LAUGFS ENGINEERING (PVT) LTD


Procedure Manual Department: Engineering

Document #: LE-EN-PR-007 Issue #: 01 Date: 28/02/2014 Page No: 01 of 04

Title: Hydro Testing Procedure

1. Scope

This work instructions applicable for Hydro Testing of liquid petroleum gas (LPG) pipe line
system.

2. Equipment

Blank flanges.

Pressure gauges (0-30 bar) with calibration certificates.

Pressure pump.

1. Model : Dozen Pump / S.NO: 110320317

2. Capacity – 0-50 LPH Electrical driven.

3. Max. Operating pressure: 20 Bar.

3. Responsibility

Project Engineer/Quality Engineer & Site supervisor are responsible for below mentioned
descriptions prior to Hydro test including all necessary safety items.

 Supplying of any equipment/accessories needed.

 Ensuring that punched checklist items are cleared & no any constructions on going.

 Implementation of Hydro testing as per approved procedure.

 Monitoring of behavior and post cleaning of the tank.

 Safety related pre-cautions & necessary allocations.

Reviewed By: ……………………….. Approved By: ………………………..


Management Representative Chief Executive Officer
reated on 01/06/2011 11:32:00 AM
LAUGFS ENGINEERING (PVT) LTD
Procedure Manual Department: Engineering

Document #: LE-EN-PR-007 Issue #: 01 Date: 28/02/2014 Page No: 02 of 04

Title: Hydro Testing Procedure

4. Operating Procedure.

4.1 General

Ensure that all mechanical fabrications and installations have been completed, & no
remaining scope related to the Test piece.

All welding seams of the LPG pipes shall be free from paint, grease, oil etc which may
hinder any leak during the test.

Any fitting (pressure gauges, relief valves, level sensors, Pressure switches, etc.) shall not
be fitted to directly to the Test portion and those shall be blanked using blind flanges or
dually isolated from the system .

Original packing/ bolts shall not be used for blanking of flanges.

Make sure to check the all gauges are dually calibrated & the tags are in place.

There should be continuous supervision/monitoring of the FP pipe line from the start of
filling and complete releasing of pressure after testing.

Movement of people around the location should be minimized during filling/pressurizing


and only authorized personnel should be allowed for inspection.

There should be a notice/warning signs indicating status of the pipe line and should be
available in languages understood by all personnel in the area.

If there is any indication of movement shell of lines, Filling/pressurizing must be haltered.

4.2 Filling & Pressurising

Fill the water in to the pre-prepared piping system between the pre-agreed points where
the pressure test perform. Make sure to isolate all necessary accessories mentioned in 4.2.

Then pressurized the system by using pressure pump. Max. Pressure will be 20 Bar.
Working pressure will be 5-6 bar. That will last for 24 hrs & the readings will be noted
within 2 hrs period.

Reviewed By: ……………………….. Approved By: ………………………..


Management Representative Chief Executive Officer
reated on 01/06/2011 11:32:00 AM
LAUGFS ENGINEERING (PVT) LTD
Procedure Manual Department: Engineering

Document #: LE-EN-PR-007 Issue #: 01 Date: 28/02/2014 Page No: 03 of 04

Title: Hydro Testing Procedure

Pressure should read from gauge mounted on pump.

If there any pressure drops, Pipe line inspection will be commenced. Once the defected
joint identified, the rectification will be commenced.

After completion the rectification, entire procedure will be resumed. Measurements &
the time will be recorded.

Releasing of pressure should be done gradually through the vent.

4.4 Report

After successfully completion of the test, a report will be issued by the QA & QC Department of
LAUGFS engineering.

Reviewed By: ……………………….. Approved By: ………………………..


Management Representative Chief Executive Officer