Award of Project 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM 26-Jan-16 08:00 PM, Award of Project
A1540 Final PO Receipt & Start of Project 25-Jan-16 08:00 PM 0d Final PO Receipt & Start of Project
Safety Trainings 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM 26-Jan-16 08:00 PM, Safety Trainings
A1000 Workers Safety Training 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM Workers Safety Training
A1010 PTW Receiver Training 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM PTW Receiver Training
Installation of Pumps /Pipe line 26-Jan-16 08:00 PM 7d 02-Feb-16 08:00 PM 02-Feb-16 08:00 PM, Installation of Pumps /Pipe line
A1020 Taking Measurements 26-Jan-16 08:00 PM 1d 27-Jan-16 08:00 PM Taking Measurements
A1025 Mobilization of Tools & Welding Equipments 26-Jan-16 08:00 PM 1d 27-Jan-16 08:00 PM Mobilization of Tools & Welding Equipments
A1030 Making ISO Hand Drgs 27-Jan-16 08:00 PM 1d 28-Jan-16 08:00 PM Making ISO Hand Drgs
A1040 ISO Drgs Approval 28-Jan-16 08:00 PM 1d 29-Jan-16 08:00 PM ISO Drgs Approval
A1060 Temp Piping Fabrication 29-Jan-16 08:00 PM 1d 30-Jan-16 08:00 PM Temp Piping Fabrication
A1080 Installation of Pipes & Valves 31-Jan-16 08:00 PM 1d 01-Feb-16 08:00 PM Installation of Pipes & Valves
A1090 Isolation by Valve Closure 01-Feb-16 08:00 PM 1d 02-Feb-16 08:00 PM Isolation by Valve Closure
ICOM Workshop Fabrication 27-Jan-16 09:00 AM 8d 04-Feb-16 09:00 AM 04-Feb-16 09:00 AM, ICOM Workshop Fabrication
A1260 Plates & Structural Materials Receiving by Sendan 27-Jan-16 09:00 AM 1d 28-Jan-16 09:00 AM Plates & Structural Materials Receiving by Sendan
A1270 Liner Plates Cutting,Drilling,Bevelling 28-Jan-16 09:00 AM 3d 31-Jan-16 09:00 AM Liner Plates Cutting,Drilling,Bevelling
A1280 Structural Members Cutting 28-Jan-16 09:00 AM 2d 30-Jan-16 09:00 AM Structural Members Cutting
A1290 Coating of Liner Plates (As Per Sendan Paint Code) 31-Jan-16 09:00 AM 2d 02-Feb-16 09:00 AM Coating of Liner Plates (As Per Sendan Paint Code)
A1550 Transport of Prefabricated Plates,Structural Items (From ICOM
02-Feb-16
to S-Chem)
09:00 AM 2d 04-Feb-16 09:00 AM Transport of Prefabricated Plates,Structural Items (From ICOM to S-Chem)
Decontamination of Sump 31-Jan-16 08:00 PM 8d 08-Feb-16 08:00 PM 08-Feb-16 08:00 PM, Decontamination of Sump
A1100 Mobilization of Super Sucker (By ICOM) 31-Jan-16 08:00 PM 1d 01-Feb-16 08:00 PM Mobilization of Super Sucker (By ICOM)
A1110 Arrangement of Fixing for Sucking (By ICOM) 01-Feb-16 08:00 PM 1d 02-Feb-16 08:00 PM Arrangement of Fixing for Sucking (By ICOM)
A1120 Sucking of Contaminated Water (By ICOM) 02-Feb-16 08:00 PM 1d 03-Feb-16 08:00 PM Sucking of Contaminated Water (By ICOM)
A1130 Transportation of Contaminated Water (By Sendan) 03-Feb-16 08:00 PM 1d 04-Feb-16 08:00 PM Transportation of Contaminated Water (By Sendan)
A1140 Steaming (By Sendan) 04-Feb-16 08:00 PM 1d 05-Feb-16 08:00 PM Steaming (By Sendan)
A1150 Chemical Decontamination (By Sendan) 05-Feb-16 08:00 PM 1d 06-Feb-16 08:00 PM Chemical Decontamination (By Sendan)
Sludge Removal (By Sendan) 06-Feb-16 08:00 PM 2d 08-Feb-16 08:00 PM 08-Feb-16 08:00 PM, Sludge Removal (By Sendan)
A1160 Destagging & Depropping 06-Feb-16 08:00 PM 1d 07-Feb-16 08:00 PM Destagging & Depropping
A1170 Final Cleaning & Sludge Removal 07-Feb-16 08:00 PM 1d 08-Feb-16 08:00 PM Final Cleaning & Sludge Removal
Uninstallation of instrument & Comp. Isolation 03-Feb-16 09:00 AM 1d 04-Feb-16 09:00 AM 04-Feb-16 09:00 AM, Uninstallation of instrument & Comp. Isolation
A1220 Stage-1 Cutting & Repair (By Sendan) 04-Feb-16 09:00 AM 3d 07-Feb-16 09:00 AM Stage-1 Cutting & Repair (By Sendan)
A1230 Fixing of Insert Plates with Anchor Fastners 07-Feb-16 09:00 AM 1d 08-Feb-16 09:00 AM Fixing of Insert Plates with Anchor Fastners
A1240 Welding of Main Beam to Insert Plates 08-Feb-16 09:00 AM 1d 09-Feb-16 09:00 AM Welding of Main Beam to Insert Plates
A1250 Stage-2 Cutting & Repair (By Sendan) 09-Feb-16 08:00 PM 2d 11-Feb-16 08:00 PM Stage-2 Cutting & Repair (By Sendan)
A1300 Fixing of Insert Plates with Anchor Fastners 11-Feb-16 08:00 PM 1d 12-Feb-16 08:00 PM Fixing of Insert Plates with Anchor Fastners
A1310 Welding of Secondary Beam to Insert Plates 12-Feb-16 08:00 PM 2d 14-Feb-16 08:00 PM Welding of Secondary Beam to Insert Plates
Insp. and repair of Existing wall (By Sendan) 14-Feb-16 08:00 PM 4d 18-Feb-16 08:00 PM 18-Feb-16 08:00 PM, Insp. and repair of Existing wall (By Sendan)
A1320 Inspection of Existing Wall 14-Feb-16 08:00 PM 1d 15-Feb-16 08:00 PM Inspection of Existing Wall
A1330 Finalization of Methodology of Repair 15-Feb-16 08:00 PM 0d 15-Feb-16 08:00 PM Finalization of Methodology of Repair
A1340 Repair of The Wall & Curing time 15-Feb-16 08:00 PM 2d 17-Feb-16 08:00 PM Repair of The Wall & Curing time
A1420 Fill Up the Tank 02-Mar-16 08:00 AM 1d 03-Mar-16 08:00 AM Fill Up the Tank
A1430 Holding the Water for 24Hrs 02-Mar-16 08:00 AM 1d 03-Mar-16 08:00 AM Holding the Water for 24Hrs
A1440 Check the Level Drop & Draining 02-Mar-16 08:00 AM 2d 04-Mar-16 08:00 AM Check the Level Drop & Draining
Completion of Frame work and top slab 04-Mar-16 08:00 AM 6d 10-Mar-16 08:00 AM 10-Mar-16 08:00 AM, Completion of Frame work and top slab