Вы находитесь на странице: 1из 16

WORK EXPERIENCE

1. Company Name : PT. Arkonin Engineering Manggala Pratama


Jl. Bintaro Taman Timur, Bintaro Jaya,
2. Company Adress :
Jakarta Selatan 12330
3. Personnel Name : Elwansyah Risman, ST., MT.
4. Place / Date of Birth : Magelang, 29 March 1982
5. Formal Education : - Magister S2 Civil Engineering – Infrastructure
Management Engineering, Institute Technology
Bandung, 2009.
- Bachelor S1 Civil Engineering – Civil Engineering,
Institute Technology Bandung, 2006.
6. Non Formal Education : - STAAD Pro v8i, Jakarta 2012
- SketchUp 8, Jakarta 2012
- Basic Diving Course, Bandung 2006.
- Basic Japanese Language Course, Bandung, 2006.
- SAP (Structure Analysis Program) course in Civil
Engineering ITB, 2004.
- AutoCAD course in Civil Engineering ITB, Bandung,
2002.
- Advanced English Language Course, LIA English
Course, Bandung 1998 - 1999.
- Basic to Advance English Language Course,
Bandung, 1991 - 1995.
7. English Vocabulary : Good
8. Work Experience :

Year 2013-Ongoing
8.1. a. Project Name : Palik 1 and 2 (total kapacity 10 MW) Mini-
Hydro Power Plant Project
b. Project Location : Air Palik River, Palik, North Bengkulu,
Bengkulu
c. Project Owner : PT. Gema Bentara Energi
d. Company : PT. Arkonin Engineering MP
e. Job Description :
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility study of the Mini-Hydro Power Plant
- Hydrology and Hydraulic Analysis
- Access Road Analysis and Basic Design
- Access Road Drainage Basic Design and Analysis
- Grading, Retaining wall Structure Basic Design and Analysis
- Water Way and Head Pond Basic Design and Analysis
- DAM Basic Design and Analysis
- Power House and Tail Race Structure Basic Design and Analysis
- Mechanical (Penstock, Power House Crane) Placing, and Design (coordinating
with mechanical engineer)
- Electricity (Instrument and Control House, Switchyard) Placing, and Design
(coordinating with electrical engineer)
- Preparing complete Basic Design Report (Hardcopy and Softcopy)
- Preparing the Cost Estimates and Financial Projection for an operating Mini-Hydro
Power Plant.
- Presentation to Owner and Stakeholders
- Presentation to Local Government
f. Implementation Time : November 2013 – ongoing
g. Position : Civil (Structure, Drainage, Road, Water
Management) Engineer
h. Employment Status : Permanent

Year 2013-Ongoing
8.2. a. Project Name : Nakai (2 x 2.5 MW) Mini-Hydro Power Plant
Project
b. Project Location : Air Nakai River, Nakai, North Bengkulu,
Bengkulu
c. Project Owner : PT. Gema Elektrik Nusantara
d. Company : PT. Arkonin Engineering MP
e. Job Description :
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Hydrology and Hydraulic Analysis
- Review the feasibility study of the Mini-Hydro Power Plant
- Access Road Analysis and Basic Design
- Access Road Drainage Basic Design and Analysis
- Grading, Retaining wall Structure Basic Design and Analysis
- Water Way and Head Pond Basic Design and Analysis
- DAM Basic Design and Analysis
- Power House and Tail Race Structure Detail Design and Analysis
- Mechanical (Penstock, Power House Crane) Placing, and Design (coordinating with
mechanical engineer)
- Electricity (Instrument and Control House, Switchyard) Placing, and Design
(coordinating with electrical engineer)
- Preparing complete Basic Design Report (Hardcopy and Softcopy)
- Preparing the Cost Estimates and Financial Projection for an operating Mini-Hydro
Power Plant.
- Presentation to Owner and Stakeholders
- Presentation to Local Government
f. Implementation Time : November 2013 – ongoing
g. Position : Civil (Structure, Drainage, Road, Water
Management) Engineer
h. Employment Status : Permanent

Year 2013-Ongoing
8.3. a. Project Name : Muara Sahung (2 x 5 MW) Mini-Hydro
Power Plant Project
b. Project Location : Air Luas River, Muara Sahung, Kaur,
Bengkulu
c. Project Owner : PT. Gema Muara Energi
d. Company : PT. Arkonin Engineering MP
e. Job Description :
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility study of the Mini-Hydro Power Plant
- Hydrology and Hidraulic Analysis
- Access Road Analysis and Detail Design
- Access Bridge Analysis and Detail Design
- Drainage Detail Design and Analysis
- Grading, Retaining wall Structure Detail Design and Analysis
- Water Way Detail Design and Analysis
- DAM Detail Design and Analysis
- Power House Structure Detail Design and Analysis
- Mechanical (Penstock, Power House Crane) Placing, and Design (coordinating with
mechanical engineer)
- Electricity (Instrument and Control House, Switchyard) Placing, and Design
(coordinating with electrical engineer)
- Preparing complete Detail Design Report (Hardcopy and Softcopy)
- Preparing the Cost Estimates and Financial Projection for an operating Mini-Hydro
Power PLant.
- Presentation to Owner and Stakeholders
- Presentation to Local Government
f. Implementation Time : November 2013 – ongoing
g. Position : Civil (Structure, Drainage, Road, Water
Management) Engineer
h. Employment Status : Permanent

Year 2013
8.4. a. Project Name : Detail Engineering Design in Mandiri Office
Complex, Wijayakusuma
b. Project Location : Wijaya Kusuma, Pesing, West Jakarta
c. Project Owner : PT. Bank Mandiri (Persero)
d. Company : PT. Arkonin Engineering MP
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility study of the Office Complex Project
- Acces Road Analysis and Detail Design
- Drainage Detail Design and Analysis
- Grading, Retaining wall Structure Detail Design and Analysis
- Mechanical (Drainage Pump) Placing, Engineering and Design (coordinating with
mechanical engineer)
- Electricity Control House Placing, Engineering and Design (coordinating with
electrical engineer)
- Preparing complete Detail Design Report (Hardcopy and Softcopy)
- Preparing the Cost Estimates for an operating Office Complex.
- Presentation to Public Works Department (drainage and drainage pump plan)
- Presentation to Owner
- Presentation to Local Government
f. Implementation Time : September 2013 – February 2014
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2013
8.5. a. Project Name : Feasibility Study Tanjung Batu Baru Coal
Powered Steam Power Plant 2 x 7 MW
b. Project Location : Tanjung Batu, Kepulauan Riau
c. Project Owner : PT. PLN (Persero) Engineering
d. Company : PT. Arkonin Engineering MP
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government
f. Implementation Time : August 2013 – November 2013
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2013
8.6. a. Project Name : Detail Engineering Design of Senoro Pipe
Rack, Central Sulawesi
b. Project Location : Senoro, Central Sulawesi
c. Project Owner : PT. Tripatra Engineering Consultant
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Pipe Rack Structure Calculation
- Bill of Quantity (BoQ) calculation
- Schedule Monitoring
f. Implementation Time : May 2013 – August 2013
g. Position : Structure Engineer
h. Employment Status : Permanent

Year 2013
8.7. a. Project Name : Detail Engineering Design Gedung Wisma
Pelatihan PT. FIF
b. Project Location : Hambalang, West Java
c. Project Owner : PT. FIF
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Retaining Wall
- Design and Presentation of Road Designs.
- Progress monitoring, Reporting.
- Data Inspection.
f. Implementation Time : March 2013
g. Position : Structure Engineer
h. Employment Status : Permanent

Year 2013
8.8. a. Project Name : Detail Engineering Design Gedung BPN
Sentul
b. Project Location : Sentul, West Java
c. Project Owner : BPN
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Retaining Wall
- Design and Presentation of Road Designs.
- Progress monitoring, Reporting.
- Data Inspection.
f. Implementation Time : March 2013
g. Position : Structure Engineer
h. Employment Status : Permanent
Year 2012
8.9. a. Project Name : Masterplan of Water Management in
Mandiri Office Complex, Wijayakusuma
b. Project Location : Wijaya Kusuma, Pesing, West Jakarta
c. Project Owner : PT. Bank Mandiri (Persero)
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Road.
- Design and Presentation of Drainage System
- Design and Presentation of Retaining Pond Designs
- Progress monitoring, Reporting.
- Field Survey and Data Inspection
- Presentation for Stakeholders
- Contract Preparation
f. Implementation Time : September 2012 – December 2012
g. Position : Drainage Engineer, Highway Engineer
h. Employment Status : Permanent

Year 2012
8.10. a. Project Name : Detail Design of ROW 54 Leisure Park
Street, Deltamas
b. Project Location : Kota Deltamas, Cikarang, Bekasi
c. Project Owner : PT. Puradelta Lestari
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Drainage System
- Design and Presentation of Highway Designs.
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.
f. Implementation Time : August 2012 – October 2012
g. Position : Structure Engineer, highway Engineer
h. Employment Status : Permanent

Year 2012
8.11. a. Project Name : Detail Design of KBP Sport Center, Kota
Baru Parahyangan
b. Project Location : Kota Baru Parahyangan, Padalarang, West
Java
c. Project Owner : PT. Belaputra Intiland
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Retaining Wall.
- Design and Presentation of Road Designs.
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.

f. Implementation Time : July 2012 – September 2012


g. Position : Structure Engineer, highway Engineer
h. Employment Status : Permanent

Year 2012
8.12. a. Project Name : Assessment of Buntok MTU Coal Mine
Facility
b. Project Location : MTU Coal Mine, Buntok, Central Kalimantan
c. Project Owner : PT. Indika Logistic and Support Services
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Road Designs
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.
- Hauling Road, Bridge, Port Existing Condition Evaluation.

f. Implementation Time : June 2012 – August 2012


g. Position : Structure Engineer, highway Engineer
h. Employment Status : Permanent

Year 2012
8.13. a. Project Name : DED of of Batu-batu Coal Mine Hauling
Road, Crossing Bridge and Port, Berau
b. Project Location : Batu-batu, Berau, East Kalimantan
c. Project Owner : PT. Harita Jaya Raya
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Hauling Road, Drainage and Building Foundation
Designs.
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.
- Hauling Road Pavement Calculation, Analysis.
- Retaining Wall Calculation, Analysis.
- Volume and Bill of Quantity Planning

f. Implementation Time : March 2012 – September 2012


g. Position : Highway Engineer, Drainage Engineer,
Structure Engineer
h. Employment Status : Permanent

Year 2012
8.14. a. Project Name : DED of Slope Retaining Wall of Batu-batu
Coal Mine, Berau
b. Project Location : Batu-batu, Berau, East Kalimantan
c. Project Owner : PT. Harita Jaya Raya
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Drainage System and Retaining Pond Design.
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.
- Retaining Wall Slope Analysis and Evaluation.

f. Implementation Time : March 2012 – September 2012


g. Position : Drainage Engineer
h. Employment Status : Permanent

Year 2011
8.15. a. Project Name : Pre-Feasibility Study Giant Sea Wall, North
Coast Jakarta
b. Project Location : North Coast Jakarta (Priok)
c. Project Owner : DKI Jaya Government
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Review of Jakarta Drainage System (13 main drainage channel)
- Hydrology Analysis
- Analysis, Reporting and Recommendation
- Cost Estimation
- Presentation of reports.

f. Implementation Time : December 2011


g. Position : Hydrology Engineer
h. Employment Status : Permanent

Year 2011-2012
8.16. a. Project Name : Detail Engineering Design of Cipamingkis
Bridge, Kota Deltamas, Bekasi
b. Project Location : Kota Deltamas, Cikarang, Bekasi
c. Project Owner : Dept. Planning, PT. Puradelta Lestari
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Schedule Planning and monitoring
- Design and Presentation of Approach Road Design.
- Progress monitoring, Reporting and Tender Documents Preparation.
- Field Survey and Data Inspection.
- Volume and Bill of Quantity Planning

f. Implementation Time : November 2011 – March 2012


g. Position : Site Manager, Highway Engineer, Scheduler
h. Employment Status : Permanent

Year 2011
8.17. a. Project Name : Detail Engineering Design of Kotabaru
Parahyangan Clusters R-0, R-15 – R-18,
Collector Road
b. Project Location : Kotabaru Parahyangan, Padalarang, West
Java
c. Project Owner : Dept. Planning, PT. Kotabaru Parahyangan
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Existing Data, Topography and Soil Investigation Review
- Retaining Wall (Concrete and Masonry RW)Calculation and Analysis
- Retaining Wall Foundation Calculation and Analysis
- Highway and Pathway Calculation and Analysis for collector roads, and cluster
roads
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) or material volume for Retaining Wall and
Highway Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner

f. Implementation Time : 2010 - ongoing


g. Position : Infrastructure Engineer
h. Employment Status : Permanent

Year 2011
8.18. a. Project Name : Detail Engineering Design of Central
Business District BSD
b. Project Location : BSD City, Serpong, Tangerang
c. Project Owner : PT. BSD City, BSD
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Existing Data, Topography and Soil Investigation Review
- Highway and Pathway Calculation and Analysis for collector roads, and cluster
roads
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) or material volume for Highway, Mechanical
Electrical and Clean Water Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner
f. Implementation Time : April 2011 – November 2011
g. Position : Infrastructure Engineer
h. Employment Status : Permanent

Year 2011
8.19. a. Project Name : Detail Engineering Design Water Network
Design City de Park BSD
b. Project Location : BSD City, Serpong, Tangerang
c. Project Owner : PT. BSD City
d. Company : PT. Arkonin Engineering MP.
e. Uraian Tugas :
- Existing Data, Topography and Soil Investigation Review
- Piping, Reservoir, and Pipe Bridge Analysis for Clean Water Network
- Calculation and Analysis of Bridge for Pipes
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) for Clean Water Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner
f. Waktu Pelaksanaan : August 2011 s/d November 2011
g. Posisi Penugasan : Structure Engineer
h. Status Kepegawaian pd Perusahaan : Contract

Year 2011-2012
8.20. a. Project Name : Masterplan and DED Plywood Factory,
Kediri
b. Project Location : Kediri, East Java
c. Project Owner : Perum Perhutani Pusat, Jakarta
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Existing Data, Topography and Soil Investigation Review
- Masterplan/Siteplan Review
- Preparing and analysis of Supply Material and Equipment Route Network (log,
vynir)
- Preparing and analysis of Plywood Factory Processing (coordinating with
processing engineer)
- Preparing and analysis of Plywood Factory Mechanical and Electrical System
(coordinating with ME engineer)
- Preparing and analysis of Plywood Factory Detailed Site plan,
- Preparing and analysis of Plywood Factory Drainage System,
- Preparing and analysis of Plywood Factory Clean Water System (coordinating with
water supply engineer),
- Preparing and analysis of Plywood Factory Sewerage System (coordinating with
Environmental Engineer),
- Preparing and analysis of Plywood Factory Road Network,
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) for Plywood Factory.
- Preparing the Spesification and Tender Document
- Presentation to Owner
f. Implementation Name : August 2011 – March 2012
g. Position : Schedule Management, Infrastructure (Road,
Drainage, Structure) Engineer
h. Employment Status : Permanent

Year 2011
8.21. a. Project Name : PMC Project Supply Base Kariangau
b. Project Location : Kariangau, East Kalimantan
c. Project Owner : PT. Indika Logistic and Support Services
d. Company Name : PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Existing Data, Topography and Soil Investigation Review
- Masterplan/Siteplan Review
- Preparing and analysis of Supply Material and Route Network (for coal factory
supply and material and product)
- Preparing and analysis of Material Handling Processing (coordinating with material
handling engineer)
- Preparing and analysis of Supply Base Mechanical and Electrical System
(coordinating with ME engineer)
- Preparing and analysis of Supply Base Port (coordinating with Marine and Port
engineer)
- Preparing and analysis of Supply Base Detailed Site plan,
- Preparing and analysis of Supply Base Drainage System,
- Preparing and analysis of Supply Base Clean Water System (coordinating with
water supply engineer),
- Preparing and analysis of Supply Base Sewerage System (coordinating with
Environmental Engineer),
- Preparing and analysis of Supply Base Road Network,
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) for Supply Base Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner
- Construction Project Monitoring and review and evaluation to construction
contractor and owner
- Operation and Maintenance Recommendation
- Handover to owner
f. Implementation Time : September 2011 – September 2013
g. Position : Schedule Manager
h. Employement Status : Permanent

Year 2011-2012
8.22. a. Project Name : Detail Engineering Design of Derivate
Gondorukem and Terpentine Factory,
Kediri, East Java
b. Project Location : Kediri, East Java
c. Project Owner : Perum Perhutani East Java
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Existing Data, Topography and Soil Investigation Review
- Masterplan/Siteplan Review
- Preparing and analysis of Supply Material and Route Network (Pine forest,
gondorukem supply, )
- Preparing and analysis of Material Handling Processing (coordinating with material
handling engineer)
- Preparing and analysis of Derivate Gondorukem Factory Mechanical and Electrical
System (coordinating with ME engineer)
- Preparing and analysis of Derivate Gondorukem Factory Detailed Site plan,
- Preparing and analysis of Derivate Gondorukem Factory Drainage System,
- Preparing and analysis of Derivate Gondorukem Factory Clean Water System
(coordinating with water supply engineer),
- Preparing and analysis of Derivate Gondorukem Factory Sewerage System
(coordinating with Environmental Engineer),
- Preparing and analysis of Derivate Gondorukem Factory Road Network,
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) for Derivate Gondorukem Factory Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner

f. Implementation Time : July 2011 – February 2012


g. Position : Schedule Manager, Structure Engineer
h. Employment Status : Permanent

Year 2011
8.23. a. Project Name : Detail Engineering Design Log Pond
Hauling Road Penajam.
b. Project Location : Penajam, Passer Utara, East Kalimantan
c. Project Owner : PT. Fajar Surya Swadaya
d. Company Name : PT. Arkonin Engineering MP.
e. Job Description :
- Existing Data, Topography and Soil Investigation Review
- Hauling Road Calculation and Analysis for log hauling
- Bridges (Tunan and Mariango River Bridge) Calculation and Analysis
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) or material volume for Hauling Roads and
Bridges Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner

f. Implementation Time : April 2011 – November 2011


g. Position : Schedule Manager, Road Manager
h. Employment Status : Permanent

Year 2011
8.24. a. Project Name : Detail Engineering Design Kotabaru
Parahyangan Golf Course
b. Project Location : Kotabaru Parahyangan, Padalarang, West
Java
c. Project Owner : PT. Belaputra Lestari
d. Company : PT. Arkonin Engineering MP
e. Job Description :

- Existing Data, Topography and Soil Investigation Review


- Golf Course Road Calculation and Analysis for log hauling
- Golf Course Bridges (5 bridges) Calculation and Analysis
- Golf Course curb, pond, bunker detail design (coordination with golf course
planner)
- Preparing complete Detail Engineering Design Drawing (Hardcopy and Softcopy),
Inspection and Review
- Preparing the Bill of Quantity (BoQ) or material volume for Golf Course
Infrastructure.
- Preparing the Spesification and Tender Document
- Presentation to Owner

f. Implementation Time : Desember 2011 – Ongoing


g. Position : Schedule Manager
h. Employment Status : Permanent

Year 2011
8.25. a. Project Name : AMDAL and UPL/UKL (Environmental
Analysis) Hauling Road Penajam
b. Project Location : Penajam, Passer Utara, East Kalimantan
c. Project Owner : PT. Fajar Surya Swadaya
d. Company : PT. Arkonin Engineering MP.
e. Job Discription :
- Planning proposal, schedule and project costs
- Monitoring schedule and Manning Schedule
- Field Survey
- Social Survey (Coordinating with Social Engineer)
- Environmental Effect (air, water, land, noise pollution) Survey (Coordinating with
Environmental Engineer)
- Coordinating and commisioning meeting between owner, society and other involved
organization
- Meeting and agreement with government (Environmental Ministry)
- Preparing the complete AMDAL and UKL/UPL Reports
- Reccomendation
f. Implementation Time : August 2011 – November 2011
g. Position : Schedule manager
h. Employment Status : Permanent

Year 2011
8.26. a. Project Name : Feasibility Study Berau Steam Power Plant
2 x 7 MW
b. Project Location : Berau, East Kalimantan
c. Project Owner : PT. PLN (Persero) Engineering
d. Project Name : PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government

f. Implementation Time : July 2010 – April 2011


g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2011
8.27. a. Project Name : Feasibility Study Malinau 2 x 3 MW
b. Project Location : Malinau, East Kalimantan
c. Project Owner : PT. PLN (Persero) Engineering
d. Company : PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government
f. Implementation Time : July 2010 – April 2011
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2010 - 2011


8.28. a. Project Name : Feasibility Study Labuan Bajo Steam
Power Plant 2 x 3 MW
b. Project Location :Labuan Bajo, East Nusa Tenggara
c. Project Owner :PT. PLN (Persero) Engineering
d. Company :PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government
f. Implementation Time : July 2010 – April 2011
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2010 – 2011


8.29. a. Project Name : Feasibility Study Merauke Steam Power
Plant 2 x 7 MW
b. Project Location :Merauke, Papua
c. Project Owner :PT. PLN (Persero) Engineering
d. Company :PT. Arkonin Engineering MP.
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government
f. Implementation Time : July 2010 – April 2011
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2010 – 2011


8.30. a. Project Name : Feasibility Study Nabire Steam Power
Plant 2 x 7 MW
b. Project Location :Nabire, Papua
c. Project Owner :PT. PLN (Persero) Engineering
d. Company :PT. Arkonin Engineering MP
e. Job Description :
- Preparing the Proposal
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the power plant location
- Analysis of the coal supply and transportation
- Acces Road Analysis and engineering
- Environmental effect analysis and engineering
- Grading Basic Design and Analysis
- Drainage Basic Design and analysis
- Structure Basic Design and analysis
- Power plant cooling system Basic design and analysis
- Port Basic Design and analysis
- Mechanical and coal material handling Engineering (coordinating with mechanical
engineer)
- Electricity and Single Line Diagram Engineering (coordinating with electrical
engineer)
- Preparing the operating and maintenance route and network of an operating Steam
Power Plant
- Analyze the feasibility of a steam power plant in the chosen area
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Preparing the Cost Estimates for an operating Steam Power Plant.
- Presentation to Owner and Local Area PLN
- Presentation to Local Government
f. Implementation Time : July 2010 – April 2011
g. Position : Civil (Structure, Drainage, Road, Port)
Engineer
h. Employment Status : Permanent

Year 2008
8.31. a. Project Name : Detail Engineering Design Cooling System
Steam Power Plant Kerawang
b. Project Location :
Kerawang, Banten
c. Project Owner :
d. Company : Hydraulic and Fluid Mechanic Lab ITB
e. Job Description :
- Field Survey
- Existing Data, Topography and Soil Investigation Review
- Review the feasibility of the cooling System
- Environmental effect analysis and engineering
- Power plant cooling system Basic design and analysis
- Preparing complete Feasibility Study (Hardcopy and Softcopy), Inspection and
Review
- Presentation to Owner
f. ImplementationTime : Late 2007 – Early 2008
g. Position : Hidraulic Engineer
h. Employment Status : Temporary

9. Employment Status in this Company : Permanent

Jakarta, July 12th 2014


PT. Arkonin Engineering MP

( Elwansyah Risman, ST. MT. )


Civil Engineer
RESUME
Personal Data
Name Elwansyah Risman
Address Puri Flamboyan Citra 2 Block B-4 / 10 Rempoa, Ciputat, Jakarta 15000
elwan150@students.itb.ac.id,
Phone Mobile 0813-2006-0806 E-mail elwan150@gmail.com
Home (021) 737-5557
Gender Male
Place/DOB Magelang/March 29th 1982 Religion Islam
Interest Project (Planning, O&M) Management, Construction Design
Hobbies Reading, Learning, Music, Computing

Education
ITB (Institute Technology Bandung), Major Magister of Civil Engineering
University Bandung, West Java, Indonesia (Infrastructure Management)
Date December 20th 2009
Water Allocation Plan based by Multi-Criteria Matrix
Final Project Title in Citarum Cascade Dams System, West Java, Indonesia
Final Project Brief The goal of my final project is to achieve an analysis to study and improve the
existing water allocation operation plan in Citarum River Cascade dams by using
multi-criteria matrix derived and developed by and to satisfy the dams stakeholder’s
needs.
ITB (Institute Technology Bandung), Major Bachelor of Engineering
University Bandung, West Java, Indonesia (Civil Engineering)
Date January 13th 2006 Result GPA 2.46/4.00
Drainage Engineering Structures Planning in Griya Nusantara II Housing Complex
Final Project Title in Sangatta, Kutai, East Kalimantan, Indonesia
Final Project Brief The goal of my final project is to design a drainage plan of the Griya Nusantara II
Housing Plan to prevent ebbs flood in the complex. This final project is a part of
Griya Nusantara II Housing Complex Project, which is located in the same area.

Other Information
Training and Seminars
Speaker Date Topic
Civil Engineering 2008 New researches developed by ITB tutor and students that’s been
Journal Researchers published in International Civil Engineering Journal
Bina Marga 2008 Indonesian highway management
Representatives
European Engineer 2007 New and improved construction technology and machinery
Representatives developed by European Manufactures
Middle East Engineer 2007 An overview of Water Structures in Middle East especially Dams
Representatives and Water Allocation Infrastructure
Ari Ginanjar 2006 ESQ (Emotional Spiritual Quotient) Training
Courses
Place Date Description
Diving Course 2006 Basic Diving Course
Japanese Course 2006 Basic Japanese Language Course
SAP Course 2004 SAP short course in Civil Engineering ITB
AutoCAD Course 2002 AutoCAD short course in Civil Engineering ITB
LIA English Course 1998 - 1999 Advanced English Language Course
Oxford English Course 1991 - 1995 Basic to Advance English Language Course
Organizational Experiences
Title Date Description
Member 2000 - 2006 Student Union (KM) ITB, Bandung
Member 2000 - 2006 Civil Student Union (HMS) of ITB, Bandung
Member 2000 - 2006 Moslem Civil Student Union (KMMS) of ITB, Bandung
Member of Board 1997 OSIS (Student Union) SMUN 1 Rengat, Riau
Member 1994 - 1996 Boy Scout and Youth Red Cross Probolinggo, East Java
Skills
Type Description
Computer Windows, Office (MS Word, MS Excel), presentation (MS PowerPoint),
CAD (AutoCAD, Visio, ArchiCAD), project manager programs (MS Project), civil engineering
programs (SAP (Structure Analysis Program), STAAD Pro v8i (Structure Analysis Program),
HEC-RAS (River Analysis System), SWMM (Storm Water Management Model))
Language Indonesia (Mother Tongue), English (Fluent in speaking, reading, writing),
References
Ir. Herlien D. Setio, Head Department of Civil Engineering ITB
Ir. Ilyas Suratman, Head Department of Magister Civil Engineering ITB
Ir. Iwan Kridasantausa , Lecturer and Tutor of Civil Engineering ITB
Ir. Dantje Kardana, Lecturer and Thesis Supervisor of Civil Engineering ITB
Ir. M.Syahril Badri K., Lecturer and Thesis Supervisor of Civil Engineering ITB
Ir. Demi Harlan, Lecturer and Tutor of Civil Engineering ITB
Ir. Ahmad Nurzaman, Head Director in PT. Arkonin Consultant and Member of IAI
Ir. Syaiful Ikram, Head Director in PT. Arkonin Engineering Manggala Pratama Consultant
Ir. Beno Sarwedi, Former Head Division in PT. Arkonin Engineering Manggala Pratama Consultant
Ir. Atman Mardadi, Head Division in PT. Arkonin Engineering Manggala Pratama Consultant

Вам также может понравиться