Вы находитесь на странице: 1из 11

BUILDING PROJECT SCOPE DEFINITION USING PROJECT DEFINITION

RATING INDEX
By Chung-Suk Cho1 and G. Edward Gibson Jr.,2 Members, ASCE

ABSTRACT: Poor scope definition is recognized by industry practitioners as one of the leading causes of project
failure, adversely affecting projects in the areas of cost, schedule, and operational characteristics. Unfortunately,
many owner and contractor organizations do a poor job of adequately defining a project’s scope leading to a
poor design basis. A research team constituted by the Construction Industry Institute (CII) has developed the
Project Definition Rating Index (PDRI) to address scope definition in the building sector. The PDRI for buildings
is a comprehensive, weighted checklist of 64 scope definition elements presented in a score sheet format. It
provides a tool for an individual or project team to objectively evaluate the status of a building project during
preproject planning. This paper will discuss the PDRI development process, including input from over 100
industry professionals. Key project scope definition elements will be identified. The PDRI validation procedure,
involving over 50 projects, will be discussed. A description of the potential uses of the PDRI and a summary
of its benefits to the building construction industry will be outlined.

INTRODUCTION • A 20% cost savings with a high level of preproject plan-


ning effort
Preproject planning is the project phase encompassing all • A 39% schedule savings with a high level of preproject
the tasks between project initiation to detailed design. Over planning effort
the past nine years, the Construction Industry Institute (CII)
has funded several research projects focused on preproject Because of the significant savings associated with improved
planning. Findings from these investigations have dramatically project predictability, the study concluded that a complete
changed the awareness of project management professionals scope definition prior to project execution is imperative to
within CII toward the importance of the process and the ben- project success.
efits of early project planning. Research results have shown A more recent CII research study focused on developing a
that greater preproject planning efforts lead to improved per- useful tool for measuring the level of project definition at the
formance on industrial projects in the areas of cost, schedule, time the project is authorized for final funding. This new tool,
and operational characteristics (Gibson and Hamilton 1994; the PDRI for Industrial Projects, is a project management tool
CII 1995; Griffith and Gibson 1995; Griffith et al. 1998). Syn- that assists in calculating a total score representing the level
thesizing these efforts was the development of the Project Def- of project definition. Developed specifically for industrial proj-
inition Rating Index (PDRI) for industrial projects, a scope ects such as refineries, chemical plants, power plants, and
definition tool that is widely used by planners in the industrial heavy manufacturing, the PDRI provides project team mem-
projects sector. bers with a structured approach for developing a good scope
One of the major subprocesses of the preproject planning definition package.
process is the development of the project scope definition The PDRI for Industrial Projects consists of 70 scope def-
package. Project scope definition is the process by which proj- inition elements in a weighted checklist format. The 70 ele-
ects are defined and prepared for execution. It is at this crucial ments are divided into three main sections and 15 categories
stage where risks associated with the project are analyzed and (Gibson and Dumont 1996; Dumont et al. 1997). The project
the specific project execution approach is defined. Success dur- team assessing the level of definition of each of the 70 ele-
ing the detailed design, construction, and start-up phases of a ments and a score is calculated; the lower the score, the more
project is highly dependent on the level of effort expended well defined the project. A score of 200 points or below using
during this scope definition phase (Gibson and Hamilton this tool was shown to statistically increase the predictability
1994). of project outcome. A sample of 40 projects using the indus-
Research has shown the importance of preproject planning trial version of the PDRI indicated that those projects scoring
on capital projects and its influence on project success. Find- below 200 versus those scoring above 200 had:
ings of a recent study have proven that higher levels of pre-
project planning effort can result in significant cost and sched- • Average cost savings of 19% versus estimated for design
ule savings. Specifically, the research study categorized 53 and construction
capital facility projects into three different intensities of pre- • Schedule reduction by 13% versus estimated for design
project planning effort and compared total potential cost and and construction
schedule performance differences as follows (CII 1994; Ham- • Fewer project changes
ilton and Gibson 1996): • Increased predictability of operational performance

With the success of the PDRI for industrial projects, many


1
Project Engr., ADP Marshall, 75 Newman Ave., Rumford, RI 02916.
building industry planners wanted a similar tool to address
2
Assoc. Prof. and Fluor Centennial Teaching Fellow, Dept. of Civ. scope development of buildings. CII constituted a team and
Engrg., Univ. of Texas, Austin, TX 78712. E-mail: egibson@mail.utexas. funded a research effort to facilitate this development effort.
edu The rest of this paper will introduce the PDRI for building
Note. Discussion open until May 1, 2002. To extend the closing date projects. The primary structure and format of the PDRI and
one month, a written request must be filed with the ASCE Manager of its development will be explained. This will be followed by a
Journals. The manuscript for this paper was submitted for review and
possible publication on January 9, 2001; revised July 30, 2001. This paper
brief synopsis of its validation on 33 completed building proj-
is part of the Journal of Architectural Engineering, Vol. 7, No. 4, De- ects and its use on 20 ongoing projects. The paper will con-
cember, 2001. 䉷ASCE, ISSN 1076-0431/01/0004-0115–0125/$8.00 ⫹ clude by describing the potential uses of the PDRI and sum-
$.50 per page. Paper No. 21939. marizing its benefits to building construction practitioners.
JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 115
BACKGROUND • Airport terminals
• Recreational/athletic facilities
Planning has long been a subject of discussion in the build- • Public assembly/performance halls
ing industry. Many guides have been developed and much • Industrial control buildings
knowledge resides with experienced practitioners (Griffin
1972; Pena 1987; Billings 1993; Preiser 1993; Haviland 1996;
Cherry 1999; ASCE 2000). However, early planning in many DEVELOPMENT OF PDRI FOR BUILDING PROJECTS
cases is not performed well in the building industry. Conse- Initial development work on the PDRI for building projects
quently, the building sector suffers from poor or incomplete began in June 1997 at the University of Texas using the PDRI
scope definition, frequently experiencing considerable changes for Industrial Projects as a basis. This effort included input
that result in significant cost and schedule overruns (Gibson and review from approximately 30 industry experts, as well
et al. 1997; Cho et al. 1999; Cho 2000). Because of these as extensive use of literature sources for terminology and key
problems, there existed a need for a better method of assisting scope element refinement (O’Reilly 1997). The 12 member,
in defining project scope. CII PDRI for Buildings Research Team, constituted in Feb-
The building industry is different from the industrial sector ruary 1998, refined and streamlined the list of PDRI elements
in various ways, such as the approach of planning, design, and and their descriptions, starting with the draft of 71 elements
construction of facilities; the owner’s perspective; the archi- to the final draft in December 1998.
tectural focus; and so on. Nonetheless, there are many simi- A complete list of the PDRI’s three sections, 11 categories,
larities. Like the industrial sector, the building industry suffers and 64 elements is given in Fig. 2. The 64 elements in the
from poor or incomplete preproject planning. As in the indus- PDRI for Building Projects are arranged in a score sheet for-
trial sector, planning in the building industry is a process that mat and supported by 38 pages of detailed descriptions and
needs to have input from a wide variety of individuals and checklists. The score sheet is given in Appendix I and will be
must have significant owner involvement. However, at the described in more detail later in this paper. A representative
time of this study, a quantitative understanding of scope def- example description for element G1, Equipment List, is given
inition issues for buildings had not been well-studied and no in Fig. 3. Due to limitations of space, the entire list of detailed
tool existed to help with scope definition. element descriptions are not included in this document.
As developed, the PDRI for Building Projects is a user-
friendly checklist that identifies and precisely describes each PDRI Element Weighting
critical element in a project scope definition package to assist
project managers in understanding the scope of work. It pro- The writers knew that the 64 elements within the PDRI were
vides a means for an individual or team to evaluate the status not equally important with respect to their potential impact on
of a building project during preproject planning with a score overall project success. Therefore, it was decided that the el-
corresponding to project’s overall level of definition. The ements needed to be weighted relative to each other to enhance
PDRI helps stakeholders of a project quickly analyze the scope their usefulness as a risk analysis tool. The method chosen to
definition package and predict factors that may impact project quickly develop reasonable and credible weights for the PDRI
risk specifically in regard to buildings. (CII 1999; Cho 2000) elements was to rely on the expertise of a broad range of
As illustrated in Fig. 1, the PDRI for building projects is de- construction industry practitioners marshaled together in work-
signed for use at varying times during the project’s lifecycle shops. The weighting development was therefore an inductive
prior to detailed design and development of construction doc- process in nature that incorporated expert input into develop-
uments. ing final weights.
This tool is applicable to multistory or single-story com- From July 1998 to October 1998, seven weighting work-
mercial, institutional, or light industrial facilities, such as: shops were held for this purpose, each lasting four hours. The
workshops involved a total of 69 experienced project manag-
• Offices ers, architects, and engineers with almost 1,500 total collective
• Schools (classrooms) years of building project expertise to help evaluate and weight
• Medical facilities the PDRI elements. The participants represented 35 owner and
• Research and laboratory facilities contractor organizations from the building construction sector,
• Institutional buildings consisting of 11 owners and 24 contractors. The participants
• Stores/shopping centers were volunteers and constituted a convenience sample put to-
• Dormitories gether using contacts and acquaintances of the development
• Apartments team. In addition to keeping a balance between owner and
• Hotels/motels contractor organizations, the research team attempted to invite
• Parking structures balanced numbers of groups with different educational back-
• Warehouses grounds to evaluate and weight the PDRI elements. The 69
• Light assembly/manufacturing workshop participants consisted of 30 individuals with engi-
• Churches neering backgrounds, 31 with architectural backgrounds, and

FIG. 1. Applicability of PDRI in Project Lifecycle, Typical Building Project

116 / JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001


FIG. 2. PDRI SECTIONS, Categories, and Elements

eight other professionals directly involved in planning building completed, the workshop participants were instructed to apply
projects (Cho et al. 1999; Cho 2000). what they felt to be an appropriate cost contingency to each
Each participant completed a series of documents at the element, given two circumstances—the element was unde-
workshops. In addition to personal history, they were initially fined (level of definition 5), or it was completely defined (level
asked to list and consider a typical project that they had re- of definition 1). The weighting was based on their opinions as
cently worked on for the organization they represented. Each to the relative impact that each element has on the overall
was then asked to assume that he/she was estimating this par- accuracy of the project’s total installed cost (TIC) estimate. All
ticular project and evaluating its probability of success based 64 elements were reviewed in this manner.
on the level of definition of the 64 elements. The workshop The workshop concluded with critiques of the scoring meth-
proceeded in order through the 64 elements with each element odology and the tool itself. These comments were subse-
reviewed and its description read. quently evaluated and several minor corrections were made to
Assuming that scope development for the project had been the score sheet, instructions for use, and element descriptions.
JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 117
FIG. 3. Example Element Description, G1. Equipment List

The raw weights obtained from these workshops were used level 5. Depending on how well the element is defined in the
to develop the final version of the PDRI score sheet. Each scope definition package, the PDRI score sheet user can check
participant’s responses at the workshop were individually eval- the appropriate definition level for a particular element, rang-
uated and normalized to a maximum of 1,000 points. This was ing from being completely defined to incomplete or poor def-
accomplished by adding all values in the ‘‘incomplete or inition.
poorly defined’’ column and converting those scores to values Adding up the individual element evaluations and their cor-
relative to one another that added to 1,000 points. A similar responding weights yields a single PDRI score for the project,
method was used to evaluate the elements when they had which can range from 70 to 1,000. The lower the total PDRI
‘‘complete definition’’ by normalizing to 70 points (which was score, the better the project scope definition. Higher weights
chosen to be consistent with the PDRI for industrial projects). signify that certain elements within the scope package lack
Definition levels 2, 3, and 4 were interpolated between the adequate definition and should be reexamined prior to con-
extremes. struction documents development.
A single, collective weight was developed for each of five
levels of definition of each element based using the mean of ANALYSES
the 69 responses. Several statistical tests were then performed
Analyzing Weighted PDRI
to evaluate the responses including simple descriptive statis-
tics, skewness, kurtosis, and variance analyses. In some cases, The three sections and 11 categories of the PDRI were
respondents were removed from the sample because their re- sorted in order of importance as shown in Table 1. The weight
sponses were far different from the overall sample. In the end, column corresponds to a summation of all definition level 5
59 of the 69 respondents were used to develop the final values for that category or section. In other words, if all ele-
weights, and the weighted PDRI score sheet is provided in ments in that section or category were incomplete or unde-
Appendix I (Cho 2000). An unweighted PDRI score sheet and fined, these would be the scores.
38 pages of element descriptions can be found in a separate Section II, Basis of Design, and Section I, Basis of Project
document entitled Project Definition Rating Index (PDRI), Decision, in combination, comprise 841 points, or approxi-
Building Projects (CII 1999). mately 84% of a potential of 1,000 points. This indicates the
The PDRI score sheet is used to evaluate the level of com- significance of having a sound basis of design and project
pleteness of the project scope definition at a point in time. decision prepared in the project scope definition package dur-
Each of the 64 elements is subjectively evaluated by key proj- ing the preproject planning phase, as identified by the work-
ect stakeholders during preproject planning based on its level shop panelists. It also signifies the importance of owner input
of definition versus its corresponding description. Six levels and active participation of critical owner stakeholders during
of definition are listed across the top of the PDRI score sheet, the planning stage of a project. The category weights sorted
creating a matrix with the 64 elements. These six definition in hierarchical order of importance indicate that Categories
levels, including level 0 for not applicable, range from com- A and E were deemed as the most important of the 11 cate-
plete definition for level 1 to incomplete or poor definition for gories, receiving 376 of the 1,000 total points. A list of 10
118 / JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001
TABLE 1. PDRI Section and Category Weights ement status at the beginning of construction document (CD)
Section Weights Category Weights development. These data were used to build profiles of the
sample and to assess the PDRI with regard to project success.
Section Weight Category Weight The PDRI for Building Projects was tested on a total of 33
II Basis of Design 428 A Business Strategy 214 completed projects varying in size from a final cost of $0.9
I Basis of Project 413 E Building Programming 162 million to $200 million, as shown in Table 3. The sample was
Decision a nonrandom sample from 10 organizations, with the PDRI
III Execution Approach 159 C Project Requirements 131
Total 1,000 F Building/Project Design 122 scored ‘‘after-the-fact.’’ These projects represented approxi-
Parameters mately $899.5 million in total constructed cost with a $26.8
D Site Information 108 million average.
B Owner Philosophies 68 Using an unweighted PDRI score sheet, the validation ques-
K Project Control 63 tionnaire respondents were asked to rate how well developed
L Project Execution Plan 60 each of the 64 elements were at the time the project was ready
G Equipment 36
H Procurement Strategy 25 to begin development of construction documents. This use of
J Deliverables 11 an unweighted scoresheet minimized the tendency of element
Total 1,000 weights to influence the evaluation process. Respondents in-
dicated their choice for each element by placing a check mark
in the box corresponding to the appropriate level of definition
TABLE 2. Ten Highest Weighted PDRI Elements on a scale ranging from 0 to 5. When the questionnaire was
Element returned, the writers converted this series of checks into a final
designator Element Weight project score.
A1 Building Use 44 The PDRI scores for 33 sample projects ranged from 74 to
A5 Facility Requirements 31 648 (from a possible range of 70 to 1,000) with a mean value
A7 Site Selection Considerations 28 of 203 and a median of 202. Among 33 sample projects, 16
A2 Business Justification 27 projects scored below 200 and remaining 17 scored above 200.
C6 Project Cost Estimate 27 The survey questionnaire captured detailed project information
A3 Business Plan 26 such as schedule, cost, changes, financial and investment in-
C2 Project Design Criteria 24
C3 Evaluation of Existing Facilities 24 formation, operating information, and customer satisfaction
A6 Future Expansion/Alteration Considerations 22 (Cho 2000).
F2 Architectural Design 22 The writers realize that project planning data used in the
sample were collected by relying on the respondent’s subjec-
tive recollections and, therefore, could be subject to biases.
highest weighted elements in descending order is shown in However, given the level of industry input in the tool devel-
Table 2. opment phase and the sample size, the results are adequate to
These 10 elements total 275 points, or approximately 28%,
of the 1,000 total points. (Each element has a corresponding TABLE 3. PDRI Validation Projects
detailed description which is not given here.) The 10 highest
weighted elements can be regarded as the most important el- Project Estimated cost PDRI
ements in the project scope definition package and, if poorly number Type of project (million $) score
or incompletely defined during early project planning, will 1 Office $10.0 256
have the greatest negative impact on project performance. If a 2 Recreational/athletic facility $32.6 96
3 Office $34.8 164
project team lacks the time for preproject planning prior to the
4 Warehouse $45.9 203
development of construction document and construction, these 5 Recreational/athletic facility $122.5 285
elements are the critical few that should be considered. 6 Stores/shopping center $200.0 460
Oftentimes, there is a tendency in the construction industry 7 Office $10.2 141
to skip several steps in the scope definition process in an at- 8 Office $8.7 130
tempt to reduce overall project cycle time. This may be due 9 Research/laboratory facility $0.9 208
10 Research/laboratory facility $0.9 202
to several reasons, such as lack of necessary expertise within
11 Research/laboratory facility $43.4 204
the organization, demand for the end product, or an unwill- 12 Industrial control building $25 126
ingness to commit the funds required for complete scope def- 13 Office $8.7 240
inition. If this happens, at least those critical few elements 14 Office $14.1 223
defined in Table 2 should be considered during preproject 15 Government border station $4.2 172
planning in order to meet the project objectives and reduce 16 Government border station $1.7 95
risk. 17 Courthouse $132.9 238
18 Store/shopping center $1.8 233
19 Fire station $1.6 218
PDRI VALIDATION 20 Retail/car dealership $1.6 158
21 School $23.1 102
Although the weights obtained for PDRI elements were 22 School $23.0 139
based upon the expertise of experienced project managers, ar- 23 Research/laboratory facility $3.3 149
chitects, and engineers, the tool needed to be tested on actual 24 Office $13.4 648
projects to verify its capabilities and value. In order to estab- 25 Research/laboratory facility $9.7 202
26 Seismic protection $16.1 188
lish an unbiased, reliable validation data sample from an an- 27 Warehouse $25.7 151
alytical and statistical standpoint, a number of both successful 28 Office $6.4 74
and unsuccessful projects were used for the validation. The 29 School $13.2 160
primary goal of the validation process was to correlate PDRI 30 Institutional building $18.1 205
scores with projects measured in terms of cost performance, 31 Recreational/athletic facility $24.2 238
schedule performance, change orders, and customer satisfac- 32 Public assembly/performance $18.2 165
33 Office $3.6 216
tion. A mail survey was used to collect quantitative and his- Totals $899.5
torical project data as well as ‘‘level of definition’’ PDRI el-
JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 119
provide an initial tool validation, pending further study in the 200 and the projects scoring below 200 prior to development
future. of construction documents, as shown in Table 4.
Performance is the mean percentage change in actual cost
Project Performance Analyses Using Target (contingency not included) and schedule performance as com-
PDRI Score pared with that estimated prior to development of construction
documents (CDs). The reported change order value represents
In order to determine a PDRI score that distinguishes suc- the cost increase/decrease during design and construction due
cessful and unsuccessful projects, several different PDRI sam- to change orders as an absolute value.
ple segregation points (e.g., 150, 200, and 210) were used to The validation projects scoring below 200 outperformed
test the mean performance differences. Using these segregation those scoring above 200 in three important design/construction
points, mean values of project performance variables were outcome areas: cost performance, schedule performance, and
compared at a 95% confidence level. The writers found statis- the relative value of change orders as compared with the au-
tically significant mean differences on several performance thorized cost. In addition to cost and schedule differences, the
variables when the segregation point of 200 was used. projects scoring less than 200 performed better financially, had
The authors consistently observed a statistically significant fewer numbers of change orders, had less turbulence related
difference in performance between the projects scoring above to design size changes during CD development and construc-
tion, and were generally rated more successful on average than
TABLE 4. Summary of Cost, Schedule, and Change Order projects scoring higher than 200. Additional performance data
Performance for PDRI Validation Projects Using 200 Point Cutoff are summarized in Table 5.
PDRI Score
Performance <200 >200 Difference
PDRI Validation Using In-Progress Projects
Cost 1% above 6% above 5% While the validation process as discussed was performed on
budget budget complete projects, the PDRI was also used by the writers and
Schedule 2% behind 12% behind 10%
schedule schedule research team members on current, ongoing projects in a group
Change orders 7% of budget 10% of budget 3% setting to observe its effectiveness in helping teams complete
(N = 16) (N = 17) preproject planning activities. It was used on a total of 20
projects at different stages of planning, as outlined in Table 6.
In each case, the PDRI gave project team members a viable
TABLE 5. Summary of Other Performance Data for PDRI Validation platform to discuss project-specific issues and helped identify
Projects Using 200 Point Cutoff critical planning problems on every project. Examples of prob-
PDRI Score lems identified included site-specific issues such as flood plain
encroachment, fire water pressure shortfalls, traffic flow prob-
Performance <200 >200
lems, permitting surprises, and setback problems. Example
Average PDRI score 138 264 building problems identified included poor equipment lists, in-
Average number of change orders 58 95 adequate space planning, undersized utilities, code violations,
Financial performance (scale of 1–5) 3.4 3.2
Average percent design size and design 100.1 99.1 and so on. These problems were identified at a point in the
size changes project when they could be addressed with minimal disruption
During CD development or constructiona 3 7 and cost.
Project success (scale of 1–5) 4.9 4.2 Specific observations include the following:
(N = 16) (N = 17)
a
Denotes number of projects with design size changes out of subsam-
ple.
• The PDRI can be used effectively more than once during
project planning.

TABLE 6. In-Progress PDRI Validation Projects


Estimated size
Project number Description (million $) Project phase used
1 Dormitory $52 After program development
2 R and D laboratory 3 At the end of design development
3 Dormitory renovation 13 After schematic design
4 Student union 7 After program and after design development
5 Distribution center addition 2 During CD development
6 Hotel renovation 12 During CD development
7 Manufacturing planta 62 Midway through planning, during design development
8 Manufacturing/assembly plant 144 Early in planning, prior to program
9 Manufacturing plant 57 Late in planning, prior to CD development
10 Manufacturing/assembly plant 60 Late in planning, prior to CD development
11 Manufacturing/assembly plant TBD Early in planning, prior to program
12 Child care center 1 Midway through CD development of design/build project
13 Medical research 37 During design development
14 Corporate campus 120 Fast track, late in design development; site work had commenced
15 Hangar upgrade 3 Midway through design development
16 Emergency backup power generation building 4 Just prior to detailed design
17 Upgrade chill water building 3 Midway through design development
18 Upgrade computer room 0.2 Just prior to detailed design
19 Office complex 34 Just prior to detailed design
20 Dining hall renovation 13 During design development
Total $627
a
PDRI used to plan ‘‘building’’ portion of projects 7–11.

120 / JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001


• The tool provides an excellent mechanism to identify spe- project’s weak areas. It can provide a benchmark for com-
cific problems and assign actions. parison against the performance of past projects in order
• Using the tool is an excellent way to align a project team. to predict the probability of future success. Project eval-
• The PDRI is effective even when used very early in the uation can be conducted by both owners and contractors
planning process. Individual planners can use the tool at either separately or together to ensure a fair assessment
this point to identify potential problems and to organize and a consensus among all stakeholders. The detailed el-
their work effort. ement descriptions in the tool provide an objective basis
• A facilitator provides a neutral party to help maintain con- for discussion regarding the need for additional informa-
sistency when scoring projects. tion in the scope package. This is important because often
• The team or individual scoring the project should focus facility owners are not aware of the level of definition
on the scoring process, rather than the final score, in order necessary for contractors to successfully complete the
to honestly identify deficiencies. project. Finally, it can be used as one indicator in making
the decision whether to authorize the project to move for-
HOW TO USE PDRI ward with development of construction documents and
construction.
Ideally, the project team gets together to conduct a PDRI • Scope Change Control: When used effectively, the PDRI
evaluation at various points during preproject planning. Ex- forces good, written scope definition. Therefore, when
perience has shown that the scoring process works best in a scope changes occur, the affected areas can be identified
team environment with a neutral facilitator familiar with the more easily. The PDRI allows the project team to refocus
process. This facilitator provides objective feedback to the effort during project execution on any elements that were
team and controls the pace of the meeting. If this arrangement not well defined early on and take appropriate action to
is not possible, an alternate approach is to have key individuals improve their definition. It also provides a basis for ‘‘les-
evaluate the project separately, then evaluate it together and sons learned’’ during future endeavors.
reach a consensus. Even an individual using the PDRI as a
checklist can provide an effective method for project evalua- CONCLUSIONS
tion (CII 1999).
The PDRI can be easily integrated into the early planning The PDRI is a scope development tool that applies to build-
process when project scope is developed and verified. Specif- ings such as institutional, offices, light manufacturing, medical
ically, the PDRI can help improve completion of the five major facilities, etc., in the project size range of $1–50 million and
subprocesses of preproject planning (scope management): ini- has been effectively used on larger as well as smaller projects.
tiation, scope planning, scope definition, scope verification, It is an effective tool that allows a planning team to assess the
and scope change control (PMI 1996; Dumont et al. 1997): probability of achieving project objectives during preproject
planning. It can be used as:
• Initiation: The PDRI can help define the overall project
requirements for developing and assembling the project • A checklist that a project team can use for determining
team. It can help all stakeholders involved in the project the necessary steps to follow in defining the project scope
understand scope definition requirements and objectives. • A listing of standardized scope definition terminology
The PDRI also can be used in developing a baseline for throughout the building construction sector
understanding the current level of project definition of the • An industry standard for rating the completeness of the
building. project scope definition package to facilitate risk assess-
• Scope Planning: The PDRI can help the project team de- ment and prediction of escalation, potential for dis-
termine which elements are the most critical in the build- putes, etc.
ing project scope package. The hierarchy of PDRI sec- • A means to monitor progress at various stages during the
tions, categories, and elements can form the basis of a front end planning effort
work breakdown structure (WBS) for proper scope plan- • A tool that aids in communication and alignment between
ning. The PDRI also assists in developing project mile- owners and design contractors by highlighting poorly de-
stones, standardizing terminology, and communication fined areas in a scope definition package
among project participants. The ultimate results of scope • A means for project team participants to reconcile differ-
planning will be a scope management plan and a scope ences using a common basis for project evaluation
statement. • A training tool for organizations and individuals through-
• Scope Definition: The PDRI provides a structured ap- out the industry
proach to project scope definition for building projects. • A benchmarking tool for organizations to use in evaluat-
Detailed element descriptions in a checklist format help ing completion of scope definition versus the performance
ensure that each appropriate element is adequately ad- of past projects, both within their organization and exter-
dressed. The PDRI can be used to score the completeness nally, in order to predict the probability of success on
of the project scope package during the planning process future projects
in order to measure progress, assess risk, and redirect fu-
ture effort. It also can assist in assigning work responsi- The PDRI can assist owners, developers, designers, and
bilities to the scope definition WBS. contractors. Facility owners, developers, and lending institu-
If the organization has well-documented preproject tions can use it as an assessment tool for establishing a comfort
planning procedures and standards in place, many of the level at which they are willing to move forward on projects.
elements may be partially defined when project planning Designers and constructors can use it as a means of negotiating
begins. An organization may want to standardize many of with owners in identifying poorly defined project scope defi-
the PDRI elements as much as possible to improve cycle nition elements and to develop a written, detailed basis for
time of planning activities. design.
• Scope Verification: PDRI scores reflect the quality and The planning process is inherently iterative in nature and
completeness of the project scope package from the proj- any changes that occur in assumptions or planning parameters
ect participant’s perspective. Analysis of these scores can need to be resolved with earlier planning decisions. The PDRI
facilitate risk assessment by highlighting the building provides a forum for all project participants to communicate
JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 121
and reconcile differences using an objective tool as a common that the PDRI along does not ensure project success, but
basis for project scope evaluation. The PDRI target score (200 should be coupled with sound business planning, alignment,
points) may not be as important as the team’s progress over and good project execution to greatly improve the probability
time in resolving issues that harbor risk. It should be noted of meeting or exceeding project objectives.

APPENDIX I. PDRI FOR BUILDINGS SCORE SHEET, WEIGHTED

122 / JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001


JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 123
ACKNOWLEDGMENTS REFERENCES
The writers would like to thank CII and the members of the CII PDRI American Society of Civil Engineers (ASCE). (2000). Quality in the con-
for Building Projects Research Team for supporting this research inves- structed project—a guide for owners, designers, and constructors, 2nd
tigation. Without their assistance, this work would not have been possible. Ed., Reston, Va.
Chung-Suk Cho was formerly a graduate student in the Department of Billings, K. (1993). Master planning for architecture, Van Nostrand Rein-
Civil Engineering at the University of Texas at Austin. hold, New York.

124 / JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001


Cherry, E. (1999). Programming for design: from theory to practice, Wi- Gibson, G. E., and Hamilton, M. R. (1994). ‘‘Analysis of pre-project
ley, New York. planning effort and success variables for capital facility projects.’’ Rep.
Cho, C. S., Furman, J. C., and Gibson, G. E. (1999). ‘‘Development of Prepared for Construction Industry Institute, University of Texas at
the project definition rating index (PDRI) for building projects.’’ Res. Austin, Austin, Tex.
Rep. 155-11 Prepared for Construction Industry Institute, University Gibson, G. E., Liao, S., Broaddus, J. A., and Bruns, T. A. (1997). ‘‘The
of Texas at Austin, Austin, Tex. University of Texas System capital project performance, 1990–1995.’’
Cho, C. S. (2000). ‘‘Development of the project definition rating index OFPC Paper 97-1, University of Texas System, Austin, Tex.
(PDRI) for building projects.’’ PhD thesis, Dept. of Civ. Engrg., Uni- Griffin, C. W. (1972). Development building: the team approach, Wiley,
versity of Texas at Austin, Austin, Tex. New York.
Cho, C. S., and Gibson, G. E., Jr. (2000). ‘‘Development of a project Griffith, A. F., Gibson, G. E., Hamilton, M. R., Tortora, A. L., and Wilson,
definition rating index (PDRI) for general building projects.’’ Proc., C. T. (1999). ‘‘Project success index for capital facility construction
Constr. Congr. VI, ASCE, Reston, Va., 343–352. projects.’’ J. Perf. Constr. Fac., ASCE, 13(1), 39–45.
Construction Industry Institute (CII). (1995). ‘‘Pre-project planning hand- Haviland, D., ed. (1996). The architect’s handbook of professional prac-
book.’’ Special Publ. 39-2, Austin, Tex. tice. Volume 2: The project, American Institute of Architects, Washing-
Construction Industry Institute (CII). (1999). ‘‘Project definition rating ton, D.C.
index (PDRI), building projects.’’ Implementation Resour. 155-2, Aus- O’Reilly, A. (1997). ‘‘Project definition rating index for buildings.’’ MS
tin, Tex. thesis, University of Texas at Austin, Austin, Tex.
Dumont, P. R., Gibson, G. E., and Fish, J. R. (1997). ‘‘Scope management Pena, W. (1987). Problem seeking: an architectural programming primer,
using project definition rating index.’’ J. Mgmt. Engrg., ASCE, 13(5), 3rd Ed., AIA Press, Washington, D.C.
54–60. Preiser, W. F. E. (1993). Professional practice in facility programming,
Gibson, G. E., and Dumont, P. R. (1996). ‘‘Project definition rating index Van Nostrand Reinhold, New York.
(PDRI).’’ Res. Rep. 113-11 Prepared for Construction Industry Insti- Project Management Institute (PMI). (1996). A guide to the project man-
tute, University of Texas at Austin, Austin, Tex. agement body of knowledge, Upper Darby, Pa.

JOURNAL OF ARCHITECTURAL ENGINEERING / DECEMBER 2001 / 125

Вам также может понравиться