 A 27-Jun-11 A 7

A4150 Columns - Formwork 23-Jun-11 A 02-Jul-11 A 10

A4160 Columns - Casting 25-Jun-11 A 01-Jul-11 A 7

A4170 Shear Wall / Core Wall / Ret. 21-Jun-11 A 30-Jun-11 A 10


Wall Re-Bar

(c) Primavera Systems, Inc. Page 22 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4180 Shear Wall / Core Wall / Ret. 24-Jun-11 A 03-Jul-11 A 10


Wall Formwork
A4190 Shear Wall / Core Wall / Ret. 27-Jun-11 A 03-Jul-11 A 7
Wall Casting
A4200 Staircase - Formwork 02-Jul-11 A 03-Jul-11 A 2
A4210 Staircase - Re-Bar 04-Jul-11 A 05-Jul-11 A 2
A4220 Staircase - Casting 06-Jul-11 A 06-Jul-11 A 1
A4230 Slab / Beams - Formwork 29-Jun-11 A 13-Jul-11 A 15

A4240 Slab / Beams - Re-Bar 07-Jul-11 A 16-Jul-11 A 10


A4250 Slab / Beams Checking & 17-Jul-11 A 18-Jul-11 A 2
Casting
sujmall-1.1.2.2.2 UPPER GROUND FLOOR (99.90 21-Jun-11 23-Nov-11 156 0
LVL) A A

sujmall-1.1.2.2.2.1
POUR-A 26-Jun-11 28-Jul-11 33 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4260 Column Starter Marking 26-Jun-11 A 27-Jun-11 A 2

A4270 Columns - Re-Bar 28-Jun-11 A 04-Jul-11 A 7

A4280 Columns - Formwork 30-Jun-11 A 09-Jul-11 A 10

A4290 Columns - Casting 02-Jul-11 A 08-Jul-11 A 7


A4300 Shear Wall / Core Wall / Ret. 28-Jun-11 A 07-Jul-11 A 10
Wall Re-Bar
A4310 Shear Wall / Core Wall / Ret. 01-Jul-11 A 10-Jul-11 A 10
Wall Formwork
A4320 Shear Wall / Core Wall / Ret. 04-Jul-11 A 10-Jul-11 A 7
Wall Casting
A4330 Staircase - Formwork 07-Jul-11 A 08-Jul-11 A 2

(c) Primavera Systems, Inc. Page 23 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4340 Staircase - Re-Bar 09-Jul-11 A 10-Jul-11 A 2


A4350 Staircase - Casting 11-Jul-11 A 11-Jul-11 A 1
A4360 Slab / Beams - Formwork 07-Jul-11 A 22-Jul-11 A 16
A4370 Slab / Beams - Re-Bar 15-Jul-11 A 26-Jul-11 A 12
A4380 Slab / Beams Checking & 27-Jul-11 A 28-Jul-11 A 2
Casting
sujmall-1.1.2.2.2.2
POUR-B 03-Aug-11 01-Sep-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4390 Column Starter Marking 03-Aug-11 04-Aug-11 2
A A
A4400 Columns - Re-Bar 05-Aug-11 11-Aug-11 7
A A
A4410 Columns - Formwork 07-Aug-11 16-Aug-11 10
A A
A4420 Columns - Casting 09-Aug-11 15-Aug-11 7
A A
A4430 Shear Wall / Core Wall / Ret. 05-Aug-11 14-Aug-11 10
Wall Re-Bar A A
A4440 Shear Wall / Core Wall / Ret. 08-Aug-11 17-Aug-11 10
Wall Formwork A A
A4450 Shear Wall / Core Wall / Ret. 11-Aug-11 17-Aug-11 7
Wall Casting A A
A4460 Staircase - Formwork 14-Aug-11 15-Aug-11 2
A A
A4470 Staircase - Re-Bar 16-Aug-11 17-Aug-11 2
A A
A4480 Staircase - Casting 18-Aug-11 18-Aug-11 1
A A
A4490 Slab / Beams - Formwork 13-Aug-11 27-Aug-11 15
A A
A4500 Slab / Beams - Re-Bar 21-Aug-11 30-Aug-11 10
A A

(c) Primavera Systems, Inc. Page 24 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4510 Slab / Beams Checking & 31-Aug-11 01-Sep-11 2


Casting A A

sujmall-1.1.2.2.2.3
POUR-C 21-Jun-11 20-Jul-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4520 Column Starter Marking 21-Jun-11 A 22-Jun-11 A 2

A4530 Columns - Re-Bar 23-Jun-11 A 29-Jun-11 A 7

A4540 Columns - Formwork 25-Jun-11 A 04-Jul-11 A 10

A4550 Columns - Casting 27-Jun-11 A 03-Jul-11 A 7

A4560 Shear Wall / Core Wall / Ret. 23-Jun-11 A 02-Jul-11 A 10


Wall Re-Bar
A4570 Shear Wall / Core Wall / Ret. 26-Jun-11 A 05-Jul-11 A 10
Wall Formwork
A4580 Shear Wall / Core Wall / Ret. 29-Jun-11 A 05-Jul-11 A 7
Wall Casting
A4590 Staircase - Formwork 04-Jul-11 A 05-Jul-11 A 2
A4600 Staircase - Re-Bar 06-Jul-11 A 07-Jul-11 A 2
A4610 Staircase - Casting 08-Jul-11 A 08-Jul-11 A 1
A4620 Slab / Beams - Formwork 01-Jul-11 A 15-Jul-11 A 15
A4630 Slab / Beams - Re-Bar 09-Jul-11 A 18-Jul-11 A 10
A4640 Slab / Beams Checking & 19-Jul-11 A 20-Jul-11 A 2
Casting
sujmall-1.1.2.2.2.4
POUR-D 24-Jul-11 22-Aug-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4650 Column Starter Marking 24-Jul-11 A 25-Jul-11 A 2

(c) Primavera Systems, Inc. Page 25 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4660 Columns - Re-Bar 26-Jul-11 A 01-Aug-11 7


A
A4670 Columns - Formwork 28-Jul-11 A 06-Aug-11 10
A
A4680 Columns - Casting 30-Jul-11 A 05-Aug-11 7
A
A4690 Shear Wall / Core Wall / Ret. 26-Jul-11 A 04-Aug-11 10
Wall Re-Bar A
A4700 Shear Wall / Core Wall / Ret. 29-Jul-11 A 07-Aug-11 10
Wall Formwork A
A4710 Shear Wall / Core Wall / Ret. 01-Aug-11 07-Aug-11 7
Wall Casting A A
A4720 Staircase - Formwork 06-Aug-11 07-Aug-11 2
A A
A4730 Staircase - Re-Bar 08-Aug-11 09-Aug-11 2
A A
A4740 Staircase - Casting 10-Aug-11 10-Aug-11 1
A A
A4750 Slab / Beams - Formwork 03-Aug-11 17-Aug-11 15
A A
A4760 Slab / Beams - Re-Bar 11-Aug-11 20-Aug-11 10
A A
A4770 Slab / Beams Checking & 21-Aug-11 22-Aug-11 2
Casting A A

sujmall-1.1.2.2.2.5
POUR-E 28-Aug-11 26-Sep-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4780 Column Starter Marking 28-Aug-11 29-Aug-11 2
A A
A4790 Columns - Re-Bar 30-Aug-11 05-Sep-11 7
A A
A4800 Columns - Formwork 01-Sep-11 10-Sep-11 10
A A

(c) Primavera Systems, Inc. Page 26 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4810 Columns - Casting 03-Sep-11 09-Sep-11 7


A A
A4820 Shear Wall / Core Wall / Ret. 30-Aug-11 08-Sep-11 10
Wall Re-Bar A A
A4830 Shear Wall / Core Wall / Ret. 02-Sep-11 11-Sep-11 10
Wall Formwork A A
A4840 Shear Wall / Core Wall / Ret. 05-Sep-11 11-Sep-11 7
Wall Casting A A
A4850 Staircase - Formwork 10-Sep-11 11-Sep-11 2
A A
A4860 Staircase - Re-Bar 12-Sep-11 13-Sep-11 2
A A
A4870 Staircase - Casting 14-Sep-11 14-Sep-11 1
A A
A4880 Slab / Beams - Formwork 07-Sep-11 21-Sep-11 15
A A
A4890 Slab / Beams - Re-Bar 15-Sep-11 24-Sep-11 10
A A
A4900 Slab / Beams Checking & 25-Sep-11 26-Sep-11 2
Casting A A

sujmall-1.1.2.2.2.6
POUR-F 13-Aug-11 11-Sep-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A4910 Column Starter Marking 13-Aug-11 14-Aug-11 2
A A
A4920 Columns - Re-Bar 15-Aug-11 21-Aug-11 7
A A
A4930 Columns - Formwork 17-Aug-11 26-Aug-11 10
A A
A4940 Columns - Casting 19-Aug-11 25-Aug-11 7
A A
A4950 Shear Wall / Core Wall / Ret. 15-Aug-11 24-Aug-11 10
Wall Re-Bar A A

(c) Primavera Systems, Inc. Page 27 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A4960 Shear Wall / Core Wall / Ret. 18-Aug-11 27-Aug-11 10


Wall Formwork A A
A4970 Shear Wall / Core Wall / Ret. 21-Aug-11 27-Aug-11 7
Wall Casting A A
A4980 Staircase - Formwork 26-Aug-11 27-Aug-11 2
A A
A4990 Staircase - Re-Bar 28-Aug-11 29-Aug-11 2
A A
A5000 Staircase - Casting 30-Aug-11 30-Aug-11 1
A A
A5010 Slab / Beams - Formwork 23-Aug-11 06-Sep-11 15
A A
A5020 Slab / Beams - Re-Bar 31-Aug-11 09-Sep-11 10
A A
A5030 Slab / Beams Checking & 10-Sep-11 11-Sep-11 2
Casting A A

sujmall-1.1.2.2.2.7
POUR-G 25-Oct-11 23-Nov-11 30 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5040 Column Starter Marking 25-Oct-11 A 26-Oct-11 A 2

A5050 Columns - Re-Bar 27-Oct-11 A 02-Nov-11 7


A
A5060 Columns - Formwork 29-Oct-11 A 07-Nov-11 10
A
A5070 Columns - Casting 31-Oct-11 A 06-Nov-11 7
A
A5080 Shear Wall / Core Wall / Ret. 27-Oct-11 A 05-Nov-11 10
Wall Re-Bar A
A5090 Shear Wall / Core Wall / Ret. 30-Oct-11 A 08-Nov-11 10
Wall Formwork A
A5100 Shear Wall / Core Wall / Ret. 02-Nov-11 08-Nov-11 7
Wall Casting A A

(c) Primavera Systems, Inc. Page 28 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5110 Staircase - Formwork 07-Nov-11 08-Nov-11 2


A A
A5120 Staircase - Re-Bar 09-Nov-11 10-Nov-11 2
A A
A5130 Staircase - Casting 11-Nov-11 11-Nov-11 1
A A
A5140 Slab / Beams - Formwork 04-Nov-11 18-Nov-11 15
A A
A5150 Slab / Beams - Re-Bar 12-Nov-11 21-Nov-11 10
A A
A5160 Slab / Beams Checking & 22-Nov-11 23-Nov-11 2
Casting A A

sujmall-1.1.2.2.3 FIRST FLOOR (104.50 LVL) 27-Aug-11 01-Dec-11 97 0


A A

sujmall-1.1.2.2.3.1
POUR-A 27-Aug-11 18-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5170 Column Starter Marking 27-Aug-11 28-Aug-11 2
A A
A5180 Columns - Re-Bar 29-Aug-11 04-Sep-11 7
A A
A5190 Columns - Formwork 30-Aug-11 08-Sep-11 10
A A
A5200 Columns - Casting 31-Aug-11 04-Sep-11 5
A A
A5210 Shear Wall / Core Wall Re-Bar 29-Aug-11 07-Sep-11 10
A A
A5220 Shear Wall / Core Wall 01-Sep-11 10-Sep-11 10
Formwork A A
A5230 Shear Wall / Core Wall Casting 04-Sep-11 10-Sep-11 7
A A
A5240 Slab / Beams - Formwork 03-Sep-11 14-Sep-11 12
A A

(c) Primavera Systems, Inc. Page 29 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5250 Slab / Beams - Re-Bar 10-Sep-11 16-Sep-11 7


A A
A5260 Slab / Beams Checking & 17-Sep-11 18-Sep-11 2
Casting A A

sujmall-1.1.2.2.3.2
POUR-B 03-Sep-11 25-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5270 Column Starter Marking 03-Sep-11 04-Sep-11 2
A A
A5280 Columns - Re-Bar 05-Sep-11 11-Sep-11 7
A A
A5290 Column Formwork 06-Sep-11 15-Sep-11 10
A A
A5300 Column Concreting 07-Sep-11 11-Sep-11 5
A A
A5310 Shear Wall / Core Wall Re-Bar 05-Sep-11 14-Sep-11 10
A A
A5320 Shear Wall / Core Wall 08-Sep-11 17-Sep-11 10
Formwork A A
A5330 Shear Wall / Core Wall Casting 11-Sep-11 17-Sep-11 7
A A
A5340 Slab / Beams Formwork 10-Sep-11 21-Sep-11 12
A A
A5350 Slab / Beams Re-Bar 17-Sep-11 23-Sep-11 7
A A
A5360 Slab / Beams Checking & 24-Sep-11 25-Sep-11 2
Casting A A

sujmall-1.1.2.2.3.3
POUR-C 04-Sep-11 26-Sep-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5370 Column Starter Marking 04-Sep-11 05-Sep-11 2
A A

(c) Primavera Systems, Inc. Page 30 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5380 Columns - Re-Bar 06-Sep-11 12-Sep-11 7


A A
A5390 Column Formwork 07-Sep-11 16-Sep-11 10
A A
A5400 Column Concreting 08-Sep-11 12-Sep-11 5
A A
A5410 Shear Wall / Core Wall Re-Bar 06-Sep-11 15-Sep-11 10
A A
A5420 Shear Wall / Core Wall 09-Sep-11 18-Sep-11 10
Formwork A A
A5430 Shear Wall / Core Wall Casting 12-Sep-11 18-Sep-11 7
A A
A5440 Slab / Beams Formwork 11-Sep-11 22-Sep-11 12
A A
A5450 Slab / Beams Re-Bar 18-Sep-11 24-Sep-11 7
A A
A5460 Slab / Beams Checking & 25-Sep-11 26-Sep-11 2
Casting A A

sujmall-1.1.2.2.3.4
POUR-D 22-Sep-11 19-Oct-11 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5470 Column Starter Marking 22-Sep-11 23-Sep-11 2
A A
A5480 Column Re-Bar 24-Sep-11 30-Sep-11 7
A A
A5490 Column Formwork 25-Sep-11 04-Oct-11 A 10
A
A5500 Column Concreting 26-Sep-11 05-Oct-11 A 10
A
A5510 Shear Wall / Core Wall Re-Bar 24-Sep-11 03-Oct-11 A 10
A
A5520 Shear Wall / Core Wall 27-Sep-11 06-Oct-11 A 10
Formwork A

(c) Primavera Systems, Inc. Page 31 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5530 Shear Wall / Core Wall Casting 30-Sep-11 06-Oct-11 A 7


A
A5540 Slab / Beams Formwork 29-Sep-11 13-Oct-11 A 15
A
A5550 Slab / Beams Re-Bar 06-Oct-11 A 17-Oct-11 A 12

A5560 Slab / Beams Checking & 18-Oct-11 A 19-Oct-11 A 2


Casting

sujmall-1.1.2.2.3.5
POUR-E 28-Sep-11 20-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5570 Column Starter Marking 28-Sep-11 29-Sep-11 2
A A
A5580 Column Re-Bar 30-Sep-11 06-Oct-11 A 7
A
A5590 Column Formwork 01-Oct-11 A 10-Oct-11 A 10

A5600 Column Concreting 02-Oct-11 A 06-Oct-11 A 5

A5610 Shear Wall / Core Wall Re-Bar 30-Sep-11 09-Oct-11 A 10


A
A5620 Shear Wall / Core Wall 03-Oct-11 A 12-Oct-11 A 10
Formwork
A5630 Shear Wall / Core Wall Casting 06-Oct-11 A 12-Oct-11 A 7

A5640 Slab / Beams Formwork 05-Oct-11 A 16-Oct-11 A 12

A5650 Slab / Beams Re-Bar 12-Oct-11 A 18-Oct-11 A 7

A5660 Slab / Beams Checking & 19-Oct-11 A 20-Oct-11 A 2


Casting

sujmall-1.1.2.2.3.6
POUR-F 02-Oct-11 24-Oct-11 23 0
A A
(c) Primavera Systems, Inc. Page 32 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A5670 Column Starter Marking 02-Oct-11 A 03-Oct-11 A 2

A5680 Column Re-Bar 04-Oct-11 A 10-Oct-11 A 7

A5690 Column Formwork 05-Oct-11 A 14-Oct-11 A 10

A5700 Column Concreting 06-Oct-11 A 10-Oct-11 A 5

A5710 Shear Wall / Core Wall Re-Bar 04-Oct-11 A 13-Oct-11 A 10

A5720 Shear Wall / Core Wall 07-Oct-11 A 16-Oct-11 A 10


Formwork
A5730 Shear Wall / Core Wall Casting 10-Oct-11 A 16-Oct-11 A 7

A5740 Slab / Beams Formwork 09-Oct-11 A 20-Oct-11 A 12

A5750 Slab / Beams Re-Bar 16-Oct-11 A 22-Oct-11 A 7

A5760 Slab / Beams Checking & 23-Oct-11 A 24-Oct-11 A 2


Casting

sujmall-1.1.2.2.3.7
POUR-G 09-Nov-11 01-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5770 Column Starter Marking 09-Nov-11 10-Nov-11 2
A A
A5780 Column Re-Bar 11-Nov-11 17-Nov-11 7
A A
A5790 Column Formwork 12-Nov-11 21-Nov-11 10
A A
A5800 Column Concreting 13-Nov-11 17-Nov-11 5
A A
A5810 Shear Wall / Core Wall Re-Bar 11-Nov-11 20-Nov-11 10
A A
(c) Primavera Systems, Inc. Page 33 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5820 Shear Wall / Core Wall 14-Nov-11 23-Nov-11 10


Formwork A A
A5830 Shear Wall / Core Wall Casting 17-Nov-11 23-Nov-11 7
A A
A5840 Slab / Beams Formwork 16-Nov-11 27-Nov-11 12
A A
A5850 Slab / Beams Re-Bar 23-Nov-11 29-Nov-11 7
A A
A5860 Slab / Beams Checking & 30-Nov-11 01-Dec-11 2
Casting A A

sujmall-1.1.2.2.4 SECOND FLOOR (109.00 LVL) 27-Sep-11 25-Dec-11 90 0


A A

sujmall-1.1.2.2.4.1
POUR-A 04-Oct-11 26-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5870 Column Starter Marking 04-Oct-11 A 05-Oct-11 A 2

A5880 Columns - Re-Bar 06-Oct-11 A 12-Oct-11 A 7

A5890 Columns - Formwork 07-Oct-11 A 16-Oct-11 A 10

A5900 Columns - Casting 08-Oct-11 A 12-Oct-11 A 5

A5910 Shear Wall / Core Wall Re-Bar 06-Oct-11 A 15-Oct-11 A 10

A5920 Shear Wall / Core Wall 09-Oct-11 A 18-Oct-11 A 10


Formwork
A5930 Shear Wall / Core Wall Casting 12-Oct-11 A 18-Oct-11 A 7

A5940 Slab / Beams - Formwork 11-Oct-11 A 22-Oct-11 A 12

A5950 Slab / Beams - Re-Bar 18-Oct-11 A 24-Oct-11 A 7

(c) Primavera Systems, Inc. Page 34 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A5960 Slab / Beams Checking & 25-Oct-11 A 26-Oct-11 A 2


Casting

sujmall-1.1.2.2.4.2
POUR-B 27-Sep-11 19-Oct-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A5970 Column Starter Marking 27-Sep-11 28-Sep-11 2
A A
A5980 Columns - Re-Bar 29-Sep-11 05-Oct-11 A 7
A
A5990 Column Formwork 30-Sep-11 09-Oct-11 A 10
A
A6000 Column Concreting 01-Oct-11 A 05-Oct-11 A 5

A6010 Shear Wall / Core Wall Re-Bar 29-Sep-11 08-Oct-11 A 10


A
A6020 Shear Wall / Core Wall 02-Oct-11 A 11-Oct-11 A 10
Formwork
A6030 Shear Wall / Core Wall Casting 05-Oct-11 A 11-Oct-11 A 7

A6040 Slab / Beams Formwork 04-Oct-11 A 15-Oct-11 A 12

A6050 Slab / Beams Re-Bar 11-Oct-11 A 17-Oct-11 A 7

A6060 Slab / Beams Checking & 18-Oct-11 A 19-Oct-11 A 2


Casting

sujmall-1.1.2.2.4.3
POUR-C 22-Oct-11 13-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6070 Column Starter Marking 22-Oct-11 A 23-Oct-11 A 2

A6080 Columns - Re-Bar 24-Oct-11 A 30-Oct-11 A 7

(c) Primavera Systems, Inc. Page 35 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6090 Column Formwork 25-Oct-11 A 03-Nov-11 10


A
A6100 Column Concreting 26-Oct-11 A 30-Oct-11 A 5

A6110 Shear Wall / Core Wall Re-Bar 24-Oct-11 A 02-Nov-11 10


A
A6120 Shear Wall / Core Wall 27-Oct-11 A 05-Nov-11 10
Formwork A
A6130 Shear Wall / Core Wall Casting 30-Oct-11 A 05-Nov-11 7
A
A6140 Slab / Beams Formwork 29-Oct-11 A 09-Nov-11 12
A
A6150 Slab / Beams Re-Bar 05-Nov-11 11-Nov-11 7
A A
A6160 Slab / Beams Checking & 12-Nov-11 13-Nov-11 2
Casting A A

sujmall-1.1.2.2.4.4
POUR-D 04-Nov-11 01-Dec-11 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6170 Column Starter Marking 04-Nov-11 05-Nov-11 2
A A
A6180 Column Re-Bar 06-Nov-11 12-Nov-11 7
A A
A6190 Column Formwork 07-Nov-11 16-Nov-11 10
A A
A6200 Column Concreting 08-Nov-11 18-Nov-11 11
A A
A6210 Shear Wall / Core Wall Re-Bar 06-Nov-11 15-Nov-11 10
A A
A6220 Shear Wall / Core Wall 09-Nov-11 18-Nov-11 10
Formwork A A
A6230 Shear Wall / Core Wall Casting 12-Nov-11 18-Nov-11 7
A A

(c) Primavera Systems, Inc. Page 36 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6240 Slab / Beams Formwork 11-Nov-11 25-Nov-11 15


A A
A6250 Slab / Beams Re-Bar 18-Nov-11 29-Nov-11 12
A A
A6260 Slab / Beams Checking & 30-Nov-11 01-Dec-11 2
Casting A A

sujmall-1.1.2.2.4.5
POUR-E 22-Oct-11 13-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6270 Column Starter Marking 22-Oct-11 A 23-Oct-11 A 2

A6280 Column Re-Bar 24-Oct-11 A 30-Oct-11 A 7

A6290 Column Formwork 25-Oct-11 A 03-Nov-11 10


A
A6300 Column Concreting 26-Oct-11 A 30-Oct-11 A 5

A6310 Shear Wall / Core Wall Re-Bar 24-Oct-11 A 02-Nov-11 10


A
A6320 Shear Wall / Core Wall 27-Oct-11 A 05-Nov-11 10
Formwork A
A6330 Shear Wall / Core Wall Casting 30-Oct-11 A 05-Nov-11 7
A
A6340 Slab / Beams Formwork 29-Oct-11 A 09-Nov-11 12
A
A6350 Slab / Beams Re-Bar 05-Nov-11 11-Nov-11 7
A A
A6360 Slab / Beams Checking & 12-Nov-11 13-Nov-11 2
Casting A A

sujmall-1.1.2.2.4.6
POUR-F 26-Oct-11 17-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 37 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6370 Column Starter Marking 26-Oct-11 A 27-Oct-11 A 2

A6380 Column Re-Bar 28-Oct-11 A 03-Nov-11 7


A
A6390 Column Formwork 29-Oct-11 A 07-Nov-11 10
A
A6400 Column Concreting 30-Oct-11 A 03-Nov-11 5
A
A6410 Shear Wall / Core Wall Re-Bar 28-Oct-11 A 06-Nov-11 10
A
A6420 Shear Wall / Core Wall 31-Oct-11 A 09-Nov-11 10
Formwork A
A6430 Shear Wall / Core Wall Casting 03-Nov-11 09-Nov-11 7
A A
A6440 Slab / Beams Formwork 02-Nov-11 13-Nov-11 12
A A
A6450 Slab / Beams Re-Bar 09-Nov-11 15-Nov-11 7
A A
A6460 Slab / Beams Checking & 16-Nov-11 17-Nov-11 2
Casting A A

sujmall-1.1.2.2.4.7
POUR-G 03-Dec-11 25-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6470 Column Starter Marking 03-Dec-11 04-Dec-11 2
A A
A6480 Column Re-Bar 05-Dec-11 11-Dec-11 7
A A
A6490 Column Formwork 06-Dec-11 15-Dec-11 10
A A
A6500 Column Concreting 07-Dec-11 11-Dec-11 5
A A
A6510 Shear Wall / Core Wall Re-Bar 05-Dec-11 14-Dec-11 10
A A

(c) Primavera Systems, Inc. Page 38 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6520 Shear Wall / Core Wall 08-Dec-11 17-Dec-11 10


Formwork A A
A6530 Shear Wall / Core Wall Casting 11-Dec-11 17-Dec-11 7
A A
A6540 Slab / Beams Formwork 10-Dec-11 21-Dec-11 12
A A
A6550 Slab / Beams Re-Bar 17-Dec-11 23-Dec-11 7
A A
A6560 Slab / Beams Checking & 24-Dec-11 25-Dec-11 2
Casting A A

sujmall-1.1.2.2.5 THIRD FLOOR (113.50 LVL) 21-Oct-11 18-Jan-12 90 0


A A

sujmall-1.1.2.2.5.1
POUR-A 26-Nov-11 18-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6570 Column Starter Marking 26-Nov-11 27-Nov-11 2
A A
A6580 Columns - Re-Bar 28-Nov-11 04-Dec-11 7
A A
A6590 Columns - Formwork 29-Nov-11 08-Dec-11 10
A A
A6600 Columns - Casting 30-Nov-11 04-Dec-11 5
A A
A6610 Shear Wall / Core Wall Re-Bar 28-Nov-11 07-Dec-11 10
A A
A6620 Shear Wall / Core Wall 01-Dec-11 10-Dec-11 10
Formwork A A
A6630 Shear Wall / Core Wall Casting 04-Dec-11 10-Dec-11 7
A A
A6640 Slab / Beams - Formwork 03-Dec-11 14-Dec-11 12
A A
A6650 Slab / Beams - Re-Bar 10-Dec-11 16-Dec-11 7
A A

(c) Primavera Systems, Inc. Page 39 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6660 Slab / Beams Checking & 17-Dec-11 18-Dec-11 2


Casting A A

sujmall-1.1.2.2.5.2
POUR-B 21-Oct-11 12-Nov-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6670 Column Starter Marking 21-Oct-11 A 22-Oct-11 A 2

A6680 Columns - Re-Bar 23-Oct-11 A 29-Oct-11 A 7

A6690 Column Formwork 24-Oct-11 A 02-Nov-11 10


A
A6700 Column Concreting 25-Oct-11 A 29-Oct-11 A 5

A6710 Shear Wall / Core Wall Re-Bar 23-Oct-11 A 01-Nov-11 10


A
A6720 Shear Wall / Core Wall 26-Oct-11 A 04-Nov-11 10
Formwork A
A6730 Shear Wall / Core Wall Casting 29-Oct-11 A 04-Nov-11 7
A
A6740 Slab / Beams Formwork 28-Oct-11 A 08-Nov-11 12
A
A6750 Slab / Beams Re-Bar 04-Nov-11 10-Nov-11 7
A A
A6760 Slab / Beams Checking & 11-Nov-11 12-Nov-11 2
Casting A A

sujmall-1.1.2.2.5.3
POUR-C 15-Nov-11 07-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6770 Column Starter Marking 15-Nov-11 16-Nov-11 2
A A
A6780 Columns - Re-Bar 17-Nov-11 23-Nov-11 7
A A

(c) Primavera Systems, Inc. Page 40 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6790 Column Formwork 18-Nov-11 27-Nov-11 10


A A
A6800 Column Concreting 19-Nov-11 23-Nov-11 5
A A
A6810 Shear Wall / Core Wall Re-Bar 17-Nov-11 26-Nov-11 10
A A
A6820 Shear Wall / Core Wall 20-Nov-11 29-Nov-11 10
Formwork A A
A6830 Shear Wall / Core Wall Casting 23-Nov-11 29-Nov-11 7
A A
A6840 Slab / Beams Formwork 22-Nov-11 03-Dec-11 12
A A
A6850 Slab / Beams Re-Bar 29-Nov-11 05-Dec-11 7
A A
A6860 Slab / Beams Checking & 06-Dec-11 07-Dec-11 2
Casting A A

sujmall-1.1.2.2.5.4
POUR-D 17-Dec-11 13-Jan-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6870 Column Starter Marking 17-Dec-11 18-Dec-11 2
A A
A6880 Column Re-Bar 19-Dec-11 25-Dec-11 7
A A
A6890 Column Formwork 20-Dec-11 29-Dec-11 10
A A
A6900 Column Concreting 21-Dec-11 30-Dec-11 10
A A
A6910 Shear Wall / Core Wall Re-Bar 19-Dec-11 28-Dec-11 10
A A
A6920 Shear Wall / Core Wall 22-Dec-11 31-Dec-11 10
Formwork A A
A6930 Shear Wall / Core Wall Casting 25-Dec-11 31-Dec-11 7
A A

(c) Primavera Systems, Inc. Page 41 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A6940 Slab / Beams Formwork 24-Dec-11 07-Jan-12 A 15


A
A6950 Slab / Beams Re-Bar 31-Dec-11 11-Jan-12 A 12
A
A6960 Slab / Beams Checking & 12-Jan-12 A 13-Jan-12 A 2
Casting

sujmall-1.1.2.2.5.5
POUR-E 15-Nov-11 07-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A6970 Column Starter Marking 15-Nov-11 16-Nov-11 2
A A
A6980 Column Re-Bar 17-Nov-11 23-Nov-11 7
A A
A6990 Column Formwork 18-Nov-11 27-Nov-11 10
A A
A7000 Column Concreting 19-Nov-11 23-Nov-11 5
A A
A7010 Shear Wall / Core Wall Re-Bar 17-Nov-11 26-Nov-11 10
A A
A7020 Shear Wall / Core Wall 20-Nov-11 29-Nov-11 10
Formwork A A
A7030 Shear Wall / Core Wall Casting 23-Nov-11 29-Nov-11 7
A A
A7040 Slab / Beams Formwork 22-Nov-11 03-Dec-11 12
A A
A7050 Slab / Beams Re-Bar 29-Nov-11 05-Dec-11 7
A A
A7060 Slab / Beams Checking & 06-Dec-11 07-Dec-11 2
Casting A A

sujmall-1.1.2.2.5.6
POUR-F 19-Nov-11 11-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 42 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A7070 Column Starter Marking 19-Nov-11 20-Nov-11 2


A A
A7080 Column Re-Bar 21-Nov-11 27-Nov-11 7
A A
A7090 Column Formwork 22-Nov-11 01-Dec-11 10
A A
A7100 Column Concreting 23-Nov-11 27-Nov-11 5
A A
A7110 Shear Wall / Core Wall Re-Bar 21-Nov-11 30-Nov-11 10
A A
A7120 Shear Wall / Core Wall 24-Nov-11 03-Dec-11 10
Formwork A A
A7130 Shear Wall / Core Wall Casting 27-Nov-11 03-Dec-11 7
A A
A7140 Slab / Beams Formwork 26-Nov-11 07-Dec-11 12
A A
A7150 Slab / Beams Re-Bar 03-Dec-11 09-Dec-11 7
A A
A7160 Slab / Beams Checking & 10-Dec-11 11-Dec-11 2
Casting A A

sujmall-1.1.2.2.5.7
POUR-G 27-Dec-11 18-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7170 Column Starter Marking 27-Dec-11 28-Dec-11 2
A A
A7180 Column Re-Bar 29-Dec-11 04-Jan-12 A 7
A
A7190 Column Formwork 30-Dec-11 08-Jan-12 A 10
A
A7200 Column Concreting 31-Dec-11 04-Jan-12 A 5
A
A7210 Shear Wall / Core Wall Re-Bar 29-Dec-11 07-Jan-12 A 10
A

(c) Primavera Systems, Inc. Page 43 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A7220 Shear Wall / Core Wall 01-Jan-12 A 10-Jan-12 A 10


Formwork
A7230 Shear Wall / Core Wall Casting 04-Jan-12 A 10-Jan-12 A 7

A7240 Slab / Beams Formwork 03-Jan-12 A 14-Jan-12 A 12

A7250 Slab / Beams Re-Bar 10-Jan-12 A 16-Jan-12 A 7

A7260 Slab / Beams Checking & 17-Jan-12 A 18-Jan-12 A 2


Casting

sujmall-1.1.2.3 CINEMA FLOOR WORKS (4th & 14-Nov-11 29-Feb-12 108 0


5th) A A

sujmall-1.1.2.3.1 THEATRE EXIT FLOOR (117.50 14-Jan-12 08-Feb-12 26 0


LVL) A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13800 Column Starter Marking 14-Jan-12 A 15-Jan-12 A 2

A13810 Columns - Re-Bar 16-Jan-12 A 25-Jan-12 A 10

A13820 Columns - Formwork 17-Jan-12 A 31-Jan-12 A 15

A13830 Columns - Casting 18-Jan-12 A 01-Feb-12 15


A
A13840 Shear Wall / Core Wall Re-Bar 16-Jan-12 A 25-Jan-12 A 10

A13850 Shear Wall / Core Wall 19-Jan-12 A 28-Jan-12 A 10


Formwork
A13860 Shear Wall / Core Wall Casting 22-Jan-12 A 28-Jan-12 A 7

A13870 Slab / Beams - Formwork 21-Jan-12 A 04-Feb-12 15


A
A13880 Slab / Beams - Re-Bar 28-Jan-12 A 06-Feb-12 10
A

(c) Primavera Systems, Inc. Page 44 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A13890 Slab / Beams Checking & 07-Feb-12 08-Feb-12 2


Casting A A

sujmall-1.1.2.3.2 FOURTH FLOOR (120.50 LVL) 14-Nov-11 25-Feb-12 104 0


A A

sujmall-1.1.2.3.2.1
POUR-A 20-Dec-11 11-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7270 Column Starter Marking 20-Dec-11 21-Dec-11 2
A A
A7280 Columns - Re-Bar 22-Dec-11 28-Dec-11 7
A A
A7290 Columns - Formwork 23-Dec-11 01-Jan-12 A 10
A
A7300 Columns - Casting 24-Dec-11 28-Dec-11 5
A A
A7310 Shear Wall / Core Wall Re-Bar 22-Dec-11 31-Dec-11 10
A A
A7320 Shear Wall / Core Wall 25-Dec-11 03-Jan-12 A 10
Formwork A
A7330 Shear Wall / Core Wall Casting 28-Dec-11 03-Jan-12 A 7
A
A7340 Slab / Beams - Formwork 27-Dec-11 07-Jan-12 A 12
A
A7350 Slab / Beams - Re-Bar 03-Jan-12 A 09-Jan-12 A 7

A7360 Slab / Beams Checking & 10-Jan-12 A 11-Jan-12 A 2


Casting

sujmall-1.1.2.3.2.2
POUR-B 14-Nov-11 06-Dec-11 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7370 Column Starter Marking 14-Nov-11 15-Nov-11 2
A A
(c) Primavera Systems, Inc. Page 45 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A7380 Columns - Re-Bar 16-Nov-11 22-Nov-11 7


A A
A7390 Column Formwork 17-Nov-11 26-Nov-11 10
A A
A7400 Column Concreting 18-Nov-11 22-Nov-11 5
A A
A7410 Shear Wall / Core Wall Re-Bar 16-Nov-11 25-Nov-11 10
A A
A7420 Shear Wall / Core Wall 19-Nov-11 28-Nov-11 10
Formwork A A
A7430 Shear Wall / Core Wall Casting 22-Nov-11 28-Nov-11 7
A A
A7440 Slab / Beams Formwork 21-Nov-11 02-Dec-11 12
A A
A7450 Slab / Beams Re-Bar 28-Nov-11 04-Dec-11 7
A A
A7460 Slab / Beams Checking & 05-Dec-11 06-Dec-11 2
Casting A A

sujmall-1.1.2.3.2.3
POUR-C 09-Dec-11 31-Jan-12 54 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7470 Column Starter Marking 09-Dec-11 10-Dec-11 2
A A
A7480 Columns - Re-Bar 11-Dec-11 17-Dec-11 7
A A
A7490 Column Formwork 12-Dec-11 21-Dec-11 10
A A
A7500 Column Concreting 13-Dec-11 17-Dec-11 5
A A
A7510 Shear Wall / Core Wall Re-Bar 11-Dec-11 20-Dec-11 10
A A
A7520 Shear Wall / Core Wall 14-Dec-11 23-Dec-11 10
Formwork A A

(c) Primavera Systems, Inc. Page 46 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A7530 Shear Wall / Core Wall Casting 17-Dec-11 23-Dec-11 7


A A
A7540 Slab / Beams Formwork 16-Dec-11 27-Dec-11 12
A A
A7550 Slab / Beams Re-Bar 23-Dec-11 29-Dec-11 7
A A
A7560 Slab / Beams Checking & 30-Dec-11 31-Jan-12 A 33
Casting A

sujmall-1.1.2.3.2.4
POUR-D 29-Jan-12 25-Feb-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7570 Column Starter Marking 29-Jan-12 A 30-Jan-12 A 2

A7580 Column Re-Bar 31-Jan-12 A 06-Feb-12 7


A
A7590 Column Formwork 01-Feb-12 10-Feb-12 10
A A
A7600 Column Concreting 02-Feb-12 11-Feb-12 10
A A
A7610 Shear Wall / Core Wall Re-Bar 31-Jan-12 A 09-Feb-12 10
A
A7620 Shear Wall / Core Wall 03-Feb-12 12-Feb-12 10
Formwork A A
A7630 Shear Wall / Core Wall Casting 06-Feb-12 12-Feb-12 7
A A
A7640 Slab / Beams Formwork 05-Feb-12 19-Feb-12 15
A A
A7650 Slab / Beams Re-Bar 12-Feb-12 23-Feb-12 12
A A
A7660 Slab / Beams Checking & 24-Feb-12 25-Feb-12 2
Casting A A

sujmall-1.1.2.3.2.5
POUR-E 09-Dec-11 05-Jan-12 28 0
A A
(c) Primavera Systems, Inc. Page 47 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A7670 Column Starter Marking 09-Dec-11 10-Dec-11 2
A A
A7680 Column Re-Bar 11-Dec-11 17-Dec-11 7
A A
A7690 Column Formwork 12-Dec-11 21-Dec-11 10
A A
A7700 Column Concreting 13-Dec-11 22-Dec-11 10
A A
A7710 Shear Wall / Core Wall Re-Bar 11-Dec-11 20-Dec-11 10
A A
A7720 Shear Wall / Core Wall 14-Dec-11 23-Dec-11 10
Formwork A A
A7730 Shear Wall / Core Wall Casting 17-Dec-11 23-Dec-11 7
A A
A7740 Slab / Beams Formwork 16-Dec-11 30-Dec-11 15
A A
A7750 Slab / Beams Re-Bar 23-Dec-11 03-Jan-12 A 12
A
A7760 Slab / Beams Checking & 04-Jan-12 A 05-Jan-12 A 2
Casting

sujmall-1.1.2.3.2.6
POUR-F 13-Dec-11 09-Jan-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7770 Column Starter Marking 13-Dec-11 14-Dec-11 2
A A
A7780 Column Re-Bar 15-Dec-11 21-Dec-11 7
A A
A7790 Column Formwork 16-Dec-11 25-Dec-11 10
A A
A7800 Column Concreting 17-Dec-11 26-Dec-11 10
A A
A7810 Shear Wall / Core Wall Re-Bar 15-Dec-11 24-Dec-11 10
A A
(c) Primavera Systems, Inc. Page 48 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A7820 Shear Wall / Core Wall 18-Dec-11 27-Dec-11 10


Formwork A A
A7830 Shear Wall / Core Wall Casting 21-Dec-11 27-Dec-11 7
A A
A7840 Slab / Beams Formwork 20-Dec-11 03-Jan-12 A 15
A
A7850 Slab / Beams Re-Bar 27-Dec-11 07-Jan-12 A 12
A
A7860 Slab / Beams Checking & 08-Jan-12 A 09-Jan-12 A 2
Casting

sujmall-1.1.2.3.2.7
POUR-G 20-Jan-12 16-Feb-12 28 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A7870 Column Starter Marking 20-Jan-12 A 21-Jan-12 A 2

A7880 Column Re-Bar 22-Jan-12 A 28-Jan-12 A 7

A7890 Column Formwork 23-Jan-12 A 01-Feb-12 10


A
A7900 Column Concreting 24-Jan-12 A 02-Feb-12 10
A
A7910 Shear Wall / Core Wall Re-Bar 22-Jan-12 A 31-Jan-12 A 10

A7920 Shear Wall / Core Wall 25-Jan-12 A 03-Feb-12 10


Formwork A
A7930 Shear Wall / Core Wall Casting 28-Jan-12 A 03-Feb-12 7
A
A7940 Slab / Beams Formwork 27-Jan-12 A 10-Feb-12 15
A
A7950 Slab / Beams Re-Bar 03-Feb-12 14-Feb-12 12
A A
A7960 Slab / Beams Checking & 15-Feb-12 16-Feb-12 2
Casting A A

(c) Primavera Systems, Inc. Page 49 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.2.3.3 FIFTH FLOOR (124.50 LVL) 04-Feb-12 29-Feb-12 26 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13900 Columns - Formwork 07-Feb-12 21-Feb-12 15
A A
A7970 Column Starter Marking 04-Feb-12 05-Feb-12 2
A A
A7980 Columns - Re-Bar 06-Feb-12 15-Feb-12 10
A A
A7990 Columns - Casting 08-Feb-12 22-Feb-12 15
A A
A8000 Shear Wall / Core Wall Re-Bar 06-Feb-12 15-Feb-12 10
A A
A8010 Shear Wall / Core Wall 09-Feb-12 18-Feb-12 10
Formwork A A
A8020 Shear Wall / Core Wall Casting 12-Feb-12 18-Feb-12 7
A A
A8030 Slab / Beams - Formwork 11-Feb-12 25-Feb-12 15
A A
A8040 Slab / Beams - Re-Bar 18-Feb-12 27-Feb-12 10
A A
A8050 Slab / Beams Checking & 28-Feb-12 29-Feb-12 2
Casting A A

sujmall-1.1.2.4 TERRACE WORKS (6th) 02-Jan-12 11-May-12 131 0


A A

sujmall-1.1.2.4.1 TERRACE FLOOR (127.50 LVL) 02-Jan-12 11-May-12 131 0


A A

sujmall-1.1.2.4.1.1
POUR-A 13-Jan-12 04-Feb-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13910 Shear Wall / Core Wall Re-Bar 15-Jan-12 A 24-Jan-12 A 10

(c) Primavera Systems, Inc. Page 50 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A8060 Column Starter Marking 13-Jan-12 A 14-Jan-12 A 2

A8070 Columns - Re-Bar 15-Jan-12 A 21-Jan-12 A 7

A8080 Columns - Formwork 16-Jan-12 A 25-Jan-12 A 10

A8090 Columns - CastingShear Wall / 17-Jan-12 A 21-Jan-12 A 5


Core Wall Re-Bar
A8100 Shear Wall / Core Wall 18-Jan-12 A 27-Jan-12 A 10
Formwork
A8110 Shear Wall / Core Wall Casting 21-Jan-12 A 27-Jan-12 A 7

A8120 Slab / Beams - Formwork 20-Jan-12 A 30-Jan-12 A 11

A8130 Slab / Beams - Re-Bar 27-Jan-12 A 02-Feb-12 7


A
A8140 Slab / Beams Checking & 03-Feb-12 04-Feb-12 2
Casting A A

sujmall-1.1.2.4.1.2
POUR-B 06-Jan-12 28-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8150 Column Starter Marking 06-Jan-12 A 07-Jan-12 A 2

A8160 Columns - Re-Bar 08-Jan-12 A 14-Jan-12 A 7

A8170 Column Formwork 09-Jan-12 A 18-Jan-12 A 10

A8180 Column Concreting 10-Jan-12 A 14-Jan-12 A 5

A8190 Shear Wall / Core Wall Re-Bar 08-Jan-12 A 17-Jan-12 A 10

A8200 Shear Wall / Core Wall 11-Jan-12 A 20-Jan-12 A 10


Formwork

(c) Primavera Systems, Inc. Page 51 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A8210 Shear Wall / Core Wall Casting 14-Jan-12 A 20-Jan-12 A 7

A8220 Slab / Beams Formwork 13-Jan-12 A 24-Jan-12 A 12

A8230 Slab / Beams Re-Bar 20-Jan-12 A 26-Jan-12 A 7

A8240 Slab / Beams Checking & 27-Jan-12 A 28-Jan-12 A 2


Casting

sujmall-1.1.2.4.1.3
POUR-C 02-Jan-12 24-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8250 Column Starter Marking 02-Jan-12 A 03-Jan-12 A 2

A8260 Columns - Re-Bar 04-Jan-12 A 10-Jan-12 A 7

A8270 Column Formwork 05-Jan-12 A 14-Jan-12 A 10

A8280 Column Concreting 06-Jan-12 A 10-Jan-12 A 5

A8290 Shear Wall / Core Wall Re-Bar 04-Jan-12 A 13-Jan-12 A 10

A8300 Shear Wall / Core Wall 07-Jan-12 A 16-Jan-12 A 10


Formwork
A8310 Shear Wall / Core Wall Casting 10-Jan-12 A 16-Jan-12 A 7

A8320 Slab / Beams Formwork 09-Jan-12 A 20-Jan-12 A 12

A8330 Slab / Beams Re-Bar 16-Jan-12 A 22-Jan-12 A 7

A8340 Slab / Beams Checking & 23-Jan-12 A 24-Jan-12 A 2


Casting

sujmall-1.1.2.4.1.4
POUR-D 27-Feb-12 20-Mar-12 23 0
A A
(c) Primavera Systems, Inc. Page 52 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A8350 Column Starter Marking 27-Feb-12 28-Feb-12 2
A A
A8360 Column Re-Bar 29-Feb-12 06-Mar-12 7
A A
A8370 Column Formwork 01-Mar-12 10-Mar-12 10
A A
A8380 Column Concreting 02-Mar-12 06-Mar-12 5
A A
A8390 Shear Wall / Core Wall Re-Bar 29-Feb-12 09-Mar-12 10
A A
A8400 Shear Wall / Core Wall 03-Mar-12 12-Mar-12 10
Formwork A A
A8410 Shear Wall / Core Wall Casting 06-Mar-12 12-Mar-12 7
A A
A8420 Slab / Beams Formwork 05-Mar-12 16-Mar-12 12
A A
A8430 Slab / Beams Re-Bar 12-Mar-12 18-Mar-12 7
A A
A8440 Slab / Beams Checking & 19-Mar-12 20-Mar-12 2
Casting A A

sujmall-1.1.2.4.1.5
POUR-E 07-Jan-12 29-Jan-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8450 Column Starter Marking 07-Jan-12 A 08-Jan-12 A 2

A8460 Column Re-Bar 09-Jan-12 A 15-Jan-12 A 7

A8470 Column Formwork 10-Jan-12 A 19-Jan-12 A 10

A8480 Column Concreting 11-Jan-12 A 15-Jan-12 A 5

A8490 Shear Wall / Core Wall Re-Bar 09-Jan-12 A 18-Jan-12 A 10

(c) Primavera Systems, Inc. Page 53 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A8500 Shear Wall / Core Wall 12-Jan-12 A 21-Jan-12 A 10


Formwork
A8510 Shear Wall / Core Wall Casting 15-Jan-12 A 21-Jan-12 A 7

A8520 Slab / Beams Formwork 14-Jan-12 A 25-Jan-12 A 12

A8530 Slab / Beams Re-Bar 21-Jan-12 A 27-Jan-12 A 7

A8540 Slab / Beams Checking & 28-Jan-12 A 29-Jan-12 A 2


Casting

sujmall-1.1.2.4.1.6
POUR-F 11-Jan-12 02-Feb-12 23 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8550 Column Starter Marking 11-Jan-12 A 12-Jan-12 A 2

A8560 Column Re-Bar 13-Jan-12 A 19-Jan-12 A 7

A8570 Column Formwork 14-Jan-12 A 23-Jan-12 A 10

A8580 Column Concreting 15-Jan-12 A 19-Jan-12 A 5

A8590 Shear Wall / Core Wall Re-Bar 13-Jan-12 A 22-Jan-12 A 10

A8600 Shear Wall / Core Wall 16-Jan-12 A 25-Jan-12 A 10


Formwork
A8610 Shear Wall / Core Wall Casting 19-Jan-12 A 25-Jan-12 A 7

A8620 Slab / Beams Formwork 18-Jan-12 A 29-Jan-12 A 12

A8630 Slab / Beams Re-Bar 25-Jan-12 A 31-Jan-12 A 7

A8640 Slab / Beams Checking & 01-Feb-12 02-Feb-12 2


Casting A A

(c) Primavera Systems, Inc. Page 54 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.2.4.1.7
POUR-G 18-Feb-12 11-May-12 84 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8650 Column Starter Marking 18-Feb-12 19-Feb-12 2
A A
A8660 Column Re-Bar 20-Feb-12 26-Feb-12 7
A A
A8670 Column Formwork 21-Feb-12 01-Mar-12 10
A A
A8680 Column Concreting 22-Feb-12 26-Feb-12 5
A A
A8690 Shear Wall / Core Wall Re-Bar 20-Feb-12 29-Feb-12 10
A A
A8700 Shear Wall / Core Wall 23-Feb-12 03-Mar-12 10
Formwork A A
A8710 Shear Wall / Core Wall Casting 26-Feb-12 03-Mar-12 7
A A
A8720 Slab / Beams Formwork 25-Feb-12 07-Mar-12 12
A A
A8730 Slab / Beams Re-Bar 03-Mar-12 09-Mar-12 7
A A
A8740 Slab / Beams Checking & 10-May-12 11-May-12 2
Casting A A

sujmall-1.1.2.5 MLCP SLAB 30-Jan-11 08-Mar-12 404 0


A A

sujmall-1.1.2.5.1 MLCP Level 2 (102.90 LVL) 23-Oct-11 10-Nov-11 19 0


A A

sujmall-1.1.2.5.1.1
POUR-A 23-Oct-11 07-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8750 Column Starter Marking 23-Oct-11 A 23-Oct-11 A 1

(c) Primavera Systems, Inc. Page 55 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A8760 Columns - Re-Bar 24-Oct-11 A 25-Oct-11 A 2

A8770 Columns - Formwork 25-Oct-11 A 27-Oct-11 A 3

A8780 Columns - Casting 26-Oct-11 A 29-Oct-11 A 4

A8790 Slab / Beams - Formwork 29-Oct-11 A 04-Nov-11 7


A
A8800 Slab / Beams - Re-Bar 01-Nov-11 05-Nov-11 5
A A
A8810 Slab / Beams Checking & 06-Nov-11 07-Nov-11 2
Casting A A

sujmall-1.1.2.5.1.2
POUR-B 26-Oct-11 10-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8820 Column Starter Marking 26-Oct-11 A 26-Oct-11 A 1

A8830 Columns - Re-Bar 27-Oct-11 A 28-Oct-11 A 2

A8840 Columns - Formwork 28-Oct-11 A 30-Oct-11 A 3

A8850 Columns - Casting 29-Oct-11 A 01-Nov-11 4


A
A8860 Slab / Beams - Formwork 01-Nov-11 07-Nov-11 7
A A
A8870 Slab / Beams - Re-Bar 04-Nov-11 08-Nov-11 5
A A
A8880 Slab / Beams Checking & 09-Nov-11 10-Nov-11 2
Casting A A

sujmall-1.1.2.5.2 MLCP Level 3 (105.90 LVL) 09-Nov-11 27-Nov-11 19 0


A A

sujmall-1.1.2.5.2.1
POUR-A 09-Nov-11 24-Nov-11 16 0

(c) Primavera Systems, Inc. Page 56 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A8890 Column Starter Marking 09-Nov-11 09-Nov-11 1
A A
A8900 Columns - Re-Bar 10-Nov-11 11-Nov-11 2
A A
A8910 Columns - Formwork 11-Nov-11 13-Nov-11 3
A A
A8920 Columns - Casting 12-Nov-11 15-Nov-11 4
A A
A8930 Slab / Beams - Formwork 15-Nov-11 21-Nov-11 7
A A
A8940 Slab / Beams - Re-Bar 18-Nov-11 22-Nov-11 5
A A
A8950 Slab / Beams Checking & 23-Nov-11 24-Nov-11 2
Casting A A

sujmall-1.1.2.5.2.2
POUR-B 12-Nov-11 27-Nov-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A8960 Column Starter Marking 12-Nov-11 12-Nov-11 1
A A
A8970 Columns - Re-Bar 13-Nov-11 14-Nov-11 2
A A
A8980 Columns - Formwork 14-Nov-11 16-Nov-11 3
A A
A8990 Columns - Casting 15-Nov-11 18-Nov-11 4
A A
A9000 Slab / Beams - Formwork 18-Nov-11 24-Nov-11 7
A A
A9010 Slab / Beams - Re-Bar 21-Nov-11 25-Nov-11 5
A A
A9020 Slab / Beams Checking & 26-Nov-11 27-Nov-11 2
Casting A A

(c) Primavera Systems, Inc. Page 57 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.2.5.3 MLCP Level 4 (108.90 LVL) 26-Nov-11 14-Dec-11 19 0


A A

sujmall-1.1.2.5.3.1
POUR-A 26-Nov-11 11-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9030 Column Starter Marking 26-Nov-11 26-Nov-11 1
A A
A9040 Columns - Re-Bar 27-Nov-11 28-Nov-11 2
A A
A9050 Columns - Formwork 28-Nov-11 30-Nov-11 3
A A
A9060 Columns - Casting 29-Nov-11 02-Dec-11 4
A A
A9070 Slab / Beams - Formwork 02-Dec-11 08-Dec-11 7
A A
A9080 Slab / Beams - Re-Bar 05-Dec-11 09-Dec-11 5
A A
A9090 Slab / Beams Checking & 10-Dec-11 11-Dec-11 2
Casting A A

sujmall-1.1.2.5.3.2
POUR-B 29-Nov-11 14-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9100 Column Starter Marking 29-Nov-11 29-Nov-11 1
A A
A9110 Columns - Re-Bar 30-Nov-11 01-Dec-11 2
A A
A9120 Columns - Formwork 01-Dec-11 03-Dec-11 3
A A
A9130 Columns - Casting 02-Dec-11 05-Dec-11 4
A A
A9140 Slab / Beams - Formwork 05-Dec-11 11-Dec-11 7
A A

(c) Primavera Systems, Inc. Page 58 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9150 Slab / Beams - Re-Bar 08-Dec-11 12-Dec-11 5


A A
A9160 Slab / Beams Checking & 13-Dec-11 14-Dec-11 2
Casting A A

sujmall-1.1.2.5.4 MLCP Level 5 (111.90 LVL) 13-Dec-11 31-Dec-11 19 0


A A

sujmall-1.1.2.5.4.1
POUR-A 13-Dec-11 28-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9170 Column Starter Marking 13-Dec-11 13-Dec-11 1
A A
A9180 Columns - Re-Bar 14-Dec-11 15-Dec-11 2
A A
A9190 Columns - Formwork 15-Dec-11 17-Dec-11 3
A A
A9200 Columns - Casting 16-Dec-11 19-Dec-11 4
A A
A9210 Slab / Beams - Formwork 19-Dec-11 25-Dec-11 7
A A
A9220 Slab / Beams - Re-Bar 22-Dec-11 26-Dec-11 5
A A
A9230 Slab / Beams Checking & 27-Dec-11 28-Dec-11 2
Casting A A

sujmall-1.1.2.5.4.2
POUR-B 16-Dec-11 31-Dec-11 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9240 Column Starter Marking 16-Dec-11 16-Dec-11 1
A A
A9250 Columns - Re-Bar 17-Dec-11 18-Dec-11 2
A A
A9260 Columns - Formwork 18-Dec-11 20-Dec-11 3
A A
(c) Primavera Systems, Inc. Page 59 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9270 Columns - Casting 19-Dec-11 22-Dec-11 4


A A
A9280 Slab / Beams - Formwork 22-Dec-11 28-Dec-11 7
A A
A9290 Slab / Beams - Re-Bar 25-Dec-11 29-Dec-11 5
A A
A9300 Slab / Beams Checking & 30-Dec-11 31-Dec-11 2
Casting A A

sujmall-1.1.2.5.5 MLCP Level 6 (114.90 LVL) 30-Dec-11 17-Jan-12 19 0


A A

sujmall-1.1.2.5.5.1
POUR-A 30-Dec-11 14-Jan-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9310 Column Starter Marking 30-Dec-11 30-Dec-11 1
A A
A9320 Columns - Re-Bar 31-Dec-11 01-Jan-12 A 2
A
A9330 Columns - Formwork 01-Jan-12 A 03-Jan-12 A 3

A9340 Columns - Casting 02-Jan-12 A 05-Jan-12 A 4

A9350 Slab / Beams - Formwork 05-Jan-12 A 11-Jan-12 A 7

A9360 Slab / Beams - Re-Bar 08-Jan-12 A 12-Jan-12 A 5

A9370 Slab / Beams Checking & 13-Jan-12 A 14-Jan-12 A 2


Casting

sujmall-1.1.2.5.5.2
POUR-B 02-Jan-12 17-Jan-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9380 Column Starter Marking 02-Jan-12 A 02-Jan-12 A 1

(c) Primavera Systems, Inc. Page 60 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9390 Columns - Re-Bar 03-Jan-12 A 04-Jan-12 A 2

A9400 Columns - Formwork 04-Jan-12 A 06-Jan-12 A 3

A9410 Columns - Casting 05-Jan-12 A 08-Jan-12 A 4

A9420 Slab / Beams - Formwork 08-Jan-12 A 14-Jan-12 A 7

A9430 Slab / Beams - Re-Bar 11-Jan-12 A 15-Jan-12 A 5

A9440 Slab / Beams Checking & 16-Jan-12 A 17-Jan-12 A 2


Casting

sujmall-1.1.2.5.6 MLCP Level 7 (117.90 LVL) 30-Jan-11 03-Feb-12 370 0


A A

sujmall-1.1.2.5.6.1
POUR-A 30-Jan-11 29-Jan-12 365 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9450 Column Starter Marking 16-Jan-12 A 16-Jan-12 A 1

A9460 Columns - Re-Bar 17-Jan-12 A 18-Jan-12 A 2

A9470 Columns - Formwork 18-Jan-12 A 20-Jan-12 A 3

A9480 Columns - Casting 19-Jan-12 A 22-Jan-12 A 4

A9490 Slab / Beams - Formwork 22-Jan-12 A 28-Jan-12 A 7

A9500 Slab / Beams - Re-Bar 25-Jan-12 A 29-Jan-12 A 5

A9510 Slab / Beams Checking & 30-Jan-11 A 31-Jan-11 A 2


Casting

sujmall-1.1.2.5.6.2
POUR-B 19-Jan-12 03-Feb-12 16 0

(c) Primavera Systems, Inc. Page 61 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A9520 Column Starter Marking 19-Jan-12 A 19-Jan-12 A 1

A9530 Columns - Re-Bar 20-Jan-12 A 21-Jan-12 A 2

A9540 Columns - Formwork 21-Jan-12 A 23-Jan-12 A 3

A9550 Columns - Casting 22-Jan-12 A 25-Jan-12 A 4

A9560 Slab / Beams - Formwork 25-Jan-12 A 31-Jan-12 A 7

A9570 Slab / Beams - Re-Bar 28-Jan-12 A 01-Feb-12 5


A
A9580 Slab / Beams Checking & 02-Feb-12 03-Feb-12 2
Casting A A

sujmall-1.1.2.5.7 MLCP Level 8 (120.90 LVL) 02-Feb-12 20-Feb-12 19 0


A A

sujmall-1.1.2.5.7.1
POUR-A 02-Feb-12 17-Feb-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9590 Column Starter Marking 02-Feb-12 02-Feb-12 1
A A
A9600 Columns - Re-Bar 03-Feb-12 04-Feb-12 2
A A
A9610 Columns - Formwork 04-Feb-12 06-Feb-12 3
A A
A9620 Columns - Casting 05-Feb-12 08-Feb-12 4
A A
A9630 Slab / Beams - Formwork 08-Feb-12 14-Feb-12 7
A A
A9640 Slab / Beams - Re-Bar 11-Feb-12 15-Feb-12 5
A A

(c) Primavera Systems, Inc. Page 62 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9650 Slab / Beams Checking & 16-Feb-12 17-Feb-12 2


Casting A A

sujmall-1.1.2.5.7.2
POUR-B 05-Feb-12 20-Feb-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9660 Column Starter Marking 05-Feb-12 05-Feb-12 1
A A
A9670 Columns - Re-Bar 06-Feb-12 07-Feb-12 2
A A
A9680 Columns - Formwork 07-Feb-12 09-Feb-12 3
A A
A9690 Columns - Casting 08-Feb-12 11-Feb-12 4
A A
A9700 Slab / Beams - Formwork 11-Feb-12 17-Feb-12 7
A A
A9710 Slab / Beams - Re-Bar 14-Feb-12 18-Feb-12 5
A A
A9720 Slab / Beams Checking & 19-Feb-12 20-Feb-12 2
Casting A A

sujmall-1.1.2.5.8 MLCP Level 9 (123.90 LVL) 19-Feb-12 08-Mar-12 19 0


A A

sujmall-1.1.2.5.8.1
POUR-A 19-Feb-12 05-Mar-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9730 Column Starter Marking 19-Feb-12 19-Feb-12 1
A A
A9740 Columns - Re-Bar 20-Feb-12 21-Feb-12 2
A A
A9750 Columns - Formwork 21-Feb-12 23-Feb-12 3
A A
A9760 Columns - Casting 22-Feb-12 25-Feb-12 4
A A
(c) Primavera Systems, Inc. Page 63 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9770 Slab / Beams - Formwork 25-Feb-12 02-Mar-12 7


A A
A9780 Slab / Beams - Re-Bar 28-Feb-12 03-Mar-12 5
A A
A9790 Slab / Beams Checking & 04-Mar-12 05-Mar-12 2
Casting A A

sujmall-1.1.2.5.8.2
POUR-B 22-Feb-12 08-Mar-12 16 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9800 Column Starter Marking 22-Feb-12 22-Feb-12 1
A A
A9810 Columns - Re-Bar 23-Feb-12 24-Feb-12 2
A A
A9820 Columns - Formwork 24-Feb-12 26-Feb-12 3
A A
A9830 Columns - Casting 25-Feb-12 28-Feb-12 4
A A
A9840 Slab / Beams - Formwork 28-Feb-12 05-Mar-12 7
A A
A9850 Slab / Beams - Re-Bar 02-Mar-12 06-Mar-12 5
A A
A9860 Slab / Beams Checking & 07-Mar-12 08-Mar-12 2
Casting A A

sujmall-1.1.2.6 STRUCTURAL STEEL WORKS 09-Dec-11 30-Mar-12 113 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9870 First Floor 09-Dec-11 28-Dec-11 20
A A
A9880 Second Floor 02-Jan-12 A 21-Jan-12 A 20

A9890 Third Floor 26-Jan-12 A 14-Feb-12 20


A

(c) Primavera Systems, Inc. Page 64 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A9900 Fourth Floor 04-Mar-12 23-Mar-12 20


A A
A9910 Terrace Floor Structural works 20-Feb-12 30-Mar-12 40
A A

sujmall-1.1.3 FINISHING WORKS 20-Jun-11 31-Jul-12 403 5 161


A

sujmall-1.1.3.1 Mock up for Toilet and Corridor 09-Dec-11 16-Feb-12 70 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A9920 Making Ready miscellneous civil 09-Dec-11 18-Dec-11 10
works A A
A9930 Waterproofing works for Toilets 19-Dec-11 28-Dec-11 10
A A
A9940 PHE works in Toilets 29-Dec-11 07-Jan-12 A 10
A
A9950 False ceiling in Toilets 08-Jan-12 A 17-Jan-12 A 10

A9960 Fixing CP and Sanitary Fixtures 18-Jan-12 A 27-Jan-12 A 10

A9970 Completion of miscellaneous civil 28-Jan-12 A 06-Feb-12 10


works in corridor A
A9980 False ceiling works in corridor 07-Feb-12 16-Feb-12 10
A A

sujmall-1.1.3.2 MLCP & RAMP FLOORING 19-Jan-12 19-Mar-12 61 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10000 MLCP Flooring 04-Feb-12 19-Mar-12 45
A A
A9990 Ramp Flooring 19-Jan-12 A 17-Feb-12 30
A

sujmall-1.1.3.3 EXPANSION JOINT WORKS 05-Feb-12 14-May-12 100 0


(c) Primavera Systems, Inc. Page 65 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A10010 B2 LEVEL 05-Feb-12 14-Feb-12 10
A A
A10020 B1 LVL 15-Feb-12 24-Feb-12 10
A A
A10030 LGF 25-Feb-12 05-Mar-12 10
A A
A10040 UGF 06-Mar-12 15-Mar-12 10
A A
A10050 1 ST FLOOR 16-Mar-12 25-Mar-12 10
A A
A10060 2ND FLOOR 26-Mar-12 04-Apr-12 A 10
A
A10070 3 RD FLOOR 05-Apr-12 A 14-Apr-12 A 10

A10080 4TH FLOOR 15-Apr-12 A 24-Apr-12 A 10

A10090 5TH FLOOR 25-Apr-12 A 04-May-12 10


A
A10100 TERAACE FLOOR 05-May-12 14-May-12 10
A A

sujmall-1.1.3.4 BLOCK MASONRY 20-Jun-11 07-May-12 323 0


A A

sujmall-1.1.3.4.1 Basement 3 Floor 20-Jun-11 30-Jul-11 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10110 Masonry upto Lintel 20-Jun-11 A 14-Jul-11 A 25

A10120 Lintel / Chejja Concreting 27-Jun-11 A 11-Jul-11 A 15

A10130 Masonry Above Lintel 11-Jul-11 A 30-Jul-11 A 20

(c) Primavera Systems, Inc. Page 66 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.3.4.2 Basement 2 Floor 31-Jul-11 09-Sep-11 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10140 Masonry upto Lintel 31-Jul-11 A 24-Aug-11 25
A
A10150 Lintel / Chejja Concreting 07-Aug-11 21-Aug-11 15
A A
A10160 Masonry Above Lintel 21-Aug-11 09-Sep-11 20
A A

sujmall-1.1.3.4.3 Basement 1 Floor 10-Sep-11 20-Oct-11 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10170 Masonry upto Lintel 10-Sep-11 04-Oct-11 A 25
A
A10180 Lintel / Chejja Concreting 17-Sep-11 01-Oct-11 A 15
A
A10190 Masonry Above Lintel 01-Oct-11 A 20-Oct-11 A 20

sujmall-1.1.3.4.4 Lower Ground Floor 21-Oct-11 30-Nov-11 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10200 Masonry upto Lintel 21-Oct-11 A 14-Nov-11 25
A
A10210 Lintel / Chejja Concreting 28-Oct-11 A 11-Nov-11 15
A
A10220 Masonry Above Lintel 11-Nov-11 30-Nov-11 20
A A

sujmall-1.1.3.4.5 Upper Ground Floor 01-Dec-11 10-Jan-12 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 67 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10230 Masonry upto Lintel 01-Dec-11 25-Dec-11 25


A A
A10240 Lintel / Chejja Concreting 08-Dec-11 22-Dec-11 15
A A
A10250 Masonry Above Lintel 22-Dec-11 10-Jan-12 A 20
A

sujmall-1.1.3.4.6 First Floor 11-Jan-12 13-Feb-12 34 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10260 Masonry upto Lintel 11-Jan-12 A 04-Feb-12 25
A
A10270 Lintel / Chejja Concreting 18-Jan-12 A 01-Feb-12 15
A
A10280 Masonry Above Lintel 25-Jan-12 A 13-Feb-12 20
A

sujmall-1.1.3.4.7 Second Floor 25-Jan-12 05-Mar-12 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10290 Masonry upto Lintel 25-Jan-12 A 18-Feb-12 25
A
A10300 Lintel / Chejja Concreting 01-Feb-12 15-Feb-12 15
A A
A10310 Masonry Above Lintel 15-Feb-12 05-Mar-12 20
A A

sujmall-1.1.3.4.8 Third Floor 15-Feb-12 26-Mar-12 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10320 Masonry upto Lintel 15-Feb-12 10-Mar-12 25
A A
A10330 Lintel / Chejja Concreting 22-Feb-12 07-Mar-12 15
A A

(c) Primavera Systems, Inc. Page 68 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10340 Masonry Above Lintel 07-Mar-12 26-Mar-12 20


A A

sujmall-1.1.3.4.9 Fourth Floor 07-Mar-12 16-Apr-12 41 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10350 Masonry upto Lintel 07-Mar-12 31-Mar-12 25
A A
A10360 Lintel / Chejja Concreting 14-Mar-12 28-Mar-12 15
A A
A10370 Masonry Above Lintel 28-Mar-12 16-Apr-12 A 20
A

sujmall-1.1.3.4.10Terrace Floor 18-Mar-12 07-May-12 51 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10380 Masonry upto Lintel 18-Mar-12 21-Apr-12 A 35
A
A10390 Lintel / Chejja Concreting 04-Apr-12 A 18-Apr-12 A 15

A10400 Masonry Above Lintel 18-Apr-12 A 07-May-12 20


A

sujmall-1.1.3.5 INTERNAL PLASTERING 14-Aug-11 21-May-12 282 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10410 Basement 3 Floor 14-Aug-11 07-Sep-11 25
A A
A10420 Basement 2 Floor 24-Sep-11 18-Oct-11 A 25
A
A10430 Basement 1 Floor 21-Oct-11 A 14-Nov-11 25
A
A10440 Lower Ground Floor 01-Dec-11 25-Dec-11 25
A A

(c) Primavera Systems, Inc. Page 69 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10450 Upper Ground Floor 21-Dec-11 14-Jan-12 A 25


A
A10460 Fitst Floor 31-Jan-12 A 24-Feb-12 25
A
A10470 Second Floor 14-Feb-12 09-Mar-12 25
A A
A10480 Third Floor 06-Mar-12 30-Mar-12 25
A A
A10490 Fourth Floor 27-Mar-12 30-Apr-12 A 35
A
A10500 Fifth Floor 17-Apr-12 A 21-May-12 35
A

sujmall-1.1.3.6 EXTERNAL PLASTERING 07-Apr-12 20-Jun-12 75 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10510 North Side 07-Apr-12 A 06-May-12 30
A
A10520 East Side 22-Apr-12 A 21-May-12 30
A
A10530 South Side 07-May-12 06-Jun-12 A 31
A
A10540 West Side 22-May-12 20-Jun-12 A 30
A

sujmall-1.1.3.7 EXTERNAL CLADDING 22-May-12 20-Jul-12 60 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10550 All Levels/Sides 22-May-12 20-Jul-12 A 60
A

sujmall-1.1.3.8 FLOORING/DADO 30-Dec-11 26-Jun-12 180 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 70 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10560 Basement 3 Floor 30-Dec-11 18-Jan-12 A 20


A
A10570 Basement 2 Floor 19-Jan-12 A 07-Feb-12 20
A
A10580 Basement 1 Floor 08-Feb-12 27-Feb-12 20
A A
A10590 Lower Ground Floor 28-Feb-12 18-Mar-12 20
A A
A10600 Upper Ground Floor 19-Mar-12 07-Apr-12 A 20
A
A10610 First Floor 08-Apr-12 A 27-Apr-12 A 20

A10620 Second Floor 28-Apr-12 A 17-May-12 20


A
A10630 Third Floor 18-May-12 06-Jun-12 A 20
A
A10640 Fourth Floor 07-Jun-12 A 26-Jun-12 A 20

sujmall-1.1.3.9 KOTASTONE FLOORING FOR 20-Nov-11 01-Jun-12 195 0


STAIRCASES A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10650 B3 Flooring 20-Nov-11 09-Dec-11 20
A A
A10660 B2 Flooring 10-Dec-11 29-Dec-11 20
A A
A10670 B1 Flooring 30-Dec-11 18-Jan-12 A 20
A
A10680 LGF 19-Jan-12 A 07-Feb-12 20
A
A10690 UGF 08-Feb-12 27-Feb-12 20
A A
A10700 FIRST FLOOR 28-Feb-12 18-Mar-12 20
A A

(c) Primavera Systems, Inc. Page 71 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10710 SECOND FLOOR 19-Mar-12 07-Apr-12 A 20


A
A10720 THIRD FLOOR 08-Apr-12 A 27-Apr-12 A 20

A10730 FOURTH FLOOR & 5 TH 28-Apr-12 A 01-Jun-12 A 35


FLOOR

sujmall-1.1.3.10 STAIRCASE HAND RAILING 10-Dec-11 26-May-12 169 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10740 B3 Flooring 10-Dec-11 24-Dec-11 15
A A
A10750 B2 Flooring 25-Dec-11 08-Jan-12 A 15
A
A10760 B1 Flooring 09-Jan-12 A 23-Jan-12 A 15

A10770 LGF 03-Feb-12 17-Feb-12 15


A A
A10780 UGF 18-Feb-12 03-Mar-12 15
A A
A10790 FIRST FLOOR 11-Mar-12 25-Mar-12 15
A A
A10800 SECOND FLOOR 29-Mar-12 12-Apr-12 A 15
A
A10810 THIRD FLOOR 20-Apr-12 A 04-May-12 15
A
A10820 FOURTH FLOOR 12-May-12 26-May-12 15
A A

sujmall-1.1.3.11 WATER PROOFING - Toilets & 22-Nov-11 03-Jun-12 195 0


Terrace A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10830 Basement 3 Floor 22-Nov-11 06-Dec-11 15
A A

(c) Primavera Systems, Inc. Page 72 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10840 Basement 2 Floor 07-Dec-11 21-Dec-11 15


A A
A10850 Basement 1 Floor 22-Dec-11 05-Jan-12 A 15
A
A10860 Lower Ground Floor 06-Jan-12 A 25-Jan-12 A 20

A10870 Upper Ground Floor 26-Jan-12 A 14-Feb-12 20


A
A10880 Fitst Floor 15-Feb-12 05-Mar-12 20
A A
A10890 Second Floor 06-Mar-12 25-Mar-12 20
A A
A10900 Third Floor 26-Mar-12 14-Apr-12 A 20
A
A10910 Fourth Floor 15-Apr-12 A 04-May-12 20
A
A10920 Terrace Waterproofing 05-May-12 03-Jun-12 A 30
A

sujmall-1.1.3.12 JOINERY WORKS 17-Feb-12 15-Jun-12 120 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A10930 Basement 3 Floor 17-Feb-12 26-Feb-12 10
A A
A10940 Basement 2 Floor 27-Feb-12 07-Mar-12 10
A A
A10950 Basement 1 Floor 08-Mar-12 17-Mar-12 10
A A
A10960 Lower Ground Floor 18-Mar-12 27-Mar-12 10
A A
A10970 Upper Ground Floor 28-Mar-12 06-Apr-12 A 10
A
A10980 First Floor 07-Apr-12 A 16-Apr-12 A 10

(c) Primavera Systems, Inc. Page 73 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A10990 Second Floor 17-Apr-12 A 26-Apr-12 A 10

A11000 Third Floor 27-Apr-12 A 06-May-12 10


A
A11010 Theatre Exit Floor 07-May-12 16-May-12 10
A A
A11020 Fourth Floor 17-May-12 26-May-12 10
A A
A11030 Fifth Floor 27-May-12 05-Jun-12 A 10
A
A11040 Terrace Floor 06-Jun-12 A 15-Jun-12 A 10

sujmall-1.1.3.13 COMPOUND WALL WORKS 17-Jan-12 02-Apr-12 77 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A11050 Earth work excavation 17-Jan-12 A 05-Feb-12 20
A
A11060 SS Masonry works 20-Jan-12 A 18-Feb-12 30
A
A11070 Block Masonry works 24-Jan-12 A 22-Feb-12 30
A
A11080 Plastering of compound wall 03-Feb-12 27-Feb-12 25
A A
A11090 Fixing of MS Grills 18-Feb-12 18-Mar-12 30
A A
A11100 Fixing of Gates 19-Mar-12 02-Apr-12 A 15
A

sujmall-1.1.3.14 ROAD WORKS 03-Apr-12 01-Jun-12 60 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A11110 Excavation and levelling Works 03-Apr-12 A 12-Apr-12 A 10

(c) Primavera Systems, Inc. Page 74 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11120 Laying the GSB 13-Apr-12 A 27-Apr-12 A 15

A11130 Fixing of Kerbs 28-Apr-12 A 17-May-12 20


A
A11140 Laying of Concrete for Roads 18-May-12 01-Jun-12 A 15
A

sujmall-1.1.3.15 EXTERNAL WORKS 18-May-12 31-Jul-12 70 5 161


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11150 Water body concreting 18-May-12 16-Jun-12 A 30
A
A11160 Water body tiling works 17-Jun-12 A 01-Jul-12 A 15

A11170 Fixing of Pavers 02-Jul-12 A 31-Jul-12 30 161


A11180 External Granite works 02-Jul-12 A 16-Jul-12 A 15

sujmall-1.1.3.16 HANDING OVER AFTER CIVIL 27-Jun-12 29-Jul-12 30 3 73


WORKS A
Activity ID Activity Name Start Finish Original Duration Total Float
A11190 All Floors - Snags and Handover 27-Jun-12 A 29-Jul-12 33 73

sujmall-1.1.4 ALL OTHER FINISHES/WORKS 31-Mar-12 27-Oct-12 118 93 73


A

sujmall-1.1.4.1 Fire Doors 31-Mar-12 28-Jul-12 118 2 164


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11200 Basement 3 Floor 31-Mar-12 09-Apr-12 A 10
A
A11210 Basement 2 Floor 10-Apr-12 A 19-Apr-12 A 10

(c) Primavera Systems, Inc. Page 75 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11220 Basement 1 Floor 20-Apr-12 A 29-Apr-12 A 10

A11230 Lower Ground Floor 30-Apr-12 A 09-May-12 10


A
A11240 Upper Ground Floor 10-May-12 19-May-12 10
A A
A11250 First Floor 20-May-12 29-May-12 10
A A
A11260 Second Floor 30-May-12 08-Jun-12 A 10
A
A11270 Third Floor 09-Jun-12 A 18-Jun-12 A 10

A11280 Theatre Exit Floor 19-Jun-12 A 28-Jun-12 A 10

A11290 Fourth Floor 29-Jun-12 A 08-Jul-12 A 10

A11300 Fifth Floor 09-Jul-12 A 18-Jul-12 A 10


A11310 Terrace Floor 19-Jul-12 A 28-Jul-12 10 164

sujmall-1.1.4.2 SS Hand Railing 27-Jun-12 14-Sep-12 30 50 116


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11320 Supply 27-Jun-12 A 26-Jul-12 A 30

A11330 Bracketing/Support structures 07-Jul-12 A 05-Aug-12 30 116


A11340 Fixtures/Railing 17-Jul-12 A 15-Aug-12 30 116
A11350 Fixing of Toughned Glass 16-Aug-12* 14-Sep-12 30 116

sujmall-1.1.4.3 Structural Glazing 15-Apr-12 20-Jul-12 97 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A11360 Supply & Fabrication 15-Apr-12 A 04-May-12 20
A
(c) Primavera Systems, Inc. Page 76 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11370 Bracketing/Support structures 20-Apr-12 A 19-May-12 30


A
A11380 Installation 22-Apr-12 A 05-Jun-12 A 45

A11390 Canopy works 06-Jun-12 A 20-Jul-12 A 45

A11400 Final Sealant and Cleaning 27-May-12 26-Jun-12 A 31


A

sujmall-1.1.4.4 FALSE CEILING WORKS 08-Apr-12 05-Aug-12 110 10 156


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11410 Supply 08-Apr-12 A 07-May-12 30
A
A11420 Fixing of grids 23-Apr-12 A 21-Jul-12 A 90

A11430 Fixing of Panels 08-May-12 05-Aug-12 90 156


A
A11440 Final Finishing 11-May-12 09-Jun-12 A 30
A

sujmall-1.1.4.5 PAINTING WORKS 08-Apr-12 18-Oct-12 110 84 82


A

sujmall-1.1.4.5.1 Internal 08-Apr-12 04-Oct-12 110 70 96


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11450 Basement 3 08-Apr-12 A 27-Apr-12 A 20

A11460 Basement 2 28-Apr-12 A 17-May-12 20


A
A11470 Basement 1 18-May-12 06-Jun-12 A 20
A
A11480 Lower ground Floor 07-Jun-12 A 26-Jun-12 A 20

(c) Primavera Systems, Inc. Page 77 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11490 Upper Ground Floor 27-Jun-12 A 16-Jul-12 A 20

A11500 First Floor 17-Jul-12 A 05-Aug-12 20 96


A11510 Second Floor 06-Aug-12* 25-Aug-12 20 96
A11520 Third Floor 26-Aug-12* 14-Sep-12 20 96
A11530 Fourth Floor 02-Jul-12 A 06-Jul-12 A 5
A11540 Fifth Floor 15-Sep-12* 04-Oct-12 20 96

sujmall-1.1.4.5.2 External 21-Jul-12 18-Oct-12 6 84 82


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11550 North Side 21-Jul-12 A 19-Aug-12 30 82
A11560 East Side 31-Jul-12* 29-Aug-12 30 82
A11570 South Side 10-Aug-12* 08-Sep-12 30 82
A11580 west Side 20-Aug-12* 18-Sep-12 30 82
A11590 Compound Wall 19-Sep-12* 18-Oct-12 30 82

sujmall-1.1.4.6 LANDSCAPING WORKS 30-Jul-12 27-Oct-12 0 90 73


Activity ID Activity Name Start Finish Original Duration Total Float
A11600 Softscaping works 30-Jul-12* 27-Oct-12 90 73

sujmall-1.1.5 MEP WORKS 19-Jul-11 29-Dec-12 374 156 10


A

sujmall-1.1.5.1 Sewage Treatment Plant 21-Mar-12 01-Sep-12 128 37 99


Installation A
Activity ID Activity Name Start Finish Original Duration Total Float
A11610 Design/Procurement of Plant 21-Mar-12 18-Jun-12 A 90
A
A11620 Installation 19-Jun-12 A 17-Aug-12 60 99

(c) Primavera Systems, Inc. Page 78 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11630 Testing and commisioning 18-Aug-12* 01-Sep-12 15 99

sujmall-1.1.5.2 FIRE PROTECTION SERVICES 19-Jul-11 30-Jul-12 374 4 162


A

sujmall-1.1.5.2.1 DESIGN & ENGINEERING 19-Jul-11 18-Nov-11 123 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A11640 Receipt of Order 19-Jul-11 A 19-Jul-11 A 1
A11650 Receipt of Input drawings 20-Jul-11 A 17-Sep-11 60
A
A11660 Submission of Drawings 30-Jul-11 A 27-Oct-11 A 90

A11670 Submission of QAP / Safty 18-Sep-11 01-Nov-11 45


Manual / Technical Data Sheet A A
A11680 Receipt of Approved darwings 09-Aug-11 22-Sep-11 45
A A
A11690 Receipt of Approved QAP/Safty 20-Oct-11 A 18-Nov-11 30
Manual / Data Sheets A

sujmall-1.1.5.2.2 SUPPLY 20-Jul-11 19-May-12 305 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A11700 Pipes 20-Jul-11 A 02-Sep-11 45
A
A11710 Fittings 20-Jul-11 A 17-Oct-11 A 90

A11720 Cables 19-Aug-11 16-Nov-11 90


A A
A11730 "Hydrant Valves, Hoses Etc" 03-Sep-11 16-Nov-11 75
A A
A11740 Fire Alarm Detectors 23-Sep-11 21-Nov-11 60
A A
A11750 PA System Amplifiers & Speakers 22-Nov-11 19-Feb-12 90
(c) Primavera Systems, Inc. Page 79 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11760 Water Flow Detectors 22-Nov-11 19-Feb-12 90


A A
A11770 Sprinklers 20-Oct-11 A 08-Dec-11 50
A
A11780 Wayer Curtain System Nozzle 05-Dec-11 02-Feb-12 60
A A
A11790 Extinguishers 20-Feb-12 19-May-12 90
A A
A11800 "Gate Valves, NRV, Strainers" 03-Nov-11 01-Mar-12 120
A A
A11810 Butterfly Valves 22-Nov-11 20-Jan-12 A 60
A
A11820 Alarm Valves 07-Nov-11 20-Jan-12 A 75
A
A11830 Control Panel for Fire Pumps 19-Nov-11 16-Feb-12 90
A A
A11840 "Hydrant, Sprinkler, Booster & 07-Nov-11 04-Feb-12 90
Jockey Pumpsets" A A
A11850 Addressable Fire Alarm Panels 07-Nov-11 20-Jan-12 A 75
& Repeater Panels A

sujmall-1.1.5.2.3 ERECTION 19-Nov-11 29-Jul-12 251 3 163


A
Activity ID Activity Name Start Finish Original Duration Total Float
A11860 Mobilsation of Manpower 19-Nov-11 28-Nov-11 10
A A

sujmall-1.1.5.2.3.1
SPRINKLER & HYDRANT SYSTEM 21-Nov-11 29-Jul-12 249 3 163
A

sujmall-1.1.5.2.3.1.1
BASEMENT-3 21-Nov-11 18-Feb-12 90 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A11870 Fabrication of Sprinkler Pipes 21-Nov-11 19-Jan-12 A 60

(c) Primavera Systems, Inc. Page 80 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11880 Erection of Sprinkler Pipes 06-Dec-11 03-Feb-12 60


A A
A11890 Testing of the Sprinkler Pipes 04-Feb-12 18-Feb-12 15
A A

sujmall-1.1.5.2.3.1.2
BASEMENT-2 01-Dec-11 28-Feb-12 90 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A11900 Fabrication of Sprinkler Pipes 01-Dec-11 29-Jan-12 A 60


A
A11910 Erection of Sprinkler Pipes 16-Dec-11 13-Feb-12 60
A A
A11920 Testing of the Sprinkler Pipes 14-Feb-12 28-Feb-12 15
A A

sujmall-1.1.5.2.3.1.3
BASEMENT-1 11-Dec-11 28-Feb-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A11930 Fabrication of Sprinkler Pipes 11-Dec-11 08-Feb-12 60


A A
A11940 Erection of Sprinkler Pipes 26-Dec-11 13-Feb-12 50
A A
A11950 Testing of the Sprinkler Pipes 14-Feb-12 28-Feb-12 15
A A

sujmall-1.1.5.2.3.1.4
LOWER GROUND FLOOR 1 21-Dec-11 09-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A11960 Fabrication of Sprinkler Pipes 21-Dec-11 18-Feb-12 60


A A
A11970 Erection of Sprinkler Pipes 05-Jan-12 A 23-Feb-12 50
A

(c) Primavera Systems, Inc. Page 81 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A11980 Testing of the Sprinkler Pipes 24-Feb-12 09-Mar-12 15


A A

sujmall-1.1.5.2.3.1.5
UPPER GROUND FLOOR 31-Dec-11 19-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A11990 Fabrication of Sprinkler Pipes 31-Dec-11 28-Feb-12 60


A A
A12000 Erection of Sprinkler Pipes 05-Jan-12 A 04-Mar-12 60
A
A12010 Testing of the Sprinkler Pipes 05-Mar-12 19-Mar-12 15
A A

sujmall-1.1.5.2.3.1.6
FIRST FLOOR 10-Jan-12 29-Mar-12 80 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A12020 Fabrication of Sprinkler Pipes 10-Jan-12 A 09-Mar-12 60


A
A12030 Erection of Sprinkler Pipes 25-Jan-12 A 14-Mar-12 50
A
A12040 Testing of the Sprinkler Pipes 15-Mar-12 29-Mar-12 15
A A

sujmall-1.1.5.2.3.1.7
SECOND FLOOR 20-Jan-12 29-Jul-12 189 3 163
A
Activity ID Activity Name Start Finish Original Duration Total Float

A12050 Fabrication of Sprinkler Pipes 20-Jan-12 A 19-Mar-12 60


A
A12060 Erection of Sprinkler Pipes 04-Feb-12 14-Mar-12 40
A A
A12070 Testing of the Sprinkler Pipes 15-Jul-12 A 29-Jul-12 15 163

(c) Primavera Systems, Inc. Page 82 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.5.2.3.1.8
THIRD FLOOR 30-Jan-12 03-Apr-12 65 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A12080 Fabrication of Sprinkler Pipes 30-Jan-12 A 14-Mar-12 45


A
A12090 Erection of Sprinkler Pipes 14-Feb-12 24-Mar-12 40
A A
A12100 Testing of the Sprinkler Pipes 25-Mar-12 03-Apr-12 A 10
A

sujmall-1.1.5.2.3.1.9
THEATER EXIT FLOOR 09-Feb-12 29-Mar-12 50 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A12110 Fabrication of Sprinkler Pipes 09-Feb-12 09-Mar-12 30


A A
A12120 Erection of Sprinkler Pipes 24-Feb-12 19-Mar-12 25
A A
A12130 Testing of the Sprinkler Pipes 20-Mar-12 29-Mar-12 10
A A

sujmall-1.1.5.2.3.1.10
FOURTH FLOOR 19-Feb-12 08-Apr-12 50 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float

A12140 Fabrication of Sprinkler Pipes 19-Feb-12 09-Mar-12 20


A A
A12150 Erection of Sprinkler Pipes 05-Mar-12 29-Mar-12 25
A A
A12160 Testing of the Sprinkler Pipes 30-Mar-12 08-Apr-12 A 10
A

sujmall-1.1.5.2.3.1.11
FIFTH FLOOR 29-Feb-12 23-Apr-12 55 0
A A

(c) Primavera Systems, Inc. Page 83 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float

A12170 Fabrication of Sprinkler Pipes 29-Feb-12 19-Mar-12 20


A A
A12180 Erection of Sprinkler Pipes 15-Mar-12 13-Apr-12 A 30
A
A12190 Testing of the Sprinkler Pipes 14-Apr-12 A 23-Apr-12 A 10

sujmall-1.1.5.2.3.2
FIRE SHAFT 10-Jan-12 23-Apr-12 105 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12200 Fabrication of Sprinkler Pipes 10-Jan-12 A 23-Feb-12 45
A
A12210 Erection of Sprinkler Pipes 07-Feb-12 06-Apr-12 A 60
A
A12220 Testing of the Sprinkler Pipes 14-Apr-12 A 23-Apr-12 A 10

sujmall-1.1.5.2.3.3
MLCP 24-Feb-12 03-Jun-12 101 0
A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12230 Fabrication of Sprinkler Pipes 24-Feb-12 23-Apr-12 A 60
A
A12240 Erection of Sprinkler Pipes 25-Mar-12 23-May-12 60
A A
A12250 Testing of the Sprinkler Pipes 20-May-12 03-Jun-12 A 15
A

sujmall-1.1.5.2.4 EXTERNAL HYDRANT 30-Jan-12 29-Mar-12 60 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12260 Fabrication of Hydrant Pipes 30-Jan-12 A 28-Feb-12 30
A

(c) Primavera Systems, Inc. Page 84 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A12270 Erection of Hydrant Pipes 19-Feb-12 19-Mar-12 30


A A
A12280 Testing of Hydrant Pipes 20-Mar-12 29-Mar-12 10
A A

sujmall-1.1.5.2.5 WATER CURTAIN SYSTEM 24-Feb-12 23-Apr-12 60 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12290 Fabrication of Pipes 24-Feb-12 24-Mar-12 30
A A
A12300 "Erection of Pipes,DV,Nozzles" 25-Mar-12 13-Apr-12 A 20
A
A12310 Testing & Commissioning of 14-Apr-12 A 23-Apr-12 A 10
Water Curtain System

sujmall-1.1.5.2.6 FDA & PA SYSTEM 12-Dec-11 30-Jun-12 202 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12320 FDA CABLING WORKS 12-Dec-11 20-Mar-12 100
A A
A12330 "FIXING OF Junction 07-Feb-12 21-Apr-12 A 75
Box,DETECTORS Base" A
A12340 "FIXING OF 22-Apr-12 A 05-Jun-12 A 45
DETECTORS,SPEAKERS"
A12350 Testing of FDA & PA SYSTEM 01-Jun-12 A 30-Jun-12 A 30

sujmall-1.1.5.2.7 FIRE WATER PUMP HOUSE 24-Apr-12 17-Jun-12 55 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12360 "Erection,Testing of Gate Valves. 24-Apr-12 A 23-May-12 30
NRV & Pump House A
Equipments"
A12370 "Erection,Testing of Pump sets." 24-May-12 17-Jun-12 A 25
A
(c) Primavera Systems, Inc. Page 85 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.5.2.8 FIRE EXTINGUISHERS 24-Apr-12 13-May-12 20 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12380 FIXING AT RESPECTIVE 24-Apr-12 A 13-May-12 20
PLACE / FLOORS A

sujmall-1.1.5.2.9 TESTING & COMMISSIONING 01-Jun-12 30-Jul-12 56 4 162


A
Activity ID Activity Name Start Finish Original Duration Total Float
A12390 Testing of Hydrant and Sprinkler 01-Jun-12 A 30-Jun-12 A 30
pipes
A12400 Commisioning of Pump House 05-Jun-12 A 24-Jun-12 A 20

A12410 Commisioning of FDA & PA 11-Jun-12 A 30-Jun-12 A 20


SYSTEM
A12420 Attending Punch List 21-Jun-12 A 30-Jun-12 A 10

A12430 Handing Over 01-Jul-12 A 30-Jul-12 30 0

sujmall-1.1.5.3 Electrical (LT & HT Works) 19-Nov-11 13-Oct-12 251 79 87


A
Activity ID Activity Name Start Finish Original Duration Total Float
A12440 Conduiting and Wiring 19-Nov-11 16-Apr-12 A 150
A
A12450 Installation of Cable Tray 19-Nov-11 17-Mar-12 120
A A
A12460 Laying of LT cables 19-Dec-11 17-Mar-12 90
A A
A12470 Erection of Lighting & Power DB 18-Mar-12 01-May-12 45
A A
A12480 Erection of LT Panels 02-May-12 30-Jun-12 A 60
A
A12490 Installation of RMU 01-Jul-12 A 14-Aug-12 45 57
(c) Primavera Systems, Inc. Page 86 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A12500 Erection of HT Panel & 01-Jul-12 A 30-Jul-12 30 57


Switchgear
A12510 Erection of Transformer 01-Jul-12 A 30-Jul-12 30 57
A12520 Bringing electricity to site 31-Jul-12* 28-Aug-12 29 57
A12530 Installation of Busduct 31-Jul-12* 28-Aug-12 29 57
A12540 Installation of Rising Main 31-Jul-12* 13-Sep-12 45 57
A12550 Fixing of Light Fixtures 01-Jul-12 A 29-Aug-12 60 132
A12560 External Electrical Works & 31-Jul-12* 13-Sep-12 45 57
Earthing
A12570 Testing and commisioning 14-Sep-12* 13-Oct-12 30 57

sujmall-1.1.5.4 PHE WORKS 19-Nov-11 27-Aug-12 251 32 134


A
Activity ID Activity Name Start Finish Original Duration Total Float
A12580 Mobilization of Labor 19-Nov-11 03-Dec-11 15
A A
A12590 Material Procurement 19-Nov-11 25-Jul-12 A 250
A

sujmall-1.1.5.4.1 BASEMENT 1 CEILING WORKS 04-Dec-11 31-Jan-12 59 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12600 Marking and Drilling 04-Dec-11 10-Dec-11 7
A A
A12610 Fixing of Supports 11-Dec-11 17-Dec-11 7
A A
A12620 Installation of Drainage Pipes 11-Dec-11 30-Dec-11 20
A A
A12630 Installation of solid and waste 18-Dec-11 31-Jan-12 A 45
Pipes A
A12640 Installation of Water Supply 21-Dec-11 19-Jan-12 A 30
Pipes A

(c) Primavera Systems, Inc. Page 87 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A12650 Shaft Piping from B1 to B3 10-Jan-12 A 29-Jan-12 A 20

sujmall-1.1.5.4.2 BASMENT 3 PIPING AND 10-Jan-12 07-Mar-12 58 0


RELATED WORKS A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12660 Marking and Drilling 10-Jan-12 A 14-Jan-12 A 5

A12670 Fixing of Supports 12-Jan-12 A 16-Jan-12 A 5

A12680 Installation of Drainage Pipes 02-Feb-12 16-Feb-12 15


A A
A12690 Installation of Strom water 27-Feb-12 07-Mar-12 10
Pumps and Piping A A
A12700 Installation of Water Supply 07-Feb-12 16-Feb-12 10
Pipes A A

sujmall-1.1.5.4.3 BASEMENT 2 CEILING WORKS 07-Feb-12 02-Mar-12 25 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12710 Marking and Drilling 07-Feb-12 16-Feb-12 10
A A
A12720 Fixing of Supports 11-Feb-12 20-Feb-12 10
A A
A12730 Installation of Drainage Pipes 16-Feb-12 25-Feb-12 10
A A
A12740 Installation of solid and waste 19-Feb-12 25-Feb-12 7
Pipes A A
A12750 Installation of Water Supply 22-Feb-12 02-Mar-12 10
Pipes A A

sujmall-1.1.5.4.4 LOWER GROUND FLOOR TOILETS 22-Feb-12 07-Mar-12 15 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 88 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A12760 Marking and Chasing 22-Feb-12 24-Feb-12 3


A A
A12770 Water Supply Piping 25-Feb-12 29-Feb-12 5
A A
A12780 Soil and Waste Disposal Piping 01-Mar-12 05-Mar-12 5
A A
A12790 Testing of Pipes 06-Mar-12 07-Mar-12 2
A A

sujmall-1.1.5.4.5 UPPER GROUND FLOOR TOILETS 06-Mar-12 27-Mar-12 22 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12800 Marking and Chasing 06-Mar-12 15-Mar-12 10
A A
A12810 Water Supply Piping 08-Mar-12 22-Mar-12 15
A A
A12820 Soil and Waste Disposal Piping 11-Mar-12 25-Mar-12 15
A A
A12830 Testing of Pipes 21-Mar-12 27-Mar-12 7
A A

sujmall-1.1.5.4.6 FIRST FLOOR TOILETS 21-Mar-12 14-Apr-12 25 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12840 Marking and Chasing 21-Mar-12 30-Mar-12 10
A A
A12850 Water Supply Piping 23-Mar-12 04-Apr-12 A 13
A
A12860 Soil and Waste Disposal Piping 27-Mar-12 08-Apr-12 A 13
A
A12870 Testing of Pipes 08-Apr-12 A 14-Apr-12 A 7

sujmall-1.1.5.4.7 SECOND FLOOR TOILETS 08-Apr-12 04-May-12 27 0


A A
(c) Primavera Systems, Inc. Page 89 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A12880 Marking and Chasing 08-Apr-12 A 20-Apr-12 A 13

A12890 Water Supply Piping 10-Apr-12 A 22-Apr-12 A 13

A12900 Soil and Waste Disposal Piping 14-Apr-12 A 26-Apr-12 A 13

A12910 Testing of Pipes 26-Apr-12 A 04-May-12 9


A

sujmall-1.1.5.4.8 THIRD FLOOR TOILETS 26-Apr-12 22-May-12 27 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12920 Marking and Chasing 26-Apr-12 A 08-May-12 13
A
A12930 Water Supply Piping 28-Apr-12 A 10-May-12 13
A
A12940 Soil and Waste Disposal Piping 02-May-12 14-May-12 13
A A
A12950 Testing of Pipes 14-May-12 22-May-12 9
A A

sujmall-1.1.5.4.9 THEATRE EXIT FLOOR TOILETS 14-May-12 23-May-12 10 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A12960 Marking and Chasing 14-May-12 15-May-12 2
A A
A12970 Water Supply Piping 16-May-12 17-May-12 2
A A
A12980 Soil and Waste Disposal Piping 20-May-12 21-May-12 2
A A
A12990 Testing of Pipes 22-May-12 23-May-12 2
A A

(c) Primavera Systems, Inc. Page 90 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.5.4.10FOURTH FLOOR TOILETS 22-May-12 17-Jun-12 27 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13000 Marking and Chasing 22-May-12 03-Jun-12 A 13
A
A13010 Water Supply Piping 24-May-12 05-Jun-12 A 13
A
A13020 Soil and Waste Disposal Piping 28-May-12 09-Jun-12 A 13
A
A13030 Testing of Pipes 09-Jun-12 A 17-Jun-12 A 9

sujmall-1.1.5.4.11FIFTH FLOOR TOILETS 09-Jun-12 18-Jun-12 10 0


A A
Activity ID Activity Name Start Finish Original Duration Total Float
A13040 Marking and Chasing 09-Jun-12 A 10-Jun-12 A 2

A13050 Water Supply Piping 11-Jun-12 A 12-Jun-12 A 2

A13060 Soil and Waste Disposal Piping 15-Jun-12 A 16-Jun-12 A 2

A13070 Testing of Pipes 17-Jun-12 A 18-Jun-12 A 2

sujmall-1.1.5.4.12"SHAFT WATER SUPPLY, SOIL 09-Jun-12 07-Aug-12 48 12 154


AND WASTE PIPING" A
Activity ID Activity Name Start Finish Original Duration Total Float
A13080 Fixing of MS Brackets 09-Jun-12 A 08-Jul-12 A 30

A13090 Installation of Pipes 29-Jun-12 A 07-Aug-12 40 154

A13100 Connecting the Down takes to 14-Jul-12 A 28-Jul-12 15 164


Basement Headers

(c) Primavera Systems, Inc. Page 91 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.5.4.13RAIN WATER DOWNTAKES 09-Jun-12 02-Aug-12 48 7 134


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13110 Marking and Drilling 09-Jun-12 A 23-Jun-12 A 15

A13120 Fixing of MS Brackets 13-Jun-12 A 12-Jul-12 A 30

A13130 Installation of Pipes 24-Jun-12 A 02-Aug-12 40 134

A13140 Connecting the Down takes to 14-Jul-12 A 28-Jul-12 15 134


External Drain

sujmall-1.1.5.4.14PUMP ROOM WORKS 14-Jul-12 27-Aug-12 13 32 134


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13150 Installation of Pum Base Frame 14-Jul-12 A 28-Jul-12 15 134
A13160 Installtion of Pumps and WTP 24-Jul-12 A 07-Aug-12 15 134
A13170 Plant Room Piping 03-Aug-12* 17-Aug-12 15 134
A13180 Linking of Suction and Delivery 13-Aug-12* 17-Aug-12 5 134
Header
A13190 Commissioning of Pumps 23-Aug-12* 27-Aug-12 5 134

sujmall-1.1.5.4.15SANITARY FIXTURES 14-Jul-12 27-Aug-12 13 32 134


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13200 Installation of Fixtures 14-Jul-12 A 22-Aug-12 40 134
A13210 Testing and Commissioning 24-Jul-12 A 22-Aug-12 30 134
A13220 Snag rectification and final 08-Aug-12* 27-Aug-12 20 134
handing over

sujmall-1.1.5.5 LIFTS 19-Nov-11 30-Aug-12 251 35 131


A
(c) Primavera Systems, Inc. Page 92 of 97
SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A13230 Drawing Approval 19-Nov-11 03-Dec-11 15
A A
A13240 Letter of Credit 04-Dec-11 18-Dec-11 15
A A
A13250 Making ready the shafts 19-Dec-11 16-Apr-12 A 120
A
A13260 Procurement/Receipt of 19-Dec-11 16-Apr-12 A 120
Equipment A
A13270 Installation in shaft incl car cage 17-Apr-12 A 15-Jul-12 A 90

A13280 Installation in LMR 02-May-12 15-Jun-12 A 45


A
A13290 Lift Finishes 17-Jun-12 A 16-Jul-12 A 30

A13300 Trial Run 17-Jul-12 A 31-Jul-12 15 101


A13310 "Final Testing, Balancing and 01-Aug-12* 30-Aug-12 30 101
commisioning"

sujmall-1.1.5.6 ESCALATORS 19-Nov-11 13-Oct-12 251 79 87


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13320 Drawing Approval 19-Nov-11 03-Dec-11 15
A A
A13330 Letter of Credit 04-Dec-11 18-Dec-11 15
A A
A13340 Procurement/Receipt of 19-Dec-11 16-Apr-12 A 120
Equipment A
A13350 Installation 17-Apr-12 A 14-Aug-12 120 106

A13360 Trial Run 15-Aug-12* 13-Sep-12 30 87


A13370 Testing and commisioning 14-Sep-12* 13-Oct-12 30 87

(c) Primavera Systems, Inc. Page 93 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

sujmall-1.1.5.7 ACMV 18-Jan-12 29-Nov-12 191 126 40


A

sujmall-1.1.5.7.1 High Side - Chillers 18-Jan-12 29-Aug-12 191 34 10


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13380 Drawing Approval 18-Jan-12 A 16-Feb-12 30
A
A13390 Letter of Credit 17-Feb-12 02-Mar-12 15
A A
A13400 Procurement of Chillers 03-Mar-12 29-Aug-12 180 10
A

sujmall-1.1.5.7.2 Low Side 03-Mar-12 29-Nov-12 146 126 40


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13410 Chilled Water Main lines 03-Mar-12 30-Jun-12 A 120
A
A13420 Condenser Water lines 03-Mar-12 31-May-12 90
A A
A13430 Ducting Works 01-Jul-12 A 28-Oct-12 120 72
A13440 Cooling Tower Works 01-Jun-12 A 30-Jun-12 A 30

A13450 Installation of FCU's & AHU's 01-Jun-12 A 29-Aug-12 90 132

A13460 Installation of Chiller Plant 01-Sep-12* 30-Oct-12 60 10


A13470 Mechanical Ventilation system 01-Jun-12 A 15-Jul-12 A 45

A13480 Testing and commisioning 31-Oct-12* 29-Nov-12 30 10

sujmall-1.1.5.8 DG Equipment & Low Side Works 19-Dec-11 04-Nov-12 221 101 65
A
Activity ID Activity Name Start Finish Original Duration Total Float

(c) Primavera Systems, Inc. Page 94 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

A13490 Drawing Approval 19-Dec-11 17-Jan-12 A 30


A
A13500 Letter of Credit 18-Jan-12 A 01-Feb-12 15
A
A13510 Procuremen/Receiptt of DG 02-Feb-12 31-May-12 120
Equipment A A
A13520 Installation 01-Jun-12 A 28-Sep-12 120 35

A13530 Exhaust Works - Piping & 02-Apr-12 A 01-May-12 30


Radiator Works A
A13540 Ducting Works by HVAC Vendor 02-Apr-12 A 01-May-12 30
A
A13550 Insulation/Accoustics to DG 03-May-12 01-Jun-12 A 30
Room A
A13560 Trial Run - No Load 02-Jun-12 A 08-Jun-12 A 7

A13570 Testing and commisioning 06-Oct-12* 04-Nov-12 30 35

sujmall-1.1.5.9 BUSDUCTS/PANELS 19-Dec-11 14-Aug-12 221 19 117


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13580 Drawing Approval 19-Dec-11 17-Jan-12 A 30
A
A13590 Letter of Credit 18-Jan-12 A 01-Feb-12 15
A
A13600 Procurement/Receipt of 18-Jan-12 A 16-Apr-12 A 90
Equipment
A13610 Installation 17-Apr-12 A 15-Jun-12 A 60

A13620 Procurement & Fixing of End 16-Jun-12 A 15-Jul-12 A 30


pieces
A13630 Testing and commisioning 16-Jul-12 A 14-Aug-12 30 117

sujmall-1.1.5.10 Security System & IBMS 01-Aug-12 29-Dec-12 0 151 10

(c) Primavera Systems, Inc. Page 95 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Activity ID Activity Name Start Finish Original Duration Total Float


A13640 Supply 01-Aug-12* 30-Aug-12 30 71
A13650 Parking Management 31-Aug-12* 14-Oct-12 45 71
A13660 CCTV 31-Aug-12* 29-Sep-12 30 101
A13670 Head Count System 15-Oct-12* 29-Oct-12 15 71
A13680 PA system 31-Aug-12* 29-Sep-12 30 101
A13690 Data Cable for Communication 31-Aug-12* 29-Oct-12 60 71
A13700 Integration of BMS 31-Aug-12* 29-Sep-12 30 101
A13710 Testing And Commissioning 30-Nov-12* 29-Dec-12 30 10

sujmall-1.1.6 HANDING OVER FOR FITOUTS 27-Jun-12 24-Oct-12 30 60 76


A
Activity ID Activity Name Start Finish Original Duration Total Float
A13720 "Anchors, Cinema & Hyper 27-Jun-12 A 26-Jul-12 A 30
Market"
A13730 Handover to Vanilla/Shops 26-Aug-12* 24-Oct-12 60 76

sujmall-1.1.7 POST CONSTRUCTION 30-Aug-12 08-Jan-13 0 132 0


APPROVALS
Activity ID Activity Name Start Finish Original Duration Total Float
A13740 Fire Inspection and Approval 30-Aug-12* 13-Oct-12 45 0
A13750 Ocupancy Certificate 29-Oct-12* 12-Dec-12 45 0
A13760 Consent for Operation of DG 05-Nov-12* 04-Dec-12 30 35
A13770 Permanent Power sanction 20-Dec-12* 08-Jan-13 20 0
A13780 Permanent Water Sanction 20-Dec-12* 08-Jan-13 20 0
A13790 Permanent Sanitary Sanction 20-Dec-12* 08-Jan-13 20 0

(c) Primavera Systems, Inc. Page 96 of 97


SUJANA MALL - Hyderabad 31-Jul-12 11:57

schedule delay in construction project using TIA

WBS Code WBS Name Start Finish Actual Remaining Total Float
Duration Duration

Total 10-Mar-10 08-Jan-13 870 166


A

(c) Primavera Systems, Inc. Page 97 of 97

Вам также может понравиться