PCI CKT N

Conveyor/JH/Bldg details
front
Other mech
Sl.No. Conveyor Concerned Conveyor availablity
Name Drives handover
Drive(KW) ECR/Location Drive(KW) Status
(KW)
25.05.16
1 PC#1 490 RM#5 1 Available 15.06.16 (R1)
20-07-16

10.06.16
25.06.16 (R1)
2 PC#2 370 RM#5 1 Not Available 30-07-16
12-08-16
22-08-16

25.06.16
CTT-1 3.7 25-07-16
3 RM#5 2 Not Available
12-08-16
24-08-16

30-07-2016
PC-3 132 20-08-16
4 RM#11 1 Not Available
10-09-16

PC-4 160 20-08-2016


5 RM#11 1 Not Available
10-09-16

PC-5 75 30-08-2016
6 RM#11 1 Not Available
10-09-16
7 Portal reclaimer RM#5 Available Available
PCI CKT NLT STATUS
commissioning
tray Cable
Testing No Load Trial date with field
completion laying & Ter
switches

7/25/2016 completed completed completed completd

20-08-2016
21-08-2016 22-08-2016
16-08-2016 05-09-16
06-09-16 07-09-16 9/12/2016
02-09-16 08-09-16
09-09-16 10-09-16

loop checking ,
18-08-2016 21-08-2016 25-08-2016
14-08-2016 power charging
03-09-16 05-09-16 09-09-16
02-09--16 & trial by 15-09-
done done 12-09-16
16

filed switches
termination by
30-08-2016
25-08-2016 26-08-2016 09-09-16
Completed 20-09-16
15-09-16 16-09-16 trial with field
12-09-16
switches by 15-
09-16

27-09-2016
30-08-2016 10-09-2016 11-09-2016 15-09-2016 subjected to
14-09-16 22-09-16 23-09-16 24-09-16 mech handover
by 10-09-16

10-09-2001 15-09-2016 16-09-2016 20-09-2016


9/30/2016
20-09-16 25-09-16 26-09-16 28-09-16
Completed completed completed completed 9/20/2016
8/22/2016

Remarks

cable laying HT in
progress will
completed by 09-
09-16, termination
by 09-09-16
control cable
Cable conduits & front for tray pending ( expected date termibnation
of availability by 12-08-16 R1, 25-08-16 R2 completion by 09-
pit front made available by 03-09-16 09-16
scheme checking
by 09-09-16 field termination by 10-09-16

CRD drum
power cable laid, erection
power charging by pending
09-09-16 from strl

cable laying after PC#4 conveyor gallery readiness


strl front given on 01-09-16.
tray pending-150 mtr , completd by 09-09-16
cable laying LT- 1500 mtr done,900 mtr baalnce , cable cable termination at
laying by 11-09-16 motor side by 09-
09-16
CJH#16 not ready , motor not installed,CJH#16 to
PC#4 gallery connectivity pending
tech strl not given front
front of PF tray not given
tech strl start 6th sep to 15 sep
PC#5 conveyor gallery not ready
tech strl start 15th to 18th sep
commissioning by 20-09-16