2. Monitoring energy usage To track overall energy usage Identify and eliminate waste Identify saving opportunities 3. Replacing R22 refrigerant to hydrocarbon refrigerant Improve aircond’s electricity consumption – Target saving 12% to 30% 4. Preparation and release of complete POC report Projected savings for KPTM HQ 5. Presentation on POC & Sign off Audit Report
Project Schedule
16 October 2017 Start installation of energy monitoring system.
23 October 2017 Monitoring energy usage. 27 November 2017 Replacing R22 refrigerant to hydrocarbon refrigerant. 27 December 2017 Monitoring energy usage by Replacing R22 refrigerant to hydrocarbon refrigerant. 4 January 2017 complete POC report/ Presentation on POC & Sign off Audit Report.