Академический Документы
Профессиональный Документы
Культура Документы
cn
rn
h,
v
strength in innovative and difficult package design own chart showing the usual flow of orders through
and the ability to fold and glue the complex blanks. the plant's departments (Exhibit 5).
President Rand had asked Milliken to focus on
three problem areas: cost, quality, and delivery. At the
end of November 20ll Rand had fired the previous Quality Control
Iong-serving VP of Operations. Rand told Milliken, Milliken left his office and crossed the factory floor to
"Our sales are up-we have to run two shifts now. But the Quality Control office to find QC Manager Fran
we ran a loss for the first time last year since 2001. Schuler inside. They chatted about the procedures for
[See Exhibit 1 for income statements.] We're getting the start of each shift, then Milliken asked where the
more and more complaints about quality, and, what main problems arose.
might be even worse for our customers, wdre deliver- Schuler told him that quality problems were
ing late more often. I understand we're a job shop and concentrated in Fold & Glue with either missing glued
there's usually a tradeoff between keeping your costs Iines or excess glue. Schuler showed him a report from
down, getting good quality, and hitting your delivery October, their worst month of fiscal 2011, indicat-
promises-but lately it seems we cant even hit two out ing that 60/o of products were found defective due to
of the three. What started to go so wrong for us? Your glue problems and were scrapped, with a further 1%
predecessor couldnt explain it to me, and his plan of of shipped product rejected by the customer due
'We'll just have to try harder' told me he had no idea to glue problems. There were also some problems
what to do. I hope you can do betterl' in Finishing-a much lower volume department-
primarily due to orders shipping with some or all
pieces missing an attachment like a button or zipper.
TOURIhIG THE FACTCIRY If the customer returned these they could usually be
reworked rather than scrapped.
IN JANUARY 2OI2 "Whatt your staffing, and your procedures for
fohn Milliken graduated in 2001 from Rensselaer preventing or finding defects?" asked Milliken. "The
Polltechnic Institute with a BS in Mechanical Engi- supervisor signs offon the first good piece the opera-
neering. For the past five years he had been the Oper- tor runsl' said Schuler. "That goes in the Work Order
ations Manager of a small packaging firm serving the facket." The Work Order facket traveled with the job;
northern New /ersey pharmaceuticals industry, so he it listed the routing, the standard setup and run times,
came to Bayonne familiar with the general manufac- any special instructions, and ship-to information. It
turing processes Bayonne used to design and deliver also held the customert signed proof along with sam-
customized small-unit packaging. During the hiring ples signed by operators, supervisors, and QC at each
process he met most of the management at Bayonne operation.
and also the factory supervisors on both shifts, and Schuler told him that QC had one inspector on
had asked for several reports to be prepared for him each shift covering the Composition, Sheet, Print, and
when he came to work in lanuary. Digging into the Die-cut departments, and a second for Fold & Glue,
pile, Milliken focused on October 201 I since that was Finishing, and the shipping dock. The inspectors went
Bayonne's highest-volume month and, as October 31 from machine to machine checking two pieces every
closes the fiscal year, it would show him complete and hour during the production run, and performed a final
audited l2-month financial statements for the com- inspection of material before it shipped out. Schuler
pany. He reviewed the Income Statement, keeping in said, "In Shipping we check the product against the
mind Bayonne's practice-a common one-of rec- proof in the Work Order facket, and against any spe-
ognizing revenue when it billed the customer, and it cial instructions like special packing or ship-to. Usu-
billed when it shipped product. Milliken then turned ally it takes about 15 minutes to do an order. Of course
to a production report that listed standard setup and we might not have the Work Order facket at that point
run times, as well as scheduled production and stan- if it's been partialed since the jacket gets filed up in
dard hours for October in key work centers (Exhibit 2). the Production office after the first shipmentl' If an
A second report showed 'good pieces in/ out" for the order was running late it was sometimes possible to
month (Exhibit 3). The last report presented the daily rush a "partial" quantity of the whole order to satisfy
and cumulative dollar volumes shipped in October, part of the customer need, with the rest of the order
net of customer returns (Exhibit 4). He also had his completed and shipped later.
EXHIBIT I lncome Statements for Bayonne Packaging,2oog-Oct.2ot1 ($ooo)
Gross Sales $5,140,467 101 .5% $4,438,500 100.8% $3,075,860 1OO.7% $30,758,666 100.9% $37,071,038 100.6% $35,069,202 100.5%
Less: Customer Rejects (75,455) -15% -0.8%
(33,834) -0.7%
(21,531) -0.9%
(276,828) (222,426)-0.6% (175,346) -O5%
Net Sales 5,065,012 100.0% 4,404,666 100.0% 3,054,329 100.0% 30,481 ,B3B 100.0% 36,848,61 2 100.0% 34,893,856 100.0%
COGS:
Shipped Material 3,285,673 64.9"/" 2,704,465 61.4% 1,820,380 59.6% 17,770,912 58.3% 20,782,617 56/% 19,296,302 55.3%
(Scrap) 597,671 11 .8"k 405,2299.2% 268,781 8.8% 2,529,993 8.3% 2,616,251 7.1% 2,163,419 6.2%
Regular DL 525,748 10/% 396,4209.0% 271,835 B.S% 2,499,511 8.2% 2,874,192 7.8"/" 2,547,251 73% o
o
OT DL 1 16,495 2.3% 1.7%
74,879 12,217 0.4o/o 173,746 0.6% 294,789 0.8% 265,193 0,8% o
lL, supervisory 29,884 0.6% 0.6%
25,107 15,272 o.5% 134,120 0.47" 125,285 0.3% 139,575 0.4k N
!
gc
o
o\
c-362 Part 2 Cases in Crafting and Executing Strategy
EXHIBIT 2 October Scheduled Orders, Standard Setup and Run Time (minutes)
Nofej October 2011 had 347 scheduled work hours net of breaks, including half-day Saturdays.
a "Standard Times" were estimates of setup and run time per job, derived from times recorded in Work Order Jackets from previous, similar
jobs.
b ln
Composition, Setup time is per order while Run time is per plate. App rox. 213 ol the orders were for 4-color (4 plate) printing; the rest
were for 6-color.
c
Changing dies took 2-3 hours but the standards assumed that four to six or more different orders using the same die would be "ganged',
or run together on a single setup. Since Cost Estimating could not know-when routing any individual order-how many orders it might be
ganged with at Die-cutting, Estimating simply routed each order for 30 minutes.
d Blanks
could run on a Royal/ Queen or a dtaude, but no order ran on both.
e
30 of the 3A orders ran on the Royal/ Queens, the remaining 58 on the Staudes.
r
Finishing was labor-intensive piece-work. Bayonne was able to vary the labor as needed, and so effectively could apply as much capacity
as it needed.
EXHIBIT 5 Material Flow through ads, Internet, direct marketing mailings, point-of-
purchase display units and coupons, commission pay-
Operations, October 2ot'l
ments to the retail channel so they'll push the product,
people handing out samples on the street-you name
it. Its all scheduled to hit, to have impact, on a spe-
Sheet 9,555,097 9,4A8,2i1 cific date. If our product isn t there, the customer goes
Print 9,488,211 9,326,912 nuts. We have orders as small as 1,000 pieces, but we
Die-cut 9,326,912 9,233,643 sell some of those for a high price per piece-they're
Royal/Queen 6,209,329 5,588,396 just as important to the customer. In October, since
Staude 2,242,039 2,085,096 you ask, we were late more than 20o/o of the time. Two
34 782,274 768,193 years ago I hit the roof if it was 5% in a month. The
Finishing 687,601 675,335 factory doesnt agree with me on this, they take a bow
Total pieces shipped: 8,441 ,6BG
for being 'bn time" if they get a partial out. But that's
nowhere near good enough for the customer. You try
a getting the customer to give us a second look if weve
Material scheduled at Sheet, Print, Die-cut has been converted
from sheets to pieces, sheets averaged 3 pieces been late once. I'm telling you, it's getting worse not
better, year after yeari' Milliken nodded. "The second
biggest problem is the boxes popping open with not
Sales Management enough glue or no glue at all. Sometimes there's too
Milliken next spoke with VP Sales AIex Wascov and much glue laid on so it bleeds out, it looks bad or you
asked him about his biggest concerns. "On-time deliv- cant open it because it's stuck so bad. Dont get me
ery," said Wascov. "We're selling a piece of an expen- wrong-we have a beautiful product, great designs,
sive promotional campaign. The customer has bought classy printing. tsut the giue problems are real, or
Case z7 Bayonne Packaging, Inc c-363
sometimes the product is just missing some Finishing could come together sooner. Fourth, sometimes the
piece. Delivery is the big issue, thoughi' customer was putting together the project for some
Milliken asked why customers sometimes wanted other company that wanted more lead-time-for
to "move up'or expedite a due date to receive prod- example, it was not uncommon for retail channels to
uct sooner than they had originally been promised, demand that promotional materials be staged sooner
assuming schedule was part of a coordinated market- than originally promised.
ing project. Wascov said that, first, some customers Hoping to switch away from this iitany of woe,
had learned or heard that Bayonne on-time delivery Milliken asked, "Other than the problems, how is
was not to be trusted. Second, the customer may have Bayonne doing?" Wascov looked immediately happier.
originally wanted the material sooner but someone had "Greatl" he said. "We're grabbing into new markets,
settled for the standard date, and then later come back getting aggressive about taking customers wdve never
to get what they really wanted. Third, some other had before. This year for the first time weve had some
component of the marketing project might become big, solid hits, like up to two-hundred thousand piece
available earlier than anticipated, giving the cus- orders in candies, pretty much a whole new product for
tomer hope that all of the pieces, including Bayonne's, us. Same thing with those little corporate gift sets. I told
c-364 Part z Cases in Craftlng and Executing Strategy
i ..r:.1.... ..,,.,.t.'.. I
:; Larqe
I
Y
I
j
f
I
I
' ;' Order
size? -l I
v v I
'Statdac
;l r
I
tl
I
I ves I
I
;r:r.
F':.r
I $heer,i,'rrj *i
.ltD,,tq,!l;.:,,.. j
I
Y
a.
..:.. .. i
:t. r:':Ffifif.,::::::,i
1:: :.
..b 1.,,.r1.!
my sales people to do what it takes, price aggressively to finalized, printing plates made, and die-cutting dies
the market, and boy they surely did. Dave Rand com- ordered. From there Milliken passed through the Sheet
plains about the margins, but he doesnt complain about Department, where the fagenburg sheeter turned
getting the volume. The designers had to learn a few roll stock into sheets of paper stacked on skids to be
new tricks, and the Fold and Glue operators too, plus printed. In the Print Department he watched 4- and
we got into some FDA requirements about coatings, 6-color Heidelberg presses print the sheets. He fin-
adhesives, and liners, but the amount of business were ished this part of his tour in the Die-Cut Department,
pulling in is great. If we could just get a track record where Bobst die-cutters cut the printed sheets into
for delivering on time we can win a lot more custom- blanks-the flat cut-out shapes of printed paper ready
ers too, especially with the kinds of products we havent to be folded and glued into finished product. He was
touched before, just over the river. You know how much led through these areas by Sean Quinn, the manager
promotional material money there is in Manhattan?!" for these departments. Quinn had a supervisor within
each department on both shifts reporting to him.
Cornpositicn, Sheeting, Frinting, Watching the assistant sheeter operator expertly
maneuver the clamp truck to fetch and stack up rolls
and *ie-Cut of paper, Milliken asked Quinn how they scheduled
By mid-afternoon Milliken had worked his way the sheeter and the Heidelberg printers, and how
through most of Bayonne's factory work centers. First often a lack ofstock caused delays.
he toured the Composition Department, where both Quinn told him that he scheduled the sheeter by
printing and package designs were developed and what needed to be printed in the following day or two.
Case z7 Bayonne Packaging, Inc c-36s
gX${6ffi&T &A Bobst Die-Cut Machine gX&"{$ffi*Y &ffi lnternational Queen Fold
and Glue Machine
They rarely stocked out of because they kept enough and its die number. Most were placed neatly in col-
variety on hand, and their supplier, International Paper, umns under the two Bobst machine numbers, lined
could restock from their warehouse in Montvale, New up in the order to be run. Pushed off to one side of
fersey, within a day or two in almost all cases. the board was a jumble of clips with orders that had
Quinn scheduled printing by due dates, which not yet been scheduled to run. Miliiken studied the
were either the standard ones originally promised jumble for a moment. Each order appeared to have
to the customer (typically three weeks from signed a different die number. Milliken asked Quinn about
proof, depending on the number of operations and the schedule that was generated twice weekly by the
the size of the order), rush orders soid from the start computerized scheduling system. "It's uselessi' Quinn
with shorter-than-standard lead times or, about twice said bluntly. Milliken asked him why. Quinn said,
a day, dates expedited after the order was placed. "The biggest reason being, between rush orders and
In Quinnt office looking out a window at pallets ganging the orders to keep the machines running, I
of printed sheets waiting to be die-cut into blanks, couldnt afford time-wise to do what the printout says.
Milliken asked how the Bobst die-cutters were sched- Apart from that, what the schedule tells you is, excuse
uled. 'As much as we can by having the same diel' me, garbage. It says you have an order when you've
Quinn said. "We sell enough of the same package never seen it, or that you still have an order that you
designs so we can gang orders.2 Jerry, the cost estima- know you finished and got out of here. That doesnt
tor, knows that when Order Entry routes the orders have to happen too many times before you just dont
they give us 30 minutes as a standard setup time- worry about the printouti'
they know it really takes two or three hours if you have
to change over a Bobst die, but they figure on me gang-
ing. I juggle the orders I have in the department and Fold & Glure
that generally allows me to gang six or eight orders on Milliken's next stop was the Fold & Glue Department,
a setup. If I didnt gang, I couldnt get enough run time where the die-cut blanks were turned into finished
to stay on schedule." Milliken asked how long Quinn product. The department had four kinds of machines:
usually held an order waiting for more to come in to two International Queens and one International
the department for ganging. Quinn said it was usually Royal, which were high-speed machines but complex
about a week, sometimes as much as two. to setup; four International Staudes, which were slow
While he taiked, Quinn illustrated his scheduling machines but easier to setup, best used for low-volume
by pointing to a board where small magnetic clips jobs; and two International 3.A machines which were
each held a piece of paper with a Work Order number "window/patch" machines, using rotating cylinders
c-366 Part z Cases in Crafting and Executing Strategy
which attached clear plastic "windows" and also tear- They watched, a grizzled operator setting up the
strips on envelope-style products. Royal, banging forcefully on a sword adjustment with
Milliken asked department manager Rick Gomes a steel mallet. The part didnt move. The operator
about his problems. Gomes told him, "The department swung the mallet harder and the part jumped about
runs pretty good, but we get a lot of problems that are an inch. "What's your maintenance schedule?" asked
not our fault. Sean Quinn sends me a lot of orders that Milliken. "Well, operators are responsible for clean-up
are one or two days from the due date, or even late at the end ofshift, and checking oil and grease points
already. So we have to run them as soon as possible, but at the start. If something breaks down, Maintenance is
there are already orders ahead ofthem here lined up. So good about getting right on it. Weve got a pretty good
I cant gang orders like he can. With those, and the rush supply ofspare parts there in the cageJ'
orders too, I have to breakinto runs, get the order done,
and then go back to the first order I broke into-so that
makes for partialsl' "\{hat about the glue problems?" Scheduling
asked Milliken. "Getting the hot melt glue guns q/n- The Finishing Department manager was out sick so
chronized to the belts and swords3 is the tough thing Milliken decided to tour there the next day. Back in the
about a setupi' said Gomes. "If you do the setup quick Production office Milliken sat down with fim Worthen,
and dirty, it runs slow-but I cant run slow with our the plant scheduler, and asked him about his job.
volume. Usually we get it alright, but sometimes not. Worthen told Milliken that his job was to do
Let me show you here on this Queen." Milliken was whatever it took to deliver on time. The plant held a
familiar with fold & glue machines, but he stood with daily production meeting every morning where the
Gomes looking at the 35' straight-line machine and main topic was what had gone wrong the previous
nodded while Gomes talked over the noise. "The feed day, the status of large, important orders, and what the
takes the blank from the stack here we get from Die- department managers would do to deliver on time any
cut, lays it down flat, then the fingers grab and move newly expedited orders. Worthen indicated that gen-
it. At the first glue gun a line of glue gets laid down, erally they did not tell Sales if an order was going to
then the swords pick up the tabs, fold them over and lay be late. He said, "We're supposed to but a lot of times
them down. They go between the top and bottom belts, we dont know for sure until the end because we're
which squeeze the fold while the glue sets, for the first hoping to get a partial out on time. If you tell Sales
fold. On this order, that happens again at the second ahead of time an order is going to be late, Wascov just
guns. Getting it running at 22,000 to 27,000-an-hour starts hammering us and calling up Dave Rand and
like this with the swords, belts and guns synched, not the rep starts screaming. It creates a lot of unneces-
too little, not too much, and not folding off-it's not sary work-and then they bump something else, so
easy. The Staudes are quick to setup. They're great for the ripple effect is just more jobs late. Of course, they
little jobs, but they run slow, of coursel' dont blame themselves for that, do they?"
Milliken looked at a hot melt glue gun closely. Milliken asked, "When you partial, do you
The tiny glue orifice in the brass nozzle was open, break orders in half or have a little part and a bigger
with some hardened residue around it. The fitting part usually? And do you break into more than two
from the glue canister was tightened on with an auto- pieces?" Worthen said, "It's always just the first and
mobile-style hose clamp. He touched the nozzle and it second piece, and they're just about always the same
shifted slightly. "How often do you change the filter?" size-itt easier that way to justify doing all the addi-
he asked. Gomes said, "When it's needed-we can tell." tional setups if the partials dont have tiny numbers."
Milliken asked, "How do you decide between Milliken said, "Sean Quinn and Rick Gomes say
the Royal and Queens or the Staudes where to run they cant use the schedule. Why is that?" Worthen
orders?" Gomes said, "If we could do what we wanted told him that much of the shop floor reporting was
we'd run orders of 60,000 or more on the Queens or missing or wrong, forcing Worthen to spend several
the Royal, and an1'thing less on the Staudes. 'Course, a hours each day trying to scrub the data using informa-
lot of times we cant do thatl'Milliken asked about the tion on work order pieces completed in each opera-
shop floor schedule. Gomes said, "|ust personally, I tion which the operators recorded by hand in the
dont look at it. By the time I get orders, I'm just going Work Order Jackets.
by what's getting expedited and due dates. Whatever Milliken asked why the data reported through
fire is hottest, I'm putting it out." the shop floor computer terminals was so inaccurate.
CasezT Bayonne Packaging, Inc. c-367
Worthen told him that operators recorded pieces to the work time there, got something to do with
completed in the Work Order Jacket and their start partials, like the orders really turn into two orders on
and stop times on setup and run. The Estimator used their way through?" Worthen said, "No, it's a bunch of
that data for estimating standard times, and Payroll things that cause orders to just sit around and not get
got attendance data when the operators swiped their worked on; I'm just telling you that in my experience,
bar-coded ID cards through the terminals. Milliken anl,thing less than a two ratio is almost always latei'
knew that operators got a 30-minute meal break Milliken asked, "\Arho has authority to expedite
in the middle of their 8-hour shift. Roll stock use at orders?" Worthen said, "Well, Dave Rand of course.
the sheeter, plates in Comp, and ink in Print were Wascov gets on the horn to him, or he would call lohn
recorded by different, manual systems, and the expe- McNulty [Milliken's predecessor] directly to get orders
rienced operators there maintained their own local expedited. Since |ohn's gone, Wascov's been calling me.
inventory records to make sure that they did not run Quinn and Gomes complain, and Joe Pensiero in Fin,
short. As a result, no one felt a real need for accurate ishing actually gets it worst of all since he's dead last after
terminal-based shop floor production reporting. any other delays. But the system actually works pretty
Milliken asked what rules the computer-based good. If an order gets expedited after it's out on the floor,
scheduling system used. Worthen told him that the com- we give it to Neil Rand. He takes the Work Order right
puter recalculated and printed a new schedule tvyice a through whatever is left and makes sure it happens, puts
week for two "buckets"-the machine capacity in hours it on a machine right away with no delays, wherever it's
available in each work center in the Monday-Tuesday- routed. Red carpet treatmentl' Worthen grinned. "Of
Wednesday and the Thursday-Friday-saturday (half- course Neil's worked all over the factory since he was a
day) buckets. The system added up the standard setup kid-het actually a good setup man himself in Fold &
and run hours for every order released to the plant and Glue. His orders are never late unless we hand it to him
"filled the buckets" by scheduling orders by priority. already past due-so of course Wascov is always trying
Priority was set by the 'tritical ratio'. The ratio's to get expedites authorizedl' Milliken asked politely,
numerator was the number of hours between the cal- "Neil is a family member?" "Yeahl' said Worthen. "He's
culation date and the due date, and the denomina- Dave's uncle. He wasnt ever really executive material,
tor was the total standard setup and run hours for all but he's a great guy; everybody loves himl'
remaining operations plus 48 hours for each remain- Back in Milliken's office the mid-afternoon lanu-
ing operation. The lower the ratio, the higher the pri- ary sun was already sinking. Aware that President
ority. Worthen added, "My rule of thumb is that if the Rand wanted his recommendations by the end of the
critical ratio when the job starts is lower than 2,Ihave week, Milliken pulled out a fresh pad of paper and
to watch that job, it's born in trouble." started organizing his thoughts. He had quite a few
While Worthen was explaining this, Milliken questions to answer, among them:
sketched his understanding of the rules with an exam-
ple (see Exhibit 7). He showed this to Worthen, who 1. Why were delivery, cost, and quality all lanl<rng
nodded and remarked, "Nobody ever got that before last October? It seemed like a good month to ana-
the first time I told himl' Iyze because he had fairly complete data for it, and
Milliken asked, "Has this extra two days at each it probably showed Bayonne operating under its
work center for scheduling purposes, in addition greatest stress.
Comp J
Sheet 2
Print 6
Die-cut J
Fold & Glue 8
Total hours: 22 setup and run + (5 ops x 48 hours each):262
Today: January 2. Due date: January 25. Hours: 23 x 24: 552
Critical ratio: 552/262 :2.11
c-368 Part z Cases in Crafting and Executing Strategy
) The plant had seemed relatively busy as he walked machines? Could he quantify the effect of the runs
through, though he knew that operators and super- being broken into by the expediting and partialing?
visors tended to look that way while the boss was 3. What was the practical effect of the informal sys-
touring. Still, given Bayonne's delivery perfor- tem Bayonne used to schedule the order in which
mance, he wondered if capacity were adequate, or jobs were run? The computer system was obviously
if some or even most of the work centers would be useless right now, but would it be worth trying to
over-stretched even with better management than fix the data and then get adherence to the schedul-
he had observed. How did the quality problems ing system?
play into this? Were orders being run on the right