Вы находитесь на странице: 1из 189

SECTION 3.

1
VOLUME 2 PAGE 1 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

SECTION 3.1

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 2 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

CONTENTS
PAGE
1.  SCOPE OF WORKS 4 

1.1  DESCRIPTION OF WORKS .......................................................................................... 4 

2.  BRIEF SCOPE OF WORKS: 4 

2.1  PACKAGE S-1 ............................................................................................................... 4 

2.2  PACKAGE S-2 ............................................................................................................... 5 


2.3  PACKAGE S-3 ............................................................................................................... 5 

2.4  PACKAGE S-4 ............................................................................................................... 6 

2.5  PACKAGE S-5 ............................................................................................................... 7 


2.6  PACKAGE S-6 ............................................................................................................... 7 
2.7  PACKAGE S-7 ............................................................................................................... 7 

3.  DETAILED SCOPE OF WORKS: 9 

3.1  PACKAGE S-1 ............................................................................................................. 11 


3.1.1  132/66/11KV GHARAFA REPLACEMENT 11 
3.1.2  132/33KV QP-HALUL SUBSTATION 23 
3.1.3  132/11KV UNIVERSITY SOUTH SUBSTATION 28 
3.1.4  220/132/66/11KV DOHA INDUSTRIAL SUPER (DIS) SUBSTATION 33 
3.1.5  132/11KV LOGISTIC VILLAGE SUBSTATION 46 

3.2  PACKAGE S-2 ............................................................................................................. 52 


3.2.1  132/11KV AL KARA’ANA SUBSTATION 52 
3.2.2  132/11KV MADINAT AL-KABAAN SUBSTATION 57 
3.2.3  132/11KV AL RUWAIS SUBSTATION 63 
3.2.4  132/11KV AL ZUBARAH SUBSTATION 68 
3.2.5  132/11KV BARZAN CAMP 1 (BC 1) SUBSTATION 73 
3.2.6  132/11KV BARZAN CAMP 2 (BC 2) SUBSTATION 78 

3.3  PACKAGE S-3 ............................................................................................................. 81 


3.3.1  66/11KV GHARAFA NORTH SUBSTATION UPGRADE 81 
3.3.2  66/11KV BIN MAHMOOD SUBSTATION 85 
3.3.3  66/11KV AL MERGAB MALL 91 
3.3.4  66/11KV MINISTRY OF INTERIOR (MOI) 94 
3.3.5  66/11KV DOHA INDUSTRIAL F (DIF) 101 

3.4  PACKAGE S-4 ........................................................................................................... 104 

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 3 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.1  DOHA LAND (PREV. CALLED HEART OF DOHA) UNDERGROUND SUBSTATIONS104 


3.4.2  66/11KV DOHA LAND 1 SUBSTATION (PREV. NAMED HEART OF DOHA 1) 106 
3.4.3  66/11KV DOHA LAND 2 SUBSTATION (PREV. CALLED HEART OF DOHA 2) 110 
3.4.4  66/11KV SHERATON PARK SUBSTATION 116 
3.4.5  66/11KV BARWA AL DOHA SUBSTATION 121 

3.5  PACKAGE S-5: .......................................................................................................... 127 


3.5.1  66/11KV GRAND HAMAD AVENUE SUBSTATION 127 
3.5.2  220/66/11KV NEW DOHA-B SUPER (NDBS) 133 
3.5.3  220/66/11KV ABU HAMOUR SUPER (AHS) 140 

3.6  PACKAGE S-6 ........................................................................................................... 151 


3.6.1  132/22KV AEROSPACE CITY 1 SUBSTATION 151 
3.6.2  132/22KV AEROSPACE CITY 2 SUBSTATION 156 

3.7  PACKAGE S-7: TELECOMMUNICATIONS SYSTEM ............................................... 161 


3.7.1  INTRODUCTION 161 
3.7.2  SCOPE OF WORK 161 
4.  NOTES TO BIDDERS 171 

5.  IMPORTANT NOTES APPLICABLE FOR ALL PACKAGES 174 

6.  EXTENT OF SUBSTATION CONTRACT 176 

6.1  SCOPE OF SUPPLY ................................................................................................. 176 


6.2  SCOPE OF SERVICES ............................................................................................. 177 

6.3  REQUIRED DISTANCES IN GIS / CONTROL ROOMS ............................................ 179 

6.4  INTERFACES BETWEEN CONTRACTORS ............................................................. 180 

Annexure 1 – Scope of Work for 66/11 kV Doha Land Substation


Annexure 2 – Scope of Work for 66/11 kV Sheraton Park Substation
Annexure 3 – Scope of Work for 66/11 kV Barwa Al Doha Substation

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 4 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

1. SCOPE OF WORKS
1.1 DESCRIPTION OF WORKS

As continuation to Phase 9 Project, KAHRAMAA intends to further develop, expand and


improve the existing power transmission network under the project entitled 'Qatar Power
Transmission System Expansion – Phase 10’. The objective of this project is to cope with the
increased power demand and rapid development of the State of Qatar. The substation works
under the Phase 10 Project, are grouped into six substation packages and one
telecommunication package, as summarized in the Section 2 below.

The works of the Phase 10 Project are spread all over the State of Qatar including both newly
and already developed areas. The details as available at the time of preparation of this Tender
Documents are shown on the Location maps enclosed. The exact coordinates and ground
elevation shall be coordinated with the concerned Authorities during the project execution stage.

2. BRIEF SCOPE OF WORKS:


2.1 PACKAGE S-1
132/66/11kV Gharafa: New Transmission Substation (replacement of the existing
132/66/11kV Gharafa substation) incorporating 132kV GIS, 66kV GIS, 11kV metal
enclosed switchgear (AIS/GIS), 132/66kV and 66/11kV power transformers,
11/0.415kV station service transformers, 132kV shunt reactors, other associated
equipment and diversion of the existing cable lines connected to the existing Gharafa
SS as indicated elsewhere in the Tender document.

132/33kV QP-Halul: New Transmission Substation incorporating 132kV GIS, 33kV


metal enclosed switchgear (GIS), 132/33kV power transformers, 33/0.415kV station
transformers and associated equipment as required and as indicated elsewhere in
the Tender document.

132/11kV University South: New Transmission Substation incorporating 132kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

220/132/66/11kV Doha Industrial Super (DIS): New Transmission Substation


(replacement of the existing 132/66/11kV Saliyah substation) incorporating 220kV
GIS, 132kV GIS, 66kV GIS, 11kV metal enclosed switchgear (GIS), 220/132kV
autotransformers, 132/66kV and 66/11kV power transformers, 11/0.415kV station
service transformers, other associated equipment and diversion of the existing cable
and overhead lines connected to the existing Saliyah SS as indicated elsewhere in
the Tender document.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 5 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

132/11kV Logistic Village: New Transmission Substation incorporating 132kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station service transformer and associated equipment as required and as
indicated elsewhere in the Tender document.

2.2 PACKAGE S-2


132/11kV Al Kara'ana: New Transmission Substation incorporating 132kV GIS,
11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

132/11kV Madinat Al-Kabaan: New Transmission Substation incorporating 132kV


GIS, 11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

132/11kV Al Ruwais: New Transmission Substation incorporating 132kV GIS, 11kV


metal enclosed switchgear (AIS/GIS), 132/11kV power transformers, 11/0.415kV
station transformers and associated equipment as required and as indicated
elsewhere in the Tender document.

132/11kV Al Zubarah: New Transmission Substation incorporating 132kV GIS, 11kV


metal enclosed switchgear (AIS/GIS), 132/11kV power transformers, 11/0.415kV
station transformers and associated equipment as required and as indicated
elsewhere in the Tender document.

132/11kV Barzan Camp 1: New Transmission Substation incorporating 132kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

132/11kV Barzan Camp 2: New Transmission Substation incorporating 132kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 132/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

2.3 PACKAGE S-3


66/11kV Gharafa North: New Transformer Feeder Substation (replacement of the
existing 66/11kV Gharafa North substation) incorporating 11kV metal enclosed
switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV station service
transformers and associated equipment as required and as indicated elsewhere in
the Tender document.

66/11kV Bin Mahmood: New Transmission Substation incorporating 66kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 6 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

station transformers and associated equipment as required and as indicated


elsewhere in the Tender document.

66/11kV Al Mergab Mall: New Transmission Substation incorporating 66kV GIS,


11kV metal enclosed switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV
station transformers and associated equipment as required and as indicated
elsewhere in the Tender document.

66/11kV Ministry of Interior (MOI): New Transmission Substation incorporating


66kV GIS, 11kV metal enclosed switchgear (AIS/GIS), 66/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

66/11kV Doha Industrial F (DIF): New Transmission Substation incorporating 66kV


GIS, 11kV metal enclosed switchgear (AIS/GIS), 66/11kV power transformers,
11/0.415kV station transformers and associated equipment as required and as
indicated elsewhere in the Tender document.

2.4 PACKAGE S-4


66/11kV Doha Land-1 (Previously called Heart of Doha - 1): New Underground
Transmission Substation to be incorporated within the building constructed by
Developer and including 66kV GIS, 11kV metal enclosed switchgear (AIS/GIS),
66/11kV power transformers, 11/0.415kV station transformers and associated
equipment as required and as indicated elsewhere in the Tender document.

66/11kV Doha Land-2 (Previously called Heart of Doha - 2): New Underground
Transmission Substation to be incorporated within the building constructed by
Developer and including 66kV GIS, 11kV metal enclosed switchgear (AIS/GIS),
66/11kV power transformers, 11/0.415kV station transformers and associated
equipment as required and as indicated elsewhere in the Tender document.

66/11kV Sheraton Park: New Transmission Substation to be incorporated within the


building constructed by Developer and including 66kV GIS, 11kV metal enclosed
switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV station transformers
and associated equipment as required and as indicated elsewhere in the Tender
document.

66/11kV Barwa Al Doha: New Transmission Substation to be incorporated within the


building constructed by Developer and including 66kV GIS, 11kV metal enclosed
switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV station transformers
and associated equipment as required and as indicated elsewhere in the Tender
document.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 7 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

2.5 PACKAGE S-5


66/11kV Grand Hamad Avenue: New Transmission Substation to be incorporated
into public multi-storey parking facilities and including 66kV GIS, 11kV metal
enclosed switchgear (AIS/GIS), 66/11kV power transformers, 11/0.415kV station
transformers and associated equipment as required and as indicated elsewhere in
the Tender document. Construction of the public multi-storey parking facility is part of
this Package.

220/66/11kV New Doha B Super (NDBS): New Transmission Substation (upgrade


of the existing 66/11kV New Doha B substation) incorporating 220kV GIS, 66kV GIS,
11kV metal enclosed switchgear (AIS/GIS), 220/66kV and 66/11kV power
transformers, 11/0.415kV station service transformers, other associated equipment
and diversion of the existing cable lines connected to the existing New Doha B S/S
as indicated elsewhere in the Tender document.

220/66/11kV Abu Hamur Super (AHS): New Transmission Substation (upgrade of


the existing 220/66/11kV Abu Hamour substation) incorporating 220kV GIS, 66kV
GIS, 11kV metal enclosed switchgear (AIS/GIS), 220/66kV and 66/11kV power
transformers, 11/0.415kV station service transformers, other associated equipment
and diversion of the existing cable lines connected to the existing Abu Hamour SS as
indicated elsewhere in the Tender document.

2.6 PACKAGE S-6


132/22kV Aerospace City 1: New Transmission Substation incorporating 132kV
GIS, 22kV metal enclosed switchgear (GIS/AIS), 132/22kV power transformers,
22/0.415kV station service transformer, diversion of 132kV cables and associated
equipment as required and as indicated elsewhere in the Tender document.

132/22kV Aerospace City 2: New Transmission Substation incorporating 132kV


GIS, 22kV metal enclosed switchgear (GIS/AIS), 132/22kV power transformers,
22/0.415kV station service transformer and associated equipment as required and as
indicated elsewhere in the Tender document.

2.7 PACKAGE S-7


Telecommunication System: New telecommunication equipment shall be provided
for connection of the new substations to KM Telecommunication System including all
works necessary to connect these substations to NCC/ENCC/DCC and to keep
existing connections of existing substations being modified, replaced or upgraded
under the scope of Phase 10 as per detailed technical specification in Volume 3. New
substations for which telecommunication system shall be provided under the subject
Scope are: 132/33kV QP Halul substation (Package S-1) and all substations from
Package S-2 and S-4 as listed above as well as New Doha B Super (NDBS) and Abu

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 8 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Hamur Super (AHS) from Package S-5. Telecommunication system for other
substations from Phase 10, shall be provided by Others. under the Phase 9, Contract
GTC/240C/2008.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 9 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3. DETAILED SCOPE OF WORKS:


BIDDER shall note that:

Remote end modifications: The Scope of Works identifies remote end substations and type of
circuit, e.g. OHL/ cable, involved as connecting link between the two substations. In some cases
remote end substations are also part of the Phase 10 project. However there are cases where
remote ends are existing (or under construction as part of the previous Phases) substations /
generating (power) stations. In such cases, the scope of substation Contractor includes all
modifications in Protection, Station Control System, etc, related to the Contractor’s main Scope
of Works, pre-commissioning checks, end to end tests and all commissioning activities as
appropriate at the far end stations as well.

EHV and HV Cables: It is general approach that all EHV and HV cables for connections within
substations and between SWG and OHL terminal gantry / cable compound are in the substation
Contractor Scope of Works. The scope of substation Contractor also includes required co-
ordination with the Contractor(s) of far end substation(s), underground power cable Contractors
and OHL Contractors, for pre - commissioning checks, end to end tests and all commissioning
activities as appropriate. Each Contractor shall be responsible for the works (including his share
of interface points) as per the Scope of the Works. In the case of dispute, if any, KAHRAMAA ’s
decision in this regard shall be final and binding to all concerned parties.

The following is under the Scope of work for substation Contractor when is required to dismantle
oil filled cable to install new XLPE cable:
• Excavation and related civil work
• Removing oil tank
• Disconnect Gauge/manometer panels and control/alarm cables
• Cut and cap existing oil filled cables
• Remove the existing terminations
• Delivery of dismantled material to KAHRAMAA store

Dismantling works: Where substation Contractor Scope of the Works includes replacement of
existing substation, dismantling works of the existing facilities, generally, are not included in the
Scope of substation Contractor. However, site clearance of the area dedicated / required for the
substation Contractor Scope, including existing structures, if any, is obligation of substation
Contractor.

Future development: In the detailed scope of works below, planned future development for
each substation is clearly specified. Bidder should note all requirements for spare bays, space
for future bays, future transformers, capacitor banks, etc. Those should be considered during the
tendering and later in design stage in order to allocate sufficient space, to properly plan and size
cable corridors / ducts, common services such as uninterrupted power supply, HVAC and other
related facilities.

Pricing for civil works: Volume 7 of this Tender document includes site plot layout drawings
and general arrangement drawings for Control / Protection buildings. Commercial offer shall be
based on the subject drawings, considering specified minimum clearances and operation
distance requirements specified in Section 6.3 of this document and related specification,

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 10 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

considering actual Scope of Works and offered equipment. Bidder is obliged to ensure that
buildings are properly sized and to provide relevant layout drawings within the Technical offer.
Accordingly, no price variations will be allowed for change of the building size in the later stage
of Contract. Part of civil works such as perimeter fence, access road and filling works will be
measured and paid as “per actual” quantities.

Remote end modifications: Phase 10 specifications shall be apprlicable for all modification
works at remote end substations constructed under Phase 5 or earlier projects and which will be
connected to Phase 10 substations. Therefore protection relays need to be changed. Also
replacement of CTs is anticipated, and for this work separate unit price shall be provided.

It shall be noted that number of substations considered as “Remote End SS” is currently under
construction (Phase VIII, GTC 144 and Phase-IX, GTC 240A/2008, SIEMENS Consortium) and
all the equipment/systems will be under warranty for a period of 2 years from its date of Taking
Over. Hence, in case the equipment/system is still under warranty during modification under the
scope of this project, the Contractor shall execute the works in such a way as not to dilute or
nullify existing warranties in any way, whatsoever. All details of work such as, method
statements, interface requirements, intended subcontractors, etc shall be discussed and agreed
with Kahramaa well in advance of the scheduled commencement date of such works and full
clarity shall be established. The same is applicable for modification on the cable lines which are
part of this Contract.

Connection to NCC/ENCC/DCC: All modification works at Kahramaa control centers


NCC/ENCC/DCC to include new and modified / upgraded / refurbished existing substations
shall be included in a separate Contract GTC/375/2010. The scope of substation Contractor
under this project includes all interfacing works with GTC/375/2010 Contractor necessary to
include new substations and modifications to existing substations into the NCC, ENCC and
DCC, including interoperability and end-to-end testing. This includes co-ordination works with
GTC/375/2010 Contractor and both Phase IX & Phase X Telecommunication Contractors during
all stages until commissioning and end to end test.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 11 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1 PACKAGE S-1

3.1.1 132/66/11KV GHARAFA REPLACEMENT

132/66/11kV Gharafa Substation is an existing outdoor substation. KAHRAMAA


proposes to build new Gharafa substation within the boundary of the existing
substation. There is sufficient space on the South and North side of the substation
area to accommodate all facilities under the present Scope. However, it may be
required to demolish or relocate some of the existing facilities in those areas. Unused
site offices and mash wire fence are located on the south side of the plot. Gate
house, mahole and six mobile substations are located in the North area. Dismantling
of outdoor substation equipment and demolishing of structures after completion of all
diversions is under the Scope of this Contract. The Contractor shall make a
comprehensive site survey and submit method statement outlining detailed proposal
for the execution of works or demolishion, including protection of existing facilities,
which shall be subject to KAHRAMAA approval prior to start of any site works.
Contractor shall bear all the costs of repair/replacement in the case that any of the
services are damaged / disturbed. Work shall be done in a way to avoid any
interruption of supply from the existing substation during execution of the project.

The principal elements of new 132/66/11kV Gharafa substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:

- Eleven (11) Nos. outgoing feeder bays

- Three (3) Nos. 132/66 kV, 160MVA outgoing Transformer bays

- Two (2) Nos. 30MVAr shunt reactor bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Ten (10) Nos. outgoing feeder bays

- Three (3) Nos. 132/66kV, 160MVA incoming Transformer bays

- Four (4) Nos. 66/11kV, 40MVA outgoing Transformer bays

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 12 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:

11kV Switchgear A:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformer feeders

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks

11kV Switchgear B:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Three (3) Nos. Power Transformers 132/66kV, 96/120/160 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ Existing 2 Nos. 132/66 kV 150MVA transformers shall be disassembled and


transported to KM store

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 13 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc

¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer

¾ Two (2) Nos. 132kV, 30MVAr Shunt Rectors provided with terminal CTs,
neutral CTs etc.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned above is provisional.


Transformers shall be of adequate capacity to cater to the total station load with
additional 30% margin. The capacity of the transformer is to be justified by calculation
note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV and 66kV GIS
- Condition monitoring system for 160MVA, 40MVA transformers and
30MVAr shunt rectors
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil works related to new 132/11kV substation including building services
and works related to the diversion of 132kV and 66KV cables as per Appendix
F – Drawings

¾ 132kV and 66kV GIS room Crane

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 14 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.

¾ Fire protection system for power transformers and shunt reactors

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

- 132kV, 1x800 mm2, XLPE, 160MVA, triple circuits, special bonded at


Gharafa S/S cable links, single point earthed with earth continuity conductor,
between new 132/66kV transformers and new 132kV GIS switchgear laid in
unfilled concrete troughs with all accessories. Approx. route length: 100m.

- 132kV, 1x500 mm2, XLPE, 30MVA, double circuits, solid bonded at


Gharafa S/S cable links between new 132kV shunt reactors and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories Approx.
route length: 100m.

- 66kV, 1x2000 mm2, XLPE, 160MVA, triple circuits, special bonded at


Gharafa S/S cable links, single point earthed with earth continuity conductor,
between new 132/66kV transformers and new 66kV GIS switchgear laid in
unfilled concrete troughs with all accessories. Approx. route length: 100m

- 66kV, 1x500 mm2, XLPE, 40MVA, quadruple circuits, solid bonded at


Gharafa S/S cable links, between new 66/11kV transformers and new 66kV
GIS switchgear laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m

- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
Gharafa S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within S/S,
laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.

- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) cable links between 11kV switchgear and 11/0.415, 1000 kVA
Station transformers. Approx. route length: 30 m.

¾ Cable Diversions:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 15 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Existing OHL/ cable circuits from Gharafa substation are as under:

- 2 x 132kV cable circuits to Duhail, including 2x24 fiber cables,


- 2 x 132kV cable circuits to GGM, including 2x24 fiber cables,
- 3 x 132kV cable circuits to DNS, including 3x24 fiber cables,
- 2 x 132kV cable circuits to Al Sowaidi, including 2x24 fiber cables,
- 2 x 66kV cable circuits to Gharafa South including 2x24 fiber cables,
- 2 x 66kV cable circuits to KTS (Khalifa Town South) including Pilot Cu
cables,
- 2 x 66kV cable circuits to Qatar University,
- 2 x 66kV cable circuits to Feriq Bin Omran

Existing 66kV cable circuits to Qatar University and Feriq Bin Omran shall not be
diverted to new Gharafa SS. They will be dismantled as described under introductory
note of this Section.

The diversion work of remaining cable circuits from existing Gharafa to Gharafa (New)
substation shall be done by the substation Contractor as specified below. The
substation Contractor should make all necessary arrangements to connect cable
termination with new 132kV/66kV GIS. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion. The following existing cable
circuits connected to the existing Gharafa substation shall be diverted to new Gharafa
S/S:

- Gharafa to Duhail: 132kV, 1x800 mm2, XLPE, 160 MVA double circuits
shall be diverted with associated fiber optic cable (24 Fibers) and DTS cable to
132kV GIS at Gharafa New S/S. This line is with cross bonding arrangement.
Approx. route length: 200m. Laying of DTS cable of approximately 2 x 200m
from diversion point to DTS termination box, including splicing with existing
DTS Cable and re-commissioning of DTS Unit in Duhail is included in the
Scope. The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.

- Gharafa to GGM: 132kV, 1x2000 mm2, XLPE, 260 MVA double circuits
shall be diverted with associated fiber optic cable (24 Fibers) to 132 GIS at
Gharafa New S/S, special bonded cable links. Approx. route length: 200m. The
Contractor shall include for all necessary modification works in the earthing
arrangement (cross bonding, single point bonding, mixed bonding) in order to
ensure that required current rating of diverted circuit is maintained. At the
moment this line is connected to Gharafa South West substation however
under the current contract (M/s ABB) it shall be diverted to 132/11kV GGM
substation.

- Gharafa to DNS: 132kV, 1x2000 mm2, XLPE, 225 MVA triple circuits shall
be diverted with associated fiber optic cable (24 Fibers) and DTS cable to 132
GIS at Gharafa New S/S, special bonded cable links. Approx. route length:
200m. Laying of DTS cable of approximately 1 x 200m from diversion point to

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 16 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

DTS termination box, including splicing with existing DTS Cable and re-
commissioning of DTS Unit in DNS is included in the Scope. The Contractor
shall include for all necessary modification works in the earthing arrangement
(cross bonding, single point bonding, mixed bonding) in order to ensure that
required current rating of diverted circuit is maintained.

- Gharafa to Al Sowaidi: 132kV, 1x1000sqmm, XLPE, 160MVA, double


circuits, shall be diverted with associated fiber optic cable (24 Fibers) to
132kV GIS at Gharafa New S/S, special bonded cable links. Approx. Route
length: 200m. The Contractor shall include for all necessary modification works
in the earthing arrangement (cross bonding, single point bonding, mixed
bonding) in order to ensure that required current rating of diverted circuit is
maintained.

- Gharafa to Gharafa South S/S: 66kV, 1x500 mm2, XLPE, 40 MVA double
circuits shall be diverted with associated fiber optic cable (24 Fibers) to 66kV
GIS at Gharafa New S/S, special bonded cable links. Approx. route length:
200m. The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.

- Gharafa to KTS (Khalifa Town South): 66kV, 3 x 150 mm2, Oil filled Cable,
Cu, 26 MVA double circuits shall be diverted to 66kV GIS at Gharafa New
S/S via 66kV, 1 x 300 mm2, Cu, XLPE Cable and Transition Joints,
including dismantling the terminations at Gharafa S/S and suction the oil from
existing cables*. Approx. route length: 500m. Necessary oil feeding
modification (oil tank, alarm panel, oil pressure gauge manometer, oil pipe
feeding, all test required for oil filled cables and concrete manhole for oil tank
and transition joint) for the existing cables shall be done according to the oil
profile details for existing cables ( design and arrangement shall be submitted
for approval). The exact location of cutting cables or diversion points and detail
design shall be responsibility of Contractor and to be covered by the contract
price. All required works for re-routing (laying) of Pilot Cu Cables shall be
included as well. Contractor shall include for all necessary modification works
in the earthing arrangement (cross bonding, single point bonding, mixed
bonding) in order to ensure that required current rating of diverted circuit is
maintained.

* - The remaining portion of diverted oil filled 66kV Cables will be abandoned along
the route and sealing the ends of oil filled cables left in ground without any
contamination or hazard to the surrounding environment (appropriate method
statement to be submitted for approval prior commencement of works).

3.1.1.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 17 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

tests, shall be included in contract prices as optional works. Cables and


terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.1.1.2 MODIFICATIONS AT DNS, AL SOWAIDI, DUHAIL, GHARAFA


SOUTH, KTS AND GGM SUBSTATIONS

The scope of work shall include but not limited to the following:

- Re-testing and re-commissioning of the existing GIS/ switchgear bays in


service along with Local Control Panels including indicating meters in the local
control panels, inscription of additional alarm facia as required, replacing of
GIS name plates and any required works including, wiring, testing & complete
re-commissioning of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC.

¾ SCS and Power Control Scope for remote end modification:

Duhail Substation:

132/66/11kV Duhail substation is existing transformer feeder substation with GIS built
under Phase 5, Contract GTC/13/2003

- Minor modifications to existing SCS supplied by SIEMENS under Phase 5 to


include changes to 2 x 66kV bay for 132/66kV transformer cable feeders in the
SCS including Gateway data mapping to NCC/ENCC and S/S works
necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

GGM Substation:

132/11kV GGM substation is under the construction as part of the separate Contract
(developer M/s Ezdan) and shall be connected to KAHRAMAA network on 132kV
level via LILO of existing 132kV cable line between substations Gharafa South West
(Contract GTC 1, Marubeni) and existing Gharafa (outdoor type substation built
before Phase 4).

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 18 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Under this (Phase 10) Contract the following shall be done:

- Minor modifications to existing SCS supplied by ABB (SAS) to include changes


to 2 x 132kV cable feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

DNS Substation:

220/132/66/11kV Doha North Super (DNS) is existing substation with GIS built under
Phase 4 project

- Existing BCUs in 3x132kV bays utilized for connection towards Gharafa S/S
shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications to SCS supplied by ABB to include changes to 3x132kV


cable feeders in the SCS.

- Minor modifications to existing RTU/TDB/TMMC to include changes to


3x132kV cable feeders including S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Al Sowaidi Substation:

- Minor modifications to existing SCS supplied by AREVA under Phase 8 to


include changes to 2 x 132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End –
to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Gharafa South Substation:

- Minor modifications to existing SCS supplies by ABB under Phase 6 to include


changes to 2 x 66kV transformer cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End –
to – End testing.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 19 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

KTS (Khalifa Town South) Substation:

- Minor modifications to existing conventional control panel and


RTU/TDB/TMMC to include changes to 2 x 66kV transformer cable feeders
including S/S work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC

¾ Protection Scope for remote end modification:

Duhail Substation:

For 2x66kV bays of 132/66kV cable transformer feeders connected to Gharafa


substation, complete functional protection system as per Standard specification shall
be provided.

- The new relays/equipment shall be installed at Duhail substation to match the


(new) protection at Gharafa substation end. Siemens make 7SD5 and ABB
make REL561 provided for transformer cable feeder protection shall be
replaced accordingly.

- All modification, Testing and commissioning, end to end test to make it fully
operational is in present Scope of works.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. If required, additional CT core
or changing of the CTs shall be the responsibility of the Contractor. Optional
price for the (132kV side, 160 MVA Transformer bushing) CT replacement and
all associated works shall be provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement.

GGM Substation:

Modifications of the remote substations Gharafa South West and Gharafa shall be
carried out by separate Contract recently awarded to M/s ABB (developer M/s.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 20 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Ezdan) and new protection shall be provided for GGM - Gharafa 132kV circuits
accordingly.

- At GGM substation, 2 x 132kV Cable feeders connected to Gharafa substation,


shall be provided with complete functional protection system as per Standard
specification by GGM Contractor. The relays/equipment to be installed at new
Gharafa substation under this Contract shall match the protection provided at
GGM substation end (under separate M/s. Ezdan contract).

- All modification, Testing and commissioning, end to end test to make it fully
operational is under the present Scope.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement

DNS Substation:

For 3x132kV Cable feeders connected to Gharafa substation, complete functional


protection system as per Standard specification shall be provided.

- The new relays/equipment shall be installed at Doha North Super substation to


match the protection at (new) Gharafa substation end.

- All modification, Testing and commissioning, end to end test to make it fully are
included in the present Scope

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. If required, additional CT core
or changing of the CTs shall be the responsibility of the Contractor. Optional
price for the (GIS) CT replacement and all associated works shall be provided

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement

Al Sowaidi Substation:

For 2 x 132kV Cable feeders connected to Gharafa substation, complete functional


protection system as per Standard specification shall be provided.

- The new relays/equipment shall be installed at Gharafa substation to match the


protection provided at Al Sowaidi substation end (P545 relay and 7SD522
relay under).

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 21 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- All modification, Testing and commissioning, end to end test to make it fully
operational are included in the present Scope

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement

Gharafa South:

For 2 x 66kV Cable transformer feeders connected to Gharafa substation, complete


functional protection system as per Standard specification shall be provided.

- The new relays/equipment shall be installed at Gharafa South substation to


match the protection at (new) Gharafa substation end. ABB make REL316*
and ABB make REL551 provided for 66kV line protection shall be replaced
accordingly.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

- Contractor has to perform proper CT sizing calculation and submit for KM


review and adequacy of existing CTs must be checked. If required, additional
CT core or changing of the CTs shall be the responsibility of the Contractor.
Optional price for the (66kV side & 11kV side, 40 MVA Transformer bushing
and 11kV Switchgear) CT replacement and all associated works shall be
provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

KTS (Khalifa Town South) Substation:

For 2x66 kV Cable transformer feeders connected to Gharafa substation, complete


functional protection system as per Standard specification shall be provided.

- The new relays/equipment shall be installed at KTS substation to match the


(new) protection at Gharafa substation end. The protection relays shall be
compatible to work satisfactorily over Pilot Cable.

- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. The new CTs required parameters are given in
Protection standard Specification and standard CT ratio. Contractor has to
perform proper CT sizing calculation for KM review. If required, additional CT

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 22 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

core or changing of the CTs shall be the responsibility of the Contractor. CTs
are anticipated to be changed for which separate unit price shall be provided.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 23 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1.2 132/33KV QP-HALUL SUBSTATION

QP-Halul 132/33kV substation will be constructed in Ras Laffan area, on the


150mx150m location provided by QP. However, only half of the plot, 150mx75m, is
dedicated for QP-Halul S/S, though remaining part is reserved for the convertor
station which shall be constructed by QP. There shall be clear boundary and different
access between those two facilities. Close coordination between KAHRAMAA S/S
Contractor and QP Contractor is mandatory. Contract for convertor station is yet to be
awarded by QP.

QP-Halul S/S shall be fed from Ras Girtas Power Station via double circuit 132kV,
250MVA, XLPE cables, which is part of Phase 10 Cable Contract (GTC 372/10). QP-
Halul S/S shall feed power demand on Halul Island via 132kV double circuit, sub
marine cables, approx. length 104km, both submarine cable and substation at Halul
Island shall be constructed by others (QP).

In order to compensate reactive power generated by the submarine cables, four shunt
reactors 132kV, shall be installed by QP: 2 of them at QP Halul S/S at Ras Laffan and
2 at QP Halul Island S/S at the island. Shunt reactors shall be connected to the
132kV Halul feeder bays through separate breakers for shunt reactors, as presented
on the relevant Single Line Diagram (SLD). Cable connection between shunt reactors
and 132kV GIS is within QP SOW. The Contract shall plan and provide sufficient
space for the subject reactors and their connections.

The principal elements of 132/33kV QP-Halul substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Four (4) Nos. Outgoing cable feeder bays

- Two (2) Nos. Outgoing cable / shunt reactor feeder bays (to Halul Island)

- Two (2) Nos. 132/33 kV, 100MVA outgoing transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 33kV, 2500A at 40˚C, 31.5kA / 3 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Two (2) Nos. 132/33 kV, 100MVA transformer incomer bays

- Ten (10) Nos. Outgoing cable feeder bays

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 24 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Two (2) Nos. Feeders for 33/0.415kV station transformer

- Two (2) Nos. Bus section bays

- Two (2) Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ 2 Nos. Power Transformers 132/33kV, 60/75/100 MVA, Dyn1


ONAN/ONAF/OFAF cooling, +5% -15% on load taps in steps of 1.25%, 15%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

¾ 2 Nos. 33kV Metallic Neutral Earthing Resistors 25.40 ohm at 50˚C rated for
750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/33kV 100MVA Power transformer.

¾ 2Nos. Station Transformers 33/0.415kV, 1000kVA, with ONAN cooling,


Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc

The power rateing of the station transformer mentioned above is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to NCC/ENCC


and S/S works necessary for NCC/ENCC End – to – End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 100MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with protection at Ras Girtas side shall be installed at QP Halul substation for
all feeders.

¾ Metering system: Energy meters shall be provided on the outgoing 132kV


feeders to Halul and to Converter substation and on all outgoing 33kV feeders.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 25 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Standard specification for the bulk consumers shall apply. Guidelines for
Protection Energy Meter and System Control Requirements for Power Supply
to Bulk Consumers are included in the technical specification as appendices
(ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with SCS using
communication protocol.

¾ All civil Works including building services as per appendix F - Drawings

¾ 132kV GIS room Crane

¾ Air-conditioning system to cover the GIS buildings, control & relay building and
all other buildings

¾ Fire protection system for power transformers and Tie-in point for shunt
reactors

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All QP requirements shall be considered while determining the capacity for fire
pumps & fire water tank, fire detection alarm system (Interfacing with QP fire
station), HSSD System inside the cable basements and other areas inside
substation, fire hydrant system including Ring Mains and if any other specific
QP requirements as per QP standards & specifications.

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables

- 132kV, 1x630 mm2, XLPE, 100MVA, double circuit, special bonded at QP-
Halul S/S cable links, single point earthed with earth continuity conductor, the
links between new 132/33kV transformers and new 132kV GIS switchgear laid
in unfilled concrete troughs with all accessories. Approx. route length: 100m.

- 132kV, 1x500 mm2, XLPE, 100MVA, double circuits, special bonded at QP-
Halul S/S cable links, single point earthed with earth continuity conductor (four
(4) cables per phase), the links between new 132/33kV transformers and new
33kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m

- 33kV, 1x500 mm2, XLPE, double circuits, cable links between 33kV NER
and 132/33kV, 100 MVA Power Transformers. Approx. route length: 20 m.

- 33kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 33kV switchgear and 33/0.415, 1000 kVA
Station transformers. Approx. route length: 30 m.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 26 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1.2.1 OPTIONAL WORKS:

¾ Installation for 33kV outgoing cable feeders between 33kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.1.2.2 MODIFICATIONS AT 132KV GIS AT RAS GIRTAS POWER


STATION:

Spare bays at of 132kV GIS at Ras Girtas Power station shall be used for connection
of new 2x132 kV cables towards QP-Halul substation. All modifications required in the
existing 132kV GIS bays at Ras Girtas Power station shall be carried out under the
present scope of work. The scope of work shall include but not be limited to the
following:

- Re-testing and re-commissioning of the existing GIS bays along with Local
Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to existing SCS supplied by ABB (SAS) to include changes


to 2 x 132kV cable feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

- For 2 x 132kV Cable feeders connected to QP Halul substation, complete


functional protection system as per Standard specification shall be provided. In

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 27 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Ras Girtas 132kV (Spare) equipped bays, Main-1 ABB make RED670 and
Main-2 Siemens make 7SD522 relays is provided for 132kV line protection.
The new relays/equipment shall be installed at QP Halul substation to match
the protection provided at 132kV Ras Girtas substation end. All modification,
Testing and commissioning, end to end test to make it fully operational shall be
Contractor's responsibility.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 28 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾
3.1.3 132/11KV UNIVERSITY SOUTH SUBSTATION

132/11kV University South is new substation. It will be connected to North Road


substation via 132kV double circuit underground cable line. North Road S/S is under
execution as part of Phase 9, Stage 1, KAHRAMAA Contract GTC/240A/2008 with
Siemens Consortium as EPC Contractor.

The principal elements of 132/11kV University South substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Four (4) Nos. outgoing underground cable feeder bays

- Four (4) Nos. 132/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3s, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:

11kV Switchgear A:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. of Outgoing cable feeders rated 630A

- Two (2) Nos. Feeder for 11/0.415kV station transformer

- Two (2) Nos. Feeders for future capacitor banks

- Space for six future bays, three on each side of the 11kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.

Alternatively, 11kV GIS is also acceptable.

11kV Switchgear B:

- Two (2) Nos. Incomers rated 2500A

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 29 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for future capacitor banks

- Space for six future bays, three on each side of the 11kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.

Alternatively, 11kV GIS is also acceptable.

¾ 4Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with ONAN/ONAF


cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on
ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ 4Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C rated for
750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV 40MVA Power transformer.

¾ 2Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN cooling,


Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc

The power rateing of the station transformer mentioned above is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing shall be provided.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kVGIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system including software from
each condition monitoring system for remote access
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection

¾ LV Service Equipment

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 30 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with North Road side shall be installed at University South substation for the
respective feeders.

¾ All civil Works including building services as per appendix F - Drawings

¾ 132kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, Quadruple circuits, solid bonded at


University South S/S cable links between new 132kV GIS and 132/11kV
transformers laid in unfilled concrete troughs with all accessories. Approx.
route length: 30m

- 11kV, 1x630 mm2, XLPE, 40MVA, Quadruple circuits, single point earthed
with earth continuity conductor underground cable links at University South
S/S cable links (four (4) cables per phase) between 132/11kV power
transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 60m

- 11kV, 1x630 mm2, XLPE, Quadruple circuit cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m

3.1.3.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 31 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

terminations will be supplied by KAHRAMAA. Contractor shall coordinate with


concern KAHRAMAA department.

3.1.3.2 MODIFICATIONS AT NORTH ROAD SUBSTATION

All required modifications in North Road substation shall be carried out under this
project. The scope of work shall include but not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to SCS supplied by SIEMENS under Phase 9, Stage 1, to


include changes to 2 x 132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End –
to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS & RTU and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2x132 kV Cable feeders connected to University South substation, complete


functional protection system as per Standard specification shall be provided.

- In North Road S/S, 132kV (Spare) equipped bays, Main-1 Siemens make
7SD522 and Main-2 ABB make RED670 is to be provided for 132kV line
protection. The new relays/equipment shall be installed at University South
substation to match the protection provided at 132kV North Road substation
end. All modification, Testing and commissioning, end to end test to make it
fully operational shall be Contractor's responsibility.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 32 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 33 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1.4 220/132/66/11KV DOHA INDUSTRIAL SUPER (DIS) SUBSTATION

220/132/66/11kV DIS Substation is new subststion which will replace existing


132/66/11 Saliyah substation. It will be fed from the Saliyah Super Substation (under
construction, Phase 8-GTC 144A Areva) via 220kV double circuit underground cable
line.

Proposed location for DIS substation is within existing Tarig Bin Ziyad Military Camp
for Armed Forces.

The principal elements of 220/132/66/11kV DIS substation shall be as follows:

¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Five (5) Nos. cable feeder bays

- Three (3) Nos. 220/132 kV, 315MVA Outgoing transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Three (3) Nos. 220/132 kV, 315MVA Incomer transformer bays

- Three (3) Nos. 132/66 kV, 160MVA Outgoing transformer bays

- Eight (8) Nos. Outgoing cable feeder bays

- Two (2) Nos. 132/66 kV, 160MVA Outgoing transformer bays

- Two (2) Nos. 30MVAr Shunt Reactor bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Three (3) Nos. 132/66kV, 160MVA Incomer transformer bays

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 34 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Three (3) Nos. 66/11kV, 40MVA Outgoing transformer bays

- Eight (8) Nos. Outgoing cable feeder bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 3150A at 40oC, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Three (3) Nos. Incomers rated 2500A

- Two (2) Nos. Bus section bays rated 3150A

- Twenty-seven (27) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformers

- Three (3) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Three (3) Nos. Power Transformers (Auto) 220/132kV, 189/236/315 MVA,


YNa0(d1) ONAN/ONAF/OFAF cooling, +10% on load taps in steps of 1.25%,
12% impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

¾ Two (2) Nos. Power Transformer 132/66kV, 96/120/160 MVA, presently


installed at Saliyah Super substation shall be relocated to DIS. Transformers
have beein installed by M/S Siemens under contract GTC/ 123B/ 2008. The
substation contractor should include in his scope of works dismantling,
packing, transportation, re-assembly, site tests, commissioning, etc for both
transformer units. These works are to be carried out in phased manner. The
substation contractor shall submit for KM approval detailed program and
method statement for these works. The substation contractor shall also cover
these works under the warranty for the DIS substation

¾ One (1) Nos. Power Transformer 132/66kV, 96/120/160 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc The
transformer shall be identical to existing 2 numbers of 132/66kV 160MVA
Trasnformers which are in service at Saliyah substation.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 35 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Three (3) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc

¾ Two (2) Nos. Shunt Reactors, 132kV, 30MVAr provided with terminal CTs,
neutral CTs etc.

¾ Three (3) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ In the existing Saliyah substation, Siemens has installed 2Nos. of 132/66kV


160MVA transformers under contract GTC/123B/2008. The substation
Contractor shall include in his scope of works dis-connection, dismantling,
transportation from existing Saliyah substation to new site, installation, re-
connection of 132kV and 66kV transformer terminals to new 132kV and 66kV
GIS, site tests and commissioning for both transformers.

¾ 2 Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN cooling,


Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 220kV, 132kV and 66kV GIS
- Condition monitoring system for 315MVA, 160MVA & 40MVA transformers
and 30MVAr shunt reactors. Existing 160MVA Transformers are equipped
with TMS of Koncar make, installed by M/s Siemens under contract GTC/
123B/ 2008. Following features are supported: Ambient temperature, Top
oil temperature and gas monitoring by Hydran. Existing TMS installed at the
160MVA transformers shall be upgraded to support features from phase X
specification. Existing TMS server shall be upgraded to enable monitoring
of all features from the field. Integrated HMI workstation for monitoring
system including software from each condition monitoring system for
remote access
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 36 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with Saliyah Super side shall be installed at DIS substation for all the feeders
to match the protection at Remote end

¾ Metering system: Energy meters shall be provided on the 132kV feeders to


Saliyah GT. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.

¾ All civil works related to new 220/132/66/11kV substation including building


services and works related to the diversion of 132kV and 66KV cables as per
Appendix F – Drawings

¾ Demolition of all existing buildings & fence that are currently located within the
substation plot, removal and disposal of waste materials to Government
approved location.

¾ 220, 132 and 66kV GIS room Crane.

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.

¾ Fire protection system for power transformers, autotransformers and shunt


reactors

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings.

¾ Passive fire protection system for all cables in the basement of all buildings.

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

- 220kV, 1x1600 mm2, XLPE, 315MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 220/132kV power transformers and new 220kV GIS switchgear laid in
unfilled concrete troughs with all accessories. Approx. route length: 150m

- 132kV, 1x2000 mm2, XLPE, 315MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 37 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

between 220/132kV transformers and new 132kV GIS switchgear laid in


unfilled concrete troughs with all accessories. Approx. route length: 100m.

- 132kV, 1x800 mm2, XLPE, 160MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 132/66kV transformers and new 132kV GIS switchgear laid in unfilled
concrete troughs with all accessories. Approx. route length: 100m. Two
160MVA transformers which shall be shifted from Saliyah S/S have air
bushings on 132kV side. The Contractor shall provide all materials and civil
works for connection of outdoor cable sealing ends with transformer.

- 132kV, 1x500 mm2, XLPE, 30MVA, double circuits, solid bonded at DIS
S/S cable links between new 132kV shunt reactors and new 132kV GIS
switchgear laid in unfilled concrete troughs with all accessories Approx. route
length: 100m.

- 66kV, 1x2000 mm2, XLPE, 160MVA, triple circuits, special bonded at DIS
S/S cable links, single point earthed with earth continuity conductor, the links
between 132/66kV transformers and new 66kV GIS switchgear laid in unfilled
concrete troughs with all accessories. Approx. route length: 100m. Two
160MVA transformers which shall be shifted from Saliyah S/S have air
bushings on 132kV side. The Contractor shall provide all materials and civil
works for connection of outdoor cable sealing ends with transformer.

- 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at DIS S/S
cable links between 66/11kV transformers and new 66kV GIS switchgear laid
in unfilled concrete troughs with all accessories. Approx. route length: 50m

- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed with
earth continuity conductor underground cable links at DIS S/S cable links (four
(4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, triple circuit cable links between 11kV NER and
66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30m.

¾ Cable Diversions:

Existing OHL / cable circuits from Saliyah substation are as under:


- 2 x 132kV cable circuits to Saliyah South with 2x6 fiber cables
- 2 x 132kV cable circuits to GT
- 2 x 132kV OHL circuits to Doha South Super with single 24 fiber OPGW

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 38 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- 2 x 132kV OHL circuits to Al Wajbah Super with single 24 fiber OPGW,


partially replaced with with underground cable line on the Saliyah side
under the Phase 9 Scope of works
- 2 x 66kV cable circuits to Olympic Games with 2x24 fiber cables
- 2 x 66kV cable circuits to Feriq Al Murrah substation with Pilot Cu cables

The diversion work of cable / OHL circuits and pertaining communication cables (FO
and Cu cables) from existing Saliyah to DIS substation (with exception of the 132kV
cables towards Al Wajbah Super SS, which will be done by Cable Contractor) will
be done by the substation Contractor as specified below. The substation Contractor
should make all necessary arrangements to connect OHL / cable termination with
132kV / 66kV GIS.

Following Existing cable circuits of Saliyah substation shall be diverted to DIS S/S:

- Salyiah South to Salyiah: 132kV, 1x1200 mm2, XLPE, 160 MVA, double
circuits shall be diverted to New Salyiah S/S, special bonded at DIS S/S cable
links, single point earthed with earth continuity conductor, with its own fiber
optic cable (24 Fibers), route length: 250 m. The Contractor shall include for
all necessary modification works in the earthing arrangement (cross bonding,
single point bonding, mixed bonding) in order to ensure that required current
rating of diverted circuit is maintained.

- GT to Salyiah 132kV: 1x500 mm2, XLPE, 75MVA, double circuits with its
own fiber optic cable (24 Fibers) to replace existing oil filled cables, directly
earthed at both ends. Route length: 300 m. Existing oil filled cable shall be
drained up, capped, protected and left in ground.

- OHL connection DSS to Saliyah: 132kV, 1x 2000mm², XLPE, 250MVA,


double circuits, special bonded system at DIS S/S single point earthed with
earth continuity conductor, underground cable lines between DIS S/S and Al
Salyiah cable compound (to be constructed under Phase 9 – GTC 242 – NCC).
Each circuit shall be provided with its own Fiber Optic cable (24 Fibers) with all
accessories. Approx. route length: 400 m. Necessary details, schematic
drawings etc., with accurate lengths shall be submitted for approval during
detailed engineering stage. The termination is GIS at DIS S/S and outdoor
termination at Al Salyiah cable compound. Outdoor surge arresters shall be
provided for Al Saliyah cable compound, including steel supports and
foundations.

- 132kV OHL connection between Saliyah and Al Wajbah Super S/S will be
partially replaced by double circuit underground cable line between DIS and
cable compound. Though subject works are in the SOW of cable / OHL Phase
9 Contractors, it is responsibility of S/S Contractor to coordinate related works
with them and make all modifications required at the remote end due to those
changes.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 39 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Olympic Games to Salyiah: 66kV, 1x500 mm2, XLPE, 40MVA, double


circuits shall be diverted to DIS S/S, solid bonded at DIS S/S cable links, with
its own fiber optic cable (24 Fibers). Approx. route length: 100 m.

- Feriq Al Murrah to Salyiah: 66kV, 1x500 mm2, XLPE, 40MVA, double


circuits shall be diverted to DIS S/S, solid bonded at DIS S/S cable links, with
its own Pilot Cu cables, route length: 100 m.

- 66kV double circuit underground cable line between Doha Industrial F and DIS
will be established by Phase X Cable Contractor. However, coordination during
cable testing and connection into the GIS is obligation of Substation Contractor
according to Matrix of interface which is part of this document.

3.1.4.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

¾ Diversion of 132kV, 1x2000mm², XLPE, 250 MVA, double circuits between


Saliyah S/S and Cable Compound (at existing 132kV OHL Saliyah-Al Wajbah
Super tower no.14) with associated fiber optic cable (24 Fibers), into future
132kV GIS in DIS S/S. Approx. route length: 0.3km. The Contractor shall
include for all necessary modification works in the earthing arrangement (cross
bonding, single point bonding, mixed bonding) in order to ensure that required
current rating of diverted circuit is maintained. The termination is SF6 at Doha
Industrial Super S/S (new under Phase 10) and joint from the diversion part
near Saliyah S/S (existing).

3.1.4.2 MODIFICATIONS AT SALIYAH SUPER, SALIYAH SOUTH, DSS, AL


WAJBAH SUPER, OLYMPIC GAMES, FERIQ AL MURRAH AND
SALIYAH GT STATION:

The scope of work shall include but not be limited to the following:

- Re-testing and re-commissioning of the existing GIS bays in service along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 40 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

Saliyah Super Substation:

- Minor modifications to SCS supplied by AREVA under phase 8 project (under


construction) to include changes to 2x220kV cable feeders in the SCS
including Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Saliyah South Substation:

- Existing BCUs in 2 x 132/66kV transformer feeder bays utilized for connection


towards DIS shall be replaced with new BCUs. New BCUs shall be integrated
with the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications to SCS supplied by ABB under Phase 4 project to include


changes to 2 x 132/66kV transformer feeder bays in the SCS including end to
end testing.

- Minor modifications to existing RTU/TDB/TMMC supplied by AREVA under


Phase 4 project to include changes to 2 x 132kV cable feeders in NCC/ENCC
including S/S work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Saliyah GT Substation:

- Existing complete cable connection between Saliyah GT and Saliyah RTU


shall be replaced by new cable connection in order to maintain existing
connection of Saliyah GT to NCC/ENCC including migration of existing Saliyah
GT RTU located in existing Saliyah S/S to new Doha Industrial Super S/S and
S/S work necessary for NCC/ENCC end to end testing

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 41 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Minor modifications to existing conventional control panel and


RTU/TDB/TMMC to include changes to 2 x 132kV cable feeders in the
NCC/ENCC including S/S work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panel and S/S work necessary for remote
signaling to NCC/ENCC

DSS Substation:

Doha South Super (DSS) is existing 220/132/11kV substation with 132kV level under
refurbishing as part of Phase 9, Stage 1 Contract GTC/240A/2008 with M/s Siemens.

- Minor modifications to SCS supplied by M/S SIEMENS to include changes to 2


x 132kV OHL feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in SCS and S/S work necessary for remote signaling to NCC/ENCC.

Al Wajbah Super Substation:

- Minor modifications to SCS supplied by ABB under Phase 7 project to include


changes to 2 x 132kV OHL feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End – to –
End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

Olympic Games Substation:

- Minor modifications to SCS supplied by AREVA (PSN 3020) to include


changes to 2 x 66kV cable transformer feeders in the SCS including end to
end testing.

- Minor modifications to existing RTU/TDB/TMMC to include changes to 2 x


66kV cable transformer feeders in the NCC/ENCC including S/S work
necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

Feriq Al Murah Substation:

- Minor modifications to existing conventional control panel and


RTU/TDB/TMMC to include changes to 2 x 66kV transformer cable feeders in

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 42 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

the NCC/ENCC including S/S work necessary for NCC/ENCC end to end
testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panel and S/S work necessary for remote
signaling to NCC/ENCC

¾ Protection Scope for remote end modification:

Saliyah Super Substation:

Two 220kV Bays to be connected to new DIS substation will be equipped with
Protection relays under Phase 8 (GTC 144A – Areva).

- The new relays/equipment shall be installed at DIS substation to match the


protection provided at 220kV Saliyah Super end.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be provided under this
Contract. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modifications, End to End test, Testing and commissioning and putting into
service of these two circuits is part of this Contract.

Saliyah South Substation:

For 2 x 132kV Cable Transformer feeders connected to DIS, protection as per


Standard specification shall be provided.

- Existing relays are ABB make. REL561 is used for Line Differential and
RET521 is used for Transformer Differential protection. Contractor shall
replace existing relays to match the protection at DIS end. Any additional relay
required to make a complete functional protection system shall be provided by
the Contractor.

- Existing (Transformer Bushing and Transformer Neutral) CTs shall be replaced


with new CTs to match with new protection and metering requirements. The
new CTs required parameters are given in Protection standard Specification
and standard CT ratio. Contractor shall perform proper CT sizing calculation
and submit for KM review. If required, additional CT core or changing of the
CTs shall be the responsibility of the Contractor.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 43 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.

Saliyah GT Substation:

- Complete functional protection system shall be provided for the GT feeders

- New CTs shall be installed to match with new protection and metering
requirements

- Existing relays shall be replaced to match protection at the DIS side

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility

DSS Substation:

For 2 x 132kV OHL bays which will be connected to DIS substation, complete
functional protection system as per Standard specification shall be provided under
this Contract.

- In DSS S/S, 132kV equipped bays, Main-1 Siemens make 7SD522 and Main-2
ABB make RED670 is proposed to be provided for 132kV line protection under
Phase 9 Contract. The new relays/equipment shall be installed DIS substation
to match the protection provided at 132kV DSS end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility

Al Wajbah Substation:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 44 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- For 2x132 kV Feeders to be connected to DIS substation, two Bays are


equipped with Protection relays under Phase 7. 132kV equipped bays, Main-1
ABB make RED670 and Main-2 Siemens make 7SD522 relays are provided
for 132kV line protection. Contractor shall change communication module in
these Main relays and make them suitable for “Dual Fiber Optic
Communication”, if required and it shall be decided during detail engineering.

- Retesting of the relays/equipment, all modifications, End to End test, testing


and commissioning and putting into service of these two circuits is included in
the Present Scope.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

Olympic Games Substation:

For 2 x 66kV Cable Transformer feeders connected to DIS, existing relays are Alstom
make, MICOM P543 and P631 used as Current Differential and Transformer
Differential respectively.

- The two Transformer Feeders shall have Cable Differential, Transformer


Differential and Overall Differential Protection as per Standard Specification.
The corresponding relays/equipment shall be installed at Olympic Games
substation to match the protection at DIS end.

- Existing (Transformer Bushing and Transformer Neutral) CTs shall be replaced


with new CT to match with new protection and metering requirements.

- Existing CTs in 11kV Incomer A18/A28 feeder shall be replaced (or additional
core provided) to suit F87C+T (Overall differential protection) which shall be
decided during detail engineering The new CTs required parameters are given
in Protection standard Specification and standard CT ratio. Contractor shall
perform proper CT sizing calculation and submit for KM review. If required,
additional CT core or changing of the CTs shall be the responsibility of the
Contractor

- All modification, Testing and commissioning, end to end test to make it fully
operational is under the present Scope.

Feriq Al Murah Substation:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 45 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

For 2 x 66kV Cable Transformer feeders connected to DIS, complete functional


protection system as per Standard specification shall be provided.

- The relays/equipment shall be installed at Fariq Al Murrah substation to match


the protection at DIS end. New protection panels shall be provided for B11 and
B21 bays. The protection relays shall be compatible to work satisfactorily over
Pilot Cable.

- Existing (Transformer Bushing and Transformer Neutral) CTs shall be replaced


with new CTs to match with new protection and metering requirements. The
new CTs required parameters are given in Protection standard Specification
and standard CT ratio. Contractor shall perform proper CT sizing calculation for
KM review. If required, additional CT core or changing of the CTs shall be the
responsibility of the Contractor.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 46 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1.5 132/11KV LOGISTIC VILLAGE SUBSTATION

132/11kV Logistic Village substation is new substation which will be constructed on


the plot 60x60m allocated by Gulf Warehousing Company (GWC) in their premises in
the south of Doha Industrial Area. It will be fed from Abu Nakhla Super substation by
re-routing the new 132kV, 160 MVA, XLPE cables from ANS to DIE, installed under
the Phase 8 (Contract GTC/142/2006).

The principal elements of new 132/11kV Logistic Village substation shall be as


follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Eight (8) Nos. Outgoing feeder bays

- Two (2) Nos. 132/11 kV, 40MVA Outgoing Transformer bays. For the purposes
of tariff metering VT should be incorporated.

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers each rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. Outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformer feeders

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11kV switchgear

- Space vacuum contactor panel, equipped with protection and the power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 47 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for all feeders.

¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.

¾ All civil works related to new 132/11kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings

¾ 132kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 48 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded at


Logistic Village S/S cable links between new 132kV GIS and 132/11kV
transformers laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuit, single point earthed with
earth continuity conductor underground cable links (four (4) cables per
phase) between 132/11kV power transformers and 11kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m

- 11kV, 1x630 mm2, XLPE, double circuit, cable links between 11kV NER and
132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m

- Diversion works, Loop in / Loop out (LILO) of the existing 132kV, 1x1000mm2,
XLPE, 160MVA underground cable circuits with fiber optic cable (24 Fibers)
between Abu Nakhla Super and Doha Industrial E to new 132kV GIS are in
the SOW of S/S Contractor. Cable route is already diverted into substation plot
and cable joints are installed with sufficient sneaking provided. The Contractor
shall make all necessary arrangements to disconnect cables at joint bay, divert
them, connect into 132kV GIS and commission the same.

3.1.5.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 49 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.1.5.2 MODIFICATIONS AT ABU NAKHLA SUPER (ANS) AND DOHA


INDUSTRIAL E (DIE) SUBSTATION

400/220/132/66/11kV Abu Nakhla Super substation is an existing substation built


under Phase 7 projects by ABB (Contract GTC/123A/2006). All modifications required
due to LILO of the existing 132kV cable line ANS – DI E into Logistic Village S/S shall
be carried out under subject SOW.

Doha Industrial E is new 132/66/11kV transformer feeder in construction under Phase


8 by Areva (Contract GTC/144A/2006). All modifications required due to LILO of the
existing 132kV cable line ANS – DI E into Logistic Village S/S shall be carried out
under subject SOW.

The SOW includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

¾ SCS and Power Control Scope for remote end modification:

ANS Substation:

- Minor modifications to SCS supplied by ABB under Phase 7 project to include


changes to 2 x 132kV cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to end
testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

DIE substation:

- Minor modifications to SCS supplied by AREVA under Phase 8 project to


include changes to 2 x 132kV cable transformer feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S work necessary for NCC/ENCC
end to end testing.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 50 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

¾ Protection Scope for remote end modification:

ANS Substation:

For 2 x 132kV Cable feeders connected to Logistic Village substation, complete


functional protection system as per Standard specification shall be provided. In ANS
substation, 132kV equipped bays, Main-1 ABB make RED670 and Main-2 Siemens
make 7SD522 relays are provided for 132kV line protection.

- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at Logistic Village substation to match the
protection provided at 132kV ANS substation end.

- All modification, Testing and commissioning; end to end test are included in the
present Scope

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

DIE substation:

For 2 x 132kV Cable transformer feeders connected to Logistic Village substation,


complete functional protection system as per Standard specification shall be
provided. In DIE substation, 132kV equipped bays, Main-1 ABB make RED670 and
Main-2 Siemens make 7SD522 relays is provided for 132kV line protection.

- Contractor shall change communication module in these Main relays make it


suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at Logistic Village substation to match the
protection provided at 132kV DIE substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 51 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

protection operation are to be made available between the stations based on


requirement

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 52 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2 PACKAGE S-2

3.2.1 132/11KV AL KARA’ANA SUBSTATION

Al Khara’ana substation is new transformer substation which will be connected to


KAHRAMAA network at 132kV level via 132kV OHL towards Al S’halah substation.
132kV Al Khara’ana – Al S’halah OHL and OHL landing gantry are under the scope of
Phase 10 OHL Contractor. Substation Contractor will provide GI bus-ducts for direct
connection of 132kV GIS to the OHL.

The principal elements of 132/11kV Al Kara’ana substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Eight (8) Nos. Outgoing Overhead line feeder bays, two of them with GI bus –
duct for OHL direct connection

- Two (2) Nos. 132/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear.

¾ Establish 11kV, 2500A at 40˚C , 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformer

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for vacuum contactor panel equipped with protection and power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on
ONAN provided with AVR, terminal CTs, neutral CTs etc.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 53 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 54 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) sets of 132kV outdoor lightning arresters for the incoming / outgoing
overhead lines.

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Al


Kara’ana S/S cable links between new 132/11kV transformers and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories. Approx.
route length: 70m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Al Kara’ana S/S cable
links (four (4) cables per phase) between 11kV switchgear and 132/11kV
power transformers within S/S, laid in unfilled concrete troughs with all
accessories. Approx. route length: 30m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 60 m.

3.2.1.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.2.1.2 MODIFICATIONS AT AL S’HALAH SUBSTATION:

132/11kV Al S’halah substation is under Scope of Phase 9, Stage 1, Contract


GTC/240A/2008 with Siemens Consortium.

The SOW includes but is not limited to the following:

- Cable Compound to Al S’halah: Provide 132kV, 1x2000mm², XLPE,


250MVA, double circuit, special bonded system at Al Shalah S/S single point
earthed with earth continuity conductor, underground cable lines between Al
Shalah 132kV GIS and Al S’halah cable compound. Each circuit shall be
provided with its own Fiber Optic cable (48 Fibers) with all accessories.
Approx. route length: 200m. Necessary details, schematic drawings etc., with

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 55 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

accurate lengths shall be submitted for approval during detailed engineering


stage. The termination is GIS at Al Shalah S/S and outdoor termination at Al
S’halah cable compound. Outdoor surge arresters shall be provided at Al
S’halah cable compound, including steel supports and foundations.

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the OHL Contractor for the termination of the
conductors at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to SCS supplied by SIEMENS under Phase 9, Stage 1


project to include changes due to connection of 2 x 132kV OHL in the SCS
including Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2 x 132kV OHL feeders connected to Al Kara’na substation, complete functional


protection system as per Standard specification shall be provided.

- In Al S’halah S/S, 132kV (Spare) equipped bays, Main-1 Siemens make


7SD522 and Main-2 ABB make RED670 is proposed to be provided for 132kV
line protection.

- The new relays/equipment shall be installed at Al Kara’na substation to match


the protection provided at 132kV Al S'halah substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 56 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

protection operation are to be made available between the stations based on


requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 57 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.2 132/11KV MADINAT AL-KABAAN SUBSTATION

Proposed location for Madinat Al Kebaan substation is located approximately half way
between Ras Girtas Power Plant and Al Sulaimi S/S. It shall be connected into
KAHRAMAA system through 132kV OHL to be constructed under the Phase 10 OHL
Contract (GTC 373/2010) as follows:

- 132kV, 250MVA connection towards Ras Girtas will include double circuit OHL
starting from Madinat Al Kabaan, until cable compound towards Ras Girtas.
This part of the line shall be constructed under the Contract GTC 373/2010 –
OHL. 132kV cable from the cable compound up to the 132kV GIS in Ras Girtas
Power Station shall be constructed under the Contract GTC 372/2010 -
Cables.

- Another double circuit 132kV OHL shall be connected from Madinat Al Kebaan
towards the T-off tower of 132 OHL Line Al Sulaimi – Al Jiffara presently under
construction by NCC as part of Scope for Phase 9 Stage 1 Project. Eventually
there will be two 132kV circuits formed by this line (also refer to Volume 7,
Single Line Diagram for more details):

1. Madinat Al Kabaan SS/Al Sulaimi


2. Madinat Al Kabaan SS/Al Jiffara

Landing gantries for the above OHL connections at Madinat Al Kabaan S/S are under
the scope of Phase 10 OHL Contractor. Substation Contractor will provide GI bus-
ducts for direct connection of 132kV GIS to the OHL.

The principal elements of 132/11kV Madinat Al Kabaan substation shall be as


follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing Overhead line feeder bays, four of them with GI bus –
duct for OHL direct connection

- Two (2) Nos. 132/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 58 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformer

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on
ONAN provided with AVR, terminal CTs, neutral CTs etc.

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end
-

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 59 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Four (4) sets of 132kV outdoor lightning arresters for the incoming / outgoing
overhead lines.

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at


Madinat Al Kabaan S/S cable links between new 132/11kV transformers and
new 132kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length: 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Madinat Al Kabaan S/S
cable links (four (4) cables per phase) between 11kV switchgear and 132/11kV
power transformers within S/S, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.

3.2.2.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 60 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

terminations will be supplied by KAHRAMAA. Contractor shall coordinate with


concern KAHRAMAA department.

3.2.2.2 MODIFICATIONS AT AL SULAIMI, AL JIFFARA AND RAS GIRTAS

Al Sulaimi is an existing 132/66/11kV substation with 132kV GIS. It was built by ABB
under contract GTC/033/2004.

Al Jiffara is new 132/11kV S/S presently under construction by M/s HYOSUNG as


part of Contract GTC/240B/2008 under Phase 9, Stage 1.

132kV GIS at Ras Girtas Power Plant is recently completed by M/s HYUNDAI and is
ABB made.

All modifications required to the existing spare 132kV GIS bays at remote ends due to
described connections of Madinat Al Kabaan substation shall be carried out under the
present scope of work. The scope of work shall include but not limited to the following:

- Re-testing and re-commissioning of the existing GIS bays along with Local
Control

- Panels including indicating meters in the local control panels, inscription of


additional alarm facia as required, replacing of GIS name plates and any
required works including, wiring, testing & complete re-commissioning of the
above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- All necessary co-ordination with the OHL Contractor for the termination of the
conductors at both ends.

¾ SCS and Power Control Scope for remote end modification:

Al Sulaimi Substation:

- Minor modifications to SCS supplied by ABB GTC/33 project to include


changes in power supply due to Madinat Al Kabaan T-off connection from
132kV OHL feeder towards Al Jiffara in the SCS including end to end testing.

- Minor modifications to existing RTU/TDB/TMMC supplied by AREVA under


GTC 33/04 for communication to NCC/ENCC including data mapping to
NCC/ENCC and works necessary for NCC/ENCC End – to – End testing

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 61 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Al Jiffara Substation:

- Minor modifications to existing SCS supplied by Siemens under Phase 9


project to include changes in power supply due to Madinat Al Kabaan T-off
connection including Gateway data mapping to NCC/ENCC and works
necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Ras Girtas 132kV Substation:

- Minor modifications to existing SCS supplied by ABB to include changes to 2 x


132kV cable / OHL feeders in the SCS including Gateway data mapping to
NCC/ENCC and works necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

Al Sulaimi Substation:

For 132kV OHL feeder which shall be connected to Al Jiffara, and later to Madinat Al
Kabaan substation, complete functional protection system as per Standard
specification shall be provided.

- The new relays/equipment shall be installed at Madinat Al Kabaan substation


to match the protection provided at 132kV Al Sulaimi substation end. 132kV
equipped bays, Main-1 ABB make RED670 and Main-2 Siemens make
7SD522 is provided for 132kV line protection. All modification, testing and
commissioning; end to end test to make it fully operational shall be
Contractor's responsibility.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 62 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Al Jiffara Substation:

For 132 kV OHL feeder which shall be connected to Madinat Al Kabaan substation,
complete functional protection system as per Standard specification shall be
provided. In Al Jiffara S/S, 132kV equipped bays, Main-1 ABB make RED670 and
Main-2 Siemens make 7SD522 is provided for 132kV line protection.

- The new relays/equipment shall be installed at Madinat Al Kabaan substation


to match the protection provided at 132kV Al Jiffara substation end. All
modification, Testing and commissioning; end to end test to make it fully
operational shall be Contractor's responsibility.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility is included in the present Scope

Ras Girtas Substation:

For 2 x 132kV OHL feeders connected to Madinat Al Kabaan substation, Main-1 ABB
make RED670 and Main-2 Siemens make 7SD522 relays are provided for 132kV line
protection.

- The new relays/equipment shall be installed at Madinat Al Kabaan substation


to match the protection provided at 132kV Ras Girtas substation end.

- Contractor has to do the proper CT sizing calculation for KM review and


Adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 63 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.3 132/11KV AL RUWAIS SUBSTATION

Al Ruwais substation will be connected at 132kV level with 132/11kV Al Jiffara


substation.

132kV connection towards Al Jiffara will be OHL with cable compound at Al Jiffara
side. Both OHL and cable compound are under the scope of Phase 10, OHL
Contractor (GTC 373/2010). 132kV cable connection from cable compound (near Al
Jiffara SS) to 132kV GIS in Al Jiffara shall be constructed under this Contract.

Substation Contractor shall provide GI bus-ducts for direct connection of 132kV GIS
to the OHL.

The principal elements of 132/11kV Al Ruwais substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing overhead line feeder bays, two of them with GI bus –
duct for OHL direct connection

- Two (2) Nos. 132/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the
following:

- Two (2) Nos. incomers rated 2500A

- One (1) Nos. bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformers

- Two (2) Nos. Bays for future capacitor banks feeders

- Space six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panel, equipped with protection and the power-
factor switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 64 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on
ONAN provided with AVR, terminal CTs, neutral CTs etc.

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV, 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. The new relays/equipment shall be
installed at Al Ruwais substation to match the protection provided at 132kV
RGPC end.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS Room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 65 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Two (2) sets of 132kV outdoor lightning arresters for the incoming / outgoing
OHL

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Al


Ruwais S/S cable links between new 132/11kV transformers and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories Approx.
route length: 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Al Ruwais S/S (four (4)
cables per phase) between 11kV switchgear and 132/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.

3.2.3.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.2.3.2 MODIFICATIONS AT AL JIFFARA SUBSTATION

Al Jiffara substation is within Scope of Phase 9, Stage 1, Contract GTC/240B/2008


with HYOSUNG.

All modifications required at Al Jiffara due to new OHL towards Al Ruwais are within
the present Scope.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 66 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

The Scope includes but is not limited to the following:

- Cable Compound to Al Jiffarah: Provide 132kV, 1x2000mm², XLPE,


250MVA, double circuit, special bonded system at Al Jiffara S/S single point
earthed with earth continuity conductor, underground cable lines between Al
Jiffara S/S and Al Jiffara cable compound. Each circuit shall be provided with
its own Fiber Optic cable (48 Fibers) with all accessories. Approx. route length:
200m. Necessary details, schematic drawings etc., with accurate lengths shall
be submitted for approval during detailed engineering stage. The termination is
GIS at Al Jiffara S/S and outdoor termination at Al Jiffara cable compound.
Outdoor surge arresters shall be provided for Al Jiffara cable compound,
including steel supports and foundations.

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to existing SCS supplied by Siemens under Phase 9


project to include changes to 2 x 132kV OHL feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2x132 kV OHL feeders connected to Al Ruwais substation, complete functional


protection system as per Standard specification shall be provided.

- In Al Jiffara S/S, 132kV (Spare) equipped bays, Main-1 Siemens make


7SD522 and Main-2 ABB make RED670 is proposed to be provided for 132kV
line protection.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 67 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- The new relays/equipment shall be installed at Al Ruwais substation to match


the protection provided at 132kV Al Jiffara substation end. All modification,
Testing and commissioning; end to end test to make it fully operational shall be
Contractor's responsibility.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational shall be Contractor's responsibility is included in the present Scope

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 68 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.4 132/11KV AL ZUBARAH SUBSTATION


New 132/11kV Al Zubarah substation will be connected at 132kV level with 132/11kV
Al Jiffara substation. 132kV double circuits OHL Al Jiffara – Al Zubarah and OHL
landing gantries are in the Scope of Phase 10 OHL Contractor. Substation Contractor
will provide GI bus-ducts for direct connection of 132kV GIS to the OHL at Al Zubarah
side and cable link for connection to landing gantry at Al Jiffara side.

Al Zubarah is planned for future upgrade with two 400/132kV Transformers.

The principal elements of new 132/11kV Al Zubarah substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) outgoing OHL feeder bays, two of them with GI bus – duct for OHL
direct connection

- Two (2) 132/11 kV, 40MVA Outgoing transformer bays

- Two (2) Incoming transformer bays for the future 400/132kV transformers.

- Two (2) Bus section bays

- Two (2) Bus coupler bays

- Space for ten future bays, five on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section rated 2500A

- Two (2) Nos. 132/11kV, 40MVA Incoming transformer bay

- Eighteen (18) Nos. Outgoing cable feeder bays rated 630A

- Two (2) Nos. Feeder bays for 11/0.415kV station transformers

- Two (2) Nos. Feeder bays for future capacitor banks

- Space for six future bays, three on each side of the switchgear

- Space for the vacuum contactor panel, equipped with protection and the
power-controlled switching for the future capacitor banks

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 69 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing shall be provided.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kVGIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system including software from
each condition monitoring system for remote access.
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end
-

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relays and equipment compatible
with Al Jiffara side shall be installed at Al Zubarah substation.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS Room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 70 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Two sets of outdoor surge arresters including steel supports and foundations

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Al


Zubarah S/S cable links between new 132/11kV transformers and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories Approx.
route length: 50m

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at Al
Zubarah S/S cable links with earth continuity conductor, (four (4) cables per
phase) between 132/11kV power transformers and 11kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m.

3.2.4.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.2.4.2 MODIFICATIONS AT AL JIFFARA

Al Jiffara substation is within Scope of Phase 9, Stage 1, Contract GTC/240B/2008


with HYOSUNG.

All modifications required due to new OHL towards Al Zubarah are within the present
Scope.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 71 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

The Scope includes but is not limited to the following:

- Provide 132kV, 1x 2000mm², XLPE, 250MVA, double circuits, special bonded


system at Al Jiffara S/S single point earthed with earth continuity conductor,
underground cable lines between Al Jiffara 132kV GIS and landing gantries
within Al Jiffara substation plot. Each circuit shall be provided with its own Fiber
Optic cable (48 Fibers) with all accessories. Approx. route length: 100m.
Necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage. The termination is
GIS on one side and outdoor termination on the other. Outdoor surge arresters
shall be provided, including steel supports and foundations.

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to existing SCS supplied by Siemens under Phase 9


project to include changes to 2 x 132kV OHL feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2 x 132kV OHL feeders connected to Al Zubarah substation, complete functional


protection system as per Standard specification shall be provided.

- In Al Jiffara S/S, 132kV (Spare) equipped bays, Main-1 Siemens make


7SD522 and Main-2 ABB make RED670 is provided for 132kV line protection.

- The new relays/equipment shall be installed at Al Zubarah substation to match


the protection provided at 132kV Al Jiffara substation end.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 72 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Contractor shall perform proper CT sizing calculation and submit for KM


review and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

- All modification, Testing and commissioning end to end test to make it fully
operational shall be Contractor's responsibility is included in the present
Scope

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 73 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.5 132/11KV BARZAN CAMP 1 (BC 1) SUBSTATION


New 132/11kV Barzan Camp 1 substation will be located in Al Wajbah area. It will be
connected into KAHRAMAA network at 132kV level with Bani Hajer Super substation
via 132kV double circuit underground cable line, which is included in the Scope of
Phase 10 cable contractor (GTC 372/2010). Two cable feeders will be used to fed
Berzan Camp 2 substation, which is included in the Scope of Phase 10 substation
contractor (Item 3.2.6 below)

The principal elements of new 132/11kV BC 1 substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) outgoing cable feeder bays

- Four (4) 132/11 kV, 40MVA, Outgoing transformer bays

- Two (2) Bus section bays

- Two (2) Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3s, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the
following:

11kV Switchgear A:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. of Outgoing cable feeders rated 630A

- Two (2) Nos. Feeder for 11/0.415kV station transformer

- Two (2) Nos. Feeders for future capacitor banks

- Space for six future bays, three on each side of the 11kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.

Alternatively, 11kV GIS is also acceptable.

11kV Switchgear B:

- Two (2) Nos. Incomers rated 2500A

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 74 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for future capacitor banks

- Space for six future bays, three on each side of the 11kV switchgear

- Space for the vacuum contactor panel, equipped with protection and power-
factor controlled switching for the future capacitor banks.

Alternatively, 11kV GIS is also acceptable.

¾ Four (4) Nos. Power Transformers 132/11kV, 32/40 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to – End
testing shall be provided.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kVGIS
- Partial discharge monitoring system for 11kV GIS (optional)
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system including software from
each condition monitoring system for remote access.
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 75 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS Room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x500 mm2, XLPE, 40MVA, quadralupe circuits, solid bonded at


Barzan Camp 1 S/S cable links between new 132/11kV transformers and new
132kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length: 50m

- 11kV, 1x630 mm2, XLPE, 40MVA, quadralupe circuits, single point earthed
at Barzan Camp 1 S/S cable links with earth continuity conductor, (four (4)
cables per phase) between 132/11kV power transformers and 11kV
switchgear, layed in unfilled concrete troughs with all accessories. Approx.
route length: 50m.

- 11kV, 1x630 mm2, XLPE, quadralupe circuits, cable links between 11kV
NER and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA station
transformers. Approx. route length: 30 m.

3.2.5.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 76 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.5.2 MODIFICATIONS AT BANI HAJER SUPER SUBSTATION

Bani Hajer Super is substation, constructed by M/s HYUNDAI under Phase 8 Project.

All modifications required due to new cable connections towards Barzan Camp 1
substation are within the present Scope.

The Scope includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to existing Areva SCS supplied under Phase 8 Project to


include changes to 2 x 132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End –
to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2 x 132kV cable feeders connected to Bani Hajer Super substation, complete
functional protection system as per Standard specification shall be provided.

- The new relays/equipment shall be installed at Barzan Camp 1 substation to


match the protection provided at 132kV Bani Hajer Super substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM


review and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 77 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

protection operation are to be made available between the stations based on


requirement

- All modification, Testing and commissioning end to end test to make it fully
operational shall be Contractor's responsibility is included in the present
Scope

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 78 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.2.6 132/11KV BARZAN CAMP 2 (BC 2) SUBSTATION


New 132/11kV Barzan Camp 2 substation will be located in Al Wajbah area. It will be
connected into KAHRAMAA network at 132kV level with Barzan Camp 1 substation
via 132kV double circuit underground cable line, which is included in the Scope of
Phase 10 cable contractor (GTC 372/2010). Berzan Camp 1 substation is included in
the Scope of Phase 10 substation contractor (Item 3.2.5 above)

The principal elements of new 132/11kV BC 2 substation shall be as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Four (4) Nos. Outgoing cable feeder bays

- Two (2) Nos. 132/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the
following:

- Two (2) Nos. incomers rated 2500A

- One (1) Nos. bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformers

- Two (2) Nos. Bays for future capacitor banks feeders

- Space six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panel, equipped with protection and the power-
factor switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on
ONAN provided with AVR, terminal CTs, neutral CTs etc.

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 132/11kV, 40MVA Power transformer.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 79 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. The new relays/equipment shall be
installed at BC 2 substation to match the protection provided at 132kV BC 1
end.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 132kV GIS Room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 80 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- 132kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Barzan
Camp 2 S/S cable links between new 132/11kV transformers and new 132kV
GIS switchgear laid in unfilled concrete troughs with all accessories Approx.
route length: 50m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor underground cable links at Barzan Camp 2 S/S
(four (4) cables per phase) between 11kV switchgear and 132/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 132/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits solid bonded (one cable
per phase), between 11kV switchgear and 11/0.415, 1000 kVA Station
transformers. Approx. route length: 30 m.

3.2.6.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 81 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3 PACKAGE S-3


3.3.1 66/11KV GHARAFA NORTH SUBSTATION UPGRADE
66/11kV Gharafa North is an existing transformer feeder station with 66/11kV 25MVA
Power transformers and associated equipment. It is connected at 66kV level with
220/132/66/11kV Doha North Super substation via double circuit underground cable
line. Scope of work includes upgrade of existing substation as detailed below within
the boundary of existing Gharafa North substation. Existing 25MVA Power
transformers and associated earthing transformers are to be replaced by 32/40 MVA
Power transformers, Station Service Transformers and NER respectively. Also
existing 11kV switchgears shall be replaced completely by new 11kV switchgears.
S/S will be upgraded in the future with 66kV GIS.

There is sufficient space in the N-E side of the plot to accommodate all facilities under
the Scope of works. 66kV incomers are entering substation through this area.
Alternativelly, S-E area foreseen for the future 66kV SWG may be utilized considering
that existing facilities will be demolished upon completion of the works. Dismantlig of
outdoor substation equipment and demolishing of existing structures are included in
the Scope of this Contract. The Contractor shall make a comprehensive site survey
and submit method statement outlining detailed proposal for the execution of works,
including protection of existing facilities, which shall be subject to KAHRAMAA
approval prior to start of any site works. Contractor shall bear all the costs of repair in
case that any of the services are damaged / disturbed. Work shall be done in a way to
avoid any interruption of supply from the existing substation during execution of the
project.

The principal elements of 66/11kV primary GIS substation at Gharafa North shall be
as follows:

¾ Establish 11kV, 2500A at 40oC, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. incomers rated 2500A

- One (1) Nos. bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformers

- Two (2) Nos. Feeders for future capacitor banks

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for vacuum contactor panel, equipped with protection and the power-
factor controlled switching for the future capacitor banks

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 82 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Alternatively 11kV GIS is also acceptable

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, Bushing CTs in line with remote ends ,
neutral CTs, etc.

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 500kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 4.75% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection.

¾ LV Service Equipment.

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules.

¾ All civil Works including building services as per appendix F - Drawings

¾ Air-conditioning and ventilation systems to cover the control & relay building
and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the 11kV SWG room, control & relay building and all
other buildings

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 83 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

- Existing 2 x 66kV Underground cable circuits with associated fiber optic cable
(24 Fibers), coming from Doha North Super substation are connected to
66/11kV 25MVA transformers which are presently in service at Gharafa North
substation. Diversion and re-connection of those cables to new 40MVA
transformers are also included in the Scope of Works of substation Contractor.
Approx. route length: 100m

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed with
earth continuity conductor cable links, (four (4) cables per phase), between
66/11kV power transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m

- 11kV, 1x500mm2, XLPE, 500kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 500kVA station
transformers. Approx. route length: 30m

3.3.1.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.3.1.2 MODIFICATIONS AT 220/132/66/11KV DOHA NORTH SUPER


REMOTE SUBSTATION:

220/132/66/11kV Doha North Super is the existing substation with GIS built under
Phase 4 Project. All modifications required due to refurbishment works in Ghafara
North substation shall be carried out under the scope of this project. The scope of
work shall include but not be limited to the following:

¾ Re-testing and re-commissioning of the 66kV GIS bays along with Local
Control Panels, inscription of additional alarm facia, modification of indicating
meters, wiring, replacing of GIS name plates and any required works

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 84 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

¾ Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC (included in package
1)

¾ Protection Scope for remote end modification:

For 2 x 66kV Cable transformer feeders connected to Gharafa North substation,


complete functional protection system as per Standard specification shall be
provided.

- The new relays/equipment shall be installed at Doha North Super substation to


match the (new) protection at Gharafa North substation end.

- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. Contractor shall perform proper CT sizing calculation
and submit for KM review. The new CTs’ construction and other dimensions
shall be identical to the existing CTs so that it can be mounted in the limited
space available in the indoor switchgear bay. The Contractor shall be fully
responsible for all associated works and required interfaces.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope

¾ SCS and Power Control Scope for remote end modification:

- Existing BCUs in 2 x 66kV bays utilized for connection towards Gharafa North
S/S shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications to SCS supplied by ABB under Phase 4 to include upgrade


of 2 x 66kV transformer feeders.

- Minor modification for existing Microsol RTU/TDB/ TMMC equipment to include


changes to 2 x 66kV transformer feeders in the NCC/ENCC including S/S work
necessary for NCC/ENCC end to end testing.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 85 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3.2 66/11KV BIN MAHMOOD SUBSTATION

66/11kV Bin Mahmood is new substation. It will be connected into KAHRAMAA


network on 66kV level via two cable lines which are under the Scope of Phase 9,
Cable Contractor:

Diversion works, Loop in / Loop out (LILO) of two 66kV, 1x2000sqmm, XLPE,
120MVA, underground cable circuits with fiber optic cable (24 Fibers) between
Doha Super S/S and Mergab Mall S/S to the new 66kV GIS in Bin Mahmood S/S.
Approx. route length: 300m. All equipment and works necessary for earthing system
arrangement, in order to maintain specified current rating, shall be provided.
Necessary details, schematic drawings etc., with accurate lengths shall be submitted
for approval during detailed engineering stage. The terminations are GIS at Bin
Mahmood S/S and joints at the diversion point near Bin Mahmood S/S. Refer to
attached drawing no. EHV-72-2010.

The substation Contractor should include in his scope of work co-ordination with the
cable Contractor to connect cable with the GIS, pre commissioning checks, end to
end tests and commissioning of the respective circuits.

The principal elements of 66/11kV Bin Mahmood substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Two (2) Nos. 66/11 kV, 40MVA Outgoing Transformer bays

- One (1) Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. incomers rated 2500A

- One (1) Nos. bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Feeders for 11/0.415kV station transformers

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of 11kV switchgear

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 86 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc.

¾ Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection.

¾ LV Service Equipment.

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Since Bin Mahmud S/S will be fed
from new 220/66/11kV Doha Super substation, constructed by Areva under
Phase 8, it is required that compatible relays and equipment shall be installed
at Bin Mahmood substation for all the feeders.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 66kV GIS room Crane

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 87 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Bin
Mahmood S/S underground cable links between new 66/11kV transformers
and new 66kV GIS switchgear laid in unfilled concrete troughs with all
accessories. Approx. route length: 30m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
Bin Mahmood S/S underground cable links with earth continuity conductor,
(four (4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 60m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.3.2.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.3.2.2 MODIFICATIONS AT 220/66/11KV DOHA SUPER AND 66/11KV AL MERGAB


MALL SUBSTATIONS:

220/66/11kV Doha Super is a new substation with Gas insulated switchgears being
constructed under Phase 8. The 66kV GIS spare bays at Doha Super Substation
shall be used for establishing the above underground cable connections between the

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 88 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

two substations. All modifications required due to LILO of the existing 66 kV cable line
Doha Super – AMM into Bin Mahmood S/S shall be carried out under subject SOW
All modifications required at Doha Super substation due to new cable connection
towards substation shall be carried out under the present scope of work.

Al Mergab Mall 66/11 kV substation was originally part of the Phase 10 Project
However, due to the needs for fast completion, it is excluded from Phase 10 and
awarded Phase 9 Project. All modifications required due to LILO of the existing 66 kV
cable line Doha Super – AMM into Bin Mahmood S/S shall be carried out under
subject SOW

The scope of work shall include but not limited to the following:

- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Bin Mahmood
substation. If necessary, existing termination female parts shall be replaced by
suitable one, including all necessary material and works required for such
modification.

- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

¾ SCS and Power Control Scope for remote end modification:

Doha Super S/S:

- Minor modifications to SCS supplied by AREVA under Phase 8 project to


include changes to 2 x 66kV cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End – to –
End testing.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 89 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

All Mergab Mall S/S:

- Minor modifications to Siemens SCS under Phase 9 project to include changes


to 2 x 66kV cable feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

Doha Super S/S:

For 2x66 kV Cable feeders connected to Bin Mahmood substation, complete


functional protection system as per Standard specification shall be provided.

- In Doha Super Substation, 66kV (Spare) equipped bays, Main-1 AREVA make
P545 and Main-2 Siemens make 7SD532 is provided for 66kV line protection.

- The new relays/equipment shall be installed at Bin Mahmood substation to


match the protection provided at 66kV Doha Super substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and Adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

All Mergab Mall S/S:

For 2x66 kV Cable feeders connected to Bin Mahmood substation, complete


functional protection system as per Standard specification shall be provided.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 90 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- The new relays / equipment shall be installed at Bin Mahmood substation to


match the protection provided at Al Mergab Mall substation end. All
modification, testing and comissioning, end to end test to make it fully
operational shall be Contractor’s responsibilty.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 91 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3.3 66/11KV AL MERGAB MALL

66/11kV Al Mergab Mall is new substation. It will be connected into KAHRAMAA


network on 66kV level to Bin Mahmood substation via double circuit underground
cable line which is under the Scope of Phase 10, Cable Contractor. Bin Mahmood
substation is within scope of Phase 10 project (see 3.3.2 above).

The substation Contractor should include in his scope of work co-ordination with the
cable Contractor to connect cable with the GIS, pre commissioning checks, end to
end tests and commissioning of the respective circuits.

The principal elements of 66/11kV Al Mergab Mall substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformer feeders

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 92 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the transformer is to
be justified by calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection.

¾ LV Service Equipment.

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil Works including building services as per appendix F- Drawings,

¾ 66kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 93 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Al


Mergab Mall S/S cable links between new 66/11kV transformers and new
66kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length : 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at Al
Mergab Mall S/S underground cable links with earth continuity conductor, (four
(4) cables per phase), between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.3.3.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 94 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3.4 66/11KV MINISTRY OF INTERIOR (MOI)

66/11kV Ministry of Interior is new substation. It will be connected into KAHRAMAA


network on 66kV level to Doha Central Substation. Two underground cable lines
which are under the Scope of Phase 10 Cable Contractor, will be connected:
- 2 x 66kV underground cable line Doha Central – MOI
- 2 x 66kV underground cable line MOI – Feriq Bin Omran

The substation Contractor should include in his scope co-ordination with the cable
Contractor to connect cable with the GIS, pre commissioning checks, end to end tests
and commissioning of the respective circuits.

The principal elements of 66/11kV MOI substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- One (1) Nos. Bus section bay

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformers

- Two (2) Nos. Bays for future Capacitor Banks.

- Space for six future bays, three on each side of the switchgear

- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 95 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the transformer is to
be justified by calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection.

¾ LV Service Equipment.

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil Works including building services as per appendix F- Drawings,

¾ 66kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 96 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at MOI S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories Approx. route length:
100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
MOI S/S underground cable links with earth continuity conductors, (four (4)
cables per phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.3.4.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

¾ If construction of MOI is in delay, Feriq Bin Omran substation will be connected


directly to Doha Central with 66kV double circuit underground cable line which
will be in the scope of Cable Contractor. Once, MOI Substation is completed,
following works is required at MOI substation and is in the Scope of S/S
contractor:

¾ Diversion works, Loop in / Loop out (LILO) of two 66kV, 1x2000sqmm, XLPE,
120MVA, underground cable circuits with fiber optic cable (24 Fibers)
between Doha Central S/S and Feriq Bin Omran S/S, to the new 66kV GIS in
MOI S/S. Approx. route length: 100m. All equipment and works necessary for
earthing system arrangement, in order to maintain specified current rating,
shall be provided. Necessary details, schematic drawings etc., with accurate
lengths shall be submitted for approval during detailed engineering stage. The
terminations are GIS at MOI S/S.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 97 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3.4.2 MODIFICATIONS AT DOHA CENTRAL SUBSTATION:

220/66/1kV Doha Central is existing substation, constructed by Siemens under


KAHRAMAA Phase 5 Project, presently in the process of upgrade with 220kV GIS
under KAHRAMAA Contract GTC/318B/2009 (yet to be awaded).

66kV GIS spare bays at Doha Central Substation shall be used for establishing the
underground cable connections between the two substations. All the required
modifications to the spare 66kV GIS bays at Doha Central substation shall be carried
out under the present scope of work. The scope of work shall include but not limited
to the following:

- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from MOI substation.
If necessary, existing termination female parts shall be replaced by suitable
one, including all necessary material and works required for such modification

- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

¾ SCS and Power Control System Scope for remote end modification:

- Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect
new signals as per latest specification requirements. Hence Contractor shall
install additional BCU or other suitable device to transfer all the required
signals to SCC/NCC as per specification, including additional spre BI/BO.

- Modifications to existing SCS system Siemens (Sicam SAS) to include spare 2


x 66kV cable feeders, including S/S work necessary for Gateway data mapping
to NCC/ENCC and NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

- VTs are not available in 66kV GIS Spare bays. New GIS 66kV VT shall be
provided at Doha Central. The Contractor shall be fully responsible for all
associated works, interlocks and required interfaces

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 98 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- For 2x66 kV Cable feeders connected to MOI substation, complete functional


protection system as per Standard specification shall be provided. The new
relays/equipment shall be installed at Doha Central substation to match the
(new) protection at MOI substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- Testing and commissioning, end to end test to make it fully operational is


included in the present Scope.

¾ Optional:

If construction of MOI is delayed, Feriq Bin Omran substation will be connected


directly to Doha Central with 66kV double circuit underground cable line which will be
in the scope of Cable Contractor. All works detailed under 3.3.4.1 and below, shall
remain under the present Scope, considering connection to Feriq Bin Omran, instead
to MOI substation.

- New matching relays/equipment provided at both substations, Fariq bin Omran


and Doha Central, shall be according to the latest specification requirements.

- Minor modifications in SCS and protection system at Doha Central to reflect


changed configuration of power supply due to connection of MOI into network,
testing and end to end tests to make them fully operational are in the SOW of
S/S Contractor.

3.3.4.3 MODIFICATIONS AT FERIQ BIN OMRAN SUBSTATION:

Feriq Bin Omran is existing 66/11kV transformer feeder station with 2x40MVA power
transformers, upgraded under KAHRAMAA Phase 6 Project (Contract GTC/116/2006
with ABB). It is presently fed from Gharafa substation. It is foreseen, Under Scope of
Phase 10, to install new 66kV double circuit underground cable line between MOI and
Feriq Bin Omran substations and cancel connection towards Gharafa. Subject works
will be in the SOW of Phase 10 Cable Contractor.

All modifications required at Feriq Bin Omran substation due to changed power
connections shall be carried out under the present scope of work. The scope of work
shall include but not be limited to the following:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 99 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

- Testing and re-commissioning of the 40 MVA transformers.

- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

¾ SCS and Power Control System Scope for remote end modification:

- Modifications to existing SCS system supplied by ABB under Phase 6 to reflect


change in power supply rearrangement from Gharafa S/S to MOI S/S in the
SCS including Gateway data mapping to NCC/ENCC and S/S work necessary
for NCC/ENCC end to end testing including removal of existing 2 x 66kV
underground cable line Gharafa to Feriq Bin Omran.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

- For 2 x 66kV Cable transformer feeders connected to MOI substation,


complete functional protection system as per Standard specification shall be
provided. The new relays/equipment shall be installed at Fariq bin Omran
substation to match the (new) protection at Ministry of Interior substation end.

- Contractor has to do the proper CT sizing calculation for KM review and


Adequacy of existing CTs must be checked. Additional CT core or changing of
the CTs shall be the responsibility of the Contractor. Optional price for the
(66kV side & 11kV side, 40 MVA Transformer bushing and 11kV Switchgear)
CT replacement and all associated works shall be provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 100 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Optional:

If construction of MOI is in delay, Feriq Bin Omran substation will be connected


directly to Doha Central with 66kV double circuit underground cable line which will be
in the scope of Cable Contractor. All works detailed under 3.3.4.2 and below, shall
remain under the present Scope, considering connection to Doha Central instead to
MOI substation.

- New matching relays/equipment provided at both substations, Feriq Bin Omran


substation and Doha Central substation, shall be according to the latest
specification requirements.

- Minor modifications in SCS and protection system at Feriq Bin Omran


substation to reflect changed configuration of power supply due to connection
of MOI into network, testing and end to end tests to make them fully
operational are in the SOW of S/S Contractor.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 101 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.3.5 66/11KV DOHA INDUSTRIAL F (DIF)

66/11kV Doha Industrial F is new substation. Location proposed for construction of


DIF is in the Industrial Area within KAHRAMAA Warehouse.

DIF S/S will be connected into KAHRAMAA network on 66kV level to New Doha
Industrial Super S/S (under Scope of Phase X, see Section 3.1.4 above) via double
circuit underground cable line which is under the Scope of Phase 10 Cable
Contractor.

The substation Contractor should include in his scope co-ordination with the cable
Contractor to connect cable with the GIS, pre commissioning checks, end to end tests
and commissioning of the respective circuits.

The principal elements of 66/11kV DIF substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bay rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformers

- Two (2) Nos. Bays for future Capacitor Banks.

- Space for six future bays, three on each side of the switchgear

- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 102 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ One (1) Nos. 11kV metal enclosed switchgear, the same as described above
excluding bays for 11/0.415kV station transformers, will be installed in the
future development of substation. The Contractor shall consider this in the
design and sizing of the relevant systems.

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc.

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the transformer is to
be justified by calculation note which shall be subject to approval.

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with associated neutral
earthing resistors, cable connections and other related equipment will be
installed in the future development of substation

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing & Lightning Protection.

¾ LV Service Equipment.

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Protection for incoming feeders
(from new Saliyah) shall be provided to match with the protection at new Doha

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 103 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Industrial Super (Package 1, Phase 10 Project). The Contractor to coordinate


with the respective Phase 10 Contractor.

¾ All civil Works including building services as per appendix F- Drawings,

¾ 66kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS buildings, control &
relay building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at DIF S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories Approx. route length:
100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
DIF S/S underground cable links with earth continuity conductors, (four (4)
cables per phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one cable
per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.3.5.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 104 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4 PACKAGE S-4

3.4.1 DOHA LAND (PREV. CALLED HEART OF DOHA) UNDERGROUND


SUBSTATIONS

The Doha Land Development is located in the centre of Doha, with boundaries
defined by Al Rayan Rd, Al Diwan St, Musherib St and Jassim Bin Mohammed St. It
will be a mixed use development including residential, commercial, retail and leisure.
To meet the electrical power demand of the development, KAHRAMAA has identified
requirement for two one primary substations within the development area: Doha Land
1 (DL1) and Doha Land 2 (DL2) included in the Scope of Phase 9 10 Project.

Substations will be connected into KAHRAMAA network on 66kV level with the
following underground cable lines all of which are in the Scope of Phase 10, Cable
Contractor:
- Double circuits line SED – DL2
- Double circuits line DL2 – DL1
- Double circuit line DL1 – Grand Hamad Avenue

Both Substations will be multi-levelled, located underground, accessed by the main


service tunnels.

The lowest level, B4 will be cable basement. Above it will be level B3 foreseen for
transformer cells, service yard for transformers, fire suppression plant room, 66kV
SWG room, 11kV room, battery room, access and escape routes. Level B2 is
foreseen for control and relay room, telecommunication room, LV power supply
system, HVAC plant room. Additionally, DL1 will include staff facilities on the level B2.
Level B1 is spared for other services. On the ground level above DL1 the EID prayer
ground will be located; above DL2 will be new road.

Civil works associated with the substation buildings will be undertaken by developer,
Doha Land, as follows:
- Water retaining ground slab and retaining walls to form basement “box”
- Building frame with cast in-situ reinforced concrete columns and beams
- Floor slabs with cast in-situ reinforced concrete
- Earth electrode and mesh cast within piles and slabs as necessary and to
substation Contractor’s Design requirements described elsewhere on this
report. Substation Contractor will also be responsible for site test
- Ground level ventilation apertures and associated louvers for general
ventilation and transformer cell ventilation
- External wall – cast in-situ reinforced concrete with adequate water sealing
- Internal walls – non-load bearing block work

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 105 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Wall finishes – painted plaster to all internal wall surfaces. In the battery room,
Acid alkaline resistant painted wall
- Ceiling finish – Fair-faced concrete with a paint finish
- Floor finishes – Cable Basement, 66kV GIS and 11kV AIS: non slip 5mm thick
heavy duty epoxy paint finish; Battery room: chemical resistant 5mm thick
epoxy Acid and alkaline resistant paint finish; Control/Relay room,
LVAC/LVDC, and communication room: 700mm raised false floor. Raised floor
panels will be steel encapsulated mineral type, Toilet, Pantry, locker and mess:
non slip ceramic floor tiles
- Access doors and their frames – Steel framed self closing doors. All internal
doors are fire rated with the exception of toilets, mess pantry, and locker room
which will be timber doors and frames completed with required ironmongeries.
- Windows and their frames - Aluminium with powder coated finish completed
with security grills complete with required ironmongeries
- Ironmongeries - Master key for the main access door. Panic bars will be
provided to all external doors.
- Steel framed louvers to transformer cell fronts
- Electrically and manually operated steel roller shutters to GIS room access and
associated with required controls
- Fire shutters to transformer loading area (to be controlled by the substation
Contractors Fire detection System as well as tunnel fire detection system)
- Internal hand rails to all staircases
- Builders work holes and penetrations as specified by the substation Contractor
based upon their design
- Transformer cells subject as per substation Contractor requirements
- Rails to the transformer cells to put them in place and pulling anchors as per
substation Contractors design details
- Linear slots cast into the floor to mount GIS and other equipment as per
substation Contractors design details
- Potable water connection up to tie-in point for substation area
- Capped water connection for fire suppression system in the plant room
- Transformer oil and water catch pit and any additional drainage connection
point in the substation
- Drainage requirement as per substation Contractors design details
- Fire walls and fire compartments
- Permanent access roads to the substation via underground services tunnels
- Cable routes within the development area and entrances into the substation
building

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 106 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Furniture will not be provided as part of the base built substation. It will be
responsibility of KM appointed EPC Contractor to provide furniture as required
for substation operation
- KM appointed EPC Contractor’s Scope includes all substation equipment
according to KAHRAMAA specifications
- All required building service within the substation building, are within KM
appointed EPC Contractor’s Scope, including, but not limited to: small power,
lighting and emergency lighting, fire detection and alarm system, GIS cranes,
HVAC, air-conditioning and ventilation system within the substation building,
fire protection system, telecommunication

Detailed civil and structural design of the public facilities in which substations are
incorporated is completed. Interface between KM appointed EPC Contractor and civil
design team will be required in the early stage of the project, to ensure that any
specific builders’ work requirements are defined and integrated in construction works
in due time. High level of coordination between developer and substation Contractor
will be required during the complete construction period as specified in Annexure 1 –
Scope of Work for Doha Land Substation.

3.4.2 66/11KV DOHA LAND 1 SUBSTATION (PREV. NAMED HEART OF DOHA 1)

66/11kV Doha Land 1 is new substation. It will be connected into KAHRAMAA


network on 66kV level via two cable lines which are under the Scope of Phase 10,
Cable Contractor:
- 2 x 66kV Grand Hamad Avenue – Doha Land 1 (2000sqmm cables)
- 2 x 66kV Doha Land 1- Doha Land 2 (2000sqmm cables)

The substation Contractor should include in his scope of work co-ordination with the
Phase 10 Cable Contractor to connect cable with the GIS, pre commissioning checks,
end to end tests and commissioning of the respective circuits. Also coordination with
Substation Contractor Phase 10, Package 5 (Grand Hamad Avenue SS) is required.

The principal elements of 66/11kV Doha Land 1 (DL1) substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 107 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Six bays, three on each side of the switchgear, are planned for future
development

¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV Station transformer

- Space for six future bays, three on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Space for six future bays, three on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

¾ Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of


Dyn1, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN,
AVR, neutral CTs, etc. Due to absence of natural ventilation, substation
Contractor is obliged to perform detailed study of ventilation requirements and
coordinate design for the same with civil Contractor. Preferred are transformers
with standard, ONAN / ONAF, cooling system and with FO winding
temperature monitoring which should be offered as optional item. Optionally,
gas insulated transformer may be proposed. Bidders should include in their
technical offer detailed specification of the proposed cooling system and
special construction requirements for the same, if any.

¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 108 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing Protection according to limit of works as specified in Item 3.4 above

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ Building services and civil works according to limit of works as specified in Item
3.4 above

¾ 66kV GIS crane

¾ All building services as specified in Item 3.4 above

¾ Air-conditioning and ventilation systems covering substation area

¾ Explosion prevention system and Fire protection system for power


transformers

¾ Fire protection system for the substation premises

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 109 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, quadruple circuits, solid bonded at DL1
S/S cable links between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx. route
length: 30m.

- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
DL1 S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within S/S,
laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.

- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.4.2.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.4.2.2 MODIFICATIONS AT RAS ABU ABOUD (RAA) SUPER SUBSTATION:


(Optional)

220/66/11kV RAA Super is an existing substation completed under KAHRAMAA


Contract GTC/05 by Siemens.

In the case that Grand Hamad Avenue substation, planned for Phase 10,Package 5 is
delayed, DL 1 substation will be connected directly to Ras Abu Aboud Super (RAA)
substation via 66kV double circuit underground cable line. Third circuit from RAA will
be installed by cable Contractor for future connection in Grand Hamad Avenue. In
that case, all works as specified in Item 3.5.1.1 below (Modifications at RAA Super
substation as remote end for Grand Hamad Avenue substation) shall be in the scope
for DL 1, considering connection DL 1 – RAA Super.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 110 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.3 66/11KV DOHA LAND 2 SUBSTATION (PREV. CALLED HEART OF DOHA 2)

66/11kV Doha Land 2 is new substation. It will be connected into KAHRAMAA


network on 66kV level via two cable lines which are under the Scope of Phase 10,
Cable Contractor:
- 2 x 66kV SED – Doha Land 2 (1000sqmm cables)
- 2 x 66kV Doha Land 1- Doha Land 2 (2000sqmm cables)

SED is existing substation upgraded under Phase 6 (GTC 05) by ABB.

The substation Contractor should include in his scope of work co-ordination with the
Phase 10 Cable Contractor to connect cable with the GIS, pre commissioning checks,
end to end tests and commissioning of the respective circuits. Also coordination with
Substation Contractor Phase 10, Package 5 (Grand Hamad Avenue SS) is required.

The principal elements of 66/11kV Doha Land 2 (DL 2) substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Six bays, three on each side of the switchgear, are planned for future
development

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV Station transformer

- Space for six future bays, three on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of


Dyn1, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN,

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 111 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

AVR, neutral CTs, etc. Due to absence of natural ventilation, substation


Contractor is obliged to perform detailed study of ventilation requirements and
coordinate design for the same with civil Contractor. Preferred are transformers
with standard, ONAN / ONAF, cooling system and with FO winding
temperature monitoring which should be offered as optional item. Optionally,
gas insulated transformer may be proposed. Bidders should include in their
technical offer detailed specification of the proposed cooling system and
special construction requirements for the same, if any.

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing Protection according to limit of works as specified in Item 3.4 above

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ Building services and mechanical works according to limit of works as specified


in Item 3.4 above

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 112 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ 66kV GIS crane

¾ All building services as specified in Item 3.4 above

¾ Air-conditioning and ventilation systems covering substation area

¾ Explosion prevention system and Fire protection system for power


transformers

¾ Fire protection system for the substation premises

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at DL2 S/S
cable links between new 66/11kV transformers and new 66kV GIS switchgear
laid in unfilled concrete troughs with all accessories. Approx. route length:
30m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
DL2 S/S cable links with earth continuity conductor, (four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.4.3.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 113 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.3.2 MODIFICATIONS AT 66/11KV SED SUBSTATION:

132/66/11kV transformer feeder station SED is an existing substation with 66kV


indoor air insulated switchgear constructed in late seventies and upgraded by ABB
under KAHRAMAA Contract GTC/05 by ABB.

The existing 66kV bays of Eid Mosque substation at SED shall be used for
establishing cable connection between SED and DL 2 substation. All modifications
required to the existing 66kV switchgear at SED substation due to connection towards
DL 2 shall be carried out under the present scope of work. These works are to be
carried out in phase manner after the commissioning of Doha Land 1 substation by
66kV supply from Grand Hamad Avenue New / Ras Abu Aboud substation. The
scope of work shall include but not limited to the following:

- Re-testing and re-commissioning of the existing 66kV spare bays along with
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of name plates and any required
works including, wiring, testing & complete re-commissioning of the above 66kV
bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
power cables rated 66kV and above at both ends.

¾ SCS and Power Control System Scope for remote end modification:

- Minor modifications to existing conventional control panel and


RTU/TDB/TMMC to include changes to 2 x 66kV cable feeders including S/S
work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC.

¾ Protection Scope for remote end modification:

- Existing CTs shall be replaced with new CT to match with new protection and
metering requirements. Contractor shall perform proper CT sizing calculation
and submit for KM review. Additional CT core or changing of the CTs shall be
the responsibility of the Contractor. The existing CTs are of make Moser
Glaser of type ATE 72.5. The new CTs’ construction and other dimensions
shall be identical to the existing CTs so that it can be mounted in the limited

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 114 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

space available in the indoor switchgear bay. The Contractor shall be fully
responsible for all associated works and required interfaces.

- For 2x66 kV Cable feeders connected to Doha Land 2 substation, complete


functional protection system as per Standard specification shall be provided.
The new relays/equipment shall be installed at SED substation to match the
(new) protection at Doha Land 2 substation end. Contractor shall study the
feasibility of installing new protection panels at appropriate location and shall
take KAHRAMAA’s approval before installing it. Testing and commissioning,
end to end test to make it fully operational shall be Contractor's responsibility.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

3.4.3.3 MODIFICATIONS AT 66/11KV DOHA LAND 1 (DL1) SUBSTATION


(OPTIONAL):

Doha Land 1 substation was originally part of the Phase 10 Project. However, due to
the needs for fast completion, it is excluded from Phase 10 and awarded to M/s ABB
under the Project GTC 318.

In the case that completion of DL2 S/S is delayed, a (ll modifications required at DL1
substation due to 66kV cable connection DL1 – DL2 shall be carried out under
subject SOW.

The scope of work shall include but not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to SCS supplied by ABB, to include subject 2 x 66kV cable


connection between DL1 and DL2 in the SCS including Gateway data mapping

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 115 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

to NCC/ENCC and S/S works necessary for NCC/ENCC End – to – End


testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

For 2x66 kV Cable feeders connected to DL2 substation, complete functional


protection system as per Standard specification shall be provided.

- In DL1, 66kV equipped bays shall be provided under the Project GTC 318 by
M/s. ABB. The new relays / equipment shall be installed at DL2 substation to
match the protection provided at DL1 substation end. All modification, testing
and comissioning, end to end test to make it fully operational shall be
Contractor’s responsibilty.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 116 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.4 66/11KV SHERATON PARK SUBSTATION

66/11kV Sheraton Park is new substation, which will be integrated in the Sheraton
Park Project, hereby referred to as SPP. SPP is planned to be public landscaped park
with high aesthetics, quality and safety standards. Site is located in the West Bay, Al
Dafna area of Doha, adjacent to and towards the north west of the Sheraton Hotel.
Area is currently designated as a car park for the Sheraton Hotel and covers
approximately 76,926 square meters and faces the Cornice Road.

Sheraton Park substation will be connected into the KAHRAMAA network on 66kV
level via double circuit underground cable line to West Bay Super 1 substation, build
by M/s Siemens undr GTC 53 Project. It will feed Sheraton Park Project: Maintenance
and Storage Facility Area (MSF) and the Automatic People Mover system for the
West Bay Area, Doha Convention Center & Tower (DCC&T) and other consumers in
the West Bay Area.

Substation will be at below ground level.


Civil works associated with the substation buildings will be undertaken by Developer,
Qatari Diar, including:
- Shell and Core Civil Works for the 66kV Substation.
- External wall and roof architectural finishes for the Shell and Core Structure
- Access requirements for personnel, equipment, emergency services, cables
and other service corridors outside the 66kV Substation
- Stub-ins for MEP services up to the 66kV Substation, comprising of water
supply, drainage points, provision of Qtel voice-data points in the main panel,
sprinkler system and ground level ventilation louvers
- All civil works, structural works and embedded services including earthing
required by the EPC Contractor

Detailed civil and structural design of the public facilities in which substations are
incorporated is under progress. Interface between KM appointed EPC Contractor and
civil design team will be required in the early stage of the project, to ensure that any
specific builders’ work requirements are defined and integrated in construction works
in due time. High level of coordination between developer and substation Contractor
will be required during the complete construction period as specified in Annexure 2 –
Scope of Works for 66/11 kV Sheraton Park Substation.

Cable connection will be installed by Phase 10 Cable Contractor. It is within


substation scope of works to coordinate with the cable Contractor to connect cable
with the GIS, complete pre commissioning checks, end to end tests and
commissioning of the respective circuits.

Principal elements of 66/11kV Sheraton Park substations shall be as follows:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 117 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Outgoing feeder bays

- Three (3) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Six bays, three on each side of the switchgear, are planned for future
development

¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

- Three (3) Nos. Incomers rated 2500A

- Two (2) Nos. Bus section bays rated 3150A

- Twenty-seven (27) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV Station transformer

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Three (3) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of


Dyn1, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN,
AVR, neutral CTs, etc. Due to absence of natural ventilation, substation
Contractor is obliged to perform detailed study of ventilation requirements and
coordinate design for the same with civil Contractor. Preferred are transformers
with standard, ONAN / ONAF, cooling system and with FO winding
temperature monitoring which should be offered as optional item. Optionally,
gas insulated transformer may be proposed. Bidders should include in their
technical offer detailed specification of the proposed cooling system and
special construction requirements for the same, if any.

¾ Three (3) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 118 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing Protection according to limit of works as specified in Item 3.4.3 above

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ Civil and mechanical works according to limit of works as specified in Item


3.4.3 above

¾ 66kV GIS crane

¾ All building services as specified in Item 3.4.3 above

¾ Air-conditioning and ventilation systems covering substation area

¾ Explosion prevention system and Fire protection system for power


transformers

¾ Fire protection system for the substation premises

¾ Passive fire protection system for all cables in the basement of all buildings

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 119 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS,
pre commissioning checks, end to end tests and commissioning of the
respective circuits

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at Sheraton
Park S/S cable links between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
Sheraton Park S/S cable links with earth continuity conductor underground,
(four (4) cables per phase), between 11kV switchgear and 66/11kV power
transformers, laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.

- 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER and
66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

3.4.4.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.4.4.2 MODIFICATIONS AT 220/66/11KV WEST BAY SUPER 1 SUBSTATION:


220/66/11kV West Bay Super 1 is existing substation, completed by Siemens under
Contract GTC/53.

Two 66kV GIS spare bays at West Bay Super-1 Substation shall be utilized for cable
connection towards Sheraton Park substation. All modifications required at West Bay
Super 1 substation due to subject connection, shall be carried out under the present
scope of work. The scope of work shall include but not limited to the following:

- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Sheraton Park
substation. If necessary, existing termination female parts shall be replaced by

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 120 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

suitable one, including all necessary material and works required for such
modification

- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

¾ SCS and Power Control Scope for remote end substation:

- Minor modifications to SCS supplied by SIEMENS under above Contract to


include changes to 2 x 66kV cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End – to –
End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end substation:

For 2x66 kV Cable feeders connected to Sheraton Park substation, complete


functional protection system as per Standard specification shall be provided.

- 66kV spare bay in WBS-1 substation shall be utilized to connect new Sheraton
Park substation. The new relays/equipment shall be installed at WBS-1
substation to match the protection provided at new 66kV Sheraton Park
substation end.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- Testing and commissioning, end to end test to make it fully operational is


included in present Scope.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 121 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.5 66/11KV BARWA AL DOHA SUBSTATION


66/11kV Barwa Al Doha Substation will be integrated within BARAYA development
project. The project comprise of office building, hotel and residential hotel apartment,
mall with retail and anchor store, supermarket and spa, basement parking and stand
alone parking building. Development plot is 65863 m2, located in Doha Al-Jadeeda
area. It is situated at the intersection of two main roads: A Ring Road (Ahmed Bin
Mohammed Bin Thani Street) and the radial artery Al Muntazah Street.

Substation will be located within the development boundary in the vicinity of parking
building in the southeast corner of the plot, at the intersection of Doha al-Jadeeda
Road and Salah Eddine Street.

Primary Substation building or shell (i.e. substructure, superstructure and external


envelope) will be constructed by the developer, Barwa Al Doha. All other works
associated with the Primary Substation will be executed by KAHRAMAA appointed
EPC Contractor.

The following building works associated with the Substation for the BARAYA
development will be undertaken by Developer:

- Site access: Provision of sufficient access completed prior to the


commencement of the Substation installation.
- Substation shell civil works
- Builders work holes and penetrations according to the KM appointed EPC
Contractor’s design drawings and include in completed Substation shell
construction.
- 66kV cable entry/exit to the Substation: necessary cable ducts and trenches
based on the KM appointed EPC Contractor’s design details
- Substation Earthing: Installation of earthing electrodes and earth mats within
the Substation substructures as per KM appointed EPC Contractor’s design
drawings
- Substation Fire protection system: Provision of one capped water connection
within the Substation (for domestic and fire suppression use)
- Substation HVAC: Provision of capped chilled water connection, necessary
ventilation louver openings within the building envelope based upon KM
appointed EPC Contractor’s detailed design drawings
- Domestic Cold Water services: Provision of one capped water connection
within the Substation (for domestic and fire suppression use)
- Transformer Cell oil/water system: Construction of the transformer catch pit
system based upon KM appointed EPC Contractor’s detailed design drawings
detailed drawings

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 122 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Cable containment: Provision of cable containments to outgoing 11kV Feeders


within the Project premises only
- 11 kV Cables: Provision of 11kV cables, termination kits and pilot cables and
terminate all 11kV cables in the 11kV Substations on the premises.

Interface between KM appointed EPC Contractor and civil design team will be
required in the early stage of the project, to ensure that any specific builders’ work
requirements are defined and integrated in construction works in due time and
targeted completion dates are met from both parties. High level of coordination
between developer and substation Contractor will be required during the complete
construction period as specified in Annexure 3 – Scope of Works for 66/11 kV Barwa
Al Doha Substation.

Barwa Al Doha substation shall be connected into KAHRAMAA network on 66kV level
to Airport Super substation. Cable connection will be installed by Phase 10 Cable
Contractor. It is within substation scope of works to coordinate with the Cable
Contractor to connect cable with the GIS, complete pre commissioning checks, end to
end tests and commissioning of the respective circuits.

The principal elements of 66/11kV Barwa Al Doha substation shall be as follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Four (4) Nos. Outgoing feeder bays

- Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Six bays, three on each side of the switchgear, are planned for future
development

¾ Establish two 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV Station transformer

- Two (2) Nos. Bays for future capacitor banks feeders

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 123 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Space for six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for future capacitor banks feeders

- Space for six future bays, three on each side of the 11kV switchgear

- Space for vacuum contactor panels, equipped with protection and power-factor
controlled switching for the future capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling system, Vector group of Dyn1, OLTC with +5% to -15% in steps of
1.25%, 13.6% impedance at ONAN, AVR, neutral CTs, etc.

¾ Four (4) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 124 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Condition monitoring system for 40MVA transformers


- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

¾ Earthing Protection according to limit of works as specified in Item 3.4.4 above

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ Civil and mechanical works according to limit of works as specified in Item


3.4.4 above

¾ 66kV GIS crane

¾ All building services as specified in Item 3.4.4 above

¾ Air-conditioning and ventilation systems covering substation area

¾ Fire protection system for power transformers

¾ Fire protection system for the substation premises

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, quadruple circuits, solid bonded at


Barwa Al Doha S/S cable links between new 66/11kV transformers and new
66kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length: 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, quadruple circuits, single point earthed at
Barwa Al Doha S/S cable links with earth continuity conductor, (four (4) cables
per phase) between 11kV switchgear and 66/11kV power transformers within
S/S, laid in unfilled concrete troughs with all accessories. Approx. route length:
50m.

- 11kV, 1x630 mm2, XLPE, quadruple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

¾ 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 125 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.4.5.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.4.5.2 MODIFICATIONS AT 220/66KV AIRPORT SUPER SUBSTATION:

220/66kV Airport Super is an existing substation with Gas Insulated Switchgears


constructed under Phase 4 by Areva. To feed the new 66/11kV Barwa Al Doha
substation existing cable link between Airport Super and existing 66/11kV Asmakh
substation is to be diverted to the new substation.

The existing 66kV GIS bays of Asmakh feeder shall be used for establishing the
above underground cable connections between the two substations. All modifications
required to the existing 66kV GIS at Airport Super substation due to change in power
connection shall be carried out under the present scope of work. The scope of work
shall include but not limited to the following:

- Re-testing and re-commissioning of the existing GIS spare bays along with
Local Control Panels including indicating meters in the local control panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC /ENCC

¾ SCS and Power Control Scope for remote end substation:

- Existing BCUs in 2 x 66kV bays utilized for connection towards Barwa Al Doha
S/S shall be replaced with new BCUs. New BCUs shall be integrated with the
existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications for existing ABB SCS system supplied under Phase 4
project.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 126 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Minor modifications to existing RTU/TDB/TMMC to include changes to 2 x


66kV cable feeders in the NCC/ENCC including S/S work necessary for
NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end substation:

Details of the existing 66kV GIS are as follows:


- Make: GEC Alstom
- GIS Type: B 95

For 2 x 66kV cable feeders connected to Barwa Al Doha substation, complete


functional protection system as per Standard specification shall be provided. The new
relays/equipment shall be installed at Airport Super substation to match the (new)
protection at Barwa Al Doha substation end. Contractor shall study the feasibility of
installing new protection panels at appropriate location and shall take KAHRAMAA’s
approval before installing it. Testing and commissioning, end to end test to make it
fully operational shall be Contractor's responsibility.

Existing CTs shall be replaced with new CTs to match with new protection and
metering requirements. Contractor has to do the proper CT sizing calculation for KM
review. Additional CT core or changing of the CTs shall be the responsibility of the
Contractor. The Contractor shall be fully responsible for all associated works and
required interfaces.

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 127 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.5 PACKAGE S-5:

3.5.1 66/11KV GRAND HAMAD AVENUE SUBSTATION

Grand Hamad Avenue substation will be incorporated within multi storey parking
building for which plot of 65x40m is dedicated in area of Grand Hamad Avenue as
indicated on the site layout plan. Scope of works for KM nominated EPC includes all
substation works as detailed below but also complete design, approval of the design
and Building Permit procedure and all civil and construction works and building
services as per Appendix F – drawings which are related to the parking building.

The principal elements of 66/11kV Grand Hamad Avenue substation shall be as


follows:

¾ Establish 66kV, 2500A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Seven (7) Nos. Outgoing feeder bays

- Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Six bays, three on each side of the switchgear, are planned for future
development

¾ Establish 11kV, 2500A at 40˚C, 40kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

- Two (2) Nos. Incomers rated 2500A

- One (1) Nos. Bus section bays rated 2500A

- Eighteen (18) Nos. Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV Station transformer

- Two (2) Nos. Bays for future Capacitor Banks.

- Space for six future bays, three on each side of the switchgear

- Space for the vacuum contactor panel, equipped with the protection and the
power-factor controlled switching for the future capacitor banks

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 128 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Alternatively 11kV GIS is also acceptable.

¾ One (1) Nos. 11kV metal enclosed switchgear, the same as described above
excluding bays for 11/0.415kV station transformers, will be installed in the
future development of substation.

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of


Dyn1, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN,
AVR, neutral CTs, etc. Due to absence of natural ventilation, substation
Contractor is obliged to perform detailed study of ventilation requirements and
coordinate design for the same with civil Contractor. Preferred are transformers
with standard, ONAN / ONAF, cooling system and with FO winding
temperature monitoring which should be offered as optional item. Optionally,
gas insulated transformer may be proposed. Bidders should include in their
technical offer detailed specification of the proposed cooling system and
special construction requirements for the same, if any.

¾ Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV 40MVA Power transformer.

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc. Consider rated power and indoor
installation environment, Bidder may propose dry type transformers. This
needs to be clearly indicated in the Technical Data Sheets.

¾ Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, with associated neutral
earthing resistors, cable connections and other related equipment will be
installed in the future development of substation

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing.

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 66kV GIS
- Condition monitoring system for 40MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 129 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil works including building services as per Appendix F - Drawings

¾ 66kV GIS crane

¾ Air-conditioning and ventilation systems for the complete building

¾ Explosion Prevention System and Fire protection system for power


transformers

¾ Fire protection system for the complete building

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Coordination with 66kV Cable Contractor, connection of cable with the GIS, pre
commissioning checks, end to end tests and commissioning of the respective
circuits

¾ All outdoor insulators shall be provided with RTV coating

¾ Power cables:

- 66kV, 1x500 mm2, XLPE, 40MVA, double circuits, solid bonded at Grand
Hamad Avenue S/S cable links between new 66/11kV transformers and new
66kV GIS switchgear laid in unfilled concrete troughs with all accessories
Approx. route length: 100m.

- 11kV, 1x630 mm2, XLPE, 40MVA, double circuits, single point earthed at
Grand Hamad Avenue 2 S/S cable links with earth continuity conductor, (four
(4) cables per phase) between 11kV switchgear and 66/11kV power
transformers within S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 50m.

- 11kV, 1x630 mm2, XLPE, double circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20 m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) between 11kV switchgear and 11/0.415, 1000kVA Station
transformers. Approx. route length: 30 m.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 130 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.5.1.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

¾ DL1 substation shall be connected directly to RAA substation with 66kV double
circuit underground cable line which is within the scope of Project GTC 318.
Third cable circuit, for the connection between Grand Hamad Avenue and RAA,
shall be installed by Phase 10 Cable Contractor. Once, when Grand Hamad
Avenue substation is completed, following works are required at Grand Hamad
Avenue substation and are in the Scope of S/S contractor:

- Diversion works, Loop in / Loop out (LILO) of two 66kV, 1x2000sqmm,


XLPE, 120MVA, underground cable circuits with fiber optic cable (24
Fibers) between Ras Abu Aboud Super S/S (RAA) and Doha Land 1
(DL1) S/S to the new 66kV GIS in Grand Hamad Avenue S/S. Approx.
route length: 100m. All equipment and works necessary for earthing
system arrangement, in order to maintain specified current rating, shall
be provided. Necessary details, schematic drawings etc., with accurate
lengths shall be submitted for approval during detailed engineering stage.
The terminations are GIS at Grand Hamad Avenue S/S cable joints at
diversion point.

3.5.1.2 MODIFICATIONS AT RAA SUPER AND DL1 SUBSTATIONS:

Grand Hamad Avenue will be connected into KAHRAMAA network on 66kV level to
the existing RAA Super substation via triple circuit underground cable and to DL 1
substation (under the separate Contract GTC 318 between KAHRAMAA and M/s
ABB) via double circuit underground cable.

220/66/11kV Ras Abu Aboud substation is existing substation with GIS built under
Phase 6, Project GTC/05/2004. All modifications required to the existing 66kV
switchgear at RAA substation due to this connection shall be carried out under the
scope of this Contract. The scope of work shall include but not limited to the following:

- Contractor shall check suitability of the existing termination female part in 66kV
GIS considering the size (2000sqmm) of incoming cables from Grand Hamad
Avenue substation. If necessary, existing termination female parts shall be
replaced by suitable one, including all necessary material and works required
for such modification

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 131 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Re-testing and re-commissioning of the existing 66kV spare bays along with
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of name plates and any required
works including, wiring, testing & complete re-commissioning of the above 66kV
bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

¾ SCS and Power Control System Scope for remote end modification:

Ras Abu Aboud Super Substation:

- Minor modifications to SCS supplied by SIEMENS under Phase 6 project to


include changes to 3 x 66kV cable feeders in the SCS and NCC/ENCC
including Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Doha Land 1 Substation:

- Minor modifications to SCS supplied by by ABB under Contract GTC 318B


project to include changes to 2 x 66kV cable feeders in the SCS and
NCC/ENCC including Gateway data mapping to NCC/ENCC and S/S works
necessary for NCC/ENCC End – to – End testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

Ras Abu Aboud Super Substation:

For 3 x 66kV Cable feeders connected to Grand Hamad Avenue substation,


complete functional protection system as per Standard specification shall be
provided.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 132 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- In Ras Abu Aboud substation 66kV equipped bays, Main-1 Siemens make
7SD532 and Main-2 ABB make REL561 relays are provided for 66kV line
protection.

- The new relays/equipment shall be installed at Ras Abu Aboud substation to


match the (new) protection at Grand Hamad Avenue substation end. If any of
the existing Main relay at Ras Abu Aboud substation is proposed to be
retained, Contractor shall change communication module in these Main relays
and make it suitable for “Dual Fiber Optic Communication”, if required and it
shall be decided during detail engineering.

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked. Additional CT core or
changing of the CTs shall be the responsibility of the Contractor. Optional price
for the (66kV GIS) CT replacement and all associated works shall be provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

- Testing and commissioning, end to end test to make it fully operational shall be
Contractor's responsibility.

Doha Land 1 Substation:

For 2x66 kV Cable feeders connected to Grand Hamad Avenue substation, complete
functional protection system as per Standard specification shall be provided.

- In DL1, 66kV equipped bays shall be provided under the Project GTC 318 by
M/s. ABB. The new relays / equipment shall be installed at Grand Hamad
Avenue substation to match the protection provided at DL1 substation end. All
modification, testing and commissioning, end to end test to make it fully
operational shall be Contractor’s responsibility.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 133 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.5.2 220/66/11KV NEW DOHA-B SUPER (NDBS)

66/11 kV New Doha-B (NDB) substation is an existing substation. KAHRAMAA


intends to replace and upgrade NDB into new 220/66/11 kV Doha-B Super (NDBS)
substation. Proposed location for the NDBS is within the boundary of the existing
NDB substation. There is sufficient space on the West side of the substation area to
accommodate all facilities under the present Scope. However, it may be required to
demolish or relocate some of the existing facilities in those areas. The Contractor
shall make a comprehensive site survey and submit method statement with detailed
proposal for the execution of relocation works or demolishion, including protection of
existing facilities, which shall be subject to KAHRAMAA approval prior to start of any
site works. Contractor shall bear all the costs of repair/replacement in the case that
any of the services are damaged / disturbed. Work shall be done in a way to avoid
any interruption of supply from the existing substation during execution of the project.

The principal elements of new 220/66/11kV New Doha-B Super substation shall be
as follows:

¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. cable feeder bays (including 2 spare)

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Two (2) Nos. 220/66 kV, 120/150/200 MVA Outgoing transformer bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 66kV, 3150A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Two (2) Nos. 220/66kV, 120/150/200 MVA incoming Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Three (3) Nos. 66/11kV, 32/40 MVA outgoing Transformer bays

- Six (6) Nos. outgoing feeder bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgears with vacuum circuit breakers, consisting of the following:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 134 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Three (3) Nos. Incomers rated 2500A

- Two (2) Nos. Bus section bays rated 3150A

- Twenty-seven (27) Nos. of Bays for outgoing feeders rated 630A

- Two (2) Nos. Bays for 11/0.415kV station transformer feeders

- Three (3) Nos. Bays for capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 220/66kV, 120/150/200 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ Three (3) Nos. Power Transformers 66/11kV, 32/40 MVA, with ONAN/ONAF
cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc

¾ Three (3) Nos. 11 kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000 kVA, with ONAN
cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

¾ 66 kV, 200 MVA bus duct between 220/66 kV power transformers & 66 kV
GIS

The rated power of the station transformer mentioned above is provisional.


Transformers shall be of adequate capacity to cater to the total station load with
additional 30% margin. The capacity of the transformer is to be justified by calculation
note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 220 kV and 66 kV GIS
- Condition monitoring system for 120/150/200 MVA and 32/40 MVA power
transformers

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 135 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Integrated HMI workstation for monitoring system


- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil works related to new 220/66/11kV substation including building


services and works related to the diversion of 66 kV and 11 KV cables as per
Appendix F – Drawings. Sufficient space for the third 220/66kV power
transformer, foreseen in the future, and adjusted facilities (primary
connections, LV supply and control cabling, etc.) should be considered by the
Contractor during the detailed design and construction.

¾ 220 kV and 66 kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

- 220 kV, 1x1200 mm2, XLPE, 200 MVA, duble circuits, special bonded
at NDBS S/S cable links, single point earthed with earth continuity
conductor, the links between 220/66 kV power transformers and new 220
kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approximate route length: 150 m

- 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at


NBDS S/S cable links, between new 66/11kV transformers and new
66kV GIS switchgear laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 136 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
NDBS S/S cable links with earth continuity conductor, four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers
within S/S, laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.

- 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.

- 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) cable links between 11kV switchgear and 11/0.415,
1000 kVA Station transformers. Approx. route length: 30 m.

Diversion works, Loop in / Loop out (LILO) of the existing 220 kV, 1x1600mm2,
XLPE, 315 MVA underground cable Feeders 1 & 2 with fiber optic cable (24 Fibers)
between Doha North Super and New Doha – J (NDJ) to the new 220kV GIS in
NDBS Substation are in the present SOW of S/S Contractor. Approximate routhe
length: 600m. Cable route shall be diverted into substation plot with sufficient snaking
provided. The Contractor shall make all necessary arrangements to connect cables
at joint bay, divert them, connect into 220kV GIS and commission the same. All
equipment and works necessary for earthing system arrangement, in order to
maintain specified current rating, shall be provided. Necessary details, schematic
drawings etc., with accurate lengths shall be submitted for approval during detailed
engineering stage. The terminations will be in 220kV GIS in New Doha B Super S/S
and cable joints at diversion point.

3.5.2.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.5.2.2 MODIFICATIONS AT NEW DOHA J (NDJ), NEW DOHA C AND DOHA NORTH
SUPER (DNS) SUBSTATIONS

220/66/11kV New Doha J (NDJ) substation is an existing substation fed by three


220kV cable feeders from Doha North Super (DNS) substation. New 220kV Gas
Insulated switchgear was established at the substation in GTC/123B, Phase 7 project.
All modifications required due to LILO of the existing 220 kV cable line NDJ – DNS
into New Doha-B S/S shall be carried out under the subject SOW.

220/132/66/11kV Doha North Super (DNS) is existing substation with Gas Insulated
switchgear, built under Phase 4 project. All modifications required due to LILO of the
existing 220 kV cable line NDJ – DNS into New Doha-B S/S shall be carried out
under subject SOW.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 137 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

The SOW includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

¾ SCS and Power Control Scope for remote end modification:

NDJ Substation:

- Minor modifications to SCS supplied by Siemens under Phase 7 project to


include changes to 2 x 220 kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

DNS substation:

- Existing BCUs in 2x220kV bays utilized for connection towards New Doha B
Super S/S shall be replaced with new BCUs. New BCUs shall be integrated
with the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications to SCS supplied by ABB to include changes to 2x220kV


cable feeders in the SCS.

- Minor modifications to existing RTU/TDB/TMMC to include changes to


2x220kV cable feeders including S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 138 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

New Doha C:

- Minor modifications to existing RTU/TDB/TMMC to include changes to 2x66kV


cable feeders including S/S work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

¾ Protection Scope for remote end modification:

NDJ Substation:

For 2 x 220 kV Cable feeders connected to New Doha-B Super substation, complete
functional protection system as per Standard specification shall be provided. In NDJ
substation, 220 kV equipped bays, Main-1 Siemens make 7SD532 and Main-2 ABB
make RED670 relays are provided for 220 kV line protection.

- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at NDBS substation to match the protection
provided at 220 kV NDJ substation end.

- It shall be decided during detailed engineering whether existing trip relays /


TCS relays need to be replaced or not. This shall be Contractor responsibility
and price shall be provided for the same as required in the Bill of Quantities.

- All modification, Testing and commissioning, end to end test are included in the
present Scope.

- Contractor shall perform proper CT sizing calculation to verify adequacy of the


existing CTs and submit the same for KM review. If required, additional CT
core or changing of the CTs shall be the responsibility of the Contractor.
Optional price for the CT replacement and all associated works shall be
provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

DNS Substation:

For 2 x 220 kV Cable feeders connected to New Doha-B Super substation, complete
functional protection system as per Standard specification shall be provided. In NDJ

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 139 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

substation, 220 kV equipped bays, Main-1 Siemens make 7SD532 and Main-2 ABB
make RED670 relays are provided for 220 kV line protection.

- Contractor shall change communication module in those relays and make them
suitable for “Dual Fiber Optic Communication”, if required. The new
relays/equipment shall be installed at NDBS substation to match the protection
provided at 220 kV DNS substation end.

- It shall be decided during detailed engineering whether existing trip relays /


TCS relays need to be replaced or not. This shall be Contractor responsibility
and price shall be provided for the same as required in the Bill of Quantities.

- All modification, Testing and commissioning, end to end test are included in the
present Scope

- Contractor shall perform proper CT sizing calculation to verify adequacy of the


existing CTs and submit the same for KM review. If required, additional CT
core or changing of the CTs shall be the responsibility of the Contractor.
Optional price for the CT replacement and all associated works shall be
provided.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 140 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.5.3 220/66/11KV ABU HAMOUR SUPER (AHS)

132/66/11 kV Abu Hamour Substation is an existing substation. KAHRAMAA intends


to disburden Abu Hamour substation with new 220/66/11 kV Abu Hamour Super
(AHS) substation. Proposed location for the AHS is within the adjacent KM
warehouse plot. It may be required to demolish or relocate some of the existing
facilities in those areas. The Contractor shall make a comprehensive site survey and
submit method statement with detailed proposal for the execution of works or
demolishion, including protection of existing facilities, which shall be subject to
KAHRAMAA approval prior to start of any site works. Contractor shall bear all the
costs of repair/replacement in the case that any of the services are damaged /
disturbed. Work shall be done in a way to avoid any interruption of supply from the
existing substation during execution of the project.

The principal elements of new 220/66/11kV Abu Hamour Super substation shall be
as follows:

¾ Establish 220kV, 4000A at 40˚C, 50kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Five (5) Nos. cable feeder bays (including 1 spare)

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Three (3) Nos. 220/66 kV, 120/150/200 MVA Outgoing transformer bays

- Two (2) Nos. shunt reactor bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 66kV, 3150A at 40˚C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Three (3) Nos. 220/66kV, 120/150/200 MVA incoming Transformer bays

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Three (3) Nos. 66/11kV, 32/40 MVA outgoing Transformer bays

- Ten (10) Nos. outgoing feeder bays

- Space for six future bays, three on each side of the switchgear

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 141 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Establish 11kV, 3150A at 40˚C, 40kA / 3 sec, single bus bar metal enclosed
switchgears with vacuum circuit breakers, consisting of the following:

- Three (3) Nos. Incomers rated 2500 A

- Two (2) Nos. Bus section bays rated 3150 A

- Twentyseven (27) Nos. of Bays for outgoing feeders rated 630 A

- Two (2) Nos. Bays for 11/0.415kV station transformer feeders

- Three (3) Nos. Bays for capacitor banks feeders

- Space for six future bays, three on each side of the 11 kV switchgear

- Space for the vacuum contactor panel, equipped with protection and the
power-factor controlled switching for the capacitor banks

Alternatively 11kV GIS is also acceptable.

¾ Two (2) Nos. Power Transformers 220/66kV, 120/150/200 MVA, YNyn0 (d1)
ONAN/ ONAF/ OFAF cooling, +10% on load taps in steps of 1.25%, 12%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

¾ Three (3) Nos. Power Transformers 66/11kV, 32/40MVA, with ONAN/ONAF


cooling, Vector group of Dyn1, OLTC with +5% to -15% in steps of 1.25%,
13.6% impedance at ONAN, AVR, neutral CTs, etc

¾ Three (3) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50˚C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing
the neutral of 66/11kV Power transformer

¾ 66 kV, 200 MVA bus duct between 220/66 kV power transformers & 66 kV
GIS

¾ Two (2) Nos. Station Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned above is provisional.


Transformers shall be of adequate capacity to cater to the total station load with
additional 30% margin. The capacity of the transformer is to be justified by calculation
note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 142 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Partial discharge monitoring system for 220 kV and 66 kV GIS


- Condition monitoring system for 120/150/200 MVA and 32/40 MVA
transformers (enough spare for furture expansion to be considered)
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules

¾ All civil works related to new 220/11kV substation including building services
and works related to the diversion of 220 kV and 66 kV cables as per Appendix
F – Drawings. Plinth and fire wall for the third 220/66kV power transformer,
foreseen for the future, is included in the present Scope of works.

¾ 220 kV and 66 kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and control & relay
building and all other buildings.

¾ Fire protection system for power transformers and shunt reactors

¾ Fire protection system for the GIS buildings, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating.

¾ Power cables:

1. 220 kV, 1x1200 mm2, XLPE, 200 MVA, duble circuits, special bonded
at AHS S/S cable links, single point earthed with earth continuity
conductor, the links between 220/66 kV power transformers and new 220
kV GIS switchgear laid in unfilled concrete troughs with all accessories.
Approximate route length: 150 m

2. 66kV, 1x500 mm2, XLPE, 40MVA, triple circuits, solid bonded at AHS
S/S cable links, between new 66/11kV transformers and new 66kV GIS
switchgear laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 143 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3. 11kV, 1x630 mm2, XLPE, 40MVA, triple circuits, single point earthed at
AHS S/S cable links with earth continuity conductor, four (4) cables per
phase), between 11kV switchgear and 66/11kV power transformers within
S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

4. 11kV, 1x630 mm2, XLPE, triple circuits, cable links between 11kV NER
and 66/11kV, 40 MVA Power Transformers. Approx. route length: 20m.

5. 11kV, 1x500 mm2, XLPE, 1000kVA, double circuits, solid bonded (one
cable per phase) cable links between 11kV switchgear and 11/0.415,
1000 kVA Station transformers. Approx. route length: 30 m.

¾ Diversion works, Loop in / Loop out (LILO) of the existing 220 kV,
1x2500mm2, XLPE, 515 MVA underground cable circuits with fiber optic (24
Fibers) and DTS cable between Abu Hamour North and DSS to the new
220kV GIS in Abu Hamour Super Substation, are in the SOW of S/S
Contractor. Approximate routhe length: 500m. Cable route shall be diverted
into substation plot and cable joints to be installed with sufficient sneaking
provided. The Contractor shall make all necessary arrangements to connect
cables at joint bay, divert them, connect into 220kV GIS and commission the
same. All equipment and works necessary for earthing system arrangement, in
order to maintain specified current rating, shall be provided. Necessary details,
schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage. The terminations will be in 220kV GIS in
Abu Hamour Super S/S and cable joints at diversion point.

Laying of DTS cable, approximately length 2 x (500+500)m, from diversion


point along with the each cable circuit up to cable sealing end at Abu Hamour
Super Substation and same DTS cable from cable sealing end up to diversion
point, i.e. one DTS cable shall monitor existing Feeder 1 with respective loop
in / loop out at Abu Hamour Super Substation, including splicing with existing
DTS Cable and re-commissioning of DTS Unit in Abu Hamour North (to
monitor two cable lines at the same time, at Channel 1 : feeder 1 of DSS –
AHS and feeder 1 of AHS – AHN and at Channel 2: feeder 2 of DSS –AHS
and feeder 2 of AHS – AHN).

¾ Cable Diversions:

Existing OHL/ cable circuits, listed below, shall be diverted from Abu Hamour to AHS
substation under the present Scope of substation Contractor:

- 2 x 66 kV cable circuits to Abu Hamour East,


- 2 x 66 kV cable circuits to KSSS,

The substation Contractor should make all necessary arrangements to connect cable
termination with new 66kV GIS. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 144 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Abu Hamour to Abu Hamour East: 66 kV, 1x500 mm2, XLPE, 40 MVA
double circuits shall be diverted with associated multimode fiber optic cable
and telephone cables to 66 kV GIS at new Abu Hamour Super S/S.
Approximate routhe length: 500 m. Also new single mode fiber optic cables
(24 Fibers) shall be provided from Abu Hamour East to Abu Hamour Super.
The Contractor shall include for all necessary modification works in the
earthing arrangement (cross bonding, single point bonding, mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.
Necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage. The terminations will
be in 66kV GIS in Abu Hamour Super S/S and cable joints at diversion point.

¾ Abu Hamour to Abu Hamour Super: New single mode fiber optic cables (24
Fibers) shall be provided from from Abu Hamour to Abu Hamour Super.
Approximate routhe length: 500 m.

¾ Abu Hamour to KSS: 66 kV, 1x500 mm2, XLPE, 40 MVA double circuits
shall be diverted with associated copper pilot cable to 66 kV GIS at new Abu
Hamour Super S/S. Approximate routhe length: 500m. The Contractor shall
include all necessary modification works in the earthing arrangement (cross
bonding, single point bonding, mixed bonding) in order to ensure that required
current rating of diverted circuit is maintained. Necessary details, schematic
drawings etc., with accurate lengths shall be submitted for approval during
detailed engineering stage. The terminations will be in 66kV GIS in Abu
Hamour Super S/S.

3.5.3.1 OPTIONAL WORKS:

¾ Installation for 11kV outgoing cable feeders between 11kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.5.3.2 MODIFICATIONS AT ABU HAMOUR NORTH (AHN), DOHA SOUTH SUPER


(DSS), KHALIFA SPORT STADIUM SOUTH (KSSS), ABU HAMOUR EAST (AHE)
AND ABU HAMOUR (AH) SUBSTATIONS

220/66/11kV Abu Hamour North (AHN) substation is an existing substation built under
phase 5 project. All modifications required due to LILO of the existing 220 kV cable
line AHN – DSS into Abu Hamour Super S/S shall be carried out under subject SOW.

220/132kV DSS substation is an existing substation with 220kV GIS built by


Schneiderunder phase 4 Project, with 220kV GIS and is fed by two 220kV cable
feeders from Doha North Super substation All modifications required due to LILO of

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 145 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

the existing 220 kV cable line AHN – DSS into Abu Hamour Super S/S shall be
carried out under subject SOW.

66/11IV Khalifa Sport Stadium South (KSSS) substation is an existing substation built
under earlier KM project. All modifications required due to diversion of the existing
2x66 kV cables for KSSS substation to 66 kV GIS at new AHS shall be carried out
under subject SOW.

Abu Hamour East (AHE) substation is an existing substation built under earlier KM
project GTC/21. All modifications required due to diversion of the existing 2x66 kV
cables for Abu Hamour East substation to 66 kV GIS at new AHS shall be carried out
under subject SOW.

Abu Hamour 132/66/11 kV is an existing substation built under earlier KM project but
upgraded with 66kV GIS under phase 7 project by M/s Siemens. All modifications
required due to diversion of the existing 2x66 kV cables for Abu Hamour East
substation and the existing 2x66 kV cables for KSSS substation to 66 kV GIS at new
AHS shall be carried out under subject SOW.

The SOW includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation to be made available between the stations based on
requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC.

- All necessary co-ordination with the cable Contractor for the termination of the
EHV cables at both ends.

- All outdoor insulators shall be provided with RTV coating.

¾ SCS and Power Control Scope for remote end modification:

All modification, Testing and commissioning; end to end test are included in the
present Scope

AHN Substation:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 146 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Minor modifications to SCS supplied by Siemens under Phase 5 project to


include changes to 2 x 220 kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

DSS substation:

Doha South Super (DSS) is existing substation with GIS built under Phase 4 project

- Existing BCUs in 2x220kV bays utilized for connection towards Abu Hamur
Super S/S shall be replaced with new BCUs. New BCUs shall be integrated
with the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractor’s
responsibility

- Minor modifications to SCS supplied by ABB to include changes to 2x220kV


cable feeders in the SCS.

- Minor modifications to existing Microsol RTU/TDB/TMMC equipment including


changes to 2x220kV cable feeders and S/S work necessary for NCC/ENCC
end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Khalifa Sport Stadium South (KSSS):

- Minor modifications to existing conventional control panel and


RTU/TDB/TMMC to include changes to 2 x 66kV transformer cable feeders
including S/S work necessary for NCC/ENCC end to end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC.

ABU HAMOUR EAST (AHE):

- Minor modifications to SCS supplied by SIEMENS to include changes to


2x66kV cable feeders in the SCS.

- Minor modifications to existing RTU/TDB/TMMC to include changes to 2x66kV


cable feeders including S/S work necessary for NCC/ENCC end to end testing.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 147 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC.

ABU HAMOUR (AH):

- Minor modifications to SCS supplied by Siemens under Phase VII project to


include changes to 4 x 66 kV cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to end
testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

¾ Protection Scope for remote end modification:

AHN Substation:

For 2 x 220 kV Cable feeders connected to Abu Hamour Super substation, complete
functional protection system as per Standard specification shall be provided. The new
relays/equipment shall be installed at Abu Hamour North substation to match the
(new) protection at Abu Hamour Super substation end.

- Contractor shall perform proper CT sizing calculation in order to verify


adequacy of existing CTs and to submit the same for KM review. Installation of
additional CT core or changing of the existing CTs shall be the responsibility of
the Contractor. Optional price for the (220kV GIS) CT replacement and all
associated works shall be provided.

- It shall be decided during detailed engineering whether it is necessary or not to


replace existing trip relays / TCS relays. This shall be responsibilty of the
substation Contractor under and price shall be stated as required in the Bill of
quantities.

- All modification, Testing and commissioning; end to end test are included in the
present Scope.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

DSS Substation:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 148 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

For 2 x 220 kV Cable feeders connected to new Abu Hamour Super substation,
complete functional protection system as per Standard specification shall be
provided. The new relays/equipment shall be installed at Doha South Super
substation to match the (new) protection at Abu Hamour Super substation end.

- Contractor shall perform proper CT sizing calculation in order to verify


adequacy of existing CTs and to submit the same for KM review. Installation of
additional CT core or changing of the existing CTs shall be the responsibility of
the Contractor. Optional price for the (220kV GIS) CT replacement and all
associated works shall be provided.

- It shall be decided during detailed engineering whether it is necessary or not to


replace existing trip relays / TCS relays. This shall be responsibilty of the
substation Contractor under and price shall be stated as required in the Bill of
quantities.

- All modification, Testing and commissioning; end to end test are included in the
present Scope.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

ABU HAMOUR EAST (AHE):

- For 2 x 66kV Cable Transformer feeders connected to Abu Hamour Super


substation, complete functional protection system as per Standard specification
shall be provided. The new relays/equipment shall be installed at Abu Hamour
East substation to match the protection at Abu Hamour Super end.

- Existing protection panels may not have adequate space to install new relays
and hence, new protection panels shall be provided for B11 and B21 bays.
Transformer differential relay (7UT61), REF relay (F87NH) and Over current
relay (F511) are located presently in 132/66/11 kV Abu Hamour Substation (in
the same compound) and all these relays are required to be installed in the
new panel in Abu Hamour East substation. Otherwise Contractor shall replace
existing relays to provide the complete new protection for 40MVA transformer
at Abu Hamour East substation. Any additional relay required to make a
complete functional protection system shall be provided by the Contractor.

- There is no CT available on the HV side of 40MVA (Koncar make) transformer.


All the required modifications shall be done in the transformer HV side (Cable
Box) to provide necessary CTs to match with new protection and metering
requirements. The new CTs required parameters are given in Protection
standard Specification and standard CT ratio. If required, according to the CT

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 149 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

sizing calculation, installation of additional CT core or changing of the CTs


shall be the responsibility of the Contractor.

- Existing CTs in 11kV Incomer A18/A28 feeder shall be replaced (or additional
core provided) to suit F87C+T (Overall differential protection). The new CTs
required parameters are given in Protection standard Specification and
standard CT ratio. If required, according to the CT sizing calculation,
installation of additional CT core or changing of the CTs shall be the
responsibility of the Contractor

- Contractor shall perform proper CT sizing calculation and submit for KM


review.

- It shall be decided during detailed engineering whether it is necessary or not to


replace existing trip relays / TCS relays. This shall be responsibilty of the
substation Contractor under and price shall be stated as required in the Bill of
quantities.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

- Modification of the existing Partial bus bar protection, including conducting


partial bus bar stability test shall be the responsibility of the Contractor. All
direct inter-trips are to be made available between the stations based on
requirement.

Works for pilot copper cables:

Substation Contractor shall provide the following for each pilot copper cable
diversion of existing double circuit Abu Hamur – Khalifa Sport Stadium South
(KSSS) cable lines to be Abu Hamour Super–KSSS cable lines.

• Pilot Copper Cable Terminal Box with all accessories required for
connection of protection equipment. Works for dismantling of existing
Pilot Copper Cable Terminal Box at Abu Hamur S/S. Alternatively,
existing Pilot Copper Cable Terminal Box at Abu Hamur S/S can be
utilized for installing the same in Abu Hamour Super substation.

Khalifa Sport Stadium South (KSSS):

Existing 66/11kV KSSS substation is presently supplied from 132/66/11kV Abu


Hamour Substation.

For 2x66 kV Cable transformer feeders connected to Abu Hamour Super substation,
complete functional protection system as per Standard specification shall be
provided. The new relays/equipment shall be installed at KSSS substation to match

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 150 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

the (new) protection at Abu Hamour Super substation end. The protection relays shall
be compatible to work satisfactorily over Pilot Cable.

- Contractor shall perform proper CT sizing calculation to verify adequacy of


existing CTs and submit the same for KM review. Installation of additional CT
core or changing of the existing CTs shall be the responsibility of the
Contractor. Optional price for the (66kV, 36MVA Transformer) CT replacement
and all associated works shall be provided.

- It shall be decided during detailed engineering whether it is necessary or not to


replace existing trip relays / TCS relays. This shall be responsibilty of the
substation Contractor under and price shall be stated as required in the Bill of
quantities.

- All modification, Testing and commissioning, end to end test to make it fully
operational is included in the present Scope.

- Modification of the existing Partial bus bar protection, including conducting


partial bus bar stability shall be the responsibility of the Contractor. All the
direct inter-trips are to be made available between the stations based on
requirement.

ABU HAMOUR (AH):

- 132/66/11kV Abu Hamour Substation is an existing substation with Gas


insulated switchgears built under Phase 7. At present, Abu Hamour East and
Khalifa Sports Stadium South substation are fed from 66 kV bays at Abu
Hamour Substation. It is envisaged to shift the feeding point for those two
substations from Abu Hamour to Abu Hamour Super substation. Diversion
work of cable circuits shall be carried as mentioned above in SOW. However
the substation contractor should ensure completeness of the works at
132/66/11kV Abu Hamour Substation for disconnection of the cable circuits.
All the required modifications in the substation shall be carried out under the
present scope of work. The scope of work shall include but not limited to the
following:

- Modification of inscription of alarm facia as required, replacing of GIS name


plates and any required works including, disconnection, isolation of LV
auxiliary supplies, wiring modification, etc of the related GIS bays.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 151 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.6 PACKAGE S-6


3.6.1 132/22KV AEROSPACE CITY 1 SUBSTATION

132/22kV Qatar Aerospace City 1 (ASCQ1) substation is a new substation which will
be constructed on the plot 75x75m located in south of Al-Khore area. It will be fed
from existing 132kV Khore South Substation (under construction, Phase 9, GTC
240A), constructing LILO (Loop In Loop Out) on the existing 132kV, 250MVA
underground cable line Khore South – Semaisma (currently under installation under
Phase 9, GTC 241A/2008 Siemens Consortium).

The principal elements of new 132/22kV Qatar Aerospace City 1 substation shall be
as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Cable feeder bays

- Two (2) Nos. 132/22kV, 60/75/100MVA Transformer bays for 132/22kV TXs.
For the purposes of tariff metering VT should be incorporated.

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 22kV, 3150A at 40˚C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear (GIS) with vacuum circuit breakers, consisting of the
following:

- Two (2) Nos. Incomers each rated 3150A for 132/22kV 60/75/100MVA TXs

- One (1) Nos. Bus section bay rated 3150A

- Ten (10) Nos. Outgoing feeder bays rated 630A

- Two (2) Nos. Bays for 22/0.415kV station transformers

- Space for six future bays, three on each side of the 22kV switchgear

Alternatively 22kV AIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/22kV, 60/75/100MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 152 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. of 22kV Metallic Neutral Earthing Resistors 17 ohm at 50˚C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/22kV 60/75/100MVA Power transformer.

¾ Two (2) Nos. Station Transformers 22/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers shall be of adequate capacity to cater to the total station load with
additional 30% margin. The capacity of the transformer is to be justified by calculation
note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 60/75/100MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for feeders connected to Khore South SS.

¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.

¾ All civil works related to new 132/22kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings

¾ 132kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and Control & Relay
building and all other buildings.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 153 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x630 mm2, XLPE, 100MVA, double circuit, special bonded at


Qatar Aerospace City 1 S/S cable links, single point earthed with earth
continuity conductor, the links between new 132kV GIS and 132/22kV
transformers laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.

- 22kV, 1x800 mm2, XLPE, 100MVA, double circuit, single point earthed
with earth continuity conductor underground cable links (four (4) cables per
phase) between 132/22kV power transformers and 22kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.

- 22kV, 1x800 mm2, XLPE, double circuit cable links between 22kV NER and
132/22kV, 60/75/100MVA Power Transformers. Approx. route length: 20 m

- 22kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 22kV switchgear and 22/0.415, 1000kVA station
transformers. Approx. route length: 30 m

¾ Diversion works, Loop in / Loop out (LI-LO), of the existing 132kV,


1x2000mm2, XLPE, 250MVA underground double cable circuits with fiber
optic cable (24 Fibers) between Khore South and Semaisma to the new
132kV GIS in Aero Space City 1 Substation, is in the scope of this Contract.
Approx. route length: 2.5km. All equipment and works necessary for earthing
system arrangement, in order to maintain specified current rating, shall be
provided. Necessary details, schematic drawings etc., with accurate lengths
shall be submitted for approval during detailed engineering stage. The
terminations are GIS at Aero Space City 1 S/S.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 154 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.6.1.1 OPTIONAL WORKS

¾ Installation for 22kV outgoing cable feeders between 22kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable
laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.6.1.2 MODIFICATIONS AT KHORE SOUTH SUBSTATION

132/66/11kV Khore South substation is an existing substation built under Phase 9


project by Hyosung (Contract GTC/240B/2008). All modifications required due to LILO
of the existing 132kV cable line Khore South – Semaisma into Qatar Aerospace City
1 S/S shall be carried out under this Contract.

The SOW includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the Phase IX cable Contractor (Siemens


Consortium) for LILO arangement of the EHV cables.

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to SCS supplied by Siemens under Phase 9 project to


include changes to 2 x 132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

¾ Protection Scope for remote end modification:

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 155 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

For 2 x 132kV Cable feeders connected to Qatar Aerospace City 1 substation,


complete functional protection system as per Standard specification shall be
provided.

- In Khore South substation, 132kV equipped bays, Main-1 Siemens make


7SD522 and Main-2 ABB make RED670 relays are provided for 132kV line
protection. The new relays/equipment shall be installed at Qatar Aerspace City
1 substation to match the protection provided at 132kV Khore South substation
end.

- All modification, Testing and commissioning; end to end test are included in the
present Scope

- Contractor shall perform proper CT sizing calculation and submit for KM review
and adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 156 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.6.2 132/22KV AEROSPACE CITY 2 SUBSTATION

132/22kV Qatar Aerospace City 2 (ASCQ2) substation is a new substation which will
be constructed on the plot 75x75m located in south of Al-Khore area. It will be fed
from new 132kV Qatar Aerospace City 1 Substation, constructing LILO (Loop In Loop
Out) on existing 132kV, 250MVA underground cable line Khore South – Semaisma,
currently under installation under the Phase 9 project (GTC 241A/2008 Siemens
Consortium).

The principal elements of new 132/22kV Qatar Aerospace City 2 substation shall be
as follows:

¾ Establish 132kV, 3150A at 40˚C, 40kA / 1 sec, 3-phase, 50Hz, double bus
bar GIS consisting of following bays:

- Six (6) Nos. Cable feeder bays

- Two (2) Nos. 132/22kV, 60/75/100MVA Transformer bays for 132/22kV TXs.
For the purposes of tariff metering VT should be incorporated.

- Two (2) Nos. Bus section bays

- Two (2) Nos. Bus coupler bays

- Space for six future bays, three on each side of the switchgear

¾ Establish 22kV, 3150A at 40˚C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear (GIS) with vacuum circuit breakers, consisting of the
following:

- Two (2) Nos. Incomers each rated 3150A for 132/22kV 60/75/100MVA TXs

- One (1) Nos. Bus section bay rated 3150A

- Ten (10) Nos. Outgoing feeder bays rated 630A

- Two (2) Nos. Bays for 22/0.415kV station transformers

- Space for six future bays, three on each side of the 22kV switchgear

Alternatively 22kV AIS is also acceptable.

¾ Two (2) Nos. Power Transformers 132/22kV, 60/75/100 MVA, Dyn1, with
ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 157 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Two (2) Nos. of 22kV Metallic Neutral Earthing Resistors 17 ohm at 50˚C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/22kV 60/75/100MVA Power transformer.

¾ Two (2) Nos. Station Transformers 22/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps
of 2.5%, 5.45% impedance, neutral CTs, etc

The rated power of the station transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the transformer is to be justified by
calculation note which shall be subject to approval.

¾ Substation Control System Including Gateway data mapping to


NCC/ENCC/DCC and S/S works necessary for NCC/ENCC/DCC End – to –
End testing

¾ Online monitoring system comprising of:


- Partial discharge monitoring system for 132kV GIS
- Condition monitoring system for 60/75/100MVA transformers
- Integrated HMI workstation for monitoring system
- Necessary LAN & WAN equipment including router/firewall for connection
to remote end

¾ LV Power Cables, Control Cables with all accessories

¾ Earthing & Lightning Protection

¾ LV Service Equipment

¾ Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification,
Protection SLD and Technical Schedules. Relay and equipment compatible
with remote ends shall be provided for feeders connected to Semaisma SS.

¾ Metering system: Tariff meters shall be provided on the 132kV sides of power
transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification as
appendices (ET-P26-G1&ET-P26-G2). Energy meters shall be integrated with
SCS using communication protocol.

¾ All civil works related to new 132/22kV substation including building services
and works related to LILO of 132kV cables as per Appendix F - Drawings

¾ 132kV GIS room Crane

¾ Air-conditioning and ventilation systems to cover the GIS and Control & Relay
building and all other buildings.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 158 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Fire protection system for power transformers

¾ Fire protection system for the GIS building, control & relay building and all
other buildings

¾ Passive fire protection system for all cables in the basement of all buildings

¾ Civil work, erection, laying and installation for 22kV outgoing cable feeders
(between 22kV GIS at S/S to substation boundary wall) included but not limited
to cable support, cable cleat, heat shrinkable cap and commissioning test shall
be part of scope of work, and shall include in contract prices. Contractor shall
coordinate with concerning KAHRAMAA department.

¾ All outdoor insulators shall be provided with RTV coating

¾ Power Cables:

- 132kV, 1x630 mm2, XLPE, 100MVA, double circuit, special bonded at


Qatar Aerospace City 2 S/S cable links, single point earthed with earth
continuity conductor, the links between new 132kV GIS and 132/22kV
transformers laid in unfilled concrete troughs with all accessories. Approx.
route length: 50m.

- 22kV, 1x800 mm2, XLPE, 100MVA, double circuit, single point earthed
with earth continuity conductor underground cable links (four (4) cables per
phase) between 132/22kV power transformers and 22kV switchgear, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.

- 22kV, 1x800 mm2, XLPE, double circuit cable links between 22kV NER and
132/22kV, 60/75/100MVA Power Transformers. Approx. route length: 20 m

- 22kV, 1x500 mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable
per phase) between 22kV switchgear and 22/0.415, 1000kVA station
transformers. Approx. route length: 30 m

- Diversion works, Loop in / Loop out (LILO) of the existing 132kV, 1x2000mm2,
XLPE, 250MVA underground cable circuits with fiber optic cable (24 Fibers)
between Khore South and Semaisma to the new 132kV GIS in Aero Space
City 2 Substation, is in the scope of this Contract. Approx. route length: 500m.
All equipment and works necessary for earthing system arrangement, in order
to maintain specified current rating, shall be provided. Necessary details,
schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage. The terminations are GIS at Aero Space
City 2 S/S.

3.6.2.1 OPTIONAL WORKS

¾ Installation for 22kV outgoing cable feeders between 22kV SWG and service
corridor outside the Substation boundary wall, included but not limited to cable

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 159 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

laying, cable supports, cable cleats, heat shrinkable caps and commissioning
tests, shall be included in contract prices as optional works. Cables and
terminations will be supplied by KAHRAMAA. Contractor shall coordinate with
concern KAHRAMAA department.

3.6.2.2 MODIFICATIONS AT SEMAISMA SUBSTATION

132/11kV Semaisma substation is an existing substation built under Phase 9 project


by Hyosung (Contract GTC/240B/2008). All modifications required due to LILO of the
existing 132kV cable line Khore South – Semaisma into Qatar Aerospace City 2 S/S
shall be carried out under this Contract.

The SOW includes but is not limited to the following:

- Testing and commissioning of the existing switchgear bays along with remote
Control Panels including indicating meters in the control panels, inscription of
additional alarm facia as required, replacing of switchgear name plates/ labels
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

- Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation to be made available between the stations based on requirement.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and remote signaling to NCC/ENCC

- All necessary co-ordination with the Phase IX cable Contractor (Siemens


Consortium) for LILO arangement of the EHV cables.

¾ SCS and Power Control Scope for remote end modification:

- Minor modifications to SCS supplied by Siemens under Phase 9 project to


include changes to 2 x 132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S work necessary for NCC/ENCC end to
end testing.

- Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

¾ Protection Scope for remote end modification:

For 2 x 132kV Cable feeders connected to Qatar Aerospace City 2 substation,


complete functional protection system as per Standard specification shall be
provided.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 160 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- In Semaisma substation, 132kV equipped bays, Main-1 Siemens make


7SD522 and Main-2 ABB make RED670 relays are provided for 132kV line
protection. The new relays/equipment shall be installed at Qatar Aerspace City
2 substation to match the protection provided at 132kV Semaisma substation
end.

- All modification, Testing and commissioning; end to end test are included in the
present Scope

- Contractor has to do the proper CT sizing calculation for KM review and


adequacy of existing CTs must be checked.

- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 161 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

3.7 PACKAGE S-7: TELECOMMUNICATIONS SYSTEM

3.7.1 INTRODUCTION

The works under the Phase 10 project includes substation works for establishment of
new transmission substations as well as refurbishment/ modification/ upgrade/
replacement of existing transmission substations, overhead lines works and
underground power cables works.

The substation works under the Phase 10, are grouped into Packages S-1, S-2, S-3,
S-4, S-5 and S-6.

Telecommunication System for some of Phase 10 substations, shall be provided by


Others the Phase 9, Contract GTC 240C but there is certain number of Phase 10
substations for which Telecommunication System shall be provided by this Tender as
specified hereafter.

3.7.2 SCOPE OF WORK


3.7.2.1 DESCRIPTION OF WORK

The works and services to be performed by the Contractor shall comprise the design,
manufacture, shop testing, packing, transport, insurance, unloading, storage at site,
construction works, erection, corrosion protection, site testing, submission of
documentation, commissioning, training of the Employer’s personnel and warranty of
works.

The Contractor is bound to provide complete works to provide a fully operational


system even if the equipment or services required for this are not specifically
mentioned in the following description of the scope of works.

The obligation of the Contractor is to fully inform himself about the existing
telecommunication system and to provide all necessary new equipments, upgrade of
existing equipments, network modification and/or reconfiguration for connection of the
new and refurbished substations as per Drawings reference TED-PH10-TEL-001 –
Rev. 10 Telecommunication Links Diagram.

The Contractor shall make the best design based on Power Transmission Network
and Fiber Optic availability.

The proposed design shall be based on the Power Transmission Network and shall
therefore consider necessary sizing of the Substations in terms of Optical
Termination, Optical Transmission System and cross connection facilities for potential
future expansion of the network.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 162 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

The Contractor shall meet Phase 10 S/S commissioning dates and therefore shall
establish telecom link to NCC/DCC as required in order to allow energization of S/S.
In case that approved design cannot be applied at S/S commissioning date because
of Fiber optic unavailability or any other reason, then the Contractor shall provide all
necessary temporary set up in order to establish the link on KM request.

The final design is subject to KM approval before manufacturing.

The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:

• Fiber optic cables connections.


• Required telecom services.
• Substation layout for fiber optic approach cables/Telecom room layout for
telecom panels.
• Power supply and telephone connection to the MUX equipment.

With other Contractors as follows:

- Phase 9: Substation Contractors (GTC/240A, B & D/2008), Cable Contractors


(GTC/241A&B/2008) and OHL Contractor (GTC/242/2008).

- Phase 9, Telecom Contractor (GTC/240C/2008).

- Phase 10: Substation Contractor(s), Cables Contractor(s) and OHLs Contractor.

The new fiber cables under this project shall be provided by the Phase 10: Substation
Contractor(s) GTC/371/2010, Cable Contractor(s) (GTC/372/2010) and OHLs
Contractor (GTC/373/2010) as follows:

- 1 x 24 / (48) cores FO cable associated with each new power cables.

- 2 x 48 cores OPGW cables for each new double circuit OHL.

The scope of work includes the following:

- Connection of New Substations to the telecommunication network.

- Connection of upgraded/replaced or modified substation by mean of new


telecommunication equipment and services.

- Network (Areva & ABB networks) modification/re-configuration resulting of cable


diversions, S/Ss dismantling, etc. and re-routing of all affected services. This also
includes NMS modification, PAX modification (Alcatel and Sopho), alarms to
SCADA, etc.

Only Personnel authorized by KM are allowed to work on telecom equipment.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 163 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

To enable the connection of these Substations to the existing telecommunication


Network, the following works shall be provided:

- Fiber optic cables.

- Fiber Optic Termination equipment FOPP / OTP.

- Pilot copper cables.

- SDH and PDH Equipment.

- Telephone equipment (in Areva and ABB Telecom networks).

- All KM Telecommunication management systems modifications or upgrading


resulting on modification of the KM network.

- Telecommunication power supply equipment.

- Recovery of all services affected by the insertion of a new S/S in the network.

- Recovery of telecom services (in Areva and ABB Telecom networks) due to cable
diversions and S/Ss dismantling.

- Works for telecommunication equipment dismantling.

- Updating of all Existing Drawings and update general documents such like
routing tables, overall network, IP addresses list, etc.

The detailed technical requirement for telecommunication system is given under the
General Technical Requirements and Technical Specifications in Volume 2 and
Volume 3, Section 3.3.11 of GTC/371/2010, Phase 10 Tender Documents.

3.7.2.2 SCOPE OF WORK

The Scope of Works is summarized as follows:

¾ Works for Fiber Optical cables:

- Works for Underground fiber optic approach cable between the Optical
Termination equipment (FOPP/OTP/OTB) in the substation telecommunication
room and the OPGW joint box closure (HOC - Hood Closure) located outside at
the overhead line gantry for all OHL links entering substations in addition to
FOPP/OTP works for the same.

- Works for fiber optic indoor cables to connect optical transmission equipment
(Protection, TSTU, SDH or PDH equipment) to optical termination equipment
(FOPP/OTP/OTB) at all stations.

¾ Works for optical termination equipment

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 164 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Fiber Optic Patch Panels (FOPP) and Optical Termination Panel Cubicle (OTP)
instead of wall mounted Optical Terminal Box (OTB).

- FO Termination and end to end Test shall be responsibility of the cable supplier as
follows:

1. Phase 10, GTC/371/2010 (Substations Package) is responsible in case of


Pilot Fiber Optic Cable laid along power cable inside substation
(Supply/installation, splicing at joint closures and OTP/OTB, including E2E
test OTP/OTB - OTP/OTB) or in case of approach cable within substation
area to cable compound (Supply/installation, splicing at Hood Closure on
Gantry and OTP/OTB, including E2E test OTP/OTB - OTP/OTB) as it has
been listed under price schedule for substation package.

2. Phase 10, GTC/371/2010, Telecommunication, Package S-7, under this


Tender is responsible in case of approach fiber optic cables
(Supply/installation, termination/splicing at OTP/OTB, splicing at Hood
Closure on Gantry including E2E test OTP/OTB - OTP/OTB) and in case of
fiber optic cables supplied between old and new S/S-s (Supply/installation,
splicing at joint closures, termination/splicing at OTP/OTB - OTP/OTB,
including E2E test OTP/OTB - OTP/OTB).

3. Phase 10, GTC/372/2010 is responsible in case of Pilot Fiber Optic Cable


(Supply/installation, termination/splicing at OTP/OTB including E2E test
OTP/OTB - OTP/OTB).

4. Phase 10, GTC/373/2010 is responsible in case of OPGW


(Supply/installation, splicing at OPGW Joint Closures, OPGW termination at
Hood Closure, without splicing, including E2E test Hood Closure - Hood
Closure).

¾ Works for pilot copper cables

Telecom Contractor shall provide the following for each pilot copper cable diversion of
existing double circuit Abu Hamur – Khalifa Sport Stadium South (KSSS) cable lines to
be Abu Hamur Super (AHS) –KSSS cable lines and for each pilot copper cable diversion
of existing double circuit Asmakh – Airport Super cable lines to be Barwa Al Doha –
Airport Super cable lines:

- 2MHz Barrier Transformers for connection to HDSL equipment.

- Terminal Box for installation of above barrier transformers and copper cable for
connection of Barrier Transformers Terminal Box and Pilot Copper Cable Terminal
Box.

- Screened twisted pairs copper cable for connection of barrier transformers and
telecom cabinet (HDSL equipment).

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 165 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Works for dismantling of existing Barrier Transformers, Terminal Boxes and 2MHz
Barrier Transformers at Abu Hamur S/S, Asmakh S/S, NEW DOHA B, NEW
DOHA C and delivering to KAHRAMAA stores packed and labeled as per KM
regulations.

¾ Works for SDH and PDH equipment

The works required shall include all necessary works to include the new and
refurbished/replaced/upgraded substations into the existing telecommunication network
as per drawing ref. “TED-PH10-TEL-001 – Rev.10 Telecommunication Links Diagram”,
Technical Specification section 3.3.11, and Appendix B – Price Schedule.

The drawing TED-PH10-TEL-001 – Rev. 10 Telecommunication Links Diagram indicates


the connections between substations. For more details, refer to OHL, Cables and
substations scope of works.

All S/Ss with fiber optic cable terminated shall have multiplexer equipment with optical
interface.

The scope of work is summarized as follows:

- Establishment of dual SDH links STM-1 or STM-4 (400/220 kV substation shall


have a STM-4 equipment as minimum). KAHRAMAA shall receive a detailed
design engineering of the telecom network for review and approval. A Telecom
design workshop is required after the award of contract to discuss the topology
before submission to KAHRAMAA.

- Each new and refurbished/replaced/upgraded Substations required the following


services to be transferred to NCC and DCC:

• Two PAX extensions one for NCC PAX and one for DCC PAX with
respectively 3 and 2 telephones connected in parallel at the substation (total 5
telephone sets and outdoor bell at each substation).

• Two IEC-104 64 kbps TCP/IP connections from SCS gateways to DCC


(SCADA).

• Two IEC-104 64 kbps TCP/IP connections from SCS gateways to NCC and
switching to ENCC (SCADA).

• One Ethernet connection (2Mb/s minimum) to NCC for TMS / RMS Monitoring
System.

• One Ethernet connection (2Mb/s minimum) to NCC for remote access to SCS
LAN at substation (For Fault recorder, Parameter settings …).

• One Ethernet connection connected to PMR file server at NCC and ENCC.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 166 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

• One Ethernet connection (2Mb/s minimum) to NCC for CCTV.

• Digital input alarm card with a minimum of 16 inputs.

• Engineering order wire; maintenance service telephone at MUX level.

• Connection to substation GPS for telecom equipment synchronization


purpose.

Exact channel requirements depend on the Substation and SCS design. Contractor shall
closely coordinate with Substation Contractor and SCS supplier to meet any of his
requirements with respect to communication channel to NCC, DCC and ENCC.

- Full works for Emergency switching to ENCC (Emergency National Control


Centre).

- Recovery of all services after the dismantling of any component or equipment or


when diversions are made.

- Any equipment not running any services to be dismantled and delivered to KM.

- Recovery services and network re-configuration for all the S/S connected above a
modified S/S in all affected KM network.

- All other necessary Extensions/modifications work in existing MUX equipment to


connect the new substations to NCC, DCC, ENCC or any other substations.

- All necessary works for migration of existing communication links and services to
the new location at all refurbished/replaced substations.

¾ Works for telephone equipment

- Works for telephone equipment at DCC telephone Exchanges and at NCC


telephone Exchanges to interconnect two (2) extensions at each new substation.
Extension shall be in 2 different cards in the MUX at substation side.

- Providing five executive tables/wall mounted Telephone sets at each station


paralleled together (three to NCC and two to DCC) and all necessary works to
connect to telecommunication equipment.

- One unit 240 V AC outdoor bell for each new and refurbished/replaced substation
and all necessary related works.

- Work for PAX configuration (Alcatel and Sopho) to fully interconnect the network.

- Maintain 20% spares or existing % of spares in case that less than 20% spares
are available in the KM Telphone System at NCC/DCC (Alcatel and Sopho).

¾ Works for Telecommunication Management System (TMS)

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 167 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- All communication system shall be compatible with the existing NMS systems.

- Works on existing Telecommunication Management Systems to include all new


telecommunication Equipment (allowing equipment monitoring, reporting,
controlling, configuring etc.).

- All necessary outstation equipment to connect telecom 48VDC power supply


(UPS at new and UPS or 48VDC at existing), Teleprotection and
Telecommunication Equipment alarms; TMS alarm list is to be approved by
KAHRAMAA (16 digital inputs minimum).

- Works shall include the Software and Hardware Modifications of one or more
existing TMS System to connect the new Substations.

- The NMS license should be upgraded for the required additional nodes keeping
20% spare.

- Respective NMS modification resulting of Network modification or node


cancellation.

¾ Works for teleprotection equipment (TSTU)

- Coordination activities only for data on existing TSTU if it is required to clarify


some of existing protection schemas.

¾ Works for telecommunication power supply equipment

The following to be included under telecom Contractors’ part:

- Works for connection of new telecom equipment to 240 V AC UPS as per LV


Service Equipment Volume 3, Section 3.3.5 of GTC/371/2010, Phase 10 Tender
Documents, provision of power cables from UPS MCBs to Telecom equipment
and provision of data cables between alarm terminal blocks at UPS and alarm
terminals blocks at Telecom equipment. No 48VDC power supply is required at
new substation.

- All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new equipment or modifications/upgrading of existing
equipment including, survey, calculations, connecting, documentation and DC
distribution extensions etc.

- All works for 240VAC UPS and 110VDC Batteries at relative existing substations
to accept new telecommunication equipment or modifications/upgrading of
existing equipment including, survey, calculations, connecting, documentation and
AC distribution extensions etc.

- The dismantled UPS, Batteries or Battery charger equipment shall be delivered to


KAHRAMAA stores packed and labeled as per KM regulations.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 168 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- 240 VAC / 48 VDC converter shall be sized with enough spare power capacity for
a fully equipped cabinet.

¾ Works for migration of existing telecom services at/or routed via


refurbished / replaced substations.

- Recovery of telecom services affected by OHLs/power cables dismantling and/or


connection's re-arrangement including Network optimization.
- Updating of Existing Drawings.
- Updating of all network drawings with the same existing format.

¾ Master Drawing shall be delivered updating the entire network delivered by


the Contractor during past project (including bulk consumers) in editable
format.

This shall include but not limited to:


- Overall updated Network
- Digital Block Diagram
- Routing Table
- IP addresses
- NMS network (IP and scheme)
- FO network and utilization
- Telephone network and numbering plan

- Updating of relevant existing sites (modified substations) drawings using same


existing format (accessible format; PDF or locked formats are not acceptable).
- Updating of All general documents such like routing tables, overall network, IP
addresses list etc.

3.7.2.3 SCOPE OF WORKS FOR NEW SUBSTATIONS

The new Substations to be connected to the KM telecommunication network are as


follows:

Package Name of substation

S1 QP HALUL - New 132/33kV (bulk consumer)


AL KARA'ANA - New 132/11 kV
MADINAT AL-KABAAN - New 132/11 kV
S2
AL-RUWAIS - New 132/11kV
AL ZUBARAH (future 400 kV GIS) - New 132/11 kV

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 169 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Package Name of substation

BARZAN CAMP 1 - New 132/11kV


BARZAN CAMP 2 - New 132/11kV
DOHA LAND 1 - New 66/11 kV
DOHA LAND 2 - New 66/11 kV
S4 SHERATON PARK - New 66/11 kV
Previously named Doha Conventional Center
BARWA AL DOHA - New 66/11 kV
NEW DOHA B SUPER - New 220/66/11kV
S5
ABU HAMOUR SUPER - New 220/66/11kV

Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the KM Telecommunication Network.

Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall
inform himself of Fiber Optic utilization and telecom network and to plan links
accordingly. This includes patching, network reconfiguration or any other action.

3.7.2.4 SCOPE OF WORKS FOR REFURBISHED / REPLACED /


UPGRADED SUBSTATIONS

NAME OF
PACKAGE SCOPE OF WORK
SUBSTATION
1. Works for disconnection of telecom link
between Khalifat South Sport Stadium
- KSSS (223) and Abu Hamur and re-
Phase 9, Khalifat South Sport connection of KSSS to network via new
GTC/240A/2008 Stadium - 223 copper pilot cable KSSS - Abu Hamur
North, including all necessary works at
Abu Hamur North.

1. Work for dismantling all


telecommunication system after Barwa
S4 Asmakh
al Doha is Energized.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 170 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

NAME OF
PACKAGE SCOPE OF WORK
SUBSTATION
1. Works for disconnection of telecom link
between Abu Hamur and Abu Hamur
Abu Hamur
East and network re-connection.

1. Works for disconnection of telecom link


between NEW DOHA C and NEW
S5 NEW DOHA C
DOHA B and network re-connection.

1. Work for dismantling all


telecommunication system after NEW
NEW DOHA B OLD
DOHA B SUPER is Energized.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 171 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

4. NOTES TO BIDDERS

Sequence of documents: In the case of any discrepancy between Tender


Documents, namely, Price Schedules and Scope of Works, Scope of Works is
prevailing.

Equipment/accessories: Notwithstanding absence, if any, of specific mention in the


Tender, all equipment/accessories with all support structures etc., as required to
meet the design requirement of this project are deemed to be part of the scope of
works. The end terminations shall be in line with the end equipment and chosen
appropriately after verifying the same.

Technical Requirement: The design, cable sizing etc., provided in the Tender
documents are only guiding principles. These shall be verified and it is the
responsibility of the prospective Contractor to ensure that the specified MVA rating
for each cable circuit is achieved by adopting appropriate method and/ or adequate
cable sizing, considering thermally independent cable circuits.

Technical parameters for all the equipment/ accessories required and offered shall
be filled in by Bidder even if certain specific formats are not provided in the Tender.

The total no of cable spans: The indicated cable spans are for pricing purposes.
However, necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage.

Good engineering practice in all works shall be adapted to KAHRAMAA’s


satisfaction.

Power cables for all voltage levels connecting different equipment within
substation shall be supplied and installed by the Substation Contractor which will
present nominated subcontractor for the Cable Contractor.

HV cables between the transformers and switchgears and between cable gantry
located within substation boundary to transformer / switchgear shall be laid in the
unfilled concrete cable trough which will be constructed by the substation civil works
subcontractor.

HV Connections between outdoor sealing end and SF6 wall bushing: The
Necessary Jumper for connection between outdoor termination and SF6 wall bushing
shall be part of scope of supply of substation Contractor.

EHV Connections, disconnecting and dismantling of existing termination and their


related accessories, to connect new cable shall be part of scope of work for
substation Contractor

Civil works: In addition to all related civil works along the cable route, construction of
all cable troughs/ concrete trenches, steel support, foundations, structures etc., for
cable sealing ends/ connections inside the substations for the cable feeder lines

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 172 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

(except foundations/ structures for equipments inside cable compound and OHL
gantry and cable ducts to buildings, Road Crossing ducts etc., inside substations) as
well as necessary coordination with the respective cable/ OHL Contractor(s) to
ensure technical and programme compatibility and compliance, shall be part of the
substation Contractor’s scope and responsibility.

Outdoor Cable Sealing End: Substation Contractor responsible for cable line
connection with outdoor type termination shall include following in their bid price for
outdoor sealing end connection at cable compound/gantry:

- respective foundation, steel structure and all necessary material and accessories,
surge arresters including their foundation and steel structure, all material required for
earthing of equipment and structure – connection to the earth grid, terminals for
connection to OHL down leads, removing of existing cables and sealing end, if any,
and all related civil works. In case that existing foundation is suitable to be used,
Contractor may propose such solution and appropriate structural calculation shall be
provided for KAHRAMAA approval. KAHRAMAA decision will be followed in this
regard.

Substation Contractor shall supply, install, erect and commission cable links within
substation as per execution plan of substation without any delay; all required
interface arrangement shall be cable Contractor responsibility.

Testing and Equipment: In addition to all related equipment required for cable
installation and commissioning test for cable feeders connected to GIS switchgear
and cable feeders to transformers as well as necessary coordination with substation
manufacturer/Contractor, the test bushing and degassing, and gassing and oil
filling/derange shall be part of the substation Contractor’s scope and responsibility.

Specifications, technical schedules and drawings: New route and relevant new
drawings are provided where necessary. For referring to the main contract
information, please note that Single line diagrams are in Appendix – F – Drawings,
Technical Specifications are in Sections 3.2 & 3.3 and Technical Schedules in
Section 3.4 of this Appendix.

Route Length: The quantities given for cable length in TED are approximated for
Tendering purposes and shall be adjusted according to actual results of survey.

Shutdown: The shutdown for diversion of cable circuits or connection of cable


circuits to existing substation shall be arranged by KAHRAMAA, circuit by circuit only,
according to requirement of KAHRAMAA network (operation & maintenance).

Earthing Continuity Conductor: Cross-section of earthing continuity conductor


should be provided in order to carry the full value of short circuit current, as specified.

Empty Cable Drums: KM is considering possibility that empty Cable Drums shall
remain property of Contractor. Accordingly, Contractor shall fill the cost deduction in
appropriate item in Price Schedules.
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 173 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

Fiber optic cable: A budget calculation note and cut over plan for divert the FO
cables shall be provided for KM approval.

Pilot cable: Installation of gland for termination of pilot cable at relay panel of 11kV
SWG is included in the Scope of substation Contractor.

Cable diversion: Substation Contractor will be responsible to check the existing


teleprotection cable to match with new diversion.

Dismantling of Oil Filled Cable to install new XLPE cable: the following shall be
under scope of work for substation Contractor:-

¾ Excavation and related civil work

¾ Removing oil tank

¾ Disconnect Gauge/manometer panels and control/alarm cables

¾ Cut and cap existing oil filled cables

¾ Remove the existing termination

¾ Delivery of dismantled material to KAHRAMAA store

Work inside Generation/industrial plant (Messaied, Dukhan and Ras Laffan) :


All activities/works inside Messaied, Dukhan and Ras Laffan subject require
permission from Messaied, Dukhan and Ras Laffan authority, work shall be
according to safety rules and regulations of Messaied, Dukhan and Ras Laffan,
authorise persons for holder required permit shall interview by Messaied, Dukhan
and Ras Laffan.

Alternative Offer (for HV Cable works): Optionally the Bidder is encouraged to


submit an alternative cost effective offer, if he wishes to do so, with complete design
justifications, calculations, parameters, drawings etc., as necessary. However, this
optional offer, if submitted shall be in addition to the main offer and not in lieu of it.
Bidders must use the same price schedule template with only change in the cable
conductor for this alternative offer. This shall be submitted in addition to the main
offer.

Warranty: In the event that a new cable requiring connection to an existing cable
which is under warranty by the original contractor, the new cable Contractor will make
arrangements with the original contractor of the existing cable to carry out the
connection and to follow prudent procedures in order to avoid the cancellation of the
remaining warranty period on the existing cable. The original contractor of the
existing cable is expected to be cooperative and Kahramaa will view any reluctance
from the original contractor as unacceptable behavior which will have impact on

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 174 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

future approval of bids by such contractor. The new cable Contractor guarantees that
their work will be conducted as per normal procedures and will be responsible for the
repair of any damage they may cause to the existing circuit.

Third Party Damage During Warranty Period: No reduction to the Warranty Period
"as specified in Article 9.51 of the GCC" for the Works or any part of the Works, shall
take place for whatsoever reason during the Warranty Period. The Contractor is
responsible to make good all defects that may arise, in accordance with Article 9.53
of the GCC. If third party damage to the Works or any part of the Works occurs;
KAHRAMAA and the third party shall be responsible for the repair of the damaged
works in accordance with KAHRAMAA standard regulations and the specification of
the Contract.

KAHRAMAA may instruct the original Contractor to perform the repair of any third
party damage to the Works or any part of the Works, if the Contractor accepts
KAHRAMAA instruction to perform the repair or remedy of any third party damage.
The cost of such repair shall be paid by KAHRAMAA to the Contractor and shall be
calculated based on the unit rates of the Contract or within a reasonable range of.

If KAHRAMAA performs the repair works through any of its reputable Contractors,
the repair work shall be performed under the supervision of the original Contractor if
available at seven (7) days notice. Costs of supervisor shall be based on unit rates
of the original Contract or reasonable range of. If the original Contractor does not
make available to KAHRAMAA the required resources for the repair work or the
supervisor within above notice period, KAHRAMAA may conduct the repairs without
further notice to the original Contractor or the presence of their supervisor or
representative but always in accordance with procedures agreed by KAHRAMAA and
the original Contractor and clearly specified in the original contract document, in
absence of which KAHRAMAA will operate within its standard practices.

The above repair works shall in no way be used by the Contractor as an excuse to
limit or terminate the Warranty of the Works or the repaired parts.

5. IMPORTANT NOTES APPLICABLE FOR ALL PACKAGES

Following documents included in section 3.3.8 of Volume 3 of this Tender may be


referred to understand KAHRAMAA requirements regarding equipment numbering,
interlock scheme, Protection energy meter & system control requirements for Bulk
customers and CT ratio for all voltage levels and bays:

¾ Interlocking Scheme - Transmission dept rev2 (16.10.08)

¾ Equipment numbering scheme_SOM T-08 T-28 revised

¾ ET-P26-G1 Guidelines for Protection Energy Meter Requirements for Power


Supply to Bulk Consumers
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 175 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ ET-P26-G2 Guidelines for System Control Requirements for Power Supply to Bulk
Customers

¾ Ph_9_CT Ratio for all voltage levels

All modification works at KAHRAMAA control centers NCC/ENCC/DCC to include


new and modified / upgraded / refurbished existing substations shall be included in a
separate contract GTC/375/2010. The scope of substation Contractors under this
project includes all necessary works inside the substations to complete the work
successfully. This includes co-ordination works with GTC/375/2010 Contractor and
Phase 9 Telecommunication Contractor during all stages until commissioning and
end to end test.

Note for refurbishment/ modification/ replacement of substation works:

It is planned to modify / replace / upgrade some of the KM substations in this project.


In case of some of the substations UPDA has allocated new sites adjacent to the
existing substations. Other substations are to be built within the boundary of existing
live substations. The Contractor shall adopt safety procedures related to work in live
environ. Wherever and whenever it is required to obtain outage of any circuit or part
of the substation the Contractor shall co-ordinate with transmission network
department to obtain necessary outage and safety documents. In this respect please
note that during the summer time, between months of April to month of October none
of the circuits on load can be released due to heavy load.

The Contractor shall plan his works to minimize Power supply interruption. The
dismantling and reconstruction shall be done in phased manner which has been
described in detail elsewhere. Where the shifting of respective 400kV, 220kV, 132kV
and 66kV OHL / Oil filled and /or XLPE cables work is allocated to another Contractor
under separate contract(s), all required co-ordination for work schedule, material
management etc shall be done with the other Contractor to complete the works in full
respect. The Contractor shall consider all such requirements and shall take all
necessary measures required for these works.

It may be noted that the diversion/ shifting of 11kV OHL / cable circuits, wherever
applicable, to the new substation is not within the scope of this contract unless
specified otherwise in detailed scope of works.

Wherever specified the Contractor shall supply set(s) of main protection relay e.g.
cable differential protection relay for each of the feeder for remote end stations.

If specified elsewhere some of the primary equipment (such as Reactor) may be


reused as per main scope of works. However completely new functional protection
system for ALL equipment is to be provided as per the specifications, standard
drawings and technical schedules. All 400kV, 220kV, 132 kV, 66 kV, and 11 kV
Cable / OHL feeders are to be shifted from existing substation to new switchgear.
Hence all protections at remote end substations must be changed to be compatible
with new protections as described under protection scope of works. An extensive site
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 176 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

survey may be carried out by substation Contractor to study detailed scope of work
to be undertaken at remote substations presently connected to the substation. In
case of underground cable feeders care shall be taken to choose proper protection(s)
to connect with existing oil filled cable / XLPE power cable and pilot cable /fiber optic
cable. Remote end substation(s) where panels are equipped with protections, the
required modification to make it functional and compatible with the new substation is
under the Contractor’s scope as described under protection scope of works.

6. EXTENT OF SUBSTATION CONTRACT

The project shall be executed as substation Contract. The works and services to be
performed by the substation Contractor shall comprise the design, manufacture, shop
tests, packing, transport, insurance, and charges incurred up to delivery to the port of
entry in Qatar, landing charges, customs, transport to Site, insurance, site clearing
and leveling, excavation, building road crossing ducts as required after detailed route
survey, cable laying and jointing, terminating, etc., in-fill, boundary wall, access
roads, drainage, sewage, construction works, erection of equipment, site testing,
submission of documentation, commissioning, training of KAHRAMAA ’s staff,
delivery of spare parts and tools, temporary site buildings and accommodation,
warranty and everything necessary to leave the plant complete and in full working
order at the expiration of the warranty period in accordance with the provisions of the
substation Contract.

The substation Contractor is bound to provide for all parts of the work to be
completed in every respect for commercial operation and to KAHRA-MAA’s
requirements notwithstanding that any details, accessories, etc. required for the
complete installation and satisfactory operation of the plant are not specifically
mentioned in the Specification. These are to be considered as included in the Scope
of Works and Contract Price.

6.1 SCOPE OF SUPPLY


The Scope of Supply is as specified in Technical Specifications, Technical
Schedules, and Appendix – B: Price Schedules and Appendix – F: Drawings.

The quantities indicated in the Schedule of Prices (Appendix B refers) and Drawings
(Appendix F refers) both attached to the Specification are provided for information
only. The substation Contractor is responsible to establish the exact details,
quantities of the equipment and accessories required to complete the whole of the
works as described throughout the Tender Documents, after the necessary
approvals.

General Technical Requirements are given in Section 3.2 of Appendix A, while the
specific requirements for the various equipment and works are set forth in Section
3.3 – Technical Specification and Section 3.4 – Technical Schedules of Appendix ‘A’.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 177 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

6.2 SCOPE OF SERVICES

The Scope of Services shall include but be not limited to the following:

¾ Preparation of the detailed specification for each piece of the equipment up to the
satisfaction of KAHRA-MAA before commencement of manufacturing;

¾ Establishment of the project administration and all site and installation procedures
as detailed in the Specification;

¾ Project site organization, at Doha and site offices, stores, local transport etc;

¾ Detailed soil investigation report and excavation of trial pits and testing of the
original soil properties, including thermal properties;

¾ Detailed site survey at the approved locations, detailed route survey (for
underground cables), preparation of appropriate topographical drawings and
establishment of the project set-up;

¾ Circulate the location map and civil/architectural design drawing and approval
requests to all concerned government authorities. Follow up and obtain such
approvals. Regular renewal of the approvals and work permits as necessary;

¾ Establish the subcontract agreement with the approved local civil Contractor.
Follow up and supervise the civil works and ensure timely and quality execution of
the works;

¾ Procurement of mutually compatible elements / accessories for all equipment and


installation of the same by competent personnel through active direct supervision
to ensure highest levels of quality and good engineering practice.

¾ Local transport storage and delivery to the site of the equipment;

¾ Manufacturing, factory acceptance tests, packing and transport to site;

¾ Interfaces with other Contractors of Phase 10 (GTC/371, GTC/372 and GTC/373)


and NCC control (GTC/375/2010) and equipment manufacturers at the existing
substations and make all necessary arrangement to facilitate the termination of
cables/OHL to the switchgear.

¾ Civil Works including

¾ Site survey, soils investigation work and testing of soils, water and materials used;

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 178 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Collection of information required for detailed design and construction, including


coordination with the various government ministries and departments, obtaining of
building permits, etc;

¾ Design, preparation of detailed construction drawings and bending schedules,


completion and maintenance of works;

¾ Earthworks, grading and landscaping;

¾ Site surfacing;

¾ Switchgear, control / relay buildings including all building services, compound wall,
gates, structure and plant foundations, cable ways, troughing and ducts;

¾ Temporary and permanent access roads to substation from public road and road
works within substation;

¾ Site lighting system, including security lighting, small power and lighting
installations. Fire detection & alarm system, FM200 system, passive fire protection
(fire sealant works & cable coating (for HV/ML/LV cables) inside the buildings and
fire protection system & transformer explosion prevention system for the
transformers & reactors shall be in accordance with KM HSE requirements

¾ All cables in basement shall be coated with fire resistance material

¾ To avoid damage of the power cable terminations in substation basement before


plugging in all male part termination sealing ends shall be covered with permanent
protective cap till plugging.

¾ In order to properly supervise the installation works permanent presence of your


power cables and accessories manufacturer is required. Checking of power cable
system prior to conducting LV and HV tests shall be performed by both main
contractor and the manufacturer.

¾ Air-conditioning and ventilation and smoke extract systems;

¾ Transformer compounds; construction of foundations for all transformers including


foundations for future transformers.

¾ Firewall between transformers;

¾ All necessary associated works;

¾ Guard Rooms.

¾ Installation of the equipment under the supervision of equipment manufacturers’


specialist technicians;

¾ Clearance of site;
VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22
TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 179 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

¾ Testing & Commissioning;

¾ Training of KAHRAMAA ’s staff.

¾ Defects Clearance;

¾ Provision of completion reports with the relevant documents;

¾ Documentation in accordance with the requirements;

¾ Warranty Period Services. The period of Warranty for all the works executed under
this shall be 2 years from the date of Taking Over.

The Warranty obligation and the warranty period shall NOT be changed or reduced
by any third party damages to the Works or any part of the Works, in case the
Contractor perform the repair of that damage or the damage has been repaired under
the supervision of the Contractor.

The Warranty obligation and the warranty period shall NOT be changed or reduced
by any third party damages to the Works or any part of the Works, in case the
Contractor perform the repair of that damage or the damage has been repaired under
the supervision of the Contractor.

6.3 REQUIRED DISTANCES IN GIS / CONTROL ROOMS

It should be noted that clearances in the GIS room and its final dimensions have to
be specified and confirmed by GIS manufacturer, considering GIS arrangement,
type, required space for testing, replacement of main components (such as circuit
breakers) if necessary, dimensions of specific GIS bays / components, arrangement
of pressure relief openings, etc. Drawings which clearly represent access to the
inspection points, testing arrangements, maintenance and replacement of main
components will be provided by Contractor as the base for building architectural
design.

Minimum clearance in the GIS / Control room as specified herein below are based
mainly on the regular maintenance and inspection requirements, conformity of
working space and safety requirement for minimum gangway distances.

Equipment arrangement shall be such to provide: min. personnel working area of 1m


and minimum widths of passageway 0.8m.

- All round clearance around the GIS: This space should ensure sufficient space for
the free moving of gas cart and mobile platforms. It should be min. 1.5m.
- At the entrance to GIS room, on the side of offloading area of equipment,
additional space has to be provided to enable transport of equipment inside the
GIS and handling by the crane. It should be min. 2.5m after the space for the last
future bay.

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 180 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

- Space around LCC: LCCs without requirement for the rear access are preferable,
since they require less space. In this case they can be aligned to the wall with
minimum clearance for the easier cooling (i.e. 5cm). Minimum distance between
GIS and LCC should be 2m.
- Depth of working space in the front of panels (control, protection, etc.): Min. 1.2m.
- If the panels are accessible from the rear side, minimum clearance to the wall
shall be 1m. In this case it is required that rear doors (if any) are all closing on the
same side and in direction of emergency exit which will enable fast evacuation of
persons from this area.
- If panels are arranged in two or more lines, with doors opening to the same aisle,
minimum distance between panels is 2m.
- Minimum free height of working space is 2m.

In addition to above, working space around GIS shall ensure the following for repair /
replacement:
- Sufficient horizontal free space shall be provided to facilitate removal of
components that are deemed to be withdrawn horizontally
- Similarly, sufficient vertical free space shall be provided to facilitate removal of
components deemed to be withdrawn vertically.

For 33kV and 11kV metal enclosed SWG with withdrawable components: From the
component in draw-out position minimum clear space shall be 1.5m.

6.4 INTERFACES BETWEEN CONTRACTORS

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR

A.1 GENERAL AND HV CABLES - DESIGN

Substation plot layout drawing with


1 x
coordinates
Cable Line Route drawing in SS vicinity with
2 x
coordinates

3 Matching of cable line route with plot layout x x

Substation plot layout drawing showing cable


4 x
routing inside SS
Substation basement layout drawing showing x
5 x
cable routing For existing SS
Provide road crossing drawing and duct
6 x
arrangement at s/s (if required)

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 181 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR

7 Provide fence crossing drawing x

Provide size / arrangement requirements for


8 x
the cable basement sleeves
Provide duct size and arrangement at s/s
9 x
basement and telecom room

10 Specify the cable bending radius x

Earthing grid layout drawing including details


11 x
about material and size of used conductors
Specify link box / link box support steelwork
12 requirements (include drawings and fixing x
details) and location.

13 Provide details of the cable support steelwork x

Provide GIS / Switchgear Bay details


14 x
(including section drawings)
Provide details of GIS / Switchgear Bay cable
15 x
termination kit compatibility
Cable Type (Three Core / Single core) and
Cable Construction - including cross section
16 x
drawings, details about material, cross-
sections, diameters, tolerances.
Specify no. of cables per phase and cable
17 x
formation details (Trefoil / Flat - spacing)
Provide details of 66 & 132kV GIS male size
18 x
and type for cable feeder and s/s cable links
Provide details of 66 & 132kV GIS female size
19 x
and type for cable feeder and s/s cable links
Matching of male - female cable termination
20 x x
connector parts

21 Provide transformer cable box details x

Provide details of the GA of the cable


22 termination and its fixing details (drawing to be x
supplied).
x
23 Switchgear Bay Allocation
and Kahramaa

24 Phase Identification x

25 Matching of phases on line terminal ends x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 182 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Identification of bays / (circuits and power x
26
transformer) numbers and Kahramaa

27 Matching of circuit numbers x

28 Specify GIS test bushing requirements. x

x
29 Specify cable HV test requirements

Specify safety clearance required during the


30 x
HV test as per KM Specifications.
Specify milestones for cable
installation/testing/commissioning required for
31 x
commissioning of substation (on individual
circuit basis).
Access for cable installation, preparation of
32 cable terminations, cable electrical and HVAC x x
testing.
Questionnaire for data required for protection
33 x
settings and milestone to provide required data

34 Reply to questionnaire for protection setting x

GENERAL AND HV CABLES - EQUIPMENT /


A.2
MATERIALS

1 Cable termination - female part x

2 Cable termination - male part x

Cable supports and cable cleats with fixing


3 x
material

4 Cable sleeves for basement x

5 Sealant for cable sleeves x

6 Ducts for road crossing inside SS x

7 Ducts for crossing under SS perimeter fence x

x x
8 HV Test bushing
For new SS For existing SS

9 Testing leads x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 183 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
All installation material up to and including
10 x
OTB / OTP
GENERAL AND HV CABLES - WORKS
A.3 (Including all tools and materials required
for completion)
Construction of cable trenches / ducts inside
1 SS from the perimeter fence to the GIS x
basement / transformer
Construction of cable ducts for roads and
2 x
fence crossing
Provision of free access for cable installation
3 and related civil works, preparation of cable x
terminations, electrical and HV AC testing

4 Installation and fixing of cable steel supports x

5 Cables installation x

6 Sealing of sleeves x

Gassing / de-gassing of GIS cable


x x
7 compartment and removing / establishing of
For new SS For existing SS
GIS testing link

8 Installation of Cable sealing ends x

Supervise
9 Cable termination to GIS / Transformer x
For new SS

10 Cable connection enclosure x

11 Enclosure flange or intermediate plate x

12 Seal x

13 Insulator collar or adaptor x

14 Intermediate gasket x (if needed)

15 Flange x (if needed)

16 Electrical stress control component x

17 Cable gland x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 184 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR

18 Non linear resistors x (if needed)

19 Insulating fluid x

20 Seal x

Installation and connections of Testing Supervise


21 x
equipment For new SS
Earthing bonds required for all GTC/372/2010
22 x
equipment (steel support, link boxes, etc.)

23 HV Test performance x

B FO CABLES

GTC/372/2010 FO cable design and all


1 x
technical details
GTC/371/2010 S/S FO cable design and all
2 x
technical details (in case of cable diversion)
GTC/371/2010 - Telecom FO cable design
3 and all technical details (in case of new and x
old buildings telecom connections)

4 Provision of S/S layout drawing x

5 Provision of telecom room equipment layout x

Specify OTB/OTP details (drawings and fixing


6 x x
details) and location
Specify OTB color to match with telecom
7 x
equipment
Specify FO cable routing inside S/S plot from
8 fence up to and including telecom room (to x
OTP/OTB)
Installation of OTBs included in the Scope of
9 x
GTC/372/2010
FO Patch cords from protection relays to
10 x
OTP/OTB
Splicing of all GTC/371/2010 S/S FO cables at
11 x
OTP / OTB including E-E test
Splicing of all GTC/372/2010 FO cables at
12 x
OTP / OTB including E-E test

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 185 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Splicing of all GTC/371/2010 Telecom FO
13 x
cables at OTP / OTB including E-E test
Milestones for FO laying, termination & end-to-
14 x
end testing
DTS SYSTEM – Not Applicable for New
C
Lines

1 DTS FO cable design and all technical details x

2 Provision of S/S layout drawing x

3 Provision of control room equipment layout x

Specify DTS FO cable routing inside S/S plot


4 from fence up to and including control room (to x
DTS panel)
Specify DTS Unit details (drawings, fixing
5 x
details, power supplies) and location

6 DTS unit connection to SCS x

x x
7 DTS unit connection to TCP/IP Router
For new SS For existing SS
Provision of power cables for DTS Equipment
8 x
supply

9 Milestones for FO laying, termination & testing x

Integration of DTS into integrated W/S for


10 CMS access (Provision of DTS remote access x
software)
Integration of DTS into integrated W/S for
11 CMS access (Implementation of DTS remote x
access software in W/S)

D TELECOM EQUIPMENT

1 Provision of S/S layout drawing x

2 Provision of Telecom room equipment layout x

Provision of Telecom room for installation of


3 x
Telecom equipment
Provision of cables between protection relays
4 x
and teleprotection equipment

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 186 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Provision of data cables between gateways of
5 SCS to connectors at interface cards on x
telecom equipment
Provision of TCP/IP connections for OMS
6 x
remote access and non-SCADA applications
Provision of telecom alarm connection cables
7 between SCS common bay controller and x
terminals block at telecom cabinet.
Provision of earthing system inside telecom
8 x
room as part of common earthing system
Provision of 240V, AC power supply cables
9 from station services supply up to telecom x
cabinets for aux. services
Provision of cable installation for non-critical
10 services such as PMR, CCTV, etc. for future x
connection to telecom equipment
Provision of 240V, AC UPS and MCB for
11 x
Telecom equipment supply
Provision of power cables from MCBs to
12 x
Telecom equipment
Provision of data cables between alarm
13 terminal blocks at UPS and alarm terminals x
blocks at Telecom equipment
Modification in 48V DC power supply for
14 x
telecom equipment in existing SS

E PILOT COPPER CABLES

GTC/372/2010 pilot copper cable design and


1 x
all technical details
GTC/371/2010 pilot copper cable design and
2 x
all technical details
Specify Pilot Copper Cable Terminal Box
3 details (drawings and fixing details) and x x
location
Specify Telecom Barrier Transformers
4 Terminal Box color to match with telecom x
equipment
Specify Pilot copper cable routing from
5 x
basement to telecom room
Installation of Pilot Copper Cable Terminal Box
6 x
included in the Scope of GTC/372/2010
Connection and Termination from protection
7 relays to Pilot Copper Cable Terminal Box x
(including Protection Barrier Transformer)

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 187 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION CABLE TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Connection and Termination from Telecom
8 Equipment to Pilot Copper Cable Terminal x
Box (including Telecom Barrier Transformer)
Termination of all GTC/371/2010 SS copper
cables at Pilot Copper Cable Terminal Box
including E-E test (Copper cable E2E test shall
9 x
include at least the following tests: Continuity
test, Isolation test, Attenuation test, Near End
Crosstalk, Far End Crosstalk)
Termination of all GTC/372/2010 copper
cables at Pilot Copper Cable Terminal Box
including E-E test (Copper cable E2E test shall
10 x
include at least the following tests: Continuity
test, Isolation test, Attenuation test, Near End
Crosstalk, Far End Crosstalk)
Milestones for Copper Cable laying,
11 x
termination & end-to-end testing

F NCC / ENCC / DCC CONNECTIONS

Configuration and testing of SCS for transfer of


1 x
signals to control centers from substation*
* NOTE: Configuration and testing of PCS
(SCADA) from Control centers is part of
separate contract

G ON LINE MONITORING SYSTEM (OMS)

Configuration and E-E testing of


1 x
telecommunication channels for OMS
Configuration and E-E testing of Remote
2 x
access for OMS

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR

A GENERAL AND HV CONNECTIONS

Cable Compound plot layout drawing with


1 x
coordinates

2 Cable Line Route from SS to cable compound x

3 Surge Arresters, outdoor CSE and link boxes x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 188 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR
Steel supports for surge arresters, CSE and
4 x
link boxes
Outline and dimension drawings for CSE, SA
5 and LB (equipment with support and x
foundation)
Cable compound detailed layout drawing and
6 x
cross-sections
Foundations for steel supports and surge
7 x
arresters

8 Cable compound earthing grid x

Earthing grid layout and data about conductor


9 x
used (material & sizing)
Earthing of surge arresters, CSE and link
10 x
boxes
Detailed documents of primary clamps
including drawings with dimensions and
11 x
material specification, installation instructions,
etc.
Clamps for primary connections of surge
12 x
arrester and CSE
Down leads from OHL gantry including
conductor branching clamps and primary
13 x
connections between HV equipment including
installation of clamps

14 Phase Identification x

x
15 Matching of phases on line terminal ends x

x
16 Identification of bays / circuits numbers
and Kahramaa

17 Matching of circuit numbers x x

Specify milestones for free access to cable


18 x
compound for Substation Part of works
Access in cable compound for substation part
19 x
of works
Questionnaire for data required for protection
20 x
settings and milestone to provide required data

21 Reply to questionnaire for protection setting x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.
SECTION 3.1
VOLUME 2 PAGE 189 OF 189
REV. 2

GTC/371/2010
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 10 - SUBSTATIONS

TITLE:- SCOPE OF WORKS Revision: 0

TO BE PROVIDED BY
INTERFACE POINT DESCRIPTION / SUBSTATION OHL TELECOM
Sl.No
REQUIRED ACTIVITY CONTRACTOR CONTRACTOR CONTRACTOR

B FO CONNECTIONS

GTC/371/2010 S/S FO cable design and all


1 x
technical details (in case of cable compound)
GTC/371/2010 - Telecom FO approach cable
design and all technical details (in case of
2 x
approach fiber optic cable to gantry located
inside substation)

3 OPGW cable design and all technical details x

4 Details about hood closure on OHL gantry x

5 Provision of S/S layout drawing x

Specify GTC/371/2010 S/S FO cable routing


6 from gantry inside cable compound up to and x
including telecom room (to OTP/OTB)
Specify FO approach cable routing from gantry
7 inside substation up to and including telecom x
room (to OTP/OTB)
Cable trenching passage for FO approach
8 cable from gantry inside substation up to and x
including telecom room (to OTP/OTB)

9 Installation of hood closure on OHL gantry x

Splicing of OPGW at joint closures and E-E


10 x
test (HC-HC)
Splicing of GTC/371/2010 S/S FO cable to
11 OPGW at hood closure (HC) and E-E test x
(OTP/OTB - OTP/OTB)
Splicing of FO approach cables to OPGW at
12 hood closure and E-E test (OTP/OTB - x
OTP/OTB)

13 Specify milestones for hood closure installation x

VOL 2 SEC 3 1 - SCOPE OF WORKS REV 22


TECHNICAL AFFAIRS
Electrical Projects Dept.

Вам также может понравиться