Академический Документы
Профессиональный Документы
Культура Документы
During 30” pipeline the work space for Blasting Operators in WS5 is very small. On pictures
below it is shown the blasting frame for the 26” pipe. It is needed to relocate the bulkhead الصيانة
1. TS studying the relocation, waiting for confirmation
34 a 12 highlighted in Fig.14. WS5 is the most sensible station in terms of weld position during the lay الدعم الفني
2. Main. and PE to execute
due to the topography of the room. Beside the bulkhead there is a compressed air engine room. تنفيذ المشروعات
Relocation of the bulkhead is possible to gain space
C
So far the roof in between WS5 and WS6 is made of tarpaulin. This does not prevent possibility
تنفيذ المشروعات ON going, will complete fabrication within 10 days
36 c 12 of water drop on blasted joint. Client could ask for re-blast if something is noted. It is suggested
التفتيش الهندسي Waiting for painting
C to install a small thickness steel roof
Responsible
Sr. item Page Description
department
Meeting 27 Dec. 2017
On Top of WS6 inside chemical storage area, the Component A/B are moved with trans-pallet.
Inside the brown steel structure in Fig. 17 there is the incinerator that has not been used الصيانة Completed, Incinerator removed
38 e 13
(Garbage transportation via vessels). This cover/Incinerator shall be removed in order to التفتيش الهندسي Waiting for painting the area
allow storage of higher number of tanks and easier handling.
C
IT dep. advise that it is in the Survey Dept. domain who already applied this system on
PMS to provide a dedicated PC (or dedicated monitor) for NAV screen at all offices for تكنولوجيا المعلومات
46 h 14 four client PCs, IT will help them technically if required
SAIPEM and PetroBel المساحة
C Waiting for Survey dep. to advise
1. All items onboard PMS12 that are not needed for the project shall be offloaded before the 1. ongoing and barge will be ready before sailing to project location
start.
(1) كل القأسام 2. enlarging is not applicable, new office craven contain two offices will be provided, date
52 f 15 2. SAIPEM and CLIENT offices shall be enlarged.
Once useless items are removed from office floor, space can be recovered for another office- (2) الشئون الدإارية of supply and install is required by admin. dep. and to be installed by 10 days prior
container (Client Fig.20) leaving dry dock
C
1. Kitchen air ducts are oily inside. Deep overhaul to be performed. Oil Filters to be installed, 1. Maint. dep. to advise
extraction of exhaust gas to be improved. الصيانة
54 h 16
الشئون الدإارية
2. Bakery shall be isolated from crane pedestal suitable hygienic doors 2. Admin. dep. will install new door within 15/1/2018
C
Barge Fire Safety plan shall be up to date showing the actual situation on-board. Big size, البحرية TS need to assist for update the safety plan.
65 g 17
C colored copies shall be available around the barge and posted in strategic places. الدعم الفني Safety plan need to be approved from class, to be ready before leaving the dry dock
Helideck must be provided with: 1. Lights will be installed after dry dock activities by maint. dep.
الصيانة
66 h 17 1. Green lights 2. Safety net need to be replaced, marine dep. to advise by date of supply and PE to
2. Professional marking and and safety nets. البحرية
C assist for installation
C 73 o 17 Whip-checks to be available in sufficient quantity for PMS. كل القأسام Each dep. to have enough quantities and spare quantities
كل القأسام
All barge shall be free of un-used equipment and material. All necessary equipment shall be
77 s 17
properly stored, protected and sea fastened
( مدير ااالبارج وربانااالبارجBarge Mgr., Barge cap. & Chief Eng. are responsible
C )ومهندسأولااالبارج
الصيانة
80 v 17 Portable power tools shall be identified and inspected on a regular basis.
تنفيذ المشروعات
Will be ready before sailing to work location
C
1. Toshka store require ventilation, alarm (sound or visual) and emergency exit (via clinic? Via
الصيانة 1. Maint. To advise by completion date
81 w 17 B&C Accommodation?).
تنفيذ المشروعات 2. PE dep. to advise by completion date
C 2. Proper shelves and floor to be installed
Completed
82 x 17 PMS 26 shall not be used for Project activities / personnel transfer or survey operation إدإارة المشروع
C PMS-26 upgraded and renewed in dry dock and will be used for survey activities.
Provide PMS doctor with Chlorine and Nitrite kits for daily checks of the water quality on- الصحة والسلمة المهنية1. Chlorine kit available, need additional fluids, waiting for HSE dep. to provide
83 a 17
C board. الطبية 2. Nitrite kit not available, waiting for HSE to provide
1. Gym equipment are available at Maadia store
الشئون الدإارية 2. A dedicated area under the Masjid identified.
88 f 18 Dedicated area for gym with few equipment shall be provided
البحرية 3. Material for build the area still required (PE to advise)
C 4. Admin to install a sound proof sandwich panel for the gym area.
الشئون الدإارية 1. Area identified
92 j 18 Increase number of European toilets to be available on deck and in offices / common areas تنفيذ المشروعات 2. Material for build the area still required (PE to advise)
C الصيانة 3. Maint. dep. to construct the swage system
الصيانة Removed
93 a 18 Old incinerator to be removed. This incinerator CANNOT be refurbished.
C التفتيش الهندسي Waiting for painting
PMS to get sufficient number of bin and skip for Waste management and segregation. One bin
البحرية Admin. dep. to advise by date of supply plastic pins
94 b 18 for each type of waste shall be available with a different color for the bin and the bag. Waste
shall be segregated in the skip on deck as well الشئون الدإارية Marine dep. to assist
C
Sewage water shall be collected and disposed onshore. No water discharge (treated or non
الصيانة
98 f 18 treated is allowed close to shore). Ongoing, will completed before leaving dry dock
Dedicated supply vessel shall be available to dispose this water البحرية
C
1. Improve noise level in firing line. الصيانة 1. Waiting for maint. dep to advise by action for fire line
101 i 18
C 2. Also evaluate means for noise insulation from anchor winches. الصحة والسلمة المهنية2. Waiting for Saipem rep. for further discussion for anchors winches
البنود الساسية
الدعم الفني
المشروعات
الدارة
الصيانة
البحرية
الدارية
مشترك
الطبية
HSE
QC
تك
تنفيذ المشروعات 8 16 8 5 1 6 7
الصيانة 30 13 5 30
الدارية 10 6 10
البحرية 15 5 15
تكنولوجيا المعلومات 4 3 4
HSE 2 2 2
الدعم الفني - 8 0
التفتيش الهندسي - 8 0
الطبية 1 1 1
70 62 70
33
Sr. item Page
C a 3
3 c 4
4 d 4
5 e 4
6 a 4
7 b 5
10 e 6
11 a 7
19 g 9
21 i 10
22 j 10
24 a 11
30 g 11
34 a 12
36 c 12
38 e 13
46 h 14
52 f 15
54 h 16
65 g 17
66 h 17
73 o 17
77 s 17
80 v 17
81 w 17
82 x 17
83 a 17
88 f 18
92 j 18
93 a 18
94 b 18
98 f 18
101 i 18
Description
1.5mT Lifting Beam does not allow a sufficient head room for the lifting of the 30” Induction
Coil with 1.5mT manual lever hoist, Solution could be to:
1. Purchase a short chain hoist (an air/electric hoist is preferred).
2. The lifting beam shall be certified from PMS technical department.
A transversal Lifting Beam shall be installed for facilitate coating transition operation. This
lifting beam shall be used to move the temporary head in WS0
Installation of lifting pad-eyes along the firing line (specially between WS0 and WS1) is
necessary. These pad eyes shall be used as safe lifting point during SJ movement when carrying
out initiation or any non-routine operation (i.e. Beveling on WS2).
A lifting beam between WS0 and WS1 would help handling of short pipes/heads
The size of the WS1 floor shall be enlarged in order to guarantee enough room for Welder on
the STBD and PS side during 30” pipe. This shall be done recovering 360 mm and 200 mm as
per pictures below. FL floor is a structure made of steel and wooden beams. Modifications can
be performed without any major modification on the vessel structure
WS1 removable roof shall be equipped with proper winch in order to open and close hatch
without using crawler crane.
The size of the WS2 and WS3 floor shall be enlarged in order to guarantee enough room for
Welder on the STBD side during 30” pipe welding. This shall be done recovering 360mm as
per pictures below.
A shelf shall be fabricated along the wall in front of the Interpreter for storage
Step inside the WS4 (port side) needed to be removed, making the station more spacious
The Spare Scan block for 30” will reduce the working space for the operator. Relocation shall
be performed as per Fig. 12 toward STBD side. Repair Welding machine shall be relocated
inside this station.
1. Inadequate and limited ventilation.
2. Windproof tents are necessary in WS-1 during welding activities in order to avoid porosity.
SWSe workshop for the welding technicians and for the maintenance of the welding equipment
very tiny (approx. 2 square meters).
1. Not properly insulated from the outside precipitations (water flow inside trough the
walls).
2. Computer and designated line missing for Weld tech to be used for communication,
reports, orders, etc.
SWSe system for test bench not present in the workshop.
During 30” pipeline the work space for Blasting Operators in WS5 is very small. On pictures
below it is shown the blasting frame for the 26” pipe. It is needed to relocate the bulkhead
highlighted in Fig.14. WS5 is the most sensible station in terms of weld position during the lay
due to the topography of the room. Beside the bulkhead there is a compressed air engine room.
Relocation of the bulkhead is possible to gain space
So far the roof in between WS5 and WS6 is made of tarpaulin. This does not prevent possibility
of water drop on blasted joint. Client could ask for re-blast if something is noted. It is
suggested to install a small thickness steel roof
On Top of WS6 inside chemical storage area, the Component A/B are moved with trans-pallet.
Inside the brown steel structure in Fig. 17 there is the incinerator that has not been used
(Garbage transportation via vessels). This cover/Incinerator shall be removed in order to
allow storage of higher number of tanks and easier handling.
PMS to provide a dedicated PC (or dedicated monitor) for NAV screen at all offices for
SAIPEM and PetroBel
1. All items onboard PMS12 that are not needed for the project shall be offloaded before the
start.
2. SAIPEM and CLIENT offices shall be enlarged.
Once useless items are removed from office floor, space can be recovered for another office-
container (Client Fig.20)
1. Kitchen air ducts are oily inside. Deep overhaul to be performed. Oil Filters to be installed,
extraction of exhaust gas to be improved.
Barge Fire Safety plan shall be up to date showing the actual situation on-board. Big size,
colored copies shall be available around the barge and posted in strategic places.
1. Toshka store require ventilation, alarm (sound or visual) and emergency exit (via clinic? Via
B&C Accommodation?).
2. Proper shelves and floor to be installed
PMS 26 shall not be used for Project activities / personnel transfer or survey operation
Provide PMS doctor with Chlorine and Nitrite kits for daily checks of the water quality on-
board.
Dedicated area for gym with few equipment shall be provided
Increase number of European toilets to be available on deck and in offices / common areas
PMS to get sufficient number of bin and skip for Waste management and segregation. One bin
for each type of waste shall be available with a different color for the bin and the bag. Waste
shall be segregated in the skip on deck as well
Sewage water shall be collected and disposed onshore. No water discharge (treated or non
treated is allowed close to shore).
Dedicated supply vessel shall be available to dispose this water
1. Improve noise level in firing line.
2. Also evaluate means for noise insulation from anchor winches.
Responsible department
تنفيذ المشروعات
الدعم الفني
تنفيذ المشروعات
الدعم الفني
تنفيذ المشروعات
الدعم الفني
تنفيذ المشروعات
الدعم الفني
تنفيذ المشروعات
الدعم الفني
التفتيش الهندسي
تنفيذ المشروعات
الصيانة
الصيانة
تكنولوجيا المعلومات
تنفيذ المشروعات
الدعم الفني
التفتيش الهندسي
تنفيذ المشروعات
التفتيش الهندسي
تنفيذ المشروعات
التفتيش الهندسي
تنفيذ المشروعات
التفتيش الهندسي
الصيانة
تنفيذ المشروعات
الشئون الدإارية
تكنولوجيا المعلومات
الصيانة
الدعم الفني
تنفيذ المشروعات
تنفيذ المشروعات
التفتيش الهندسي
الصيانة
التفتيش الهندسي
تكنولوجيا المعلومات
المساحة
الصيانة
الشئون الدإارية
البحرية
الدعم الفني
الصيانة
البحرية
كل القأسام
كل القأسام
)مدير ااالبارج وربانااالبارج ومهندسأول ااالبارج(
الصيانة
تنفيذ المشروعات
الصيانة
تنفيذ المشروعات
إدإارة المشروع
الشئون الدإارية
تنفيذ المشروعات
الصيانة
الصيانة
التفتيش الهندسي
البحرية
الشئون الدإارية
الصيانة
البحرية
الصيانة
الصحة والسلمة المهنية
Meeting 27 Dec. 2017
Not applicable
Waiting for Saipem rep. for further discussion for another solution
A beam is installed as a monorail
Waiting for Saipem inspection and confirmation
A beam is installed as a monorail
Waiting for Saipem inspection and confirmation
Fabrication completed
Waiting for painting
Fabrication completed
Waiting for painting
Fabrication completed
Waiting for painting
Step Removed.
Waiting for painting
Performed
Waiting for Painting
1. Maintenance to advise
2. Waiting for providing tents from PE department
1. Regular Sandwich panels will provided, date is required by admin, Waiting for
Saipem to confirm
2. Ongoing with purchasing, ETA : 1st of Feb. 2018
1. TS studying the relocation, waiting for confirmation
2. Main. and PE to execute
IT dep. advise that it is in the Survey Dept. domain who already applied this
system on four client PCs, IT will help them technically if required
Waiting for Survey dep. to advise
Completed
PMS-26 upgraded and renewed in dry dock and will be used for survey activities.
1. Chlorine kit available, need additional fluids, waiting for HSE dep. to provide
2. Nitrite kit not available, waiting for HSE to provide
1. Gym equipment are available at Maadia store
2. A dedicated area under the Masjid identified.
3. Material for build the area still required (PE to advise)
4. Admin to install a sound proof sandwich panel for the gym area.
1. Area identified
2. Material for build the area still required (PE to advise)
3. Maint. dep. to construct the swage system
Removed
Waiting for painting
Admin. dep. to advise by date of supply plastic pins
Marine dep. to assist