Академический Документы
Профессиональный Документы
Культура Документы
1
Economic Dispatch
A B C L
2
Limitations of Economic Dispatch
B C
Network
A D
B
A
LA LB
CA CB
50 $/MWh 100$/MWh
PA PB
4
PAMAX PBMAX
Acceptable ED Solution
100 MW 0 MW
300 MW
B
A
5
Unacceptable ED Solution
200 MW 0 MW
500 MW
B
A
6
Modified ED Solution
100 MW 200 MW
300 MW
B
A
16.00 16.00
15.00 15.00
14.00 14.00
13.00 13.00
12.00 12.00
0 175 350 525 700 0 350 700 1050 1400
Generator Power (MW) Total Area Generation (MW)
Bus A Bus B
300.0 MW 300.0 MW
199.6 MW 400.4 MW
AGC ON AGC ON
9
Two Bus with Unconstrained Line
With no
overloads the Transmission line
OPF matches Total Hourly Cost : 8459 $/hr is not overloaded
Area Lambda : 13.01
the economic
dispatch
300.0 MW 300.0 MW
197.0 MW 403.0 MW
AGC ON AGC ON
380.0 MW 300.0 MW
260.9 MW 419.1 MW
AGC ON AGC ON
With the line loaded to its limit, additional load at Bus A must be supplied
locally, causing the marginal costs to diverge.
Similarly, prices paid by load and paid to generators will differ bus by bus.
(In practice, some markets such as ERCOT charge zonal averaged price to load.)
11
Optimal Power Flow (OPF)
OPF functionally combines the power flow
with economic dispatch.
Minimize cost function (operating cost) while
taking into account realistic equality and
inequality constraints.
Equality constraints:
– bus real and reactive power balance
– generator voltage set points
– area MW interchange
12
OPF
Inequality constraints:
– transmission line/transformer/interface flow limits
– generator MW limits
– generator reactive power capability curves
– bus voltage magnitudes.
Available Controls:
– generator MW outputs
– transformer taps and phase shifters
13
OPF
• Optimization problem: Classical objective
function
– Minimize the cost of generation
• Equality constraints
– Power balance at each node - power flow
equations
• Inequality constraints
– Network operating limits (line flows, voltages)
– Limits on control variables
14
Mathematical Formulation of the OPF
• Control variables:
– Active power output of the generating units
– Voltage at the generating units
– Position of the transformer taps
– Position of the phase shifter taps
– Status of the switched capacitors and reactors
• Vector of control variables:
15
Mathematical Formulation of the OPF
• State variables
– Describe the response of the system to changes in
the control variables
– Magnitude of voltage at each bus
• Except generator busses, which are control variables
– Angle of voltage at each bus
• Except slack bus
• Vector of state variables:
16
Mathematical Formulation of the OPF
• Parameters
– Known characteristics of the system
– Assumed constant
• Network topology
• Network parameters (R, X, B, flow and voltage limits)
• Generator cost functions
• Generator limits
• …
• Vector of parameters:
17
Mathematical Formulation of the OPF
• Classical objective function:
– Minimize total generating cost:
• Equality constraints:
– Power balance at each node - power flow equations
• Compact expression:
18
Mathematical Formulation of the OPF
• Inequality constraints:
– Limits on the control variables:
• Compact expression:
19
Compact form of the OPF problem
Subject to:
20
OPF Challenges
21
Solving the OPF using gradient methods
• Slow convergence
• Objective function and constraints must be
differentiable
• Difficulties in handling inequality constraints
– Binding inequality constraints change as the
solution progresses
23
Linearizing the OPF problem
24
Sequential LP OPF
• Consequence of linear approximation
– The solution may be somewhat sub-optimal
– The constraints may not be respected exactly
• Need to iterate the solution of the linearized
problem
• Algorithm:
1. Linearize the problem around an operating point
2. Find the solution to this linearized optimization
3. Perform a full ac power flow at that solution to find
the new operating point
4. Repeat
25
Advantages and disadvantages
• Advantages of LPOPF method
– Convergence of linear optimization is guaranteed
– Fast
– Reliable optimization engines are available
– Used to calculate nodal prices in electricity
markets
• Disadvantages
– Need to iterate the linearization
– “Reactive power” aspects (VAr flows, voltages) are
much harder to linearize than the “active power
aspects” (MW flows)
26
Example C - 3 Bus Example
Consider a three bus case (bus 1 is system
slack), with all buses connected through 0.1 pu
reactance lines, each with a 100 MVA limit.
Let the generator marginal costs be:
Bus 1: 10 $ / MWhr; Range = 0 to 400 MW,
Bus 2: 12 $ / MWhr; Range = 0 to 400 MW,
Bus 3: 20 $ / MWhr; Range = 0 to 400 MW,
Assume a single 180 MW load at bus 3.
27
B3 with Line Limits NOT Enforced
60 MW 60 MW
Bus 2 Bus 1
10.00 $/MWh
20 MW 20 MW
Bus 2 Bus 1
10.00 $/MWh
19 MW 19 MW
Bus 2 Bus 1
10.00 $/MWh
31
Why is Bus 3 LMP $ 14 / MWh?
With the line from 1 to 3 limited, no additional
power flows are allowed on it.
To supply 1 more MW to bus 3 we need:
Extra production of 1MW: Pg1 + Pg2 = 1 MW
No more flow on line 1 to 3: 2/3 Pg1 + 1/3 Pg2 = 0;
Solving requires we increase Pg2 by 2 MW and
decrease Pg1 by 1 MW – for a net increase of
$14/h for the 1 MW increase.
That is, the marginal cost of delivering power
to bus 3 is $14/MWh. 32
Both Lines into Bus 3 Congested
0 MW 0 MW
Bus 2 Bus 1
10.00 $/MWh
33
Limiting Carbon Dioxide Emissions
• There is growing concern about the need to limit
carbon dioxide emissions.
• The two main approaches are (1) a carbon tax, or
(2) a cap-and-trade system (emissions trading)
• The tax approach involves setting a price and emitter of
CO2 pays based upon how much CO2 is emitted.
• A cap-and-trade system limits emissions by requiring
permits (allowances) to emit CO2. The government sets
the number of allowances, allocates them initially, and
then private markets set their prices and allow trade.
34