Вы находитесь на странице: 1из 8

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 23 (2005) 538–545
www.elsevier.com/locate/ijproman

Critical determinants of construction tendering costs:


Quantity surveyorsÕ standpoint
a,*
T.M.S. Elhag , A.H. Boussabaine b, T.M.A. Ballal c

a
School of Mechanical, Aerospace and Civil Engineering, University of Manchester, P.O. Box 88, Manchester M60 1QD, UK
b
School of Architecture and Building Engineering, University of Liverpool, Liverpool L69 3BX, UK
c
School of Construction Management and Engineering, University of Reading, P.O. Box 219, Reading RG6 6AW, UK

Received 19 October 2004; received in revised form 7 December 2004; accepted 12 April 2005

Abstract

Identification of cost-determinant variables and evaluation of their degree of influence play an essential role in building reliable
cost models and enhance the competitive edge of quantity surveyors as well as contracting organisations. Sixty-seven variables
affecting pre-tender construction cost estimates are identified through literature and interviews. These factors are grouped into
six categories and a comparison analysis of their impact is conducted. Priority ranking of cost-influencing factors is carried out using
a questionnaire survey commissioned amongst quantity surveyors based in the UK. Findings of this survey indicate that there is a
strong agreement between quantity surveyors in ranking cost-influencing factors of construction projects. Comparisons between the
outcomes of this research and other related studies are presented.
Ó 2005 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Cost-influencing factors; Pre-tender cost estimates; Severity index; Concordance analysis; Construction projects

1. Introduction ever, most of the significant factors affecting project costs


are qualitative such as client priority on construction
Cost estimation is an experience-based process. Con- time, contractorÕs planning capability, procurement
struction practitioners are aware of uncertainty, incom- methods and market conditions including level of con-
pleteness and unknown circumstances of factors struction activity. Due to the qualitative nature of these
affecting construction costs. Realisation and under- factors, they are difficult to structure and quantify. De-
standing of cost-determinants enrich the competence spite their importance, most of these factors are often ig-
of cost estimators, and hence along with decent cost nored by current forecasting techniques. Only some of
forecasting techniques, deliver more reliable and accu- those techniques which include a risk assessment element
rate cost estimates. usually consider some qualitative factors.
A wide range of cost forecasting techniques has been A great deal of research approaches factors affecting
exploited in the construction industry. A major limitation cost of construction projects from different angles.
of most of these models is that they only take account of Naoum [11] investigated whether the means of procure-
significant factors that can be readily quantified. How- ment influenced project performance. The study con-
*
ducted a comparison analysis of project performances
Corresponding author. Tel.: +44 161 3064634; fax: +44 161 for management and traditional contracting in the
3064646.
E-mail addresses: taha.elhag@manchester.ac.uk (T.M.S. Elhag),
UK. Project performance was measured by way of 10
a.h.boussabaine@liverpool.ac.uk (A.H. Boussabaine), t.ballal@ factors including, unit cost of building, cost overrun
reading.ac.uk (T.M.A. Ballal). and client satisfaction with cost. A model was developed

0263-7863/$30.00 Ó 2005 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2005.04.002
T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545 539

linking various project performances with different char- A number of other studies investigated factors affect-
acteristics of construction projects. The study concluded ing cost overruns. Dissanayaka and Kumaraswamy [4]
that there was not enough evidence to suggest that man- evaluated the relative influences of critical procurement
agement contracting can reduce the overall cost. Fur- and non-procurement related factors on cost perfor-
thermore, the study concluded that in order to deliver mance in a sample of Hong Kong based building pro-
better project performance and success, relationships be- jects. Using multiple linear regression, they found that
tween procurement methods on one hand and type of cost overruns are influenced by; levels of client confi-
client and project type, size, complexity and cost on dence in the construction team, risk retained by client
the other hand need to be realised. However, this study for quantity variations, levels of construction complex-
fell short of investigating the underlying critical determi- ity related new technology and payment modality. These
nants of unit costs of building or of factors affecting cost factors were then used to develop artificial neural net-
overruns under each procurement scheme. work models for predicting cost indices.
Moselhi et al. [10] developed an analogy-based model Factors influencing construction cost overruns on
for bidding strategy which mainly estimates an optimum high-rise projects in Indonesia were investigated by
mark-up percentage and a win/lose probability. The deci- Kaming et al. [8]. Project managers were consulted, via
sion support system also anticipates project profitability a questionnaire survey, to assess the different variables.
in Canada and USA. The model depends on 30 attri- The identified variables were then ranked according to
butes, which significantly influence decision-making at their perceived importance and frequencies of occur-
the tendering process stage. A detailed comparison be- rence. Using factor analysis techniques, causes of delay
tween these attributes and cost-influencing factors reveals and cost overrun were successfully grouped into factors
that a number of attributes are highly relevant, albeit in a (main categories). Inflationary increases in material cost,
different way, in the estimation of construction costs. inaccurate material estimating and project complexity
Okpala and Aniekwu [13] investigated causes of high were found to be the main causes of cost overruns. This
costs of construction in Nigeria. The study revealed 27 study relied on the judgements of project managers for
factors contributing to high costs and delays in comple- the identification of factors associated with cost over-
tion time. A questionnaire survey was conducted which runs. However, no attempt had been made to consult
included engineers, architects and quantity surveyors. cost estimators or quantity surveyors who primarily deal
The rankings of the influencing variables by the three pro- with costs.
fessions were found to be fairly similar, despite some dif- This paper assesses and ranks cost-influencing fac-
ferences in their views. The professionals generally agreed tors of construction projects at the pre-tender stage
that shortage of materials, methods of financing and pay- for building projects in the UK. A questionnaire meth-
ments for completed works and poor contract manage- odology was adopted to extract the views of a ran-
ment were the three major reasons for high construction domly selected sample of quantity surveyors in the
costs and delays. The top ranked factor was identified UK. The questionnaire was sent to 218 UK quantity
as price fluctuations. The factors identified in this study surveyors and 31% response rate was achieved. In
are largely influenced by the locality of the country in addition, the paper describes statistical analyses of
which the research was conducted. As discussed later in the survey, which include severity index and KendallÕs
this section, under-developed economies tend to exert dif- concordance test. The results indicate that there is a
ferent influences on construction costs compared to strong agreement between quantity surveyors in rank-
developed economies such as the UKÕs. This has a major ing cost-influencing factors.
impact upon critical determinants of construction costs.
Elinwa and Buba [7] investigated construction cost fac-
tors in Nigeria. A questionnaire survey was conducted, 2. Methodology of study
which involved architects, engineers and quantity survey-
ors. Thirty-one variables were assessed, and analyses of A two-stage research methodology was adopted:
results showed good agreement between the responses. First, literature survey and interviews with quantity sur-
The top ranked factors, which contributed to construc- veyors in the north of England were conducted to iden-
tion cost, included: cost of materials, fraudulent practices tify factors affecting the cost of construction projects.
and fluctuation in prices of materials. These semi-structured interviews were regarded as pilot
Some of the factors which ranked high amongst those study to adjust and modify the questionnaire manu-
affecting construction costs in Nigeria [13,7], such as script before posting it to quantity surveyors nation-
fraudulent practices and fluctuation in prices of materi- wide. Sixty-seven factors were selected; they were
als, are not always relevant in other countries particu- grouped into six different categories:
larly in the UK where there are tight control of
procurement systems, mature regulations and a stable  client characteristics,
economy with low inflation.  consultant and design parameters,
540 T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545

 contractor attributes, comparing relative variability of different responses [6].


 project characteristics, Its value is computed following Eq. (2):
 contract procedures and procurement methods, S
 external factors and market conditions. COV ¼   100%; ð2Þ
X
Second, a questionnaire methodology was adopted to where COV stands for coefficient of variation, S the
evaluate and rank these factors according to their influ- standard deviation and X the weighted mean of sample.
ence and significance regarding the tender cost estimates Statistical results show that variation of responses
of construction projects. The questionnaire survey was regarding factors affecting project cost is relatively
post mailed to 218 quantity surveyors in the UK. The low, as indicated by the coefficient of variation. This is
mailing list was obtained from the Royal Institute of a good indication and it shows a relatively high agree-
Chartered Surveyors (RICS). The response rate for the ment between quantity surveyors. This issue will widely
questionnaire survey was 31%. This response rate came be analysed using KendallÕs concordance statistical tech-
on the top range of the normal rate of 20–30% for most nique. All 52 factors identified earlier have coefficient of
postal questionnaire surveys of the construction indus- variations ranging from 10% to 40%. Relatively higher
try [1]. For assessing the degree of influence of each var- coefficients of variation, ranging between 30% and
iable a three-point scale is used as follows: 50%, are computed for the remaining 15 factors, Tables
1–6.
1 = (not significant),
2 = (moderately significant), 4.1. Kendall’s concordance test
3 = (highly significant).
The measure of the relationship between rankings of
cost factors for each category will describe the agree-
3. Analysis and ranking of cost factors ment or concordance between the quantity surveyors
in their judgements on each category of factors.
Severity index computation is used to rank the fac- KendallÕs coefficient of concordance (w) provides a
tors according to their significance in affecting cost. It measure of agreement between quantity surveyors, and
is illustrated by Eq. (1) below: concordance between rankings of cost-determinants. It
! ranges between ‘‘0’’ and ‘‘1’’, with ‘‘0’’ indicating no
X
3
100% agreement and ‘‘1’’ designating perfect concordance. It
SI ¼ wi  fi  ; ð1Þ is illustrated by Eq. (3) as follows [16]:
i¼1
n
12  s
where i represents the ratings 1–3, fi the frequency of re- w¼ 2
; ð3Þ
sponses, n the total number of responses and wi the k  n  ðn2  1Þ
weight for each rating (Fig. 1).
where s is the sum of squares of deviations of factors, k
Tables 1–6 summarise the findings of statistical anal-
the number of quantity surveyor groups, n the number
ysis. It shows that 52 factors maintained a severity index
of factors in each category.
between 65% and 95%. The remaining 15 factors have a
In order to undertake KendallÕs concordance test the
severity index in the range of 50–65%. This indicates
quantity surveyor responses were divided randomly into
that out of the 67 factors identified, 52 are regarded
three different groups. Accordingly, the six different cat-
by quantity surveyors as highly relevant for cost fore-
egories of cost-determinants were then ranked sepa-
casting of construction projects.
rately. SPSS software was used to carry out KendallÕs
concordance test. Table 7 depicts the statistical findings
of this analysis.
4. Measuring quantity surveyors concordance
It is shown that those values of KendallÕs coefficient
(w) range between 0.88 and 0.98 for the six categories.
Coefficient of variation (COV) expresses the standard
These high values of KendallÕs coefficient indicate strong
deviation as a percentage of the mean, and it is useful in
agreement between quantity surveyors on ranking of
factors affecting cost of construction projects. The val-
ues of significance level are computed between 0.0149
and 0.0001. These values indicate that, the null hypoth-
0 w1=1/3 w2=2/3 w3=3/3
esis: there is no agreement between quantity surveyors,
has to be rejected (p < 0.05). The alternative hypothesis
that, there is a significant agreement between quantity
Fig. 1. Weights for each rating. surveyors, is acceptable with confidence limit p > 95%.
T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545 541

Table 1
Ranking of client characteristics
Factors Coefficient of variation Severity index Category ranking Overall ranking
Client characteristics
Type of client (public/private/developer) 24.99 80.53 4 16
Financial ability/payment record 37.32 65.73 8 53
Project finance method/appropriate funding in place on time 32.53 75.07 5 28.5
Partnering arrangements 30.61 69.80 6 41.5
Priority on construction time/deadline requirements 15.59 92.17 1 3
Experience of procuring construction 30.46 67.63 7 49
Client requirements on quality 20.39 82.87 3 11
Certainty of project brief 23.38 86.17 2 10

Table 2
Ranking of consultant and design parameters
Factors Coefficient of Severity Category Overall
variation index ranking ranking
Consultant and design parameters
Completeness and timeliness of project information (design, drawings, specifications) 15.96 91.67 2.5 4.5
Buildability of design 25.07 79.60 5 18
Working relationships with client/contractors/other design team consultants (previous/present) 24.62 75.07 7 28.5
Variation orders and additional works (magnitude, timing, interference level) 18.18 91.67 2.5 4.5
Quality of design and specifications 17.92 88.90 4 7
Inspection, testing and approval of completed works (toughness/requirements) 42.28 61.10 8 58
Submission of early proposals for costing/cost planning 28.97 76.87 6 25
Absence of alterations and late changes to design (no ‘‘design-as-we-go’’ on site philosophy) 13.34 94.43 1 1

Table 3
Ranking of contractor attributes
Factors Coefficient of Severity Category Overall
variation index ranking ranking
Contractor attributes, firmÕs ability and site management
Management team (suitability, experience, performance) 14.29 93.53 1 2
Management/labour relationships and Confidence in work force 27.09 77.80 4 22
Financial capability 32.16 72.20 6 34
Experience on similar projects 22.83 81.97 2 13
Current work load 31.98 70.50 8 40
Level of communications within the contractor organisation 30.46 67.63 10 49
Estimation method and cost control technique (accuracy and reliability) 41.56 60.80 11 59
Planning capability and level of resource deployment/utilisation/optimisation 25.37 78.43 3 20
Productivity effects (managerial, organisational, labour, technology) 34.65 71.57 7 35
% of main contractor direct work and % of subcontracted work 37.05 58.83 12.5 61.5
Number of subcontractors 37.48 54.23 15 64
Mark up policies and % (general and project wise) (special or normal conditions applied) 33.16 50.97 17 66
Record of payments to subcontractors 37.05 58.83 12.5 61.5
Previous claims record i.e., assessment of ‘‘low tender’’–‘‘high claims’’ performance 33.05 77.47 5 23
Present claims (size and quantity) 39.06 69.80 9 41.5
Accidents on sites record 51.77 48.03 18 67
Bond/warranty arrangements 44.75 58.10 14 63
CDM regulations awareness 44.19 53.33 16 65

5. Discussion of results 67%. This indicates that the quantity surveyors perceive
that the architects and designers have more influence on
A comparison of average severity indices is portrayed construction project costs than the contractors. This
in Fig. 2 [5]. The top ranked category is found to be con- outcome is consistent with many literature views that
sultant and design parameters with an average severity the project costs are more determined by decisions at
index of 82%. On the other hand, the contractor attri- the briefing, feasibility and initial design stages rather
butes group scored the least average severity index of than by later construction stages [2,14,3]. The following
542 T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545

Table 4
Ranking of project characteristics
Factors Coefficient of Severity Category Overall
variation index ranking ranking
Project characteristics
Type/function (residential, commercial, industrial, offices) 35.75 68.63 13.5 44.5
Size/gross floor area 33.15 74.53 8 30
Height/no. of stories 31.35 75.50 7 27
No. of basement levels 31.89 82.30 3 12
Level of uncertainty of soil conditions 25.11 81.37 4 14
Complexity 24.77 87.87 2 8
Type of structures (steel, concrete, brick, timber, masonry) 33.71 68.63 13.5 44.5
Location (regions/rural; urban) (inner city/outskirts) 31.99 69.63 12 43
Site conditions/site topography 25.24 76.47 6 26
Construction method/technology 25.99 71.50 9 36
Type of foundations (pile/raft/pad/etc.) 30.24 71.43 10.5 37.5
Off-site pre-fabrication 29.70 66.60 17 52
Type of cladding and external walls (brick, double glazing, etc.) 32.10 66.67 16 51
Access to site 30.24 71.43 10.5 37.5
Intensity/complexity of building services 18.68 91.20 1 6
Phasing requirements (areas to be handed over first or initial non-availability) 25.03 80.97 5 15
Quality of finishing 29.95 68.00 15 47

Table 5
Ranking of contract procedure and procurement method
Factors Coefficient of Severity Category Overall
variation index ranking ranking
Contract procedure and procurement method
Type of contract/use of standard form of contract 31.06 68.60 5 46
Tender selection method (open, selected, negotiation, single or two stage, etc.) 22.90 77.20 2 24
Payment modalities (fixed price, cost plus, BOT, PFI-DBFO, etc.) 28.77 72.53 4 32
Method of procurement (traditional, design and build, project management, etc.) 23.00 78.07 1 21
Spread of risk between construction parties (client/consultant/contractors) 32.68 73.27 3 31
Claims and disputes resolution methods (litigation/arbitration/others) 35.84 62.83 6 55
Interviewing of selected prospective contractors 37.26 61.83 7 57

Table 6
Ranking of external market conditions
Factors Coefficient of variation Severity Category Overall
index ranking ranking
External factors and market conditions
Material prices/availability/supply/quality/imports 25.17 80.00 2 17
Labour costs/availability/supply/performance/productivity 27.25 79.03 3 19
Plant costs/availability/supply/condition/performance 32.29 71.37 5 39
Weather condition 32.36 61.90 8 56
Government regulations/policies (health and safety, fire, CDM, etc.) 29.50 60.00 9 60
Level of competition and Level of construction activity 21.27 86.73 1 9
Number of bidders on competitive projects 36.82 67.63 6 49
Interest rate/inflation rate 33.69 65.70 7 54
Stability of market conditions 30.58 72.37 4 33

sections are devoted for a more detailed discussion of and 92%. However, their overall ranking ranges between
statistical analysis and main findings regarding each 3 and 53. With the exception of two variables, quantity
individual category. surveyors perceived most of these factors as not highly
significant. The category maintained coefficient of varia-
5.1. Client characteristics tions ranging between 15% and 37% which are relatively
low and indicate a good agreement level between respon-
This category contains eight factors, Table 1. These dents. KendallÕs statistical analysis supports this result
variables achieved high severity indices between 66% even better. Table 7 shows this category maintaining a
T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545 543

Table 7
KendallÕs concordance analysis using SPSS
Category ID Degree of freedom (DF) Chi-square KendallÕs coefficient (w) Significance
Category 1 7 19.8889 0.9471 0.0058
Category 2 7 19.6734 0.9368 0.0063
Category 3 17 48.3423 0.9479 0.0001
Category 4 16 42.5310 0.8861 0.0003
Category 5 6 15.7952 0.8775 0.0149
Category 6 8 23.4667 0.9778 0.0028

100 ranked 7th overall. These types of factors are considered


90
more subjective and therefore harder, costly and time
82
80
77 75 consuming to extract as project data. However, from
71 72
67 quantity surveyorsÕ view point, they are crucial in accu-
70
severity index %

rate estimation of construction costs at the pre-tender


60
stage.
50
40
5.3. Contractor attributes and site management
30
20 This category includes 18 factors, Table 3. Eight of
10 these factors achieved severity indices between 48%
0 and 60%. This indicates that these variables have rela-
1 2 3 4 5 6
category
tively lower degree of influence on project cost. The
remaining top-10 factors in this group gained severity
Fig. 2. Average severity indices (source: [5]). indices between 67% and 93%, which indicates their
higher importance.
KendallÕs coefficient of 0.95 with a significance level less The KendallÕs coefficient of concordance for this
than 0.05, which indicates a very strong concordance group is computed as 0.95 with a significance level of
between the respondents. 0.0001, Table 7. This indicates a strong agreement be-
On the top of this category is the ‘‘priority on con- tween quantity surveyors in the ranking of these fac-
struction time’’ factor and it is ranked third on the over- tors. The top ranked factors in this category include
all scale. The paramount effect of the duration and management team suitability which is ranked 2nd over-
deadline requirements on project costs is widely under- all, experience on similar projects, and planning
standable, and this outcome backs this view [12,9]. That capability.
is why this factor is considered crucial and is used in
Artificial Neural Networks and regression models devel- 5.4. Project characteristics
oped by the authors of the paper as part of this study.
The second and third ranked factors in this group are This category consists of 17 factors, Table 4. Their
‘‘certainty of project brief’’ and ‘‘quality requirements’’ effectiveness is demonstrated by high severity indices
which ranked 10th and 11th in the overall ranking, ranging between 67% and 91%. The KendallÕs coefficient
respectively. of concordance for this group is computed as 0.89 with a
significance level of 0.0003, Table 7. This indicates a
5.2. Consultant and design parameters strong agreement between quantity surveyors in the
ranking of these factors.
Eight factors are included in this group, Table 2. The top ranked factors in this group include project
Their severity indices range between 60% and 94%. Ken- complexity, number of basement levels, and uncer-
dallÕs coefficient of concordance computed for this cate- tainty of soil conditions. The complexity issue has al-
gory is 0.94, with a significance level of 0.01, Table 7, ready been addressed by Moselhi et al. [10] and
which is an indication of strong agreement amongst Shash [15] and it was considered as a key factor. A
quantity surveyors. remarkable observation in this category is the ranking
In the overall ranking of cost-influencing factors, this of the project size/area as eighth and its overall ranking
category contains four of the top-10 factors. The top as 30th. This factor was also not ranked amongst the
ranked factors within this group include late changes top at the study conducted by Nkado [12], where it
to design which is the top factor overall; variation or- was ranked as 13th out of 28 factors. An explanation
ders; timeliness of project information both of these fac- of possible reasons for this ranking is addressed in
tors ranked 4th overall; and quality of specifications, Section 5.7.
544 T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545

5.5. Contract procedure and procurement method There was a similarity in ranking project size/area in
this study and in NkadoÕs research [12]; it was ranked as
There are seven factors in this category, Table 5. This 30th out of 67 and 13th out of 28, respectively. How-
group maintained severity indices between 62% and ever, project size/area is one of the most determinant
78%. This category achieved the lowest KendallÕs coeffi- factors of project costs, and it is widely used in practice
cient of 0.88, Table 7, which still indicates high agree- for building cost models [2,14]. One explanation for
ment between respondents in the ranking of factors. these findings might be that the respondentsÕ views were
The top ranked factors in this group are the procure- based on the unit cost per area when they considered the
ment system which ranked 21st overall; the selection effects of project size on cost in these two studies,
method which ranked 24th overall; and the spread of respectively.
construction risks which ranked 31st overall. From the
statistics computed for this category, it is evident that
quantity surveyors regarded the factors contained within 6. Summary and conclusions
the category as having little effect upon construction
estimates. This seems to support the findings of Naoum Factors affecting costs of construction projects were
[11] which concluded that no evidence was found to reviewed based upon research work undertaken in differ-
favour the management contracting procurement system ent countries. The analysis and findings of these studies
over the traditional contracting method in reducing the varied on the one hand according to the different aims
overall construction costs. and objectives they addressed and on the other, accord-
ing to the economic environment under which the stud-
5.6. External factors and market conditions ies were conducted.
The study presented and discussed in this paper, con-
This category contains nine factors, Table 6. The sulted UK-based quantity surveyors via interviews and
severity indices obtained by this category are in the questionnaire survey. The main aim was to evaluate
range 60–87%. The majority of the factors in this group and rank cost-influencing factors of construction pro-
are amongst the most insignificant variables in the over- jects considered at the pre-tender stage. Sixty-seven vari-
all ranking. There is a strong agreement between quan- ables affecting construction cost were identified through
tity surveyors in ranking this group; this is due to a high literature and pilot interviews. These factors were
KendallÕs coefficient of 0.98 and a significance level at grouped into six broad categories: client characteristics;
0.0028, Table 7. consultant and design parameters; contractor attributes;
The top variable in this category is level of construc- project characteristics; contract procedures and procure-
tion activity which ranked 9th overall. This is an indica- ment methods; external factors and market conditions.
tion that the cycles of boom and bust in the construction Statistical analysis revealed that a strong agreement
industry have a clear effect on tender prices, and partic- between quantity surveyors existed in the ranking of
ularly on mark-up and profit margins. the cost factors. This was proven by high KendallÕs coef-
Material prices, labour costs, and stability of market ficients of concordance achieved within each category
conditions represent the remaining top ranked factors and also by low coefficients of variation for each variable.
within the group. However, according to their overall The average severity index computed for each cate-
ranking, they exert little influence in the preparation of gory ranged between 82% and 67%. This result sug-
construction estimates. gested that there is no significant variation in the
ranking of each group. However, the category contain-
5.7. A comparative view ing consultant and design parameters was ranked top
followed by client characteristics with four out of the
Comparing the findings of this study with other re- 10 top factors being related to this category. The third
search projects, there are some agreements as well as and forth ranks were occupied by project characteristics
some differences in ranking the construction cost fac- and external market conditions, respectively. On the
tors. For instance, inflation rate/fluctuation in materials other hand, the fifth group of factors included contract
prices ranked very low as 54th in this study Table 6, in procedures and procurement methods. The contractor
contrast to Elinwa and Buba [7] Nigerian study where attributes group scoring the least index occupied the
it was ranked 3rd. The reason would be the difference bottom of the list. These findings indicated that con-
between the economies in the industrial and developing struction project costs were more affected by architects
countries where the inflation rate in the latter is very and consultants than by contractors. This outcome is
high compared to the former countries. These kinds of consistent with many literature views that the project
divergence contribute to the complexity of evaluating costs are more determined by decisions at the briefing,
the degree of influence of different factors on tender cost feasibility and initial design stages rather than by later
estimates at diverse situations. construction stages.
T.M.S. Elhag et al. / International Journal of Project Management 23 (2005) 538–545 545

Many of the cost factors evaluated in this study do [5] Elhag TMS. Tender Price Modelling: Artificial Neural Networks
not play a part in major databases which care for con- and Regression Techniques. PhD Thesis, University of Liverpool;
2002.
struction cost analysis, e.g. Building Cost Information [6] Elhag TMS, Boussabaine AH. An artificial neural system for cost
Service (BCIS) of the Royal Institute of Chartered Sur- estimation of construction projects. In: ARCOM 14th annual
veyors (RICS). Some of these types of variables are con- conference, Reading, UK; 1998.
sidered more subjective in nature and therefore harder, [7] Elinwa A, Buba S. Construction cost factors in Nigeria. J Constr
costly and time consuming to be extracted as project Eng Manage 1993;119(4):698–713.
[8] Kaming P, Olomolaiye P, Holt G, Harris F. Factors influencing
data. However, it would be of great benefit to quantity construction time and cost overruns on high-rise projects in
surveyorsÕ practices as well as to the construction indus- Indonesia. Constr Manage Econ 1997;15:83–94.
try at large and academia if for instance a body like the [9] Kumaraswamy M, Chan D. Determinants of construction dura-
BCIS could develop a performa to collect this kind of tion. Constr Manage Econ 1995;13:209–17.
project information. [10] Moselhi M, Hegazy T, Fazio P. DBID: analogy-based DSS for
bidding in construction. ASCE J Constr Eng Manage
1993;119(3):466–79.
[11] Naoum SG. Critical analysis of time and cost of management and
References traditional contracts. ASCE J Constr Eng Manage
1994;120(4):687–705.
[1] Akintoye A, Fitzgerald E. A survey of current cost [12] Nkado RN. Construction time-influencing factors: the contrac-
estimating practices in the UK. Constr Manage Econ torÕs perspective. Constr Manage Econ 1995;13:81–9.
2000;18(2):161–72. [13] Okpala DC, Aniekwu AN. Causes of high costs of construction in
[2] Ashworth A. Cost studies of buildings. 2nd ed. London: Long- Nigeria. ASCE J Constr Eng Manage 1988;114(2):233–44.
man Group Ltd.; 1995. [14] Seeley IH. Building economics. 4th ed. New York: Macmillan
[3] Brandon PS, Ferry DJ, Ferry JD. Cost planning of buildings. 7th Press Ltd.; 1996.
ed. Oxford: Blackwell Science; 1999. [15] Shash A. Factors considered in tendering decisions by top UK
[4] Dissanayaka SM, Kumaraswamy MM. Evaluation of factors contractors. Constr Manage Econ 1993;11:111–8.
affecting time and cost performance in Hong Kong building [16] Siegel S, Castellan Jr NJ. Non parametric statistics for the
project. Eng Constr Architect Manage 1999;6(3):287–98. behavioural sciences. New York: McGraw-Hill; 1987.

Вам также может понравиться