REVISI MASTER SCHEDULE

PROJECT APARTEMENT REGATTA PHASE 2
PT.NUSA RAYA CIPTA
ID Task Task Name Duration Start Finish Predecessors
Mode May 2017 Se
21 January 01 April 11 June 21 August
22/01 29/01 05/02 12/02 19/02 26/02 05/03 12/03 19/03 26/03 02/04 09/04 16/04 23/04 30/04 07/05 14/05 21/05 28/05 04/06 11/06 18/06 25/06 02/07 09/07 16/07 23/07 30/07 06/08 13/08 20/08 27/08
0 RESCHEDULE PROJECT REGATTA 29/01/12017 197 days Sun 29/01/17 Thu 31/08/17
1 1 BASEMENT 2 56 days Sun 29/01/17 Sat 25/03/17
2 1.1 Pelapis Dinding Toilet & Utility Room 56 days Sun 29/01/17 Sat 25/03/17
12
13 2 BASEMENT 1 58 days Sun 29/01/17 Mon 27/03/17
14 2.1 Pelapis Dinding Toilet & Utility Room 58 days Sun 29/01/17 Mon 27/03/17
24
25 3 GROUND FLOOR 26 days Sun 29/01/17 Thu 23/02/17
26 3.1 HVAC 10 days Wed 01/02/17 Fri 10/02/17
27 3.1.1 AC + Exhaust 10 days Wed 01/02/17 Fri 10/02/17
28 3.2 AREA CORE 17 days Sun 29/01/17 Tue 14/02/17
38 3.3 UNIT 1 & 2 26 days Sun 29/01/17 Thu 23/02/17
50
51 4 LANTAI 2 34 days Sun 29/01/17 Fri 03/03/17
52 4.1 HVAC 10 days Wed 08/02/17 Fri 17/02/17
53 4.1.1 AC + Exhaust 10 days Wed 08/02/17 Fri 17/02/17 27SS+7 days
54 4.2 AREA CORE 24 days Sun 29/01/17 Tue 21/02/17
64 4.3 UNIT 1 ~ 4 30 days Sun 29/01/17 Mon 27/02/17
76 4.4 UNIT 5 ~ 8 34 days Sun 29/01/17 Fri 03/03/17
88
89 5 LANTAI 3 41 days Sun 29/01/17 Fri 10/03/17
90 5.1 HVAC 10 days Wed 15/02/17 Fri 24/02/17
91 5.1.1 AC + Exhaust 10 days Wed 15/02/17 Fri 24/02/17 53SS+7 days
92 5.2 AREA CORE 31 days Sun 29/01/17 Tue 28/02/17
102 5.3 UNIT 1 ~ 4 37 days Sun 29/01/17 Mon 06/03/17
114 5.4 UNIT 5 ~ 8 41 days Sun 29/01/17 Fri 10/03/17
126
127 6 LANTAI 3A 48 days Sun 29/01/17 Fri 17/03/17
128 6.1 HVAC 10 days Wed 22/02/17 Fri 03/03/17
129 6.1.1 AC + Exhaust 10 days Wed 22/02/17 Fri 03/03/17 91SS+7 days
130 6.2 AREA CORE 38 days Sun 29/01/17 Tue 07/03/17
140 6.3 UNIT 1 ~ 4 44 days Sun 29/01/17 Mon 13/03/17
152 6.4 UNIT 5 ~ 8 48 days Sun 29/01/17 Fri 17/03/17
164
165 7 LANTAI 5 55 days Sun 29/01/17 Fri 24/03/17
166 7.1 HVAC 10 days Wed 01/03/17 Fri 10/03/17
167 7.1.1 AC + Exhaust 10 days Wed 01/03/17 Fri 10/03/17 129SS+7 days
168 7.2 AREA CORE 45 days Sun 29/01/17 Tue 14/03/17
178 7.3 UNIT 1 ~ 4 51 days Sun 29/01/17 Mon 20/03/17
190 7.4 UNIT 5 ~ 8 55 days Sun 29/01/17 Fri 24/03/17
202
203 8 LANTAI 6 62 days Sun 29/01/17 Sat 01/04/17
204 8.1 HVAC 10 days Wed 08/03/17 Fri 17/03/17
205 8.1.1 AC + Exhaust 10 days Wed 08/03/17 Fri 17/03/17 167SS+7 days
206 8.2 AREA CORE 52 days Sun 29/01/17 Tue 21/03/17
216 8.3 UNIT 1 ~ 4 58 days Sun 29/01/17 Mon 27/03/17
228 8.4 UNIT 5 ~ 8 62 days Sun 29/01/17 Sat 01/04/17
240
241 9 LANTAI 7 69 days Sun 29/01/17 Sat 08/04/17
242 9.1 HVAC 10 days Wed 15/03/17 Fri 24/03/17
243 9.1.1 AC + Exhaust 10 days Wed 15/03/17 Fri 24/03/17 205SS+7 days
244 9.2 AREA CORE 59 days Sun 29/01/17 Wed 29/03/17
254 9.3 UNIT 1 ~ 4 65 days Sun 29/01/17 Tue 04/04/17
266 9.4 UNIT 5 ~ 8 69 days Sun 29/01/17 Sat 08/04/17
278
279 10 LANTAI 8 81 days Sun 29/01/17 Fri 21/04/17
280 10.1 HVAC 10 days Wed 22/03/17 Sat 01/04/17
281 10.1.1 AC + Exhaust 10 days Wed 22/03/17 Sat 01/04/17 243SS+7 days
282 10.2 AREA CORE 65 days Sun 29/01/17 Tue 04/04/17
292 10.3 UNIT 1 ~ 4 81 days Sun 29/01/17 Fri 21/04/17
304 10.4 UNIT 5 ~ 8 77 days Sun 29/01/17 Mon 17/04/17
316
317 11 LANTAI 9 83 days Sun 29/01/17 Sun 23/04/17

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: RESCHEDULE PROJECT
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 26/01/17
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
REVISI MASTER SCHEDULE
PROJECT APARTEMENT REGATTA PHASE 2
PT.NUSA RAYA CIPTA
ID Task Task Name Duration Start Finish Predecessors
Mode May 2017 Se
21 January 01 April 11 June 21 August
22/01 29/01 05/02 12/02 19/02 26/02 05/03 12/03 19/03 26/03 02/04 09/04 16/04 23/04 30/04 07/05 14/05 21/05 28/05 04/06 11/06 18/06 25/06 02/07 09/07 16/07 23/07 30/07 06/08 13/08 20/08 27/08
318 11.1 HVAC 10 days Thu 30/03/17 Sat 08/04/17
319 11.1.1 AC + Exhaust 10 days Thu 30/03/17 Sat 08/04/17 281SS+7 days
320 11.2 AREA CORE 72 days Sun 29/01/17 Tue 11/04/17
330 11.3 UNIT 1 ~ 4 79 days Sun 29/01/17 Wed 19/04/17
342 11.4 UNIT 5 ~ 8 83 days Sun 29/01/17 Sun 23/04/17
354
355 12 LANTAI 10 90 days Sun 29/01/17 Tue 02/05/17
356 12.1 HVAC 10 days Thu 06/04/17 Sun 16/04/17
357 12.1.1 AC + Exhaust 10 days Thu 06/04/17 Sun 16/04/17 319SS+7 days
358 12.2 AREA CORE 79 days Sun 29/01/17 Wed 19/04/17
368 12.3 UNIT 1 ~ 4 86 days Sun 29/01/17 Thu 27/04/17
380 12.4 UNIT 5 ~ 8 90 days Sun 29/01/17 Tue 02/05/17
392
393 13 LANTAI 11 97 days Sun 29/01/17 Tue 09/05/17
394 13.1 HVAC 10 days Thu 13/04/17 Sun 23/04/17
395 13.1.1 AC + Exhaust 10 days Thu 13/04/17 Sun 23/04/17 357SS+7 days
396 13.2 AREA CORE 86 days Sun 29/01/17 Thu 27/04/17
406 13.3 UNIT 1 ~ 4 93 days Sun 29/01/17 Fri 05/05/17
418 13.4 UNIT 5 ~ 8 97 days Sun 29/01/17 Tue 09/05/17
430
431 14 LANTAI 12 104 days Sun 29/01/17 Wed 17/05/17
432 14.1 HVAC 10 days Fri 21/04/17 Tue 02/05/17
433 14.1.1 AC + Exhaust 10 days Fri 21/04/17 Tue 02/05/17 395SS+7 days
434 14.2 AREA CORE 93 days Sun 29/01/17 Fri 05/05/17
444 14.3 UNIT 1 ~ 4 100 days Sun 29/01/17 Sat 13/05/17
456 14.4 UNIT 5 ~ 8 104 days Sun 29/01/17 Wed 17/05/17
468
469 15 LANTAI 12.A 111 days Sun 29/01/17 Wed 24/05/17
470 15.1 HVAC 10 days Sat 29/04/17 Tue 09/05/17
471 15.1.1 AC + Exhaust 10 days Sat 29/04/17 Tue 09/05/17 433SS+7 days
472 15.2 AREA CORE 100 days Sun 29/01/17 Sat 13/05/17
482 15.3 UNIT 1 ~ 4 107 days Sun 29/01/17 Sat 20/05/17
494 15.4 UNIT 5 ~ 8 111 days Sun 29/01/17 Wed 24/05/17
506
507 16 LANTAI 12.B 118 days Sun 29/01/17 Fri 02/06/17
508 16.1 HVAC 10 days Sun 07/05/17 Wed 17/05/17
509 16.1.1 AC + Exhaust 10 days Sun 07/05/17 Wed 17/05/17 471SS+7 days
510 16.2 AREA CORE 107 days Sun 29/01/17 Sat 20/05/17
520 16.3 UNIT 1 ~ 4 114 days Sun 29/01/17 Sun 28/05/17
532 16.4 UNIT 5 ~ 8 118 days Sun 29/01/17 Fri 02/06/17
544
545 17 LANTAI 15 125 days Sun 29/01/17 Fri 09/06/17
546 17.1 HVAC 10 days Mon 15/05/17 Wed 24/05/17
547 17.1.1 AC + Exhaust 10 days Mon 15/05/17 Wed 24/05/17 509SS+7 days
548 17.2 AREA CORE 114 days Sun 29/01/17 Sun 28/05/17
558 17.3 UNIT 1 ~ 4 121 days Sun 29/01/17 Mon 05/06/17
570 17.4 UNIT 5 ~ 8 125 days Sun 29/01/17 Fri 09/06/17
582
583 18 LANTAI 16 132 days Sun 29/01/17 Fri 16/06/17
584 18.1 HVAC 10 days Mon 22/05/17 Fri 02/06/17
585 18.1.1 AC + Exhaust 10 days Mon 22/05/17 Fri 02/06/17 547SS+7 days
586 18.2 AREA CORE 121 days Sun 29/01/17 Mon 05/06/17
596 18.3 UNIT 1 ~ 4 128 days Sun 29/01/17 Mon 12/06/17
608 18.4 UNIT 5 ~ 8 132 days Sun 29/01/17 Fri 16/06/17
620
621 19 LANTAI 17 139 days Sun 29/01/17 Mon 03/07/17
622 19.1 HVAC 10 days Tue 30/05/17 Fri 09/06/17
623 19.1.1 AC + Exhaust 10 days Tue 30/05/17 Fri 09/06/17 585SS+7 days
624 19.2 AREA CORE 128 days Sun 29/01/17 Mon 12/06/17
634 19.3 UNIT 1 ~ 4 135 days Sun 29/01/17 Mon 19/06/17
646 19.4 UNIT 5 ~ 8 139 days Sun 29/01/17 Mon 03/07/17
658
659 20 LANTAI 18 145 days Sun 29/01/17 Sun 09/07/17

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: RESCHEDULE PROJECT
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 26/01/17
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
REVISI MASTER SCHEDULE
PROJECT APARTEMENT REGATTA PHASE 2
PT.NUSA RAYA CIPTA
ID Task Task Name Duration Start Finish Predecessors
Mode May 2017 Se
21 January 01 April 11 June 21 August
22/01 29/01 05/02 12/02 19/02 26/02 05/03 12/03 19/03 26/03 02/04 09/04 16/04 23/04 30/04 07/05 14/05 21/05 28/05 04/06 11/06 18/06 25/06 02/07 09/07 16/07 23/07 30/07 06/08 13/08 20/08 27/08
660 20.1 HVAC 10 days Wed 07/06/17 Fri 16/06/17
661 20.1.1 AC + Exhaust 10 days Wed 07/06/17 Fri 16/06/17 623SS+7 days
662 20.2 AREA CORE 135 days Sun 29/01/17 Mon 19/06/17
672 20.3 UNIT 1 ~ 4 142 days Sun 29/01/17 Thu 06/07/17
684 20.4 UNIT 5 ~ 8 145 days Sun 29/01/17 Sun 09/07/17
696
697 21 LANTAI 19 153 days Sun 29/01/17 Mon 17/07/17
698 21.1 HVAC 10 days Wed 14/06/17 Mon 03/07/17
699 21.1.1 AC + Exhaust 10 days Wed 14/06/17 Mon 03/07/17 661SS+7 days
700 21.2 AREA CORE 142 days Sun 29/01/17 Thu 06/07/17
710 21.3 UNIT 1 ~ 4 149 days Sun 29/01/17 Thu 13/07/17
722 21.4 UNIT 5 ~ 8 153 days Sun 29/01/17 Mon 17/07/17
734
735 22 LANTAI 20 158 days Sun 29/01/17 Sat 22/07/17
736 22.1 HVAC 10 days Wed 21/06/17 Mon 10/07/17
737 22.1.1 AC + Exhaust 10 days Wed 21/06/17 Mon 10/07/17 699SS+7 days
738 22.2 AREA CORE 149 days Sun 29/01/17 Thu 13/07/17
748 22.3 UNIT 1 ~ 4 156 days Sun 29/01/17 Thu 20/07/17
760 22.4 UNIT 5 ~ 8 158 days Sun 29/01/17 Sat 22/07/17
772
773 23 LANTAI 21 167 days Sun 29/01/17 Mon 31/07/17
774 23.1 HVAC 10 days Sat 08/07/17 Mon 17/07/17
775 23.1.1 AC + Exhaust 10 days Sat 08/07/17 Mon 17/07/17 737SS+7 days
776 23.2 AREA CORE 156 days Sun 29/01/17 Thu 20/07/17
786 23.3 UNIT 1 ~ 4 163 days Sun 29/01/17 Thu 27/07/17
798 23.4 UNIT 5 ~ 8 167 days Sun 29/01/17 Mon 31/07/17
810
811 24 LANTAI 22 174 days Sun 29/01/17 Mon 07/08/17
812 24.1 HVAC 10 days Sat 15/07/17 Mon 24/07/17
813 24.1.1 AC + Exhaust 10 days Sat 15/07/17 Mon 24/07/17 775SS+7 days
814 24.2 AREA CORE 163 days Sun 29/01/17 Thu 27/07/17
824 24.3 UNIT 1 ~ 4 170 days Sun 29/01/17 Thu 03/08/17
836 24.4 UNIT 5 ~ 8 174 days Sun 29/01/17 Mon 07/08/17
848
849 25 LANTAI 23 181 days Sun 29/01/17 Mon 14/08/17
850 25.1 HVAC 10 days Sat 22/07/17 Mon 31/07/17
851 25.1.1 AC + Exhaust 10 days Sat 22/07/17 Mon 31/07/17 813SS+7 days
852 25.2 AREA CORE 170 days Sun 29/01/17 Thu 03/08/17
862 25.3 UNIT 1 ~ 4 177 days Sun 29/01/17 Thu 10/08/17
874 25.4 UNIT 5 ~ 8 181 days Sun 29/01/17 Mon 14/08/17
886
887 26 LANTAI 23.A 188 days Sun 29/01/17 Tue 22/08/17
888 26.1 HVAC 10 days Sat 29/07/17 Mon 07/08/17
889 26.1.1 AC + Exhaust 10 days Sat 29/07/17 Mon 07/08/17 851SS+7 days
890 26.2 AREA CORE 177 days Sun 29/01/17 Thu 10/08/17
900 26.3 UNIT 1 ~ 4 184 days Sun 29/01/17 Fri 18/08/17
912 26.4 UNIT 5 ~ 8 188 days Sun 29/01/17 Tue 22/08/17
924
925 27 LANTAI ROOF 197 days Sun 29/01/17 Thu 31/08/17
926 27.1 AREA CORE 189 days Sun 29/01/17 Wed 23/08/17
936 27.2 AREA ROOF 15 days Wed 16/08/17 Thu 31/08/17

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: RESCHEDULE PROJECT
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 26/01/17
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 3