SUBMITTAL COVER
Package Title: Interior Finishing Works Number: CXR-BP09-MAT-0072
Package No: BP09 Type: Material Submittal
Specification: G11
Contract Ref:
BOQ Ref:
Other Ref:
CPG
TUR
02
CPG
TUR
03
CPG
TUR
EMPLOYER COMMENTS (IF ANY): STATUS CODES:
A Approved
B Approved with Comments
C Revise and Resubmit
D Reviewed
E Rejected
CONTRACTOR DETAILS
Prepared By: DANG QUANG VAN Reviewed By: PHAM HOANG TUAN
Title: DEPUTY SITE MANAGER Title: PROJECT MANAGER
Telephone:
Supplier Address/Địa chỉ nhà cung cấp: 09 Doan Van Bo St., Dist.4, HCMC
Refering to specification
1 DIN 18252/EN 1303 Comply/Phù hợp Tham khảo theo đặc tính kỹ thuật
Equipment Schedules/Specifications
Tiến độ trang thiết bị/ Quy cách kỹ thuật
SPECIFICATION
ASSESSMENT
NO SPECIFICATION OF MATERIAL RESULT
INDICATOR
STT TIÊU CHÍ KỸ THUẬT THÔNG SỐ KỸ KẾT QUẢ
CHỈ TIÊU ĐÁNH GIÁ
THUẬT VẬT LIỆU
I Masterkey system G11
Material
1 316 stainless steel 304 stainless steel
Vật liệu
Surface Comply
2 satin finish satin finish
Bề mặt Phù hợp
Shape Comply
3 No sharp protrustion No sharp protrustion
Hình dạng Phù hợp
32 pins/tumblers 32 pins/tumblers
Structure Comply
4 positions positions
Cấu trúc Phù hợp
8 rows 5 rows
II Lock Cylinders G11
Keys Comply
3 Nickel silver Nickel plated steel
Chìa khóa Phù hợp
Cylinder lengh Comply
4 65mm 111 mm
Chiều dài ruột khóa Phù hợp
Tamper-proof stainless Comply
5 box Yes Yes Phù hợp
Hộp inox chống trộm
Phone: +0912746263
Address: 137 Nguyen Chi Thanh St., Cam Nghia Ward, Cam Ranh, Khanh Hoa Province
Email: van.dang@lecade.com.vn
EXIT DOORS
TE
IT
SERVER ROOM & IMMIGRATION GOODS DELIVERY / GATE LOUNGE 02 BAGGAGE HANDLER'S OFFICE
O
D
PAX SERVICE
TE
MK2-KA1 MK2-KA2 MK2-KA3 MK2-KA4 MK2-KA5
D
TOLL BOOTHS
TE
IT
GATE LOUNGE 1 OFFICES EXIT DOORS BAGGAGE ROOM CLEANER'S ROOM @ 1ST
M
IT
O
GATE LOUNGE 2
M
STORE @ 1ST
O
GENERAL DIRECTOR
D
MK2-KA1 MK2-KA7 MK2-KA8
TE
MK2-KA2 MK2-KA3 MK2-KA4 MK2-KA5 MK2-KA6
IT
SMOKING LOUNGES FIRST AID ROOM BAGGAGE RECONCILIATION CLEANER'S ROOM @ 2ND EXIT DOORS CIP LOUNGE 01 CIP LOUNGE 02 VIP LOUNGE
M
DEPARTURE HALL MAA OFFICE REV ISSUE DATE
ROOM TOILET DUCTS @ 2ND TOILETS @ CIP LOUNGE 02 TOILETS @ VIP LOUNGE
O
TOILETS @ CIP LOUNGE 01
PARENTS' ROOM @ 2ND CB07 - UPDATE SPECIFICATION PER FIRE 07/11/2017
01
INVALID TOILETS @ 2ND
STORE @ 2ND AUTHORITY COMMENT
MK3-KA7 MK3-KA8
MK3-KA1 MK3-KA3 MK3-KA5 (UTILITY CENTRE) (UTILITY CENTRE)
AHU ROOMS LOAD CENTRES GENERATOR ROOM TOILET & STORE
COMMS/ MDF ROOMS
DATA RISERS TX ROOM OFFICE
LT ROOM
HT ROOM
GENERATOR CONTROL ROOM
FUEL TANK
UNDERGROUND WATER TANKS
MK3-KA2 MK3-KA4 MK3-KA6 PUMP ROOMS
1 31
TX ROOMS CV CLOSETS (ANCILLARY BUILDING) CHILLER PLANT ROOM
LT ROOMS MECH RISERS SEWERAGE TREATMENT PLANT MV ROOM
UPS ROOMS A
PASSENGER TERMINAL
BUILDING
Q
ELEVATED DRIVEWAY
N
MASTERKEY LAYOUT 1
DRAWING NO.
ROOM NAME - ROOM NAME R.C. STRUCTURE 1. ALL LOCKCASES FOR DOUBLE LEAF DOORS WITH REBATED 5. ALL INDICATING BOLTS SHALL BE SUPPLIED WITH FLAT 8. EXCEPT HINGES FOR TOILET COMPARTMENTS, ALL HINGES 12. WHERE AT IS INCLUDED IN THE " LOCATION " OF THE DOOR 15. ALL KEY SWITCH BOXES SHALL BE SUPPLIED WITH THEFT 1. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS
100 THK LIGHTWEIGHT MEETING STILES SHALL BE FITTED WITH REBATED KIT TO STRIKING PLATE AND COLOUR TO S.O.'s APPROVAL SHALL BE OF FULL STAINLESS STEEL SATIN FINISH c/w SUCH DOOR SHALL BE INSTALLED WITH ACOUSTIC SEAL RESISTANCE SCREWS BEFORE COMMENCEMENT OF WORKS.
- FINISHED FLOOR LEVEL
FFL +0050
SFL +0000 - STRUCTURAL FLOOR LEVEL BLOCKWALL SUIT THE DOORS
6. DOOR CLOSERS, IF FITTED SHALL BE ONE NUMBER EACH TO
CONCEALED BALL BEARING AND AS PER SPECIFICATION SYSTEM.
16. THE CONTRACTOR SHALL CHECK ALL DIMENSIONS BEFORE
2. ALL DIMENSIONS STATED ON DRAWING ARE IN MM UNLESS
OTHERWISE STATED.
MASTER KEY LAYOUT
200 THK CMU BLOCKWALL 2. ALL LOCKCASES SHALL BE SUPPLIED WITH FACE PLATE & 9. ALL TOILET INDICATORS SHALL BE SUPPLIED WITH CONCEALED COMMENCEMENT OF WORK 3. PROPOSED PLATFORM LEVEL = +11.3M= SFL +0.000
FLOOR FINISH - CM ALP - CEILING FINISH 13. ALL DOORS FITTED WITH ACOUSTIC DOOR SEAL SYSTEM
STRIKING PLATE DOUBLE LEAF DOORS FIXING FROM OUTSIDE 4. DETAILS AS SHOWN ARE INDICATIVE OF DIMENSIONS, SETTING
VENTILATION - A/C CM - WALL FINISH SHALL BE ABLE TO MEET 175mm WATER HEAD AND ACHIEVE 17. ALL EXPOSED METAL DOORS SHALL BE SPRAYED FINISH WITH
EXTINGUISHER 3. ALL LOWER FLUSH BOLTS SHALL BE COMPLETE WITH DUST STC 36 ENAMEL PAINT. OUT AND DESIGN INTENT ONLY ARE BY NO MEANS CONCLUSIVE
7. ALL EXPOSED DOOR CLOSERS FOR DOORS SWINGING 10. ALL FIXING SHALL BE SUPPLIED WITH TROX HEAD BOLT REV NO. :
FIRE-RATED DOOR 2.3kg PORTABLE ABC POWDER PROOF SOCKETS. IN STRUCTURAL ADEQUACY NOR COMPREHENSIVE IN PARTS
OUTWARDS FROM ROOMS (i.e. SWING TOWARDS THROUGH FIXING TO PREVENT TAMPERING 14. ALL FIRE-RATED VISION PANELS SHALL BE CLEAR AND NON
18. FOR ROOMS WITH DOORS SWING TOWARDS PUBLIC /
FIRE EXTINGUISHER FOR LEVER ACTION FLUSHBOLT & DUST PROOF SOCKET AND COMPONENTS FOR FULL INTERFACING WITH THE OTHER
PUBLIC/PASSENGER AREAS/ROOMS) SHALL BE FITTED WITH 11. WHERE STAINLESS STEEL (S.S.) IS SPECIFIED, IT SHALL BE WIRE MESH FIRE GLASS PANELS TESTED AS PART OF THE PASSENGER AREAS, DOOR CLOSERS SHALL BE INSTALLED
NON FIRE-RATED DOOR REFER TO SPEC. ADJACENT TRADES AND FOR FULL COMPLETION. CAD Ref : \\S03c06\U:\Camranh_PTB\01_Working_Folders\AA\02REVIT
OR HEIGHT FROM SFL +0
- PARALLEL ARM BRACKET OTHERWISE THEY SHALL BE FITTED FIRE-RATED DOORS AND APPROVED BY THE RELEVENT INSIDE THE ROOMS.
GLASS SWING DOOR SATIN FINISH 5. DETAILS SHOWN ARE INTENDED TO BE INDICATIVE OF THE DESIGN
OR
HEIGHT FROM SFL OF THAT 4. ALL FLOOR MOUNTED DOOR STOPS SHALL BE INSTALLED WITH WITH SLIDE ARM AND CHANNEL. AUTHORITIES Date :
PART OF THE FLOOR M8 x 50mm LONG TREADED ANCHOR BOLT INTENT, PROFILES AND DETAILING REQUIRED FOR THE WORK. THE
GLASS SLIDING DOOR CONTRACTOR IS TO FOLLOW PROPOSED MANUFACTURER'S C 2016, CPG Consultants Pte Ltd
FH PILLAR HYDRANT
ALL ABBREVIATONS, SYMBOLS AND TAGS ARE TO DETAILS AND INSTALLATION METHODS SO AS TO MAINTAIN THE
WT WATER THROAT OPTIMUM PERFORMANCE AND WARRANTY OF THE PRODUCT. CPG Consultants Pte Ltd reserves all rights to these drawings, designs and/or
BE READ IN CONJUNCTION WITH DRG NO. DWG-002
CONFLICTS BETWEEN THE DRAWN DETAILS AND any other data contained herein. No part of the said drawings, designs and/ or
TR TROLLEY PARKING MANUFACTURER'S DETAILS AND/ OR REQUIREMENTS ARE TO BE other data may be reproduced, modified, transmitted or used in any form or by
any means for any purpose without the prior written consent of CPG
HIGHLIGHTED TO THE DESIGNERS FOR RESOLUTION. ANY COST
Consultants Pte.Ltd, other than the sole purpose for which such drawings
ARISING FROM SUCH RESOLUTION SHALL NOT BE ENTERTAINED designs and/or other data are provided to licensed users on
AND SHALL BE SUFFICIENTLY PRICED/ALLOWED FOR IN THE such terms as CPG Consultants Pte Ltd may prescribe.
TENDER SUM.
Hardware Quotation
Re: SAN BAY CAM RANH
916.08.68321 RUỘT KHOÁ 1 ĐẦU VẶN 1 ĐẦU AC1, MD1, MD2, F2, F3, F5, F6, F7, SD1, SD2, T1, T2
CHÌA 35.5/35.5MM AC2, F1, MD4, LD1, LD2, S1, MD3, T4
Häfele VN LLC
Monday, Dec 04, 2017
9 Doan Van Bo street, District 4, HCMC
Page 1 of 5
(Picture of the article may be
different from actual product)
Hardware Quotation
Re: SAN BAY CAM RANH
916.00.00721
RUỘT KHOÁ PSM 31.5/31.5MM BC - SD CHO TOÀN BỘ CỬA KÍNH
Häfele VN LLC
Monday, Dec 04, 2017
9 Doan Van Bo street, District 4, HCMC
Page 2 of 5
(Picture of the article may be
different from actual product)
Hardware Quotation
Re: SAN BAY CAM RANH
916.08.68321
RUỘT KHOÁ 1 ĐẦU VẶN 1 ĐẦU CHÌA 35.5/35.5MM
Häfele VN LLC
Monday, Dec 04, 2017
9 Doan Van Bo street, District 4, HCMC
Page 3 of 5
(Picture of the article may be
different from actual product)
Hardware Quotation
Re: SAN BAY CAM RANH
916.00.01321
RUỘT KHOÁ 2 ĐẦU CHÌA PSM - SD CỬA F7
Häfele VN LLC
Monday, Dec 04, 2017
9 Doan Van Bo street, District 4, HCMC
Page 4 of 5
(Picture of the article may be
different from actual product)
Hardware Quotation
Re: SAN BAY CAM RANH
916.00.60321
RUỘT KHÓA 1 ĐẦU CHÌA PSM-GMK 35.5/10MM, KEYWAY BC - SD CỬA T3
Häfele VN LLC
Monday, Dec 04, 2017
9 Doan Van Bo street, District 4, HCMC
Page 5 of 5
(Picture of the article may be
different from actual product)
Assessment Report
22115-02
Report Sponsor:
CONTACT INFORMATION
AUSTRALIA
Victoria Singapore
UNITED KINGDOM
Exova Warringtonfire
Holmesfield Road
Warrington, WA1 2DS
United Kingdom
www.warringtonfire.net
CONTENTS
Main Body Page
1. Introduction 4
2. Requirements 4
3. Conclusions 4
4. Validity 5
7. Supporting data 7
Appendices
1 INTRODUCTION
1.1 This report presents an assessment of the fire resistance performance of the steel
doorset as previously fire tested and described in WARRES No. 100357, if modified as
described in the Appendices of this report.
1.2 The proposed steel doorset is required to be capable of a performance of 240 minutes
integrity with respect to SS 332: 2007, Clause 4.
1.3 The data referred to in Section 7 (Supporting Data) of this report has been considered for
the purpose of this assessment, which has been prepared in general accordance with the
principles of Fire Test Study Group Resolution 82, 2001.
1.4 This report may only be reproduced in full without modifications by the report sponsor.
Copies, extracts, or abridgments of this report in any form shall not be published by other
organisations without permission of Exova Warringtonfire Aus Pty Ltd.
2 REQUIREMENTS
2.1 Doorsets shall be installed into supporting construction of brickwork, concrete blockwork
or, reinforced concrete capable of providing the necessary support for the required period
of 240 minutes.
2.2 Doorsets shall be constructed in a similar manner from materials and components of the
same manufacture and equivalent quality as tested or, as otherwise appraised by Exova
Warringtonfire.
2.3 Door leaf edge clearance gaps will not exceed the tested values as recorded in WARRES
No.100357. Larger gaps will invalidate this report.
3 CONCLUSIONS
3.1 If the tested doorset described in WARRES No. 100357 had been modified as described
in the Appendices of this report, it is expected that it would have been capable of
achieving a performance of 240 minutes integrity with respect to SS 332: 2007, Clause 4.
3.2 This Conclusion is conditional on the supporting test reports being currently valid. An
expired report invalidates this Conclusion.
4 VALIDITY
4.1 This assessment report does not provide an endorsement by Exova Warringtonfire Aus
Pty Ltd of actual products supplied.
4.2 The conclusions of this assessment may be used to directly assess fire hazard, but it
should be recognised that a single test method will not provide a full assessment of fire
hazard under all conditions.
4.3 Because of the nature of fire testing, and the consequent difficulty in quantifying the
uncertainty of measurement, it is not possible to provide a stated degree of accuracy. The
inherent variability in test procedures, materials and methods of construction, and
installation may lead to variations in performance between elements of similar
construction.
4.4 The assessment can therefore only relate to the actual prototype test specimens, testing
conditions and methodology described in the supporting data, and does not imply any
performance abilities of constructions of subsequent manufacture.
4.5 This assessment is based on information and experience available at the time of
preparation. The published procedures for the conduct of tests and the assessment of
test results are the subject of constant review and improvement and it is recommended
that this report be reviewed on or, before, the stated expiry date.
4.6 The technical content of this report remains the intellectual property of Exova
Warringtonfire. Therefore to maintain its applicability, if contradictory evidence becomes
available the assessment will be unconditionally withdrawn and Hart Industries Pte Ltd
will be notified in writing. Similarly, the assessment is invalidated if the assessed
construction is subsequently tested because actual test data is deemed to take
precedence over an expressed opinion.
4.7 The information contained in this report shall not be used for the assessment of variations
other than those stated in the conclusions above. The assessment is valid provided no
modifications are made to the systems detailed in this report. All details of construction
should be consistent with the requirements stated in the relevant test reports and all
referenced documents.
4.8 This assessment is only valid if accompanied by full copies of the indicated supporting
data.
5 DECLARATION BY:
HART INDUSTRIES PTE LTD
By distributing copies of this report we, Hart Industries Pte Ltd confirm that:
we are not aware of any information that could adversely affect the conclusions of
this assessment; if we subsequently become aware of any such information, we
agree to ask the assessing authority to withdraw the assessment.
6 AUTHORISATION BY:
EXOVA WARRINGTONFIRE AUS PTY LTD
6.1 Signatures
S M Kettle K Nicholls
7 SUPPORTING DATA
7.1 The following report summary is provided for information only. Reference shall be made
to complete copies of the reports for full specimen and performance details.
The passive leaf was fitted with a glazed aperture based on a pane of Firelite of 312mm
by 162mm. The leaves were each hung on four hinges. The active leaf was latched to the
passive leaf, which was bolted.
*The performance indicated in the Addendum to the test report, on the condition that only
Dorma TS83 door closers are fitted.
A1 APPENDIX 1
SS332: 2007, Clause 4
A1.1 Proposal
A1.1.1 It is proposed that the performance achieved by the doorset assembly as described in
WARRES No. 100357 and tested in accordance with BS 476: Part 22: 1987, may be
considered to indicate a similar notional performance of 240 minutes integrity is possible
with respect to SS332: 2007, Clause 4.
A1.2 Discussion
A1.2.1 The critical testing procedures, temperature/time regime, performance criteria, and
instrumentation in BS 476: Part 22: 1987 and SS332: 2007, Clause 4, are similarly
expressed, and are technically comparable. However, there is a significant difference
relating to furnace overpressure.
A1.2.2 For BS: 476: Part 22, the furnace overpressure is controlled so that the neutral axis, or
ambient atmospheric pressure, occurs at 1000mm above the notional floor level. For
SS332: 2007 the neutral axis is set at 500mm above the notional floor level.
A1.2.3 At a given height above the notional floor level, this change in pressure effectively
increases the atmospheric furnace pressure to which test specimens are exposed relative
to the ambient pressure.
A1.2.4 Depending on the nature of the specimen, such an increase in pressure can produce
significantly different results, caused by an increased tendency for hot gases and flames
to pass to the unexposed face.
A1.2.5 Specimens that include any combustible materials are particularly at risk from either direct
ignition of the materials themselves or, ignition of evolved vapours as they exit on the
unexposed side of the specimen. In addition, the greater tendency for hot gases to flow
within gaps and voids within a specimen may affect temperature sensitive materials and
materials prone to thermal degradation or erosion by charring.
A1.2.6 The test specimen under consideration is a doorset entirely of steel construction.
Performance in a fire resistance test is expected to be determined by thermal response
alone and not complicated by thermal degradation or significant erosion, or softening as
might occur with combustible or relatively low melting point specimens, which are
generally more sensitive to variations in test methods.
A1.2.7 The thermal properties of steel are therefore expected to compensate for the increased
furnace overpressure specified in SS332: 2007: Clause 4
A1.2.8 In this case, the achieved test performance is considered to indicate a notionally similar
performance with respect to SS332: 2007: Clause 4 is possible, and the proposal is
positively appraised for the required period of 240 minutes.
A2 APPENDIX 2
Alternative ironmongery by Hafele
A2.1 Proposal
A2.1.1 It is proposed that the following items of ironmongery may be fitted in place of the
corresponding items as originally tested. The Installation Notes shall apply:
Installation notes
• Closers shall be supported by separate and specific test evidence in accordance
with BS 476: Part 22: 1987, SS 332: 2000 or, SS 332: 2007 to show they have
been fitted on the unexposed face of a completely uninsulated steel doorset that
achieved an integrity performance of at least the required period.
• If fire test data is not available, the closers shall only be fitted on the exposed face
of doorsets when the direction of risk can be clearly identified as being from one
side only.
Installation note:
Except during periods of planned maintenance or access, the dead bolt shall be
engaged.
A2.1.7 Hinges
Hafele 2BB st/st butt hinges, 100~127mm x 75~100mm x 3mm
Tectus TE 520/525 3D full solid steel hinge
Tectus TE 210 3D full solid steel hinge
Tectus TE 310 3D full slid steel hinge
Tectus TE 630 3-D full solid steel hinge
Tectus TE510 3D and TE510 HU full solid steel hinges
Installation notes
• The coordinator shall only be used when the plastic roller is replaced by a roller of
non-combustible material.
• If the plastic rollers are retained, the coordinator shall only be fitted on the exposed
face of doorsets when the direction of exposure can be clearly identified as being
from one side only, and the doorset opens towards the fire risk.
Installation note
• The panic device shall be supported by separate and specific test evidence in
accordance with BS 476: Part 22: 1987, SS 332: 2000 or, SS 332: 2007 to show it
has been fitted on the exposed face of a completely uninsulated steel doorset that
achieved an integrity performance of at least the required period.
• If fire resistance test data is not available, the panic devices shall be fitted in
addition to a mortice or cylindrical lock and top and bottom bolts, as originally
tested or, as otherwise assessed by Exova Warringtonfire.
Installation note
• Seals shall be fitted in the centre of the bottom edges of leaves.
A2.2 Discussion
A2.2.1 All the items have been tested in accordance with methods described in the appropriate
Annexes of SS 332: 2007, which requires hardware be tested for mechanical
performance in addition to acceptability with respect to fire resistance performance. The
relevant test data is summarised in the Supporting Data section of this report.
A2.2.2 The critical specifications of the proposed items have been compared against the
corresponding items as originally tested on the target doorset described in WARRES No.
100357.
A2.2.3 The proposed items have been appraised for risk in terms of:
§ quantity and configuration of leaf or frame material removed for installation
§ the melting point of critical components
§ degree of restraint of leaf in the closed position
§ potential ignition source of materials of construction
A2.2.4 In some cases, particular installation conditions are considered necessary, as discussed
below.
A2.2.5 Ignition of hydraulic fluid escaping from a heated door closer on the unexposed face of an
uninsulated steel doorset can occur in a manner constituting loss of integrity. Fluid from a
closer on the exposed face of a doorset is more likely to be consumed within the furnace
chamber.
A2.2.6 Consistent with the available certificates of conformity (CoC’s), the application of the
proposed closers is limited to the periods stated in the certificates.
A2.2.7 Where there is no specific reference to applicability to uninsulated steel doorsets, the
Installation Note requires additional appropriate fire resistance test data be made
available.
A2.2.8 As a basic premise, in the absence of specific fire test data, roller latches cannot be
accepted as appropriate means of providing positive mechanical restraint in fire resisting
applications.
A2.2.9 It is for this reason that the relevant Installation Note requires that doorsets fitted with the
proposed roller latch are normally locked except for planned maintenance or access.
Door coordinator
A2.2.10 The proposed item includes an arm and a plastic roller. The roller bears directly against
an uninsulated steel leaf of the target doorset. In view of the uninsulated nature of the
leaves and the required period of 240 minutes, there is a notional risk of ignition of the
roller material.
A2.2.11 The risk associated with the roller is avoided if it is replaced by a roller of non-combustible
material, in which case the selector would be acceptable for applications requiring 240
minutes integrity.
A2.2.12 If the plastic roller is retained, the coordinator is to be fitted only on the exposed side of
doorsets.
A2.2.13 Because rod-operated panic devices may not provide latching and bolting functions
directly comparable with a standard latch and flush bolts as originally tested, the proposal
requires specific supporting test data relating to uninsulated steel doorsets. Such test data
will be an acceptable means of providing the necessary confidence to support their use.
A2.2.14 When fitted, the aluminium seal carriers will occur between steel door leaf skins, and the
elastomeric components will occur at mid-thickness of the leaf.
A2.2.15 The elastomeric components are combustible and may flame during a standard fire test.
However, the seals are set back from the leaf faces, and the specified furnace pressure
condition at the floor level is negative, which tends to draw air into the furnace chamber.
A2.2.16 This airflow is therefore expected to reduce the risk that flaming associated with the
elastomeric components would be observed on the unexposed side for a sustained
period of 10 seconds, which would be required to constitute loss of integrity as defined in
the testing standard.
A2.2.17 in view of the relatively small mass of combustible material, its location, and the prevailing
furnace pressure condition, the proposed seals are not considered to present a significant
risk of integrity weakness for the required period of 240 minutes
Overall performance
A2.2.18 Consistent with the available certificates of conformity (C0C’s), the application of the
particular closers is limited to applications requiring 120 minutes integrity, as indicated in
the certificates.
A2.2.19 The Proposal includes Installation Notes that when satisfied, support a positive
assessment for the required period of 240 minutes.
A2.2.20 Where no Installation Notes or other conditions are stated in the Proposal, the proposed
items of ironmongery effectively replace the corresponding items as originally tested on a
like-with-like basis and are positively assessed for period of 240 minutes.