PORTO ARABIA PARCEL TOWER 

DETAILED SCHEDULE OF WORK

Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D


Duration

Total 334 01-Jun-13 30-Sep-14 30-Sep-14, T

Porto Arabia
Arabi New Project 334 01-Jun-13 30-Sep-14 30-Sep-14, P

Milestones 334 01-Jun-13 30-Sep-14 30-Sep-14, M


MLE1000 Start of Project 0 01-Jun-13 Start of Project
MLE1010 Site office 0 15-Jun-13 Site office
MLE1015 Mobilization of Manpower 0 29-Jun-13 Mobilization of Manpower
MLE1020 Temporary fire & wet riser 0 05-Aug-13 Temporary fire & wet riser
MLE1030 Issue of all Drawings 0 14-Jul-13 Issue of all Drawings
MLE1040 Structure repair completion 0 05-Aug-13 Structure repair completion
MLE1050 Foyer area completion 0 16-Nov-13 Foyer area completion
MLE1070 Amenity level completion 0 30-Nov-13 Amenity level completion
MLE1080 Facade work Completion 0 14-Dec-13 Facade work Completion
MLE1090 Mock up room completion 0 09-Dec-13 Mock up room completion
MLE1100 Podium 1 to 4 Completion 0 21-Jan-14 Podium 1 to 4 Completion
MLE1105 Roof Level Completion 0 10-Feb-14 Roof Level Completion
MLE1110 Level 1-6 Substantial Completion 0 13-Feb-14 Level 1-6 Substantial Completion
MLE1120 Level 7-12 Substantial Completion 0 20-Apr-14 Level 7-12 Substantial Completion
MLE1130 Level 13-18 Substatial Completion 0 24-Jun-14 Level 13-18 Substatial Comp
MLE1140 Level 19-20 Substatial Completion 0 16-Jul-14 Level 19-20 Substatial Co
MLE1145 Builders elevators operational 0 04-Mar-14 Builders elevators operational
MLE1150 Removal of Builders Hoist 0 18-Mar-14 Removal of Builders Hoist
MLE1160 Removal of Tower Crane 0 02-Apr-14 Removal of Tower Crane
MLE1170 Power ON 0 26-Aug-14 Power ON
MLE1180 Chilled water connection 0 04-Aug-14 Chilled water connectio
MLE1190 Wild air ON 0 04-Mar-14 Wild air ON
MLE1200 Drainage Connection 0 04-Aug-14 Drainage Connection
MLE1210 Domestic Water Connection 0 04-Aug-14 Domestic Water Conn
MLE1220 UDC Completion Certificate (Substantial) 0 30-Jul-14 UDC Completion Certif
MLE1230 QCDD Inspection & Approval 0 27-Sep-14 QCDD Inspec

Actual Work Critical Remaining Work Summary Page 1 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

MLE1240 UDC Occupation Certificate 0 30-Sep-14 UDC Occupa


Preconstruction
Preconstructi 225 01-Jun-13 24-Apr-14 24-Apr-14, Preconstruction
Engineering 115 14-Jul-13 29-Dec-13 29-Dec-13, Engineering
Submittals 90 14-Jul-13 21-Nov-13 21-Nov-13, Submittals
SU1000 All Civil & / Arch drawings 90 14-Jul-13 21-Nov-13 All Civil & / Arch drawings
SU1010 Electrical drawings 90 14-Jul-13 21-Nov-13 Electrical drawings
SU1020 Plumbing & Drainage drawings 90 14-Jul-13 21-Nov-13 Plumbing & Drainage drawings
SU1030 Fire Fighting Drawings 90 14-Jul-13 21-Nov-13 Fire Fighting Drawings
SU1040 HVAC drawings 90 14-Jul-13 21-Nov-13 HVAC drawings
Approvals 100 05-Aug-13 29-Dec-13 29-Dec-13, Approvals
AP1000 All Civil & / Arch drawings 100 05-Aug-13 29-Dec-13 All Civil & / Arch drawings
AP1010 Electrical drwaings 100 05-Aug-13 29-Dec-13 Electrical drwaings
AP1020 Plumbing & Drainage drawings 100 05-Aug-13 29-Dec-13 Plumbing & Drainage drawings
AP1030 Fire Fighting Drawings 100 05-Aug-13 29-Dec-13 Fire Fighting Drawings
AP1040 HVAC drawings 100 05-Aug-13 29-Dec-13 HVAC drawings
Procurement 225 01-Jun-13 24-Apr-14 24-Apr-14, Procurement
Civil/Arch 130 01-Jun-13 07-Dec-13 07-Dec-13, Civil/Arch
Material Submittal
Sub 60 01-Jun-13 26-Aug-13 26-Aug-13, Material Submittal
CMS1000 Marbles / Tiles 60 01-Jun-13 26-Aug-13 Marbles / Tiles
CMS1010 Gypsum & other ceiling boards 60 01-Jun-13 26-Aug-13 Gypsum & other ceiling boards
CMS1020 Wooden Doors & Accessories 60 01-Jun-13 26-Aug-13 Wooden Doors & Accessories
CMS1030 Aluminium windows & Doors 60 01-Jun-13 26-Aug-13 Aluminium windows & Doors
CMS1040 Paints & other finishes 60 01-Jun-13 26-Aug-13 Paints & other finishes
Material Approval
App 60 15-Jun-13 10-Sep-13 10-Sep-13, Material Approval
CMA1050 Marbles / Tiles 60 15-Jun-13 10-Sep-13 Marbles / Tiles
CMA1060 Gypsum & other ceiling boards 60 15-Jun-13 10-Sep-13 Gypsum & other ceiling boards
CMA1070 Wooden Doors & Accessories 60 15-Jun-13 10-Sep-13 Wooden Doors & Accessories
CMA1080 Aluminium windows & Doors 60 15-Jun-13 10-Sep-13 Aluminium windows & Doors
CMA1090 Paints & other finishes 60 15-Jun-13 10-Sep-13 Paints & other finishes
Fabrication / Delivery on site 90 29-Jul-13 07-Dec-13 07-Dec-13, Fabrication / Delivery on site
CMD1100 Marbles / Tiles 90 29-Jul-13 07-Dec-13 Marbles / Tiles
CMD1110 Gypsum & other ceiling boards 90 29-Jul-13 07-Dec-13 Gypsum & other ceiling boards
CMD1120 Wooden Doors & Accessories 90 29-Jul-13 07-Dec-13 Wooden Doors & Accessories
CMD1130 Aluminium windows & Doors 90 29-Jul-13 07-Dec-13 Aluminium windows & Doors

Actual Work Critical Remaining Work Summary Page 2 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

CMD1140 Paints & other finishes 90 29-Jul-13 07-Dec-13 Paints & other finishes
Mechanical & Plumbing 225 01-Jun-13 24-Apr-14 24-Apr-14, Mechanical & Plumbing
Material Submittal
Sub 60 01-Jun-13 26-Aug-13 26-Aug-13, Material Submittal
MMS1000 Ducts & Accessories 60 01-Jun-13 26-Aug-13 Ducts & Accessories
MMS1010 Pipes & fittings 60 01-Jun-13 26-Aug-13 Pipes & fittings
MMS1020 Sanitary fixtures 60 01-Jun-13 26-Aug-13 Sanitary fixtures
MMS1030 Chilled water pipes 60 01-Jun-13 26-Aug-13 Chilled water pipes
MMS1040 Chilled water pump 60 01-Jun-13 26-Aug-13 Chilled water pump
MMS1050 Fire fighting pumps 60 01-Jun-13 26-Aug-13 Fire fighting pumps
MMS1060 HVAC machineries 60 01-Jun-13 26-Aug-13 HVAC machineries
MMS1070 Final Fix items 60 01-Jun-13 26-Aug-13 Final Fix items
Material Approval
App 120 22-Jun-13 14-Dec-13 14-Dec-13, Material Approval
MMA1080 Ducts & Accessories 60 22-Jun-13 17-Sep-13 Ducts & Accessories
MMA1090 Pipes & fittings 60 22-Jun-13 17-Sep-13 Pipes & fittings
MMA1100 Sanitary fixtures 60 22-Jun-13 17-Sep-13 Sanitary fixtures
MMA1110 Chilled water pipes 60 22-Jun-13 17-Sep-13 Chilled water pipes
MMA1120 Chilled water pump 45 27-Aug-13 31-Oct-13 Chilled water pump
MMA1130 Fire fighting pumps 60 27-Aug-13 21-Nov-13 Fire fighting pumps
MMA1140 HVAC machineries 60 22-Jun-13 17-Sep-13 HVAC machineries
MMA1150 Final Fix items 60 17-Sep-13 14-Dec-13 Final Fix items
Fabrication / Delivery on site 180 05-Aug-13 24-Apr-14 24-Apr-14, Fabrication / Delivery on site
MMD1160 Ducts & Accessories 90 05-Aug-13 14-Dec-13 Ducts & Accessories
MMD1170 Pipes & fittings 90 05-Aug-13 14-Dec-13 Pipes & fittings
MMD1180 Sanitary fixtures 90 05-Aug-13 14-Dec-13 Sanitary fixtures
MMD1190 Chilled water pipes 90 05-Aug-13 14-Dec-13 Chilled water pipes
MMD1200 Chilled water pump 120 31-Oct-13 24-Apr-14 Chilled water pump
MMD1210 Fire fighting pumps 100 23-Nov-13 16-Apr-14 Fire fighting pumps
MMD1220 HVAC machineries 90 05-Aug-13 14-Dec-13 HVAC machineries
MMD1230 Final Fix items 90 14-Nov-13 26-Mar-14 Final Fix items
Electrical 210 01-Jun-13 02-Apr-14 02-Apr-14, Electrical
Material Submittals
Sub 60 01-Jun-13 26-Aug-13 26-Aug-13, Material Submittals
EMS1000 Cables & Wiring accessories 60 01-Jun-13 26-Aug-13 Cables & Wiring accessories
EMS1010 Mv panel & Accessories 60 01-Jun-13 26-Aug-13 Mv panel & Accessories
EMS1020 MCC, EMDB & VFD 60 01-Jun-13 26-Aug-13 MCC, EMDB & VFD

Actual Work Critical Remaining Work Summary Page 3 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

EMS1030 BMS system 60 01-Jun-13 26-Aug-13 BMS system


EMS1040 CCTV 60 01-Jun-13 26-Aug-13 CCTV
EMS1050 Diesel Generator 60 01-Jun-13 26-Aug-13 Diesel Generator
EMS1060 Light Fittings 60 01-Jun-13 26-Aug-13 Light Fittings
Material Approvals
App 60 14-Jul-13 09-Oct-13 09-Oct-13, Material Approvals
EMA1070 Cables & Wiring accessories 60 14-Jul-13 09-Oct-13 Cables & Wiring accessories
EMA1080 Mv panel & Accessories 60 14-Jul-13 09-Oct-13 Mv panel & Accessories
EMA1090 MCC, EMDB & VFD 60 14-Jul-13 09-Oct-13 MCC, EMDB & VFD
EMA1100 BMS system 60 14-Jul-13 09-Oct-13 BMS system
EMA1110 CCTV 60 14-Jul-13 09-Oct-13 CCTV
EMA1120 Diesel Generator 60 14-Jul-13 09-Oct-13 Diesel Generator
EMA1130 Light Fittings 60 14-Jul-13 09-Oct-13 Light Fittings
Fabrication / Delivery on site 150 27-Aug-13 02-Apr-14 02-Apr-14, Fabrication / Delivery on site
EMD1140 Cables & Wiring accessories 60 27-Aug-13 21-Nov-13 Cables & Wiring accessories
EMD1150 Mv panel & Accessories 120 09-Oct-13 02-Apr-14 Mv panel & Accessories
EMD1160 MCC, EMDB & VFD 60 27-Aug-13 21-Nov-13 MCC, EMDB & VFD
EMD1170 BMS system 120 09-Oct-13 02-Apr-14 BMS system
EMD1180 CCTV 120 09-Oct-13 02-Apr-14 CCTV
EMD1190 Diesel Generator 120 09-Oct-13 02-Apr-14 Diesel Generator
EMD1200 Light Fittings 100 09-Oct-13 04-Mar-14 Light Fittings
Construction 285 30-Jun-13 19-Aug-14 19-Aug-14, Constru
Facade 115 30-Jun-13 14-Dec-13 14-Dec-13, Facade
Entry elevation
elevatio 55 25-Sep-13 14-Dec-13 14-Dec-13, Entry elevation
FA1300 Rendering works 20 25-Sep-13 23-Oct-13 Rendering works
FA1310 GRC works 30 09-Oct-13 21-Nov-13 GRC works
FA1320 Aluminium windows 20 24-Oct-13 21-Nov-13 Aluminium windows
FA1330 Light fittings 15 07-Nov-13 30-Nov-13 Light fittings
FA1340 Protective Coating 10 30-Nov-13 14-Dec-13 Protective Coating
Rear elevation 55 27-Aug-13 14-Nov-13 14-Nov-13, Rear elevation
FA1250 Rendering works 20 27-Aug-13 24-Sep-13 Rendering works
FA1260 GRC works 30 10-Sep-13 23-Oct-13 GRC works
FA1270 Aluminium windows 20 25-Sep-13 23-Oct-13 Aluminium windows
FA1280 Light fittings 15 09-Oct-13 31-Oct-13 Light fittings
FA1290 Protective Coating 10 31-Oct-13 14-Nov-13 Protective Coating

Actual Work Critical Remaining Work Summary Page 4 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

Water front e
elevation 55 29-Jul-13 16-Oct-13 16-Oct-13, Water front elevation
FA1200 Rendering works 20 29-Jul-13 26-Aug-13 Rendering works
FA1210 GRC works 30 12-Aug-13 24-Sep-13 GRC works
FA1220 Aluminium windows 20 27-Aug-13 24-Sep-13 Aluminium windows
FA1230 Light fittings 15 10-Sep-13 02-Oct-13 Light fittings
FA1240 Protective Coating 10 02-Oct-13 16-Oct-13 Protective Coating
Radial elevation
elevat 55 30-Jun-13 17-Sep-13 17-Sep-13, Radial elevation
FA1150 Rendering works 20 30-Jun-13 28-Jul-13 Rendering works
FA1160 GRC works 30 14-Jul-13 26-Aug-13 GRC works
FA1170 Aluminium windows 20 29-Jul-13 26-Aug-13 Aluminium windows
FA1180 Light fittings 15 12-Aug-13 03-Sep-13 Light fittings
FA1190 Protective Coating 10 03-Sep-13 17-Sep-13 Protective Coating
Foyer Area 96 30-Jun-13 16-Nov-13 16-Nov-13, Foyer Area
Entrance Lobby
Lob 96 30-Jun-13 16-Nov-13 16-Nov-13, Entrance Lobby
Civil / Arch 96 30-Jun-13 16-Nov-13 16-Nov-13, Civil / Arch
FY1000 Masonry works 7 30-Jun-13 09-Jul-13 Masonry works
FY1010 Plastering 5 09-Jul-13 16-Jul-13 Plastering
FY1020 1st coat paint on walls 5 17-Jul-13 24-Jul-13 1st coat paint on walls
FY1030 Floor screeding 5 24-Jul-13 31-Jul-13 Floor screeding
FY1040 Marble flooring 7 31-Jul-13 11-Aug-13 Marble flooring
FY1050 Marble cladding works 7 11-Aug-13 20-Aug-13 Marble cladding works
FY1060 Ceiling gypsum works 10 31-Aug-13 15-Sep-13 Ceiling gypsum works
FY1070 Ceiling painting 1st coat 7 15-Sep-13 24-Sep-13 Ceiling painting 1st coat
FY1080 Aluminum doors & windows 5 25-Sep-13 02-Oct-13 Aluminum doors & windows
FY1090 Automatic revolving door 5 02-Oct-13 09-Oct-13 Automatic revolving door
FY1100 Wooden doors & accessories 5 09-Oct-13 16-Oct-13 Wooden doors & accessories
FY1110 Reception counter 7 16-Oct-13 27-Oct-13 Reception counter
FY1120 Final coat on celing 7 27-Oct-13 06-Nov-13 Final coat on celing
FY1130 Final coat on walls 7 06-Nov-13 16-Nov-13 Final coat on walls
MEP 36 11-Aug-13 02-Oct-13 02-Oct-13, MEP
FYM1000 Light & small power 1st & 2nd fix 5 11-Aug-13 18-Aug-13 Light & small power 1st & 2nd fix
FYM1010 Fire Fighting Pipe installation 7 11-Aug-13 20-Aug-13 Fire Fighting Pipe installation
FYM1020 Fire Alarm 1st & 2nd fix 5 11-Aug-13 18-Aug-13 Fire Alarm 1st & 2nd fix
FYM1030 BMS & data 1st & 2nd fix 5 11-Aug-13 18-Aug-13 BMS & data 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 5 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

FYM1040 CCTV 1st & 2nd fix 5 11-Aug-13 18-Aug-13 CCTV 1st & 2nd fix
FYM1045 HVAC 1st & 2nd fix 7 11-Aug-13 20-Aug-13 HVAC 1st & 2nd fix
FYM1050 MEP testing 7 21-Aug-13 31-Aug-13 MEP testing
FYM1060 MEP final fix 5 25-Sep-13 02-Oct-13 MEP final fix
Concierge room
ro 42 11-Aug-13 10-Oct-13 10-Oct-13, Concierge room
Civil / Arch 42 11-Aug-13 10-Oct-13 10-Oct-13, Civil / Arch
FCR1050 Wet area water proofing 7 11-Aug-13 20-Aug-13 Wet area water proofing
FCR1060 Wet area flooring 5 25-Aug-13 01-Sep-13 Wet area flooring
FCR1070 1st coat on walls 5 02-Sep-13 09-Sep-13 1st coat on walls
FCR1080 Wet area ceiling works 5 09-Sep-13 16-Sep-13 Wet area ceiling works
FCR1090 Dry area ceiling works 5 16-Sep-13 23-Sep-13 Dry area ceiling works
FCR1100 1st coat on ceiling 3 23-Sep-13 28-Sep-13 1st coat on ceiling
FCR1110 Wooden doors & accessories 3 28-Sep-13 02-Oct-13 Wooden doors & accessories
FCR1120 Final coat on ceiling 3 02-Oct-13 06-Oct-13 Final coat on ceiling
FCR1130 Final coat on walls 3 07-Oct-13 10-Oct-13 Final coat on walls
MEP 33 18-Aug-13 05-Oct-13 05-Oct-13, MEP
FCR1000 Light & small power 1st & 2nd fix 5 18-Aug-13 25-Aug-13 Light & small power 1st & 2nd fix
FCR1010 HVAC 1st & 2nd fix 5 18-Aug-13 25-Aug-13 HVAC 1st & 2nd fix
FCR1020 Fire fighting pipe installation 5 18-Aug-13 25-Aug-13 Fire fighting pipe installation
FCR1030 MEP testing 5 25-Aug-13 01-Sep-13 MEP testing
FCR1040 MEP final fix 5 28-Sep-13 05-Oct-13 MEP final fix
Canopy 65 17-Jul-13 20-Oct-13 20-Oct-13, Canopy
Civil / Arch 65 17-Jul-13 20-Oct-13 20-Oct-13, Civil / Arch
FC1000 Plastering works 7 17-Jul-13 27-Jul-13 Plastering works
FC1010 GRC works 7 27-Jul-13 06-Aug-13 GRC works
FC1020 Paint 1st coat on walls 5 06-Aug-13 13-Aug-13 Paint 1st coat on walls
FC1030 Celing gypsum works 7 08-Sep-13 17-Sep-13 Celing gypsum works
FC1040 1st coat paint on ceiling 5 17-Sep-13 24-Sep-13 1st coat paint on ceiling
FC1050 Flooring works 7 25-Sep-13 05-Oct-13 Flooring works
FC1060 Ceiling final coat painting 5 05-Oct-13 12-Oct-13 Ceiling final coat painting
FC1070 Final coat on walls 5 13-Oct-13 20-Oct-13 Final coat on walls
MEP 33 18-Aug-13 05-Oct-13 05-Oct-13, MEP
FCM1000 Light & small power 1st & 2nd fix 7 18-Aug-13 28-Aug-13 Light & small power 1st & 2nd fix
FCM1010 Fire fighting pipe installation 7 18-Aug-13 28-Aug-13 Fire fighting pipe installation

Actual Work Critical Remaining Work Summary Page 6 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

FCM1020 BMS 1st & 2nd fix 7 18-Aug-13 28-Aug-13 BMS 1st & 2nd fix
FCM1030 Fire Alarm 1st & 2nd fix 7 18-Aug-13 28-Aug-13 Fire Alarm 1st & 2nd fix
FCM1040 MEP testing 7 28-Aug-13 07-Sep-13 MEP testing
FCM1050 MEP final fix 7 25-Sep-13 05-Oct-13 MEP final fix
Podium 255 12-Aug-13 19-Aug-14 19-Aug-14, Podium
Parking 1 195 27-Aug-13 07-Jun-14 07-Jun-14, Parking 1
Civil / Arch 104 25-Sep-13 23-Feb-14 23-Feb-14, Civil / Arch
PA1540 Masonry Works 10 25-Sep-13 09-Oct-13 Masonry Works
PA1550 Plastering Works 10 09-Oct-13 23-Oct-13 Plastering Works
PA1560 Ceiling splatter painting 10 24-Oct-13 07-Nov-13 Ceiling splatter painting
PA1570 Wall 1st coat painting 10 07-Nov-13 21-Nov-13 Wall 1st coat painting
PA1575 Wheel stopper fixing 10 23-Nov-13 07-Dec-13 Wheel stopper fixing
PA1580 Floor screeding 7 22-Dec-13 31-Dec-13 Floor screeding
PA1590 Epoxy preparation on floor 10 31-Dec-13 15-Jan-14 Epoxy preparation on floor
PA1600 Floor epoxy coating on floor 10 15-Jan-14 29-Jan-14 Floor epoxy coating on floor
PA1610 Final Coat on wall 7 29-Jan-14 09-Feb-14 Final Coat on wall
PA1615 Column Guard fixing 7 29-Jan-14 09-Feb-14 Column Guard fixing
PA1620 Paking line & number marking 10 09-Feb-14 23-Feb-14 Paking line & number marking
PA1625 Steel Door Fixing 7 09-Feb-14 19-Feb-14 Steel Door Fixing
MEP 40 07-Nov-13 05-Jan-14 05-Jan-14, MEP
PME1000 Light & Small power 1st & 2nd fix 20 07-Nov-13 07-Dec-13 Light & Small power 1st & 2nd fix
PME1010 CCTV 1st & 2nd fix 10 07-Nov-13 21-Nov-13 CCTV 1st & 2nd fix
PME1020 Fire Alarm 1st & 2nd fix 10 07-Nov-13 21-Nov-13 Fire Alarm 1st & 2nd fix
PME1030 BMS 1st & 2nd fix 10 07-Nov-13 21-Nov-13 BMS 1st & 2nd fix
PME1040 Fire fighting pipe installation 30 07-Nov-13 21-Dec-13 Fire fighting pipe installation
PME1050 CO system 1st & 2nd fix 10 07-Nov-13 21-Nov-13 CO system 1st & 2nd fix
PME1060 Plumbing 1st & 2nd fix 10 07-Nov-13 21-Nov-13 Plumbing 1st & 2nd fix
PME1070 Ducting & Insulation works 30 07-Nov-13 21-Dec-13 Ducting & Insulation works
PME1080 MEP final fix 10 22-Dec-13 05-Jan-14 MEP final fix
Utility rooms 195 27-Aug-13 07-Jun-14 07-Jun-14, Utility rooms
Substation 75 27-Aug-13 14-Dec-13 14-Dec-13, Substation
SB1000 Civil works 15 27-Aug-13 17-Sep-13 Civil works
SB1010 Electrical Equipment Installation 20 17-Sep-13 16-Oct-13 Electrical Equipment Installation
SB1020 Cable termination 15 16-Oct-13 07-Nov-13 Cable termination

Actual Work Critical Remaining Work Summary Page 7 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

SB1030 FM 200 Installation 20 07-Nov-13 07-Dec-13 FM 200 Installation


SB1040 Light fittings 5 07-Dec-13 14-Dec-13 Light fittings
ETS room 115 17-Sep-13 04-Mar-14 04-Mar-14, ETS room
ET1000 Civil works 10 17-Sep-13 02-Oct-13 Civil works
ET1010 Chilled Water pump installation 15 02-Oct-13 23-Oct-13 Chilled Water pump installation
ET1020 Mechanical Equipments Installation 30 24-Oct-13 07-Dec-13 Mechanical Equipments Installation
ET1030 Piping & Insulation works 30 07-Dec-13 19-Jan-14 Piping & Insulation works
ET1040 Control panel Installation 10 20-Jan-14 03-Feb-14 Control panel Installation
ET1050 Cabling & termination 15 03-Feb-14 25-Feb-14 Cabling & termination
ET1060 Light fittings 5 25-Feb-14 04-Mar-14 Light fittings
Pump room 74 02-Oct-13 18-Jan-14 18-Jan-14, Pump room
PR1000 Civil works 10 02-Oct-13 16-Oct-13 Civil works
PR1010 Fire fighting pump installation 7 16-Oct-13 27-Oct-13 Fire fighting pump installation
PR1020 Domestic water pump installation 7 23-Nov-13 02-Dec-13 Domestic water pump installation
PR1030 Control panel Installation 7 02-Dec-13 12-Dec-13 Control panel Installation
PR1040 Piping works 10 12-Dec-13 26-Dec-13 Piping works
PR1050 Cabling & termination 10 28-Dec-13 11-Jan-14 Cabling & termination
PR1060 Light fittings 5 11-Jan-14 18-Jan-14 Light fittings
Generator room 45 02-Apr-14 07-Jun-14 07-Jun-14, Generator room
GE1000 Generator Installation 10 02-Apr-14 16-Apr-14 Generator Installation
GE1010 Control panel installation 10 17-Apr-14 01-May-14 Control panel installation
GE1020 Ducting 15 17-Apr-14 08-May-14 Ducting
GE1030 Cabling & termination 10 01-May-14 15-May-14 Cabling & termination
GE1040 Civil finishing works 10 17-May-14 31-May-14 Civil finishing works
GE1050 Light fittings 5 31-May-14 07-Jun-14 Light fittings
Parking 2 235 10-Sep-13 19-Aug-14 19-Aug-14, Parking
Civil / Arch 104 10-Sep-13 09-Feb-14 09-Feb-14, Civil / Arch
PA1450 Masonry Works 10 10-Sep-13 24-Sep-13 Masonry Works
PA1460 Plastering Works 10 25-Sep-13 09-Oct-13 Plastering Works
PA1470 Ceiling splatter painting 10 09-Oct-13 23-Oct-13 Ceiling splatter painting
PA1480 Wall 1st coat painting 10 24-Oct-13 07-Nov-13 Wall 1st coat painting
PA1485 Wheel stopper fixing 10 07-Nov-13 21-Nov-13 Wheel stopper fixing
PA1490 Floor screeding 7 07-Dec-13 17-Dec-13 Floor screeding
PA1500 Epoxy preparation on floor 10 17-Dec-13 31-Dec-13 Epoxy preparation on floor

Actual Work Critical Remaining Work Summary Page 8 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

PA1510 Floor epoxy coating on floor 10 31-Dec-13 15-Jan-14 Floor epoxy coating on floor
PA1520 Final Coat on wall 7 15-Jan-14 25-Jan-14 Final Coat on wall
PA1525 Column Guard fixing 7 15-Jan-14 25-Jan-14 Column Guard fixing
PA1530 Paking line & number marking 10 26-Jan-14 09-Feb-14 Paking line & number marking
PA1535 Steel Door Fixing 7 26-Jan-14 04-Feb-14 Steel Door Fixing
MEP 50 24-Oct-13 05-Jan-14 05-Jan-14, MEP
PME1090 Light & Small power 1st & 2nd fix 20 24-Oct-13 21-Nov-13 Light & Small power 1st & 2nd fix
PME1100 CCTV 1st & 2nd fix 10 24-Oct-13 07-Nov-13 CCTV 1st & 2nd fix
PME1110 Fire Alarm 1st & 2nd fix 10 24-Oct-13 07-Nov-13 Fire Alarm 1st & 2nd fix
PME1120 BMS 1st & 2nd fix 10 24-Oct-13 07-Nov-13 BMS 1st & 2nd fix
PME1130 Fire fighting pipe installation 30 24-Oct-13 07-Dec-13 Fire fighting pipe installation
PME1140 CO system 1st & 2nd fix 10 24-Oct-13 07-Nov-13 CO system 1st & 2nd fix
PME1150 Plumbing 1st & 2nd fix 10 24-Oct-13 07-Nov-13 Plumbing 1st & 2nd fix
PME1160 Ducting & Insulation works 30 24-Oct-13 07-Dec-13 Ducting & Insulation works
PME1170 MEP final fix 20 07-Dec-13 05-Jan-14 MEP final fix
MV Panel room
ro 95 02-Apr-14 19-Aug-14 19-Aug-14, MV Pan
MV1000 MV panel Installation 30 02-Apr-14 15-May-14 MV panel Installation
MV1010 Cabling & termination 30 17-May-14 29-Jun-14 Cabling & termination
MV1020 Foam system 20 29-Jun-14 28-Jul-14 Foam system
MV1030 Civil finishing works 10 28-Jul-14 11-Aug-14 Civil finishing works
MV1040 Light fittings 5 12-Aug-14 19-Aug-14 Light fittings
Parking 3 104 27-Aug-13 25-Jan-14 25-Jan-14, Parking 3
Civil / Arch 104 27-Aug-13 25-Jan-14 25-Jan-14, Civil / Arch
PA1360 Masonry Works 10 27-Aug-13 10-Sep-13 Masonry Works
PA1370 Plastering Works 10 10-Sep-13 24-Sep-13 Plastering Works
PA1380 Ceiling splatter painting 10 25-Sep-13 09-Oct-13 Ceiling splatter painting
PA1390 Wall 1st coat painting 10 09-Oct-13 23-Oct-13 Wall 1st coat painting
PA1395 Wheel stopper fixing 10 24-Oct-13 07-Nov-13 Wheel stopper fixing
PA1400 Floor screeding 7 23-Nov-13 02-Dec-13 Floor screeding
PA1410 Epoxy preparation on floor 10 02-Dec-13 17-Dec-13 Epoxy preparation on floor
PA1420 Floor epoxy coating on floor 10 17-Dec-13 31-Dec-13 Floor epoxy coating on floor
PA1430 Final Coat on wall 7 31-Dec-13 11-Jan-14 Final Coat on wall
PA1435 Column Guard fixing 7 31-Dec-13 11-Jan-14 Column Guard fixing
PA1440 Paking line & number marking 10 11-Jan-14 25-Jan-14 Paking line & number marking

Actual Work Critical Remaining Work Summary Page 9 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

PA1445 Steel Door Fixing 7 11-Jan-14 21-Jan-14 Steel Door Fixing


MEP 50 09-Oct-13 21-Dec-13 21-Dec-13, MEP
PME1180 Light & Small power 1st & 2nd fix 20 09-Oct-13 07-Nov-13 Light & Small power 1st & 2nd fix
PME1190 CCTV 1st & 2nd fix 10 09-Oct-13 23-Oct-13 CCTV 1st & 2nd fix
PME1200 Fire Alarm 1st & 2nd fix 10 09-Oct-13 23-Oct-13 Fire Alarm 1st & 2nd fix
PME1210 BMS 1st & 2nd fix 10 09-Oct-13 23-Oct-13 BMS 1st & 2nd fix
PME1220 Fire fighting pipe installation 30 09-Oct-13 21-Nov-13 Fire fighting pipe installation
PME1230 CO system 1st & 2nd fix 10 09-Oct-13 23-Oct-13 CO system 1st & 2nd fix
PME1240 Plumbing 1st & 2nd fix 10 09-Oct-13 23-Oct-13 Plumbing 1st & 2nd fix
PME1250 Ducting & Insulation works 30 09-Oct-13 21-Nov-13 Ducting & Insulation works
PME1260 MEP final fix 20 23-Nov-13 21-Dec-13 MEP final fix
Parking 4 104 12-Aug-13 11-Jan-14 11-Jan-14, Parking 4
Civil / Arch 104 12-Aug-13 11-Jan-14 11-Jan-14, Civil / Arch
PA1270 Masonry Works 10 12-Aug-13 26-Aug-13 Masonry Works
PA1280 Plastering Works 10 27-Aug-13 10-Sep-13 Plastering Works
PA1290 Ceiling splatter painting 10 10-Sep-13 24-Sep-13 Ceiling splatter painting
PA1300 Wall 1st coat painting 10 25-Sep-13 09-Oct-13 Wall 1st coat painting
PA1305 Wheel stopper fixing 10 09-Oct-13 23-Oct-13 Wheel stopper fixing
PA1310 Floor screeding 7 07-Nov-13 18-Nov-13 Floor screeding
PA1320 Epoxy preparation on floor 10 18-Nov-13 02-Dec-13 Epoxy preparation on floor
PA1330 Floor epoxy coating on floor 10 02-Dec-13 17-Dec-13 Floor epoxy coating on floor
PA1340 Final Coat on wall 7 17-Dec-13 26-Dec-13 Final Coat on wall
PA1345 Column Guard fixing 7 17-Dec-13 26-Dec-13 Column Guard fixing
PA1350 Paking line & number marking 10 28-Dec-13 11-Jan-14 Paking line & number marking
PA1355 Steel Door Fixing 7 28-Dec-13 06-Jan-14 Steel Door Fixing
MEP 50 25-Sep-13 07-Dec-13 07-Dec-13, MEP
PME1270 Light & Small power 1st & 2nd fix 20 25-Sep-13 23-Oct-13 Light & Small power 1st & 2nd fix
PME1280 CCTV 1st & 2nd fix 10 25-Sep-13 09-Oct-13 CCTV 1st & 2nd fix
PME1290 Fire Alarm 1st & 2nd fix 10 25-Sep-13 09-Oct-13 Fire Alarm 1st & 2nd fix
PME1300 BMS 1st & 2nd fix 10 25-Sep-13 09-Oct-13 BMS 1st & 2nd fix
PME1310 Fire fighting pipe installation 30 25-Sep-13 07-Nov-13 Fire fighting pipe installation
PME1320 CO system 1st & 2nd fix 10 25-Sep-13 09-Oct-13 CO system 1st & 2nd fix
PME1330 Plumbing 1st & 2nd fix 10 25-Sep-13 09-Oct-13 Plumbing 1st & 2nd fix
PME1340 Ducting & Insulation works 30 25-Sep-13 07-Nov-13 Ducting & Insulation works

Actual Work Critical Remaining Work Summary Page 10 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

PME1350 MEP final fix 20 07-Nov-13 07-Dec-13 MEP final fix


Roof level 125 12-Aug-13 10-Feb-14 10-Feb-14, Roof level
Civil / Arch 120 12-Aug-13 03-Feb-14 03-Feb-14, Civil / Arch
RF1000 Masonry Walls 10 12-Aug-13 26-Aug-13 Masonry Walls
RF1010 Plastering works 10 27-Aug-13 10-Sep-13 Plastering works
RF1015 Painting on wall 10 10-Sep-13 24-Sep-13 Painting on wall
RF1020 Waterproofing on floor 10 25-Sep-13 09-Oct-13 Waterproofing on floor
RF1030 Tiling works 10 09-Oct-13 23-Oct-13 Tiling works
RF1040 Circular tower works 30 24-Oct-13 07-Dec-13 Circular tower works
RF1050 Square tower works 30 24-Oct-13 07-Dec-13 Square tower works
RF1060 Water tank water proofing 10 25-Sep-13 09-Oct-13 Water tank water proofing
RF1070 Epoxy coating 7 09-Oct-13 20-Oct-13 Epoxy coating
RF1080 Roof structure 30 07-Nov-13 21-Dec-13 Roof structure
RF1090 Roof sheeting 30 30-Nov-13 12-Jan-14 Roof sheeting
RF1100 Roof tiling 30 22-Dec-13 03-Feb-14 Roof tiling
RF1110 Protective coating 10 07-Dec-13 21-Dec-13 Protective coating
MEP 115 27-Aug-13 10-Feb-14 10-Feb-14, MEP
RFM1000 Light & small power 1st & 2nd fix 10 27-Aug-13 10-Sep-13 Light & small power 1st & 2nd fix
RFM1010 Fire fighting pipe installation 10 10-Sep-13 24-Sep-13 Fire fighting pipe installation
RFM1020 Chilled Water piping 10 25-Sep-13 09-Oct-13 Chilled Water piping
RFM1030 Installation of AHU 15 09-Oct-13 31-Oct-13 Installation of AHU
RFM1040 Installation of Exhuast fans 20 09-Oct-13 07-Nov-13 Installation of Exhuast fans
RFM1050 Ducting & insulation works 40 07-Nov-13 05-Jan-14 Ducting & insulation works
RFM1060 BMS 1st & 2nd fix 10 10-Sep-13 24-Sep-13 BMS 1st & 2nd fix
RFM1070 MEP testing 15 05-Jan-14 27-Jan-14 MEP testing
RFM1080 MEP final fix 10 27-Jan-14 10-Feb-14 MEP final fix
Amenity Floor 147 30-Jun-13 29-Jan-14 29-Jan-14, Amenity Floor
Mockup room 42 09-Oct-13 09-Dec-13 09-Dec-13, Mockup room
Civil / Arch 20 24-Oct-13 21-Nov-13 21-Nov-13, Civil / Arch
AME1020 Light & Small power 1st & 2nd fix 5 03-Nov-13 10-Nov-13 Light & Small power 1st & 2nd fix
AME1090 Fire alarm 1st & 2nd fix 4 03-Nov-13 09-Nov-13 Fire alarm 1st & 2nd fix
AME1100 Data 1st & 2nd fix 4 03-Nov-13 09-Nov-13 Data 1st & 2nd fix
AME1110 HVAC Ducting & FCU installation 7 24-Oct-13 03-Nov-13 HVAC Ducting & FCU installation
AME1120 Chilled water piping 4 03-Nov-13 09-Nov-13 Chilled water piping

Actual Work Critical Remaining Work Summary Page 11 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

AME1130 Firefighting pipe installation 5 03-Nov-13 10-Nov-13 Firefighting pipe installation


AME1140 MEP testing 5 11-Nov-13 18-Nov-13 MEP testing
AME1150 MEP final fix 5 14-Nov-13 21-Nov-13 MEP final fix
MEP 42 09-Oct-13 09-Dec-13 09-Dec-13, MEP
AMC1140 Masonry walls 5 09-Oct-13 16-Oct-13 Masonry walls
AMC1150 Plastering 5 16-Oct-13 23-Oct-13 Plastering
AMC1160 1st coat paint on walls 5 24-Oct-13 31-Oct-13 1st coat paint on walls
AMC1170 Wet area water proofing 5 31-Oct-13 07-Nov-13 Wet area water proofing
AMC1180 Wet area flooring 4 07-Nov-13 13-Nov-13 Wet area flooring
AMC1190 Wet area wall tiles 4 13-Nov-13 19-Nov-13 Wet area wall tiles
AMC1200 Dry area Ceiling gypsum works 5 31-Oct-13 07-Nov-13 Dry area Ceiling gypsum works
AMC1210 Wet area ceiling works 4 19-Nov-13 25-Nov-13 Wet area ceiling works
AMC1220 Ceiling 1st coat painting 5 07-Nov-13 14-Nov-13 Ceiling 1st coat painting
AMC1230 Aluminum doors & windows 3 14-Nov-13 19-Nov-13 Aluminum doors & windows
AMC1240 Kitchen cabinets & wardrobes 5 25-Nov-13 02-Dec-13 Kitchen cabinets & wardrobes
AMC1250 Woodendoors & Accessories 3 14-Nov-13 19-Nov-13 Woodendoors & Accessories
AMC1260 Ceiling final coat painting 5 23-Nov-13 30-Nov-13 Ceiling final coat painting
AMC1270 Final coat paint on walls 5 02-Dec-13 09-Dec-13 Final coat paint on walls
Apartments 105 30-Jun-13 30-Nov-13 30-Nov-13, Apartments
MEP 85 30-Jun-13 31-Oct-13 31-Oct-13, MEP
AME1000 Light & Small power 1st & 2nd fix 15 21-Jul-13 12-Aug-13 Light & Small power 1st & 2nd fix
AME1010 Fire alarm 1st & 2nd fix 10 21-Jul-13 05-Aug-13 Fire alarm 1st & 2nd fix
AME1030 Data 1st & 2nd fix 10 21-Jul-13 05-Aug-13 Data 1st & 2nd fix
AME1040 HVAC Ducting & FCU installation 15 30-Jun-13 21-Jul-13 HVAC Ducting & FCU installation
AME1050 Chilled water piping 10 21-Jul-13 05-Aug-13 Chilled water piping
AME1060 Firefighting pipe installation 15 21-Jul-13 12-Aug-13 Firefighting pipe installation
AME1070 MEP testing 15 12-Aug-13 03-Sep-13 MEP testing
AME1080 MEP final fix 15 09-Oct-13 31-Oct-13 MEP final fix
Civil / Arch 105 30-Jun-13 30-Nov-13 30-Nov-13, Civil / Arch
AMC1000 Masonry walls 10 30-Jun-13 14-Jul-13 Masonry walls
AMC1010 Plastering 10 14-Jul-13 28-Jul-13 Plastering
AMC1020 1st coat paint on walls 10 29-Jul-13 12-Aug-13 1st coat paint on walls
AMC1030 Wet area water proofing 7 12-Aug-13 22-Aug-13 Wet area water proofing
AMC1040 Wet area flooring 10 22-Aug-13 05-Sep-13 Wet area flooring

Actual Work Critical Remaining Work Summary Page 12 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

AMC1050 Wet area wall tiles 10 05-Sep-13 21-Sep-13 Wet area wall tiles
AMC1060 Dry area Ceiling gypsum works 15 03-Sep-13 24-Sep-13 Dry area Ceiling gypsum works
AMC1070 Wet area ceiling works 10 21-Sep-13 05-Oct-13 Wet area ceiling works
AMC1080 Ceiling 1st coat painting 10 25-Sep-13 09-Oct-13 Ceiling 1st coat painting
AMC1090 Aluminum doors & windows 10 09-Oct-13 23-Oct-13 Aluminum doors & windows
AMC1100 Kitchen cabinets & wardrobes 10 09-Oct-13 23-Oct-13 Kitchen cabinets & wardrobes
AMC1110 Woodendoors & Accessories 10 09-Oct-13 23-Oct-13 Woodendoors & Accessories
AMC1120 Ceiling final coat painting 10 31-Oct-13 14-Nov-13 Ceiling final coat painting
AMC1130 Final coat paint on walls 10 14-Nov-13 30-Nov-13 Final coat paint on walls
Corridor 83 21-Jul-13 19-Nov-13 19-Nov-13, Corridor
Civil / Arch 78 29-Jul-13 19-Nov-13 19-Nov-13, Civil / Arch
LCC11600 Plastering works 7 29-Jul-13 07-Aug-13 Plastering works
LCC11610 1st coat paint on walls 5 07-Aug-13 14-Aug-13 1st coat paint on walls
LCC11620 Marble flooring 7 15-Aug-13 25-Aug-13 Marble flooring
LCC11630 Ceiling gypsum works 7 13-Oct-13 22-Oct-13 Ceiling gypsum works
LCC11640 1st coat paint on ceiling 5 22-Oct-13 29-Oct-13 1st coat paint on ceiling
LCC11650 Steel doors & accessories 4 30-Oct-13 04-Nov-13 Steel doors & accessories
LCC11660 Final coat paint on ceiling 5 05-Nov-13 12-Nov-13 Final coat paint on ceiling
LCC11670 Final coat paint on walls 5 12-Nov-13 19-Nov-13 Final coat paint on walls
MEP 76 21-Jul-13 09-Nov-13 09-Nov-13, MEP
LCM11600 HVAC ducting & FCU installation 15 21-Jul-13 12-Aug-13 HVAC ducting & FCU installation
LCM11610 Fire fighting pipe Installation 7 12-Aug-13 22-Aug-13 Fire fighting pipe Installation
LCM11620 Chilled water Piping 7 22-Aug-13 01-Sep-13 Chilled water Piping
LCM11630 Light & Power 1st & 2nd fix 7 02-Sep-13 11-Sep-13 Light & Power 1st & 2nd fix
LCM11640 Fire alarm 1st & 2nd fix 7 11-Sep-13 22-Sep-13 Fire alarm 1st & 2nd fix
LCM11650 BMS 1st & 2nd fix 7 22-Sep-13 02-Oct-13 BMS 1st & 2nd fix
LCM11660 MEP testing 7 02-Oct-13 12-Oct-13 MEP testing
LCM11670 MEP final fix 7 30-Oct-13 09-Nov-13 MEP final fix
Public area 137 14-Jul-13 29-Jan-14 29-Jan-14, Public area
Gym room 56 14-Jul-13 03-Oct-13 03-Oct-13, Gym room
Civil / Arch 56 14-Jul-13 03-Oct-13 03-Oct-13, Civil / Arch
PA1000 Masorny works 5 14-Jul-13 21-Jul-13 Masorny works
PA1010 Palstering 5 21-Jul-13 28-Jul-13 Palstering
PA1020 Painting 1st coat on wall 5 29-Jul-13 05-Aug-13 Painting 1st coat on wall

Actual Work Critical Remaining Work Summary Page 13 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

PA1030 Acoustic Ceiling works 5 11-Aug-13 18-Aug-13 Acoustic Ceiling works


PA1040 Ceiling 1st coat painting 5 18-Aug-13 25-Aug-13 Ceiling 1st coat painting
PA1050 Rubber flooring 5 25-Aug-13 01-Sep-13 Rubber flooring
PA1060 Final coat on ceiling 5 04-Sep-13 11-Sep-13 Final coat on ceiling
PA1070 Aluminium Doors & windows 5 11-Sep-13 18-Sep-13 Aluminium Doors & windows
PA1080 Wooden Doors & accessories 5 19-Sep-13 26-Sep-13 Wooden Doors & accessories
PA1090 Final coat on wall 5 26-Sep-13 03-Oct-13 Final coat on wall
MEP 31 21-Jul-13 04-Sep-13 04-Sep-13, MEP
LAM11600 HVAC Ducting & FCU installation 7 21-Jul-13 31-Jul-13 HVAC Ducting & FCU installation
LAM11610 Fire fighting pipe installation 7 21-Jul-13 31-Jul-13 Fire fighting pipe installation
LAM11620 Chilled water piping 7 21-Jul-13 31-Jul-13 Chilled water piping
LAM11640 Light, small power & Data 1st & 2nd fix 7 21-Jul-13 31-Jul-13 Light, small power & Data 1st & 2nd fix
LAM11650 Fire alarm 1st & 2nd fix 7 21-Jul-13 31-Jul-13 Fire alarm 1st & 2nd fix
LAM11660 MEP testing 7 31-Jul-13 11-Aug-13 MEP testing
LAM11670 MEP final fix 7 25-Aug-13 04-Sep-13 MEP final fix
Kids Play room
ro 58 21-Jul-13 14-Oct-13 14-Oct-13, Kids Play room
Civil / Arch 58 21-Jul-13 14-Oct-13 14-Oct-13, Civil / Arch
PA1100 Masorny works 5 21-Jul-13 28-Jul-13 Masorny works
PA1110 Palstering 5 29-Jul-13 05-Aug-13 Palstering
PA1120 Painting 1st coat on wall 5 05-Aug-13 12-Aug-13 Painting 1st coat on wall
PA1130 Acoustic Ceiling works 5 21-Aug-13 28-Aug-13 Acoustic Ceiling works
PA1140 Ceiling 1st coat painting 5 28-Aug-13 04-Sep-13 Ceiling 1st coat painting
PA1150 Rubber flooring 5 04-Sep-13 11-Sep-13 Rubber flooring
PA1160 Final coat on ceiling 5 15-Sep-13 22-Sep-13 Final coat on ceiling
PA1170 Aluminium Doors & windows 5 22-Sep-13 29-Sep-13 Aluminium Doors & windows
PA1180 Wooden Doors & accessories 5 29-Sep-13 06-Oct-13 Wooden Doors & accessories
PA1190 Final coat on wall 5 07-Oct-13 14-Oct-13 Final coat on wall
MEP 31 31-Jul-13 15-Sep-13 15-Sep-13, MEP
LAM11630 HVAC Ducting & FCU installation 7 31-Jul-13 11-Aug-13 HVAC Ducting & FCU installation
LAM11680 Fire fighting pipe installation 7 31-Jul-13 11-Aug-13 Fire fighting pipe installation
LAM11690 Chilled water piping 7 31-Jul-13 11-Aug-13 Chilled water piping
LAM11700 Light, small power & Data 1st & 2nd fix 7 31-Jul-13 11-Aug-13 Light, small power & Data 1st & 2nd fix
LAM11710 Fire alarm 1st & 2nd fix 7 31-Jul-13 11-Aug-13 Fire alarm 1st & 2nd fix
LAM11720 MEP testing 7 11-Aug-13 20-Aug-13 MEP testing

Actual Work Critical Remaining Work Summary Page 14 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM11730 MEP final fix 7 04-Sep-13 15-Sep-13 MEP final fix


Swimming P
Pool area 127 29-Jul-13 29-Jan-14 29-Jan-14, Swimming Pool area
SW1000 Swimming Pool Works 90 29-Jul-13 07-Dec-13 Swimming Pool Works
SW1010 Pooldeck area Screeding 7 07-Dec-13 17-Dec-13 Pooldeck area Screeding
SW1020 Pooldeck area Waterproofing 10 17-Dec-13 31-Dec-13 Pooldeck area Waterproofing
SW1030 Pooldeck area Tiling 7 31-Dec-13 11-Jan-14 Pooldeck area Tiling
SW1040 Planters 30 17-Dec-13 29-Jan-14 Planters
Landscaping 108 17-Nov-13 22-Apr-14 22-Apr-14, Landscaping
Entry side 53 17-Nov-13 02-Feb-14 02-Feb-14, Entry side
LS1000 Site preparation 7 17-Nov-13 26-Nov-13 Site preparation
LS1010 Pits for planters 7 26-Nov-13 07-Dec-13 Pits for planters
LS1020 Irrigation lines 7 07-Dec-13 17-Dec-13 Irrigation lines
LS1030 Soil filling 7 17-Dec-13 26-Dec-13 Soil filling
LS1040 Fertilizers mixing 5 28-Dec-13 04-Jan-14 Fertilizers mixing
LS1050 Planting 15 04-Jan-14 25-Jan-14 Planting
LS1060 Light fittings 5 26-Jan-14 02-Feb-14 Light fittings
Radial road s
side 60 26-Jan-14 22-Apr-14 22-Apr-14, Radial road side
LS1070 Site preparation 7 26-Jan-14 04-Feb-14 Site preparation
LS1080 Pits for planters 7 04-Feb-14 15-Feb-14 Pits for planters
LS1090 Irrigation lines 7 15-Feb-14 25-Feb-14 Irrigation lines
LS1100 Soil filling 7 25-Feb-14 06-Mar-14 Soil filling
LS1110 Fertilizers mixing 5 08-Mar-14 15-Mar-14 Fertilizers mixing
LS1120 Planting 15 15-Mar-14 05-Apr-14 Planting
LS1130 Pebbles filling 5 06-Apr-14 13-Apr-14 Pebbles filling
LS1140 Pavers tiling 7 13-Apr-14 22-Apr-14 Pavers tiling
Tower 252 14-Jul-13 16-Jul-14 16-Jul-14, Tower
Level 1 117 14-Jul-13 31-Dec-13 31-Dec-13, Level 1
Apartments 117 14-Jul-13 31-Dec-13 31-Dec-13, Apartments
Civil / Arch 117 14-Jul-13 31-Dec-13 31-Dec-13, Civil / Arch
LAC10000 Masonry walls 15 14-Jul-13 05-Aug-13 Masonry walls
LAC10010 Plastering works 15 05-Aug-13 26-Aug-13 Plastering works
LAC10020 1st coat paint on walls 15 27-Aug-13 17-Sep-13 1st coat paint on walls
LAC10030 Wet area water proofing 10 17-Sep-13 02-Oct-13 Wet area water proofing
LAC10040 Wet area flooring 10 02-Oct-13 16-Oct-13 Wet area flooring

Actual Work Critical Remaining Work Summary Page 15 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC10050 Wet area wall tile works 10 16-Oct-13 31-Oct-13 Wet area wall tile works
LAC10060 Dry area ceiling gypsum works 20 17-Sep-13 16-Oct-13 Dry area ceiling gypsum works
LAC10070 Wet area ceiling works 12 31-Oct-13 18-Nov-13 Wet area ceiling works
LAC10080 1st coat paint on ceiling 15 16-Oct-13 07-Nov-13 1st coat paint on ceiling
LAC10090 Aluminium doors & windows 12 07-Nov-13 25-Nov-13 Aluminium doors & windows
LAC10100 Kitchen cabinets & wardrobes 15 18-Nov-13 09-Dec-13 Kitchen cabinets & wardrobes
LAC10110 Wooden doors& accessories 15 07-Nov-13 30-Nov-13 Wooden doors& accessories
LAC10120 Final coat paint on ceiling 15 07-Dec-13 29-Dec-13 Final coat paint on ceiling
LAC10130 Final coat paint on walls 15 10-Dec-13 31-Dec-13 Final coat paint on walls
MEP 95 21-Jul-13 07-Dec-13 07-Dec-13, MEP
LAM10000 HVAC Ducting & FCU installation 15 21-Jul-13 12-Aug-13 HVAC Ducting & FCU installation
LAM10010 Fire fighting pipe installation 15 21-Jul-13 12-Aug-13 Fire fighting pipe installation
LAM10020 Chilled water piping 15 21-Jul-13 12-Aug-13 Chilled water piping
LAM10030 Plumbing 1st & 2nd fix 10 21-Jul-13 05-Aug-13 Plumbing 1st & 2nd fix
LAM10040 Light, small power & Data 1st & 2nd fix 15 05-Aug-13 26-Aug-13 Light, small power & Data 1st & 2nd fix
LAM10050 Fire alarm 1st & 2nd fix 10 05-Aug-13 19-Aug-13 Fire alarm 1st & 2nd fix
LAM10060 MEP testing 15 27-Aug-13 17-Sep-13 MEP testing
LAM10070 MEP final fix 20 07-Nov-13 07-Dec-13 MEP final fix
Corridor 86 12-Aug-13 15-Dec-13 15-Dec-13, Corridor
Civil / Arch 76 27-Aug-13 15-Dec-13 15-Dec-13, Civil / Arch
LCC10000 Plastering works 7 27-Aug-13 05-Sep-13 Plastering works
LCC10010 1st coat paint on walls 5 05-Sep-13 12-Sep-13 1st coat paint on walls
LCC10020 Marble flooring 7 14-Sep-13 23-Sep-13 Marble flooring
LCC10030 Ceiling gypsum works 7 03-Nov-13 13-Nov-13 Ceiling gypsum works
LCC10040 1st coat paint on ceiling 5 13-Nov-13 20-Nov-13 1st coat paint on ceiling
LCC10050 Steel doors & accessories 4 20-Nov-13 26-Nov-13 Steel doors & accessories
LCC10060 Final coat paint on ceiling 5 01-Dec-13 08-Dec-13 Final coat paint on ceiling
LCC10070 Final coat paint on walls 5 08-Dec-13 15-Dec-13 Final coat paint on walls
MEP 76 12-Aug-13 01-Dec-13 01-Dec-13, MEP
LCM10000 HVAC ducting & FCU installation 15 12-Aug-13 03-Sep-13 HVAC ducting & FCU installation
LCM10010 Fire fighting pipe Installation 7 03-Sep-13 12-Sep-13 Fire fighting pipe Installation
LCM10020 Chilled water Piping 7 14-Sep-13 23-Sep-13 Chilled water Piping
LCM10030 Light & Power 1st & 2nd fix 7 23-Sep-13 03-Oct-13 Light & Power 1st & 2nd fix
LCM10040 Fire alarm 1st & 2nd fix 7 03-Oct-13 14-Oct-13 Fire alarm 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 16 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCM10050 BMS 1st & 2nd fix 7 14-Oct-13 23-Oct-13 BMS 1st & 2nd fix
LCM10060 MEP testing 7 24-Oct-13 03-Nov-13 MEP testing
LCM10070 MEP final fix 7 20-Nov-13 01-Dec-13 MEP final fix
Level 2 117 14-Jul-13 31-Dec-13 31-Dec-13, Level 2
Apartments 117 14-Jul-13 31-Dec-13 31-Dec-13, Apartments
Civil / Arch 117 14-Jul-13 31-Dec-13 31-Dec-13, Civil / Arch
LAC10140 Masonry walls 15 14-Jul-13 05-Aug-13 Masonry walls
LAC10150 Plastering works 15 05-Aug-13 26-Aug-13 Plastering works
LAC10160 1st coat paint on walls 15 27-Aug-13 17-Sep-13 1st coat paint on walls
LAC10170 Wet area water proofing 10 17-Sep-13 02-Oct-13 Wet area water proofing
LAC10180 Wet area flooring 10 02-Oct-13 16-Oct-13 Wet area flooring
LAC10190 Wet area wall tile works 10 16-Oct-13 31-Oct-13 Wet area wall tile works
LAC10200 Dry area ceiling gypsum works 20 17-Sep-13 16-Oct-13 Dry area ceiling gypsum works
LAC10210 Wet area ceiling works 12 31-Oct-13 18-Nov-13 Wet area ceiling works
LAC10220 1st coat paint on ceiling 15 16-Oct-13 07-Nov-13 1st coat paint on ceiling
LAC10230 Aluminium doors & windows 12 07-Nov-13 25-Nov-13 Aluminium doors & windows
LAC10240 Kitchen cabinets & wardrobes 15 18-Nov-13 09-Dec-13 Kitchen cabinets & wardrobes
LAC10250 Wooden doors& accessories 15 07-Nov-13 30-Nov-13 Wooden doors& accessories
LAC10260 Final coat paint on ceiling 15 07-Dec-13 29-Dec-13 Final coat paint on ceiling
LAC10270 Final coat paint on walls 15 10-Dec-13 31-Dec-13 Final coat paint on walls
MEP 95 21-Jul-13 07-Dec-13 07-Dec-13, MEP
LAM10080 HVAC Ducting & FCU installation 15 21-Jul-13 12-Aug-13 HVAC Ducting & FCU installation
LAM10090 Fire fighting pipe installation 15 21-Jul-13 12-Aug-13 Fire fighting pipe installation
LAM10100 Chilled water piping 15 21-Jul-13 12-Aug-13 Chilled water piping
LAM10110 Plumbing 1st & 2nd fix 10 21-Jul-13 05-Aug-13 Plumbing 1st & 2nd fix
LAM10120 Light, small power & Data 1st & 2nd fix 15 05-Aug-13 26-Aug-13 Light, small power & Data 1st & 2nd fix
LAM10130 Fire alarm 1st & 2nd fix 10 05-Aug-13 19-Aug-13 Fire alarm 1st & 2nd fix
LAM10140 MEP testing 15 27-Aug-13 17-Sep-13 MEP testing
LAM10150 MEP final fix 20 07-Nov-13 07-Dec-13 MEP final fix
Corridor 86 12-Aug-13 15-Dec-13 15-Dec-13, Corridor
Civil / Arch 76 27-Aug-13 15-Dec-13 15-Dec-13, Civil / Arch
LCC10080 Plastering works 7 27-Aug-13 05-Sep-13 Plastering works
LCC10090 1st coat paint on walls 5 05-Sep-13 12-Sep-13 1st coat paint on walls
LCC10100 Marble flooring 7 14-Sep-13 23-Sep-13 Marble flooring

Actual Work Critical Remaining Work Summary Page 17 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCC10110 Ceiling gypsum works 7 03-Nov-13 13-Nov-13 Ceiling gypsum works


LCC10120 1st coat paint on ceiling 5 13-Nov-13 20-Nov-13 1st coat paint on ceiling
LCC10130 Steel doors & accessories 4 20-Nov-13 26-Nov-13 Steel doors & accessories
LCC10140 Final coat paint on ceiling 5 01-Dec-13 08-Dec-13 Final coat paint on ceiling
LCC10150 Final coat paint on walls 5 08-Dec-13 15-Dec-13 Final coat paint on walls
MEP 76 12-Aug-13 01-Dec-13 01-Dec-13, MEP
LCM10080 HVAC ducting & FCU installation 15 12-Aug-13 03-Sep-13 HVAC ducting & FCU installation
LCM10090 Fire fighting pipe Installation 7 03-Sep-13 12-Sep-13 Fire fighting pipe Installation
LCM10100 Chilled water Piping 7 14-Sep-13 23-Sep-13 Chilled water Piping
LCM10110 Light & Power 1st & 2nd fix 7 23-Sep-13 03-Oct-13 Light & Power 1st & 2nd fix
LCM10120 Fire alarm 1st & 2nd fix 7 03-Oct-13 14-Oct-13 Fire alarm 1st & 2nd fix
LCM10130 BMS 1st & 2nd fix 7 14-Oct-13 23-Oct-13 BMS 1st & 2nd fix
LCM10140 MEP testing 7 24-Oct-13 03-Nov-13 MEP testing
LCM10150 MEP final fix 7 20-Nov-13 01-Dec-13 MEP final fix
Level 3 127 21-Jul-13 22-Jan-14 22-Jan-14, Level 3
Apartments 127 21-Jul-13 22-Jan-14 22-Jan-14, Apartments
Civil / Arch 117 05-Aug-13 22-Jan-14 22-Jan-14, Civil / Arch
LAC10280 Masonry walls 15 05-Aug-13 26-Aug-13 Masonry walls
LAC10290 Plastering works 15 27-Aug-13 17-Sep-13 Plastering works
LAC10300 1st coat paint on walls 15 17-Sep-13 09-Oct-13 1st coat paint on walls
LAC10310 Wet area water proofing 10 09-Oct-13 23-Oct-13 Wet area water proofing
LAC10320 Wet area flooring 10 24-Oct-13 07-Nov-13 Wet area flooring
LAC10330 Wet area wall tile works 10 07-Nov-13 21-Nov-13 Wet area wall tile works
LAC10340 Dry area ceiling gypsum works 20 09-Oct-13 07-Nov-13 Dry area ceiling gypsum works
LAC10350 Wet area ceiling works 12 23-Nov-13 09-Dec-13 Wet area ceiling works
LAC10360 1st coat paint on ceiling 15 07-Nov-13 30-Nov-13 1st coat paint on ceiling
LAC10370 Aluminium doors & windows 12 30-Nov-13 17-Dec-13 Aluminium doors & windows
LAC10380 Kitchen cabinets & wardrobes 15 10-Dec-13 31-Dec-13 Kitchen cabinets & wardrobes
LAC10390 Wooden doors& accessories 15 30-Nov-13 21-Dec-13 Wooden doors& accessories
LAC10400 Final coat paint on ceiling 15 29-Dec-13 19-Jan-14 Final coat paint on ceiling
LAC10410 Final coat paint on walls 15 31-Dec-13 22-Jan-14 Final coat paint on walls
MEP 110 21-Jul-13 29-Dec-13 29-Dec-13, MEP
LAM10160 HVAC Ducting & FCU installation 15 21-Jul-13 12-Aug-13 HVAC Ducting & FCU installation
LAM10170 Fire fighting pipe installation 15 21-Jul-13 12-Aug-13 Fire fighting pipe installation

Actual Work Critical Remaining Work Summary Page 18 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM10180 Chilled water piping 15 21-Jul-13 12-Aug-13 Chilled water piping


LAM10190 Plumbing 1st & 2nd fix 10 21-Jul-13 05-Aug-13 Plumbing 1st & 2nd fix
LAM10200 Light, small power & Data 1st & 2nd fix 15 05-Aug-13 26-Aug-13 Light, small power & Data 1st & 2nd fix
LAM10210 Fire alarm 1st & 2nd fix 10 05-Aug-13 19-Aug-13 Fire alarm 1st & 2nd fix
LAM10220 MEP testing 15 27-Aug-13 17-Sep-13 MEP testing
LAM10230 MEP final fix 20 30-Nov-13 29-Dec-13 MEP final fix
Corridor 86 12-Aug-13 15-Dec-13 15-Dec-13, Corridor
Civil / Arch 61 17-Sep-13 15-Dec-13 15-Dec-13, Civil / Arch
LCC10160 Plastering works 7 17-Sep-13 28-Sep-13 Plastering works
LCC10170 1st coat paint on walls 5 28-Sep-13 05-Oct-13 1st coat paint on walls
LCC10180 Marble flooring 7 05-Oct-13 15-Oct-13 Marble flooring
LCC10190 Ceiling gypsum works 7 03-Nov-13 13-Nov-13 Ceiling gypsum works
LCC10200 1st coat paint on ceiling 5 13-Nov-13 20-Nov-13 1st coat paint on ceiling
LCC10210 Steel doors & accessories 4 20-Nov-13 26-Nov-13 Steel doors & accessories
LCC10220 Final coat paint on ceiling 5 01-Dec-13 08-Dec-13 Final coat paint on ceiling
LCC10230 Final coat paint on walls 5 08-Dec-13 15-Dec-13 Final coat paint on walls
MEP 76 12-Aug-13 01-Dec-13 01-Dec-13, MEP
LCM10160 HVAC ducting & FCU installation 15 12-Aug-13 03-Sep-13 HVAC ducting & FCU installation
LCM10170 Fire fighting pipe Installation 7 03-Sep-13 12-Sep-13 Fire fighting pipe Installation
LCM10180 Chilled water Piping 7 14-Sep-13 23-Sep-13 Chilled water Piping
LCM10190 Light & Power 1st & 2nd fix 7 23-Sep-13 03-Oct-13 Light & Power 1st & 2nd fix
LCM10200 Fire alarm 1st & 2nd fix 7 03-Oct-13 14-Oct-13 Fire alarm 1st & 2nd fix
LCM10210 BMS 1st & 2nd fix 7 14-Oct-13 23-Oct-13 BMS 1st & 2nd fix
LCM10220 MEP testing 7 24-Oct-13 03-Nov-13 MEP testing
LCM10230 MEP final fix 7 20-Nov-13 01-Dec-13 MEP final fix
Level 4 117 05-Aug-13 22-Jan-14 22-Jan-14, Level 4
Apartments 117 05-Aug-13 22-Jan-14 22-Jan-14, Apartments
Civil / Arch 117 05-Aug-13 22-Jan-14 22-Jan-14, Civil / Arch
LAC10420 Masonry walls 15 05-Aug-13 26-Aug-13 Masonry walls
LAC10430 Plastering works 15 27-Aug-13 17-Sep-13 Plastering works
LAC10440 1st coat paint on walls 15 17-Sep-13 09-Oct-13 1st coat paint on walls
LAC10450 Wet area water proofing 10 09-Oct-13 23-Oct-13 Wet area water proofing
LAC10460 Wet area flooring 10 24-Oct-13 07-Nov-13 Wet area flooring
LAC10470 Wet area wall tile works 10 07-Nov-13 21-Nov-13 Wet area wall tile works

Actual Work Critical Remaining Work Summary Page 19 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC10480 Dry area ceiling gypsum works 20 09-Oct-13 07-Nov-13 Dry area ceiling gypsum works
LAC10490 Wet area ceiling works 12 23-Nov-13 09-Dec-13 Wet area ceiling works
LAC10500 1st coat paint on ceiling 15 07-Nov-13 30-Nov-13 1st coat paint on ceiling
LAC10510 Aluminium doors & windows 12 30-Nov-13 17-Dec-13 Aluminium doors & windows
LAC10520 Kitchen cabinets & wardrobes 15 10-Dec-13 31-Dec-13 Kitchen cabinets & wardrobes
LAC10530 Wooden doors& accessories 15 30-Nov-13 21-Dec-13 Wooden doors& accessories
LAC10540 Final coat paint on ceiling 15 29-Dec-13 19-Jan-14 Final coat paint on ceiling
LAC10550 Final coat paint on walls 15 31-Dec-13 22-Jan-14 Final coat paint on walls
MEP 95 12-Aug-13 29-Dec-13 29-Dec-13, MEP
LAM10240 HVAC Ducting & FCU installation 15 12-Aug-13 03-Sep-13 HVAC Ducting & FCU installation
LAM10250 Fire fighting pipe installation 15 12-Aug-13 03-Sep-13 Fire fighting pipe installation
LAM10260 Chilled water piping 15 12-Aug-13 03-Sep-13 Chilled water piping
LAM10270 Plumbing 1st & 2nd fix 10 12-Aug-13 26-Aug-13 Plumbing 1st & 2nd fix
LAM10280 Light, small power & Data 1st & 2nd fix 15 27-Aug-13 17-Sep-13 Light, small power & Data 1st & 2nd fix
LAM10290 Fire alarm 1st & 2nd fix 10 27-Aug-13 10-Sep-13 Fire alarm 1st & 2nd fix
LAM10300 MEP testing 15 17-Sep-13 09-Oct-13 MEP testing
LAM10310 MEP final fix 20 30-Nov-13 29-Dec-13 MEP final fix
Corridor 86 03-Sep-13 06-Jan-14 06-Jan-14, Corridor
Civil / Arch 76 17-Sep-13 06-Jan-14 06-Jan-14, Civil / Arch
LCC10240 Plastering works 7 17-Sep-13 28-Sep-13 Plastering works
LCC10250 1st coat paint on walls 5 28-Sep-13 05-Oct-13 1st coat paint on walls
LCC10260 Marble flooring 7 05-Oct-13 15-Oct-13 Marble flooring
LCC10270 Ceiling gypsum works 7 25-Nov-13 05-Dec-13 Ceiling gypsum works
LCC10280 1st coat paint on ceiling 5 05-Dec-13 12-Dec-13 1st coat paint on ceiling
LCC10290 Steel doors & accessories 4 12-Dec-13 18-Dec-13 Steel doors & accessories
LCC10300 Final coat paint on ceiling 5 23-Dec-13 30-Dec-13 Final coat paint on ceiling
LCC10310 Final coat paint on walls 5 30-Dec-13 06-Jan-14 Final coat paint on walls
MEP 76 03-Sep-13 23-Dec-13 23-Dec-13, MEP
LCM10240 HVAC ducting & FCU installation 15 03-Sep-13 24-Sep-13 HVAC ducting & FCU installation
LCM10250 Fire fighting pipe Installation 7 25-Sep-13 05-Oct-13 Fire fighting pipe Installation
LCM10260 Chilled water Piping 7 05-Oct-13 15-Oct-13 Chilled water Piping
LCM10270 Light & Power 1st & 2nd fix 7 15-Oct-13 26-Oct-13 Light & Power 1st & 2nd fix
LCM10280 Fire alarm 1st & 2nd fix 7 26-Oct-13 04-Nov-13 Fire alarm 1st & 2nd fix
LCM10290 BMS 1st & 2nd fix 7 05-Nov-13 14-Nov-13 BMS 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 20 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCM10300 MEP testing 7 14-Nov-13 25-Nov-13 MEP testing


LCM10310 MEP final fix 7 12-Dec-13 23-Dec-13 MEP final fix
Level 5 117 27-Aug-13 13-Feb-14 13-Feb-14, Level 5
Apartments 117 27-Aug-13 13-Feb-14 13-Feb-14, Apartments
Civil / Arch 117 27-Aug-13 13-Feb-14 13-Feb-14, Civil / Arch
LAC10560 Masonry walls 15 27-Aug-13 17-Sep-13 Masonry walls
LAC10570 Plastering works 15 17-Sep-13 09-Oct-13 Plastering works
LAC10580 1st coat paint on walls 15 09-Oct-13 31-Oct-13 1st coat paint on walls
LAC10590 Wet area water proofing 10 31-Oct-13 14-Nov-13 Wet area water proofing
LAC10600 Wet area flooring 10 14-Nov-13 30-Nov-13 Wet area flooring
LAC10610 Wet area wall tile works 10 30-Nov-13 14-Dec-13 Wet area wall tile works
LAC10620 Dry area ceiling gypsum works 20 31-Oct-13 30-Nov-13 Dry area ceiling gypsum works
LAC10630 Wet area ceiling works 12 14-Dec-13 31-Dec-13 Wet area ceiling works
LAC10640 1st coat paint on ceiling 15 30-Nov-13 21-Dec-13 1st coat paint on ceiling
LAC10650 Aluminium doors & windows 12 22-Dec-13 07-Jan-14 Aluminium doors & windows
LAC10660 Kitchen cabinets & wardrobes 15 31-Dec-13 22-Jan-14 Kitchen cabinets & wardrobes
LAC10670 Wooden doors& accessories 15 22-Dec-13 12-Jan-14 Wooden doors& accessories
LAC10680 Final coat paint on ceiling 15 20-Jan-14 10-Feb-14 Final coat paint on ceiling
LAC10690 Final coat paint on walls 15 22-Jan-14 13-Feb-14 Final coat paint on walls
MEP 95 03-Sep-13 19-Jan-14 19-Jan-14, MEP
LAM10320 HVAC Ducting & FCU installation 15 03-Sep-13 24-Sep-13 HVAC Ducting & FCU installation
LAM10330 Fire fighting pipe installation 15 03-Sep-13 24-Sep-13 Fire fighting pipe installation
LAM10340 Chilled water piping 15 03-Sep-13 24-Sep-13 Chilled water piping
LAM10350 Plumbing 1st & 2nd fix 10 03-Sep-13 17-Sep-13 Plumbing 1st & 2nd fix
LAM10360 Light, small power & Data 1st & 2nd fix 15 17-Sep-13 09-Oct-13 Light, small power & Data 1st & 2nd fix
LAM10370 Fire alarm 1st & 2nd fix 10 17-Sep-13 02-Oct-13 Fire alarm 1st & 2nd fix
LAM10380 MEP testing 15 09-Oct-13 31-Oct-13 MEP testing
LAM10390 MEP final fix 20 22-Dec-13 19-Jan-14 MEP final fix
Corridor 86 25-Sep-13 28-Jan-14 28-Jan-14, Corridor
Civil / Arch 76 09-Oct-13 28-Jan-14 28-Jan-14, Civil / Arch
LCC10320 Plastering works 7 09-Oct-13 20-Oct-13 Plastering works
LCC10330 1st coat paint on walls 5 20-Oct-13 27-Oct-13 1st coat paint on walls
LCC10340 Marble flooring 7 27-Oct-13 06-Nov-13 Marble flooring
LCC10350 Ceiling gypsum works 7 17-Dec-13 26-Dec-13 Ceiling gypsum works

Actual Work Critical Remaining Work Summary Page 21 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCC10360 1st coat paint on ceiling 5 28-Dec-13 04-Jan-14 1st coat paint on ceiling
LCC10370 Steel doors & accessories 4 04-Jan-14 09-Jan-14 Steel doors & accessories
LCC10380 Final coat paint on ceiling 5 14-Jan-14 21-Jan-14 Final coat paint on ceiling
LCC10390 Final coat paint on walls 5 21-Jan-14 28-Jan-14 Final coat paint on walls
MEP 76 25-Sep-13 13-Jan-14 13-Jan-14, MEP
LCM10320 HVAC ducting & FCU installation 15 25-Sep-13 16-Oct-13 HVAC ducting & FCU installation
LCM10330 Fire fighting pipe Installation 7 16-Oct-13 27-Oct-13 Fire fighting pipe Installation
LCM10340 Chilled water Piping 7 27-Oct-13 06-Nov-13 Chilled water Piping
LCM10350 Light & Power 1st & 2nd fix 7 06-Nov-13 16-Nov-13 Light & Power 1st & 2nd fix
LCM10360 Fire alarm 1st & 2nd fix 7 17-Nov-13 26-Nov-13 Fire alarm 1st & 2nd fix
LCM10370 BMS 1st & 2nd fix 7 26-Nov-13 07-Dec-13 BMS 1st & 2nd fix
LCM10380 MEP testing 7 07-Dec-13 17-Dec-13 MEP testing
LCM10390 MEP final fix 7 04-Jan-14 13-Jan-14 MEP final fix
Level 6 117 27-Aug-13 13-Feb-14 13-Feb-14, Level 6
Apartments 117 27-Aug-13 13-Feb-14 13-Feb-14, Apartments
Civil / Arch 117 27-Aug-13 13-Feb-14 13-Feb-14, Civil / Arch
LAC10700 Masonry walls 15 27-Aug-13 17-Sep-13 Masonry walls
LAC10710 Plastering works 15 17-Sep-13 09-Oct-13 Plastering works
LAC10720 1st coat paint on walls 15 09-Oct-13 31-Oct-13 1st coat paint on walls
LAC10730 Wet area water proofing 10 31-Oct-13 14-Nov-13 Wet area water proofing
LAC10740 Wet area flooring 10 14-Nov-13 30-Nov-13 Wet area flooring
LAC10750 Wet area wall tile works 10 30-Nov-13 14-Dec-13 Wet area wall tile works
LAC10760 Dry area ceiling gypsum works 20 31-Oct-13 30-Nov-13 Dry area ceiling gypsum works
LAC10770 Wet area ceiling works 12 14-Dec-13 31-Dec-13 Wet area ceiling works
LAC10780 1st coat paint on ceiling 15 30-Nov-13 21-Dec-13 1st coat paint on ceiling
LAC10790 Aluminium doors & windows 12 22-Dec-13 07-Jan-14 Aluminium doors & windows
LAC10800 Kitchen cabinets & wardrobes 15 31-Dec-13 22-Jan-14 Kitchen cabinets & wardrobes
LAC10810 Wooden doors& accessories 15 22-Dec-13 12-Jan-14 Wooden doors& accessories
LAC10820 Final coat paint on ceiling 15 20-Jan-14 10-Feb-14 Final coat paint on ceiling
LAC10830 Final coat paint on walls 15 22-Jan-14 13-Feb-14 Final coat paint on walls
MEP 95 03-Sep-13 19-Jan-14 19-Jan-14, MEP
LAM10400 HVAC Ducting & FCU installation 15 03-Sep-13 24-Sep-13 HVAC Ducting & FCU installation
LAM10410 Fire fighting pipe installation 15 03-Sep-13 24-Sep-13 Fire fighting pipe installation
LAM10420 Chilled water piping 15 03-Sep-13 24-Sep-13 Chilled water piping

Actual Work Critical Remaining Work Summary Page 22 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM10430 Plumbing 1st & 2nd fix 10 03-Sep-13 17-Sep-13 Plumbing 1st & 2nd fix
LAM10440 Light, small power & Data 1st & 2nd fix 15 17-Sep-13 09-Oct-13 Light, small power & Data 1st & 2nd fix
LAM10450 Fire alarm 1st & 2nd fix 10 17-Sep-13 02-Oct-13 Fire alarm 1st & 2nd fix
LAM10460 MEP testing 15 09-Oct-13 31-Oct-13 MEP testing
LAM10470 MEP final fix 20 22-Dec-13 19-Jan-14 MEP final fix
Corridor 86 25-Sep-13 28-Jan-14 28-Jan-14, Corridor
Civil / Arch 76 09-Oct-13 28-Jan-14 28-Jan-14, Civil / Arch
LCC10400 Plastering works 7 09-Oct-13 20-Oct-13 Plastering works
LCC10410 1st coat paint on walls 5 20-Oct-13 27-Oct-13 1st coat paint on walls
LCC10420 Marble flooring 7 27-Oct-13 06-Nov-13 Marble flooring
LCC10430 Ceiling gypsum works 7 17-Dec-13 26-Dec-13 Ceiling gypsum works
LCC10440 1st coat paint on ceiling 5 28-Dec-13 04-Jan-14 1st coat paint on ceiling
LCC10450 Steel doors & accessories 4 04-Jan-14 09-Jan-14 Steel doors & accessories
LCC10460 Final coat paint on ceiling 5 14-Jan-14 21-Jan-14 Final coat paint on ceiling
LCC10470 Final coat paint on walls 5 21-Jan-14 28-Jan-14 Final coat paint on walls
MEP 76 25-Sep-13 13-Jan-14 13-Jan-14, MEP
LCM10400 HVAC ducting & FCU installation 15 25-Sep-13 16-Oct-13 HVAC ducting & FCU installation
LCM10410 Fire fighting pipe Installation 7 16-Oct-13 27-Oct-13 Fire fighting pipe Installation
LCM10420 Chilled water Piping 7 27-Oct-13 06-Nov-13 Chilled water Piping
LCM10430 Light & Power 1st & 2nd fix 7 06-Nov-13 16-Nov-13 Light & Power 1st & 2nd fix
LCM10440 Fire alarm 1st & 2nd fix 7 17-Nov-13 26-Nov-13 Fire alarm 1st & 2nd fix
LCM10450 BMS 1st & 2nd fix 7 26-Nov-13 07-Dec-13 BMS 1st & 2nd fix
LCM10460 MEP testing 7 07-Dec-13 17-Dec-13 MEP testing
LCM10470 MEP final fix 7 04-Jan-14 13-Jan-14 MEP final fix
Level 7 117 17-Sep-13 06-Mar-14 06-Mar-14, Level 7
Apartments 117 17-Sep-13 06-Mar-14 06-Mar-14, Apartments
Civil / Arch 117 17-Sep-13 06-Mar-14 06-Mar-14, Civil / Arch
LAC10840 Masonry walls 15 17-Sep-13 09-Oct-13 Masonry walls
LAC10850 Plastering works 15 09-Oct-13 31-Oct-13 Plastering works
LAC10860 1st coat paint on walls 15 31-Oct-13 21-Nov-13 1st coat paint on walls
LAC10870 Wet area water proofing 10 23-Nov-13 07-Dec-13 Wet area water proofing
LAC10880 Wet area flooring 10 07-Dec-13 21-Dec-13 Wet area flooring
LAC10890 Wet area wall tile works 10 22-Dec-13 05-Jan-14 Wet area wall tile works
LAC10900 Dry area ceiling gypsum works 20 23-Nov-13 21-Dec-13 Dry area ceiling gypsum works

Actual Work Critical Remaining Work Summary Page 23 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC10910 Wet area ceiling works 12 05-Jan-14 22-Jan-14 Wet area ceiling works
LAC10920 1st coat paint on ceiling 15 22-Dec-13 12-Jan-14 1st coat paint on ceiling
LAC10930 Aluminium doors & windows 12 12-Jan-14 29-Jan-14 Aluminium doors & windows
LAC10940 Kitchen cabinets & wardrobes 15 22-Jan-14 13-Feb-14 Kitchen cabinets & wardrobes
LAC10950 Wooden doors& accessories 15 12-Jan-14 03-Feb-14 Wooden doors& accessories
LAC10960 Final coat paint on ceiling 15 10-Feb-14 04-Mar-14 Final coat paint on ceiling
LAC10970 Final coat paint on walls 15 13-Feb-14 06-Mar-14 Final coat paint on walls
MEP 95 25-Sep-13 10-Feb-14 10-Feb-14, MEP
LAM10480 HVAC Ducting & FCU installation 15 25-Sep-13 16-Oct-13 HVAC Ducting & FCU installation
LAM10490 Fire fighting pipe installation 15 25-Sep-13 16-Oct-13 Fire fighting pipe installation
LAM10500 Chilled water piping 15 25-Sep-13 16-Oct-13 Chilled water piping
LAM10510 Plumbing 1st & 2nd fix 10 25-Sep-13 09-Oct-13 Plumbing 1st & 2nd fix
LAM10520 Light, small power & Data 1st & 2nd fix 15 09-Oct-13 31-Oct-13 Light, small power & Data 1st & 2nd fix
LAM10530 Fire alarm 1st & 2nd fix 10 09-Oct-13 23-Oct-13 Fire alarm 1st & 2nd fix
LAM10540 MEP testing 15 31-Oct-13 21-Nov-13 MEP testing
LAM10550 MEP final fix 20 12-Jan-14 10-Feb-14 MEP final fix
Corridor 86 16-Oct-13 19-Feb-14 19-Feb-14, Corridor
Civil / Arch 76 31-Oct-13 19-Feb-14 19-Feb-14, Civil / Arch
LCC10480 Plastering works 7 31-Oct-13 10-Nov-13 Plastering works
LCC10490 1st coat paint on walls 5 11-Nov-13 18-Nov-13 1st coat paint on walls
LCC10500 Marble flooring 7 18-Nov-13 27-Nov-13 Marble flooring
LCC10510 Ceiling gypsum works 7 08-Jan-14 18-Jan-14 Ceiling gypsum works
LCC10520 1st coat paint on ceiling 5 18-Jan-14 25-Jan-14 1st coat paint on ceiling
LCC10530 Steel doors & accessories 4 26-Jan-14 30-Jan-14 Steel doors & accessories
LCC10540 Final coat paint on ceiling 5 04-Feb-14 11-Feb-14 Final coat paint on ceiling
LCC10550 Final coat paint on walls 5 12-Feb-14 19-Feb-14 Final coat paint on walls
MEP 76 16-Oct-13 04-Feb-14 04-Feb-14, MEP
LCM10480 HVAC ducting & FCU installation 15 16-Oct-13 07-Nov-13 HVAC ducting & FCU installation
LCM10490 Fire fighting pipe Installation 7 07-Nov-13 18-Nov-13 Fire fighting pipe Installation
LCM10500 Chilled water Piping 7 18-Nov-13 27-Nov-13 Chilled water Piping
LCM10510 Light & Power 1st & 2nd fix 7 28-Nov-13 08-Dec-13 Light & Power 1st & 2nd fix
LCM10520 Fire alarm 1st & 2nd fix 7 08-Dec-13 18-Dec-13 Fire alarm 1st & 2nd fix
LCM10530 BMS 1st & 2nd fix 7 18-Dec-13 29-Dec-13 BMS 1st & 2nd fix
LCM10540 MEP testing 7 29-Dec-13 07-Jan-14 MEP testing

Actual Work Critical Remaining Work Summary Page 24 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCM10550 MEP final fix 7 26-Jan-14 04-Feb-14 MEP final fix


Level 8 117 17-Sep-13 06-Mar-14 06-Mar-14, Level 8
Apartments 117 17-Sep-13 06-Mar-14 06-Mar-14, Apartments
Civil / Arch 117 17-Sep-13 06-Mar-14 06-Mar-14, Civil / Arch
LAC10980 Masonry walls 15 17-Sep-13 09-Oct-13 Masonry walls
LAC10990 Plastering works 15 09-Oct-13 31-Oct-13 Plastering works
LAC11000 1st coat paint on walls 15 31-Oct-13 21-Nov-13 1st coat paint on walls
LAC11010 Wet area water proofing 10 23-Nov-13 07-Dec-13 Wet area water proofing
LAC11020 Wet area flooring 10 07-Dec-13 21-Dec-13 Wet area flooring
LAC11030 Wet area wall tile works 10 22-Dec-13 05-Jan-14 Wet area wall tile works
LAC11040 Dry area ceiling gypsum works 20 23-Nov-13 21-Dec-13 Dry area ceiling gypsum works
LAC11050 Wet area ceiling works 12 05-Jan-14 22-Jan-14 Wet area ceiling works
LAC11060 1st coat paint on ceiling 15 22-Dec-13 12-Jan-14 1st coat paint on ceiling
LAC11070 Aluminium doors & windows 12 12-Jan-14 29-Jan-14 Aluminium doors & windows
LAC11080 Kitchen cabinets & wardrobes 15 22-Jan-14 13-Feb-14 Kitchen cabinets & wardrobes
LAC11090 Wooden doors& accessories 15 12-Jan-14 03-Feb-14 Wooden doors& accessories
LAC11100 Final coat paint on ceiling 15 10-Feb-14 04-Mar-14 Final coat paint on ceiling
LAC11110 Final coat paint on walls 15 13-Feb-14 06-Mar-14 Final coat paint on walls
MEP 95 25-Sep-13 10-Feb-14 10-Feb-14, MEP
LAM10560 HVAC Ducting & FCU installation 15 25-Sep-13 16-Oct-13 HVAC Ducting & FCU installation
LAM10570 Fire fighting pipe installation 15 25-Sep-13 16-Oct-13 Fire fighting pipe installation
LAM10580 Chilled water piping 15 25-Sep-13 16-Oct-13 Chilled water piping
LAM10590 Plumbing 1st & 2nd fix 10 25-Sep-13 09-Oct-13 Plumbing 1st & 2nd fix
LAM10600 Light, small power & Data 1st & 2nd fix 15 09-Oct-13 31-Oct-13 Light, small power & Data 1st & 2nd fix
LAM10610 Fire alarm 1st & 2nd fix 10 09-Oct-13 23-Oct-13 Fire alarm 1st & 2nd fix
LAM10620 MEP testing 15 31-Oct-13 21-Nov-13 MEP testing
LAM10630 MEP final fix 20 12-Jan-14 10-Feb-14 MEP final fix
Corridor 86 16-Oct-13 19-Feb-14 19-Feb-14, Corridor
Civil / Arch 76 31-Oct-13 19-Feb-14 19-Feb-14, Civil / Arch
LCC10560 Plastering works 7 31-Oct-13 10-Nov-13 Plastering works
LCC10570 1st coat paint on walls 5 11-Nov-13 18-Nov-13 1st coat paint on walls
LCC10580 Marble flooring 7 18-Nov-13 27-Nov-13 Marble flooring
LCC10590 Ceiling gypsum works 7 08-Jan-14 18-Jan-14 Ceiling gypsum works
LCC10600 1st coat paint on ceiling 5 18-Jan-14 25-Jan-14 1st coat paint on ceiling

Actual Work Critical Remaining Work Summary Page 25 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCC10610 Steel doors & accessories 4 26-Jan-14 30-Jan-14 Steel doors & accessories
LCC10620 Final coat paint on ceiling 5 04-Feb-14 11-Feb-14 Final coat paint on ceiling
LCC10630 Final coat paint on walls 5 12-Feb-14 19-Feb-14 Final coat paint on walls
MEP 76 16-Oct-13 04-Feb-14 04-Feb-14, MEP
LCM10560 HVAC ducting & FCU installation 15 16-Oct-13 07-Nov-13 HVAC ducting & FCU installation
LCM10570 Fire fighting pipe Installation 7 07-Nov-13 18-Nov-13 Fire fighting pipe Installation
LCM10580 Chilled water Piping 7 18-Nov-13 27-Nov-13 Chilled water Piping
LCM10590 Light & Power 1st & 2nd fix 7 28-Nov-13 08-Dec-13 Light & Power 1st & 2nd fix
LCM10600 Fire alarm 1st & 2nd fix 7 08-Dec-13 18-Dec-13 Fire alarm 1st & 2nd fix
LCM10610 BMS 1st & 2nd fix 7 18-Dec-13 29-Dec-13 BMS 1st & 2nd fix
LCM10620 MEP testing 7 29-Dec-13 07-Jan-14 MEP testing
LCM10630 MEP final fix 7 26-Jan-14 04-Feb-14 MEP final fix
Level 9 117 09-Oct-13 29-Mar-14 29-Mar-14, Level 9
Apartments 117 09-Oct-13 29-Mar-14 29-Mar-14, Apartments
Civil / Arch 117 09-Oct-13 29-Mar-14 29-Mar-14, Civil / Arch
LAC11120 Masonry walls 15 09-Oct-13 31-Oct-13 Masonry walls
LAC11130 Plastering works 15 31-Oct-13 21-Nov-13 Plastering works
LAC11140 1st coat paint on walls 15 23-Nov-13 14-Dec-13 1st coat paint on walls
LAC11150 Wet area water proofing 10 14-Dec-13 29-Dec-13 Wet area water proofing
LAC11160 Wet area flooring 10 29-Dec-13 12-Jan-14 Wet area flooring
LAC11170 Wet area wall tile works 10 12-Jan-14 27-Jan-14 Wet area wall tile works
LAC11180 Dry area ceiling gypsum works 20 14-Dec-13 12-Jan-14 Dry area ceiling gypsum works
LAC11190 Wet area ceiling works 12 27-Jan-14 13-Feb-14 Wet area ceiling works
LAC11200 1st coat paint on ceiling 15 12-Jan-14 03-Feb-14 1st coat paint on ceiling
LAC11210 Aluminium doors & windows 12 03-Feb-14 20-Feb-14 Aluminium doors & windows
LAC11220 Kitchen cabinets & wardrobes 15 13-Feb-14 06-Mar-14 Kitchen cabinets & wardrobes
LAC11230 Wooden doors& accessories 15 03-Feb-14 25-Feb-14 Wooden doors& accessories
LAC11240 Final coat paint on ceiling 15 04-Mar-14 26-Mar-14 Final coat paint on ceiling
LAC11250 Final coat paint on walls 15 08-Mar-14 29-Mar-14 Final coat paint on walls
MEP 95 16-Oct-13 04-Mar-14 04-Mar-14, MEP
LAM10640 HVAC Ducting & FCU installation 15 16-Oct-13 07-Nov-13 HVAC Ducting & FCU installation
LAM10650 Fire fighting pipe installation 15 16-Oct-13 07-Nov-13 Fire fighting pipe installation
LAM10660 Chilled water piping 15 16-Oct-13 07-Nov-13 Chilled water piping
LAM10670 Plumbing 1st & 2nd fix 10 16-Oct-13 31-Oct-13 Plumbing 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 26 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM10680 Light, small power & Data 1st & 2nd fix 15 31-Oct-13 21-Nov-13 Light, small power & Data 1st & 2nd fix
LAM10690 Fire alarm 1st & 2nd fix 10 31-Oct-13 14-Nov-13 Fire alarm 1st & 2nd fix
LAM10700 MEP testing 15 23-Nov-13 14-Dec-13 MEP testing
LAM10710 MEP final fix 20 03-Feb-14 04-Mar-14 MEP final fix
Corridor 86 07-Nov-13 12-Mar-14 12-Mar-14, Corridor
Civil / Arch 76 23-Nov-13 12-Mar-14 12-Mar-14, Civil / Arch
LCC10640 Plastering works 7 23-Nov-13 02-Dec-13 Plastering works
LCC10650 1st coat paint on walls 5 02-Dec-13 09-Dec-13 1st coat paint on walls
LCC10660 Marble flooring 7 10-Dec-13 19-Dec-13 Marble flooring
LCC10670 Ceiling gypsum works 7 29-Jan-14 09-Feb-14 Ceiling gypsum works
LCC10680 1st coat paint on ceiling 5 09-Feb-14 16-Feb-14 1st coat paint on ceiling
LCC10690 Steel doors & accessories 4 16-Feb-14 22-Feb-14 Steel doors & accessories
LCC10700 Final coat paint on ceiling 5 26-Feb-14 05-Mar-14 Final coat paint on ceiling
LCC10710 Final coat paint on walls 5 05-Mar-14 12-Mar-14 Final coat paint on walls
MEP 76 07-Nov-13 26-Feb-14 26-Feb-14, MEP
LCM10640 HVAC ducting & FCU installation 15 07-Nov-13 30-Nov-13 HVAC ducting & FCU installation
LCM10650 Fire fighting pipe Installation 7 30-Nov-13 09-Dec-13 Fire fighting pipe Installation
LCM10660 Chilled water Piping 7 10-Dec-13 19-Dec-13 Chilled water Piping
LCM10670 Light & Power 1st & 2nd fix 7 19-Dec-13 30-Dec-13 Light & Power 1st & 2nd fix
LCM10680 Fire alarm 1st & 2nd fix 7 30-Dec-13 09-Jan-14 Fire alarm 1st & 2nd fix
LCM10690 BMS 1st & 2nd fix 7 09-Jan-14 19-Jan-14 BMS 1st & 2nd fix
LCM10700 MEP testing 7 20-Jan-14 29-Jan-14 MEP testing
LCM10710 MEP final fix 7 16-Feb-14 26-Feb-14 MEP final fix
Level 10 117 09-Oct-13 29-Mar-14 29-Mar-14, Level 10
Apartments 117 09-Oct-13 29-Mar-14 29-Mar-14, Apartments
Civil / Arch 117 09-Oct-13 29-Mar-14 29-Mar-14, Civil / Arch
LAC11260 Masonry walls 15 09-Oct-13 31-Oct-13 Masonry walls
LAC11270 Plastering works 15 31-Oct-13 21-Nov-13 Plastering works
LAC11280 1st coat paint on walls 15 23-Nov-13 14-Dec-13 1st coat paint on walls
LAC11290 Wet area water proofing 10 14-Dec-13 29-Dec-13 Wet area water proofing
LAC11300 Wet area flooring 10 29-Dec-13 12-Jan-14 Wet area flooring
LAC11310 Wet area wall tile works 10 12-Jan-14 27-Jan-14 Wet area wall tile works
LAC11320 Dry area ceiling gypsum works 20 14-Dec-13 12-Jan-14 Dry area ceiling gypsum works
LAC11330 Wet area ceiling works 12 27-Jan-14 13-Feb-14 Wet area ceiling works

Actual Work Critical Remaining Work Summary Page 27 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC11340 1st coat paint on ceiling 15 12-Jan-14 03-Feb-14 1st coat paint on ceiling
LAC11350 Aluminium doors & windows 12 03-Feb-14 20-Feb-14 Aluminium doors & windows
LAC11360 Kitchen cabinets & wardrobes 15 13-Feb-14 06-Mar-14 Kitchen cabinets & wardrobes
LAC11370 Wooden doors& accessories 15 03-Feb-14 25-Feb-14 Wooden doors& accessories
LAC11380 Final coat paint on ceiling 15 04-Mar-14 26-Mar-14 Final coat paint on ceiling
LAC11390 Final coat paint on walls 15 08-Mar-14 29-Mar-14 Final coat paint on walls
MEP 95 16-Oct-13 04-Mar-14 04-Mar-14, MEP
LAM10720 HVAC Ducting & FCU installation 15 16-Oct-13 07-Nov-13 HVAC Ducting & FCU installation
LAM10730 Fire fighting pipe installation 15 16-Oct-13 07-Nov-13 Fire fighting pipe installation
LAM10740 Chilled water piping 15 16-Oct-13 07-Nov-13 Chilled water piping
LAM10750 Plumbing 1st & 2nd fix 10 16-Oct-13 31-Oct-13 Plumbing 1st & 2nd fix
LAM10760 Light, small power & Data 1st & 2nd fix 15 31-Oct-13 21-Nov-13 Light, small power & Data 1st & 2nd fix
LAM10770 Fire alarm 1st & 2nd fix 10 31-Oct-13 14-Nov-13 Fire alarm 1st & 2nd fix
LAM10780 MEP testing 15 23-Nov-13 14-Dec-13 MEP testing
LAM10790 MEP final fix 20 03-Feb-14 04-Mar-14 MEP final fix
Corridor 86 07-Nov-13 12-Mar-14 12-Mar-14, Corridor
Civil / Arch 76 23-Nov-13 12-Mar-14 12-Mar-14, Civil / Arch
LCC10720 Plastering works 7 23-Nov-13 02-Dec-13 Plastering works
LCC10730 1st coat paint on walls 5 02-Dec-13 09-Dec-13 1st coat paint on walls
LCC10740 Marble flooring 7 10-Dec-13 19-Dec-13 Marble flooring
LCC10750 Ceiling gypsum works 7 29-Jan-14 09-Feb-14 Ceiling gypsum works
LCC10760 1st coat paint on ceiling 5 09-Feb-14 16-Feb-14 1st coat paint on ceiling
LCC10770 Steel doors & accessories 4 16-Feb-14 22-Feb-14 Steel doors & accessories
LCC10780 Final coat paint on ceiling 5 26-Feb-14 05-Mar-14 Final coat paint on ceiling
LCC10790 Final coat paint on walls 5 05-Mar-14 12-Mar-14 Final coat paint on walls
MEP 76 07-Nov-13 26-Feb-14 26-Feb-14, MEP
LCM10720 HVAC ducting & FCU installation 15 07-Nov-13 30-Nov-13 HVAC ducting & FCU installation
LCM10730 Fire fighting pipe Installation 7 30-Nov-13 09-Dec-13 Fire fighting pipe Installation
LCM10740 Chilled water Piping 7 10-Dec-13 19-Dec-13 Chilled water Piping
LCM10750 Light & Power 1st & 2nd fix 7 19-Dec-13 30-Dec-13 Light & Power 1st & 2nd fix
LCM10760 Fire alarm 1st & 2nd fix 7 30-Dec-13 09-Jan-14 Fire alarm 1st & 2nd fix
LCM10770 BMS 1st & 2nd fix 7 09-Jan-14 19-Jan-14 BMS 1st & 2nd fix
LCM10780 MEP testing 7 20-Jan-14 29-Jan-14 MEP testing
LCM10790 MEP final fix 7 16-Feb-14 26-Feb-14 MEP final fix

Actual Work Critical Remaining Work Summary Page 28 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

Level 11 117 31-Oct-13 20-Apr-14 20-Apr-14, Level 11


Apartments 117 31-Oct-13 20-Apr-14 20-Apr-14, Apartments
Civil / Arch 117 31-Oct-13 20-Apr-14 20-Apr-14, Civil / Arch
LAC11400 Masonry walls 15 31-Oct-13 21-Nov-13 Masonry walls
LAC11410 Plastering works 15 23-Nov-13 14-Dec-13 Plastering works
LAC11420 1st coat paint on walls 15 14-Dec-13 05-Jan-14 1st coat paint on walls
LAC11430 Wet area water proofing 10 05-Jan-14 19-Jan-14 Wet area water proofing
LAC11440 Wet area flooring 10 20-Jan-14 03-Feb-14 Wet area flooring
LAC11450 Wet area wall tile works 10 03-Feb-14 17-Feb-14 Wet area wall tile works
LAC11460 Dry area ceiling gypsum works 20 05-Jan-14 03-Feb-14 Dry area ceiling gypsum works
LAC11470 Wet area ceiling works 12 18-Feb-14 06-Mar-14 Wet area ceiling works
LAC11480 1st coat paint on ceiling 15 03-Feb-14 25-Feb-14 1st coat paint on ceiling
LAC11490 Aluminium doors & windows 12 25-Feb-14 15-Mar-14 Aluminium doors & windows
LAC11500 Kitchen cabinets & wardrobes 15 08-Mar-14 29-Mar-14 Kitchen cabinets & wardrobes
LAC11510 Wooden doors& accessories 15 25-Feb-14 18-Mar-14 Wooden doors& accessories
LAC11520 Final coat paint on ceiling 15 26-Mar-14 16-Apr-14 Final coat paint on ceiling
LAC11530 Final coat paint on walls 15 29-Mar-14 20-Apr-14 Final coat paint on walls
MEP 95 07-Nov-13 26-Mar-14 26-Mar-14, MEP
LAM10800 HVAC Ducting & FCU installation 15 07-Nov-13 30-Nov-13 HVAC Ducting & FCU installation
LAM10810 Fire fighting pipe installation 15 07-Nov-13 30-Nov-13 Fire fighting pipe installation
LAM10820 Chilled water piping 15 07-Nov-13 30-Nov-13 Chilled water piping
LAM10830 Plumbing 1st & 2nd fix 10 07-Nov-13 21-Nov-13 Plumbing 1st & 2nd fix
LAM10840 Light, small power & Data 1st & 2nd fix 15 23-Nov-13 14-Dec-13 Light, small power & Data 1st & 2nd fix
LAM10850 Fire alarm 1st & 2nd fix 10 23-Nov-13 07-Dec-13 Fire alarm 1st & 2nd fix
LAM10860 MEP testing 15 14-Dec-13 05-Jan-14 MEP testing
LAM10870 MEP final fix 20 25-Feb-14 26-Mar-14 MEP final fix
Corridor 86 30-Nov-13 03-Apr-14 03-Apr-14, Corridor
Civil / Arch 76 14-Dec-13 03-Apr-14 03-Apr-14, Civil / Arch
LCC10800 Plastering works 7 14-Dec-13 24-Dec-13 Plastering works
LCC10810 1st coat paint on walls 5 24-Dec-13 31-Dec-13 1st coat paint on walls
LCC10820 Marble flooring 7 31-Dec-13 11-Jan-14 Marble flooring
LCC10830 Ceiling gypsum works 7 20-Feb-14 03-Mar-14 Ceiling gypsum works
LCC10840 1st coat paint on ceiling 5 03-Mar-14 10-Mar-14 1st coat paint on ceiling
LCC10850 Steel doors & accessories 4 10-Mar-14 16-Mar-14 Steel doors & accessories

Actual Work Critical Remaining Work Summary Page 29 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCC10860 Final coat paint on ceiling 5 20-Mar-14 27-Mar-14 Final coat paint on ceiling
LCC10870 Final coat paint on walls 5 27-Mar-14 03-Apr-14 Final coat paint on walls
MEP 76 30-Nov-13 20-Mar-14 20-Mar-14, MEP
LCM10800 HVAC ducting & FCU installation 15 30-Nov-13 21-Dec-13 HVAC ducting & FCU installation
LCM10810 Fire fighting pipe Installation 7 22-Dec-13 31-Dec-13 Fire fighting pipe Installation
LCM10820 Chilled water Piping 7 31-Dec-13 11-Jan-14 Chilled water Piping
LCM10830 Light & Power 1st & 2nd fix 7 11-Jan-14 21-Jan-14 Light & Power 1st & 2nd fix
LCM10840 Fire alarm 1st & 2nd fix 7 21-Jan-14 30-Jan-14 Fire alarm 1st & 2nd fix
LCM10850 BMS 1st & 2nd fix 7 01-Feb-14 10-Feb-14 BMS 1st & 2nd fix
LCM10860 MEP testing 7 10-Feb-14 20-Feb-14 MEP testing
LCM10870 MEP final fix 7 10-Mar-14 20-Mar-14 MEP final fix
Level 12 117 31-Oct-13 20-Apr-14 20-Apr-14, Level 12
Apartments 117 31-Oct-13 20-Apr-14 20-Apr-14, Apartments
Civil / Arch 117 31-Oct-13 20-Apr-14 20-Apr-14, Civil / Arch
LAC11540 Masonry walls 15 31-Oct-13 21-Nov-13 Masonry walls
LAC11550 Plastering works 15 23-Nov-13 14-Dec-13 Plastering works
LAC11560 1st coat paint on walls 15 14-Dec-13 05-Jan-14 1st coat paint on walls
LAC11570 Wet area water proofing 10 05-Jan-14 19-Jan-14 Wet area water proofing
LAC11580 Wet area flooring 10 20-Jan-14 03-Feb-14 Wet area flooring
LAC11590 Wet area wall tile works 10 03-Feb-14 17-Feb-14 Wet area wall tile works
LAC11600 Dry area ceiling gypsum works 20 05-Jan-14 03-Feb-14 Dry area ceiling gypsum works
LAC11610 Wet area ceiling works 12 18-Feb-14 06-Mar-14 Wet area ceiling works
LAC11620 1st coat paint on ceiling 15 03-Feb-14 25-Feb-14 1st coat paint on ceiling
LAC11630 Aluminium doors & windows 12 25-Feb-14 15-Mar-14 Aluminium doors & windows
LAC11640 Kitchen cabinets & wardrobes 15 08-Mar-14 29-Mar-14 Kitchen cabinets & wardrobes
LAC11650 Wooden doors& accessories 15 25-Feb-14 18-Mar-14 Wooden doors& accessories
LAC11660 Final coat paint on ceiling 15 26-Mar-14 16-Apr-14 Final coat paint on ceiling
LAC11670 Final coat paint on walls 15 29-Mar-14 20-Apr-14 Final coat paint on walls
MEP 95 07-Nov-13 26-Mar-14 26-Mar-14, MEP
LAM10880 HVAC Ducting & FCU installation 15 07-Nov-13 30-Nov-13 HVAC Ducting & FCU installation
LAM10890 Fire fighting pipe installation 15 07-Nov-13 30-Nov-13 Fire fighting pipe installation
LAM10900 Chilled water piping 15 07-Nov-13 30-Nov-13 Chilled water piping
LAM10910 Plumbing 1st & 2nd fix 10 07-Nov-13 21-Nov-13 Plumbing 1st & 2nd fix
LAM10920 Light, small power & Data 1st & 2nd fix 15 23-Nov-13 14-Dec-13 Light, small power & Data 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 30 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM10930 Fire alarm 1st & 2nd fix 10 23-Nov-13 07-Dec-13 Fire alarm 1st & 2nd fix
LAM10940 MEP testing 15 14-Dec-13 05-Jan-14 MEP testing
LAM10950 MEP final fix 20 25-Feb-14 26-Mar-14 MEP final fix
Corridor 86 30-Nov-13 03-Apr-14 03-Apr-14, Corridor
Civil / Arch 76 14-Dec-13 03-Apr-14 03-Apr-14, Civil / Arch
LCC10880 Plastering works 7 14-Dec-13 24-Dec-13 Plastering works
LCC10890 1st coat paint on walls 5 24-Dec-13 31-Dec-13 1st coat paint on walls
LCC10900 Marble flooring 7 31-Dec-13 11-Jan-14 Marble flooring
LCC10910 Ceiling gypsum works 7 20-Feb-14 03-Mar-14 Ceiling gypsum works
LCC10920 1st coat paint on ceiling 5 03-Mar-14 10-Mar-14 1st coat paint on ceiling
LCC10930 Steel doors & accessories 4 10-Mar-14 16-Mar-14 Steel doors & accessories
LCC10940 Final coat paint on ceiling 5 20-Mar-14 27-Mar-14 Final coat paint on ceiling
LCC10950 Final coat paint on walls 5 27-Mar-14 03-Apr-14 Final coat paint on walls
MEP 76 30-Nov-13 20-Mar-14 20-Mar-14, MEP
LCM10880 HVAC ducting & FCU installation 15 30-Nov-13 21-Dec-13 HVAC ducting & FCU installation
LCM10890 Fire fighting pipe Installation 7 22-Dec-13 31-Dec-13 Fire fighting pipe Installation
LCM10900 Chilled water Piping 7 31-Dec-13 11-Jan-14 Chilled water Piping
LCM10910 Light & Power 1st & 2nd fix 7 11-Jan-14 21-Jan-14 Light & Power 1st & 2nd fix
LCM10920 Fire alarm 1st & 2nd fix 7 21-Jan-14 30-Jan-14 Fire alarm 1st & 2nd fix
LCM10930 BMS 1st & 2nd fix 7 01-Feb-14 10-Feb-14 BMS 1st & 2nd fix
LCM10940 MEP testing 7 10-Feb-14 20-Feb-14 MEP testing
LCM10950 MEP final fix 7 10-Mar-14 20-Mar-14 MEP final fix
Level 13 117 23-Nov-13 12-May-14 12-May-14, Level 13
Apartments 117 23-Nov-13 12-May-14 12-May-14, Apartments
Civil / Arch 117 23-Nov-13 12-May-14 12-May-14, Civil / Arch
LAC11680 Masonry walls 15 23-Nov-13 14-Dec-13 Masonry walls
LAC11690 Plastering works 15 14-Dec-13 05-Jan-14 Plastering works
LAC11700 1st coat paint on walls 15 05-Jan-14 27-Jan-14 1st coat paint on walls
LAC11710 Wet area water proofing 10 27-Jan-14 10-Feb-14 Wet area water proofing
LAC11720 Wet area flooring 10 10-Feb-14 25-Feb-14 Wet area flooring
LAC11730 Wet area wall tile works 10 25-Feb-14 11-Mar-14 Wet area wall tile works
LAC11740 Dry area ceiling gypsum works 20 27-Jan-14 25-Feb-14 Dry area ceiling gypsum works
LAC11750 Wet area ceiling works 12 11-Mar-14 29-Mar-14 Wet area ceiling works
LAC11760 1st coat paint on ceiling 15 25-Feb-14 18-Mar-14 1st coat paint on ceiling

Actual Work Critical Remaining Work Summary Page 31 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC11770 Aluminium doors & windows 12 19-Mar-14 05-Apr-14 Aluminium doors & windows
LAC11780 Kitchen cabinets & wardrobes 15 29-Mar-14 20-Apr-14 Kitchen cabinets & wardrobes
LAC11790 Wooden doors& accessories 15 19-Mar-14 09-Apr-14 Wooden doors& accessories
LAC11800 Final coat paint on ceiling 15 17-Apr-14 08-May-14 Final coat paint on ceiling
LAC11810 Final coat paint on walls 15 20-Apr-14 12-May-14 Final coat paint on walls
MEP 95 30-Nov-13 16-Apr-14 16-Apr-14, MEP
LAM10960 HVAC Ducting & FCU installation 15 30-Nov-13 21-Dec-13 HVAC Ducting & FCU installation
LAM10970 Fire fighting pipe installation 15 30-Nov-13 21-Dec-13 Fire fighting pipe installation
LAM10980 Chilled water piping 15 30-Nov-13 21-Dec-13 Chilled water piping
LAM10990 Plumbing 1st & 2nd fix 10 30-Nov-13 14-Dec-13 Plumbing 1st & 2nd fix
LAM11000 Light, small power & Data 1st & 2nd fix 15 14-Dec-13 05-Jan-14 Light, small power & Data 1st & 2nd fix
LAM11010 Fire alarm 1st & 2nd fix 10 14-Dec-13 29-Dec-13 Fire alarm 1st & 2nd fix
LAM11020 MEP testing 15 05-Jan-14 27-Jan-14 MEP testing
LAM11030 MEP final fix 20 19-Mar-14 16-Apr-14 MEP final fix
Corridor 86 22-Dec-13 26-Apr-14 26-Apr-14, Corridor
Civil / Arch 76 05-Jan-14 26-Apr-14 26-Apr-14, Civil / Arch
LCC10960 Plastering works 7 05-Jan-14 15-Jan-14 Plastering works
LCC10970 1st coat paint on walls 5 15-Jan-14 22-Jan-14 1st coat paint on walls
LCC10980 Marble flooring 7 22-Jan-14 02-Feb-14 Marble flooring
LCC10990 Ceiling gypsum works 7 15-Mar-14 24-Mar-14 Ceiling gypsum works
LCC11000 1st coat paint on ceiling 5 25-Mar-14 01-Apr-14 1st coat paint on ceiling
LCC11010 Steel doors & accessories 4 01-Apr-14 07-Apr-14 Steel doors & accessories
LCC11020 Final coat paint on ceiling 5 12-Apr-14 19-Apr-14 Final coat paint on ceiling
LCC11030 Final coat paint on walls 5 19-Apr-14 26-Apr-14 Final coat paint on walls
MEP 76 22-Dec-13 10-Apr-14 10-Apr-14, MEP
LCM10960 HVAC ducting & FCU installation 15 22-Dec-13 12-Jan-14 HVAC ducting & FCU installation
LCM10970 Fire fighting pipe Installation 7 12-Jan-14 22-Jan-14 Fire fighting pipe Installation
LCM10980 Chilled water Piping 7 22-Jan-14 02-Feb-14 Chilled water Piping
LCM10990 Light & Power 1st & 2nd fix 7 02-Feb-14 11-Feb-14 Light & Power 1st & 2nd fix
LCM11000 Fire alarm 1st & 2nd fix 7 12-Feb-14 22-Feb-14 Fire alarm 1st & 2nd fix
LCM11010 BMS 1st & 2nd fix 7 22-Feb-14 04-Mar-14 BMS 1st & 2nd fix
LCM11020 MEP testing 7 04-Mar-14 15-Mar-14 MEP testing
LCM11030 MEP final fix 7 01-Apr-14 10-Apr-14 MEP final fix
Level 14 117 23-Nov-13 12-May-14 12-May-14, Level 14

Actual Work Critical Remaining Work Summary Page 32 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

Apartments 117 23-Nov-13 12-May-14 12-May-14, Apartments


Civil / Arch 117 23-Nov-13 12-May-14 12-May-14, Civil / Arch
LAC11820 Masonry walls 15 23-Nov-13 14-Dec-13 Masonry walls
LAC11830 Plastering works 15 14-Dec-13 05-Jan-14 Plastering works
LAC11840 1st coat paint on walls 15 05-Jan-14 27-Jan-14 1st coat paint on walls
LAC11850 Wet area water proofing 10 27-Jan-14 10-Feb-14 Wet area water proofing
LAC11860 Wet area flooring 10 10-Feb-14 25-Feb-14 Wet area flooring
LAC11870 Wet area wall tile works 10 25-Feb-14 11-Mar-14 Wet area wall tile works
LAC11880 Dry area ceiling gypsum works 20 27-Jan-14 25-Feb-14 Dry area ceiling gypsum works
LAC11890 Wet area ceiling works 12 11-Mar-14 29-Mar-14 Wet area ceiling works
LAC11900 1st coat paint on ceiling 15 25-Feb-14 18-Mar-14 1st coat paint on ceiling
LAC11910 Aluminium doors & windows 12 19-Mar-14 05-Apr-14 Aluminium doors & windows
LAC11920 Kitchen cabinets & wardrobes 15 29-Mar-14 20-Apr-14 Kitchen cabinets & wardrobes
LAC11930 Wooden doors& accessories 15 19-Mar-14 09-Apr-14 Wooden doors& accessories
LAC11940 Final coat paint on ceiling 15 17-Apr-14 08-May-14 Final coat paint on ceiling
LAC11950 Final coat paint on walls 15 20-Apr-14 12-May-14 Final coat paint on walls
MEP 95 30-Nov-13 16-Apr-14 16-Apr-14, MEP
LAM11040 HVAC Ducting & FCU installation 15 30-Nov-13 21-Dec-13 HVAC Ducting & FCU installation
LAM11050 Fire fighting pipe installation 15 30-Nov-13 21-Dec-13 Fire fighting pipe installation
LAM11060 Chilled water piping 15 30-Nov-13 21-Dec-13 Chilled water piping
LAM11070 Plumbing 1st & 2nd fix 10 30-Nov-13 14-Dec-13 Plumbing 1st & 2nd fix
LAM11080 Light, small power & Data 1st & 2nd fix 15 14-Dec-13 05-Jan-14 Light, small power & Data 1st & 2nd fix
LAM11090 Fire alarm 1st & 2nd fix 10 14-Dec-13 29-Dec-13 Fire alarm 1st & 2nd fix
LAM11100 MEP testing 15 05-Jan-14 27-Jan-14 MEP testing
LAM11110 MEP final fix 20 19-Mar-14 16-Apr-14 MEP final fix
Corridor 86 22-Dec-13 26-Apr-14 26-Apr-14, Corridor
Civil / Arch 76 05-Jan-14 26-Apr-14 26-Apr-14, Civil / Arch
LCC11040 Plastering works 7 05-Jan-14 15-Jan-14 Plastering works
LCC11050 1st coat paint on walls 5 15-Jan-14 22-Jan-14 1st coat paint on walls
LCC11060 Marble flooring 7 22-Jan-14 02-Feb-14 Marble flooring
LCC11070 Ceiling gypsum works 7 15-Mar-14 24-Mar-14 Ceiling gypsum works
LCC11080 1st coat paint on ceiling 5 25-Mar-14 01-Apr-14 1st coat paint on ceiling
LCC11090 Steel doors & accessories 4 01-Apr-14 07-Apr-14 Steel doors & accessories
LCC11100 Final coat paint on ceiling 5 12-Apr-14 19-Apr-14 Final coat paint on ceiling

Actual Work Critical Remaining Work Summary Page 33 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCC11110 Final coat paint on walls 5 19-Apr-14 26-Apr-14 Final coat paint on walls
MEP 76 22-Dec-13 10-Apr-14 10-Apr-14, MEP
LCM11040 HVAC ducting & FCU installation 15 22-Dec-13 12-Jan-14 HVAC ducting & FCU installation
LCM11050 Fire fighting pipe Installation 7 12-Jan-14 22-Jan-14 Fire fighting pipe Installation
LCM11060 Chilled water Piping 7 22-Jan-14 02-Feb-14 Chilled water Piping
LCM11070 Light & Power 1st & 2nd fix 7 02-Feb-14 11-Feb-14 Light & Power 1st & 2nd fix
LCM11080 Fire alarm 1st & 2nd fix 7 12-Feb-14 22-Feb-14 Fire alarm 1st & 2nd fix
LCM11090 BMS 1st & 2nd fix 7 22-Feb-14 04-Mar-14 BMS 1st & 2nd fix
LCM11100 MEP testing 7 04-Mar-14 15-Mar-14 MEP testing
LCM11110 MEP final fix 7 01-Apr-14 10-Apr-14 MEP final fix
Level 15 117 14-Dec-13 02-Jun-14 02-Jun-14, Level 15
Apartments 117 14-Dec-13 02-Jun-14 02-Jun-14, Apartments
Civil / Arch 117 14-Dec-13 02-Jun-14 02-Jun-14, Civil / Arch
LAC11960 Masonry walls 15 14-Dec-13 05-Jan-14 Masonry walls
LAC11970 Plastering works 15 05-Jan-14 27-Jan-14 Plastering works
LAC11980 1st coat paint on walls 15 27-Jan-14 17-Feb-14 1st coat paint on walls
LAC11990 Wet area water proofing 10 18-Feb-14 04-Mar-14 Wet area water proofing
LAC12000 Wet area flooring 10 04-Mar-14 18-Mar-14 Wet area flooring
LAC12010 Wet area wall tile works 10 19-Mar-14 02-Apr-14 Wet area wall tile works
LAC12020 Dry area ceiling gypsum works 20 18-Feb-14 18-Mar-14 Dry area ceiling gypsum works
LAC12030 Wet area ceiling works 12 02-Apr-14 20-Apr-14 Wet area ceiling works
LAC12040 1st coat paint on ceiling 15 19-Mar-14 09-Apr-14 1st coat paint on ceiling
LAC12050 Aluminium doors & windows 12 09-Apr-14 27-Apr-14 Aluminium doors & windows
LAC12060 Kitchen cabinets & wardrobes 15 20-Apr-14 12-May-14 Kitchen cabinets & wardrobes
LAC12070 Wooden doors& accessories 15 09-Apr-14 01-May-14 Wooden doors& accessories
LAC12080 Final coat paint on ceiling 15 08-May-14 31-May-14 Final coat paint on ceiling
LAC12090 Final coat paint on walls 15 12-May-14 02-Jun-14 Final coat paint on walls
MEP 95 22-Dec-13 08-May-14 08-May-14, MEP
LAM11120 HVAC Ducting & FCU installation 15 22-Dec-13 12-Jan-14 HVAC Ducting & FCU installation
LAM11130 Fire fighting pipe installation 15 22-Dec-13 12-Jan-14 Fire fighting pipe installation
LAM11140 Chilled water piping 15 22-Dec-13 12-Jan-14 Chilled water piping
LAM11150 Plumbing 1st & 2nd fix 10 22-Dec-13 05-Jan-14 Plumbing 1st & 2nd fix
LAM11160 Light, small power & Data 1st & 2nd fix 15 05-Jan-14 27-Jan-14 Light, small power & Data 1st & 2nd fix
LAM11170 Fire alarm 1st & 2nd fix 10 05-Jan-14 19-Jan-14 Fire alarm 1st & 2nd fix

Actual Work Critical Remaining Work Summary Page 34 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM11180 MEP testing 15 27-Jan-14 17-Feb-14 MEP testing


LAM11190 MEP final fix 20 09-Apr-14 08-May-14 MEP final fix
Corridor 86 12-Jan-14 18-May-14 18-May-14, Corridor
Civil / Arch 76 27-Jan-14 18-May-14 18-May-14, Civil / Arch
LCC11120 Plastering works 7 27-Jan-14 05-Feb-14 Plastering works
LCC11130 1st coat paint on walls 5 06-Feb-14 13-Feb-14 1st coat paint on walls
LCC11140 Marble flooring 7 13-Feb-14 23-Feb-14 Marble flooring
LCC11150 Ceiling gypsum works 7 06-Apr-14 15-Apr-14 Ceiling gypsum works
LCC11160 1st coat paint on ceiling 5 15-Apr-14 22-Apr-14 1st coat paint on ceiling
LCC11170 Steel doors & accessories 4 23-Apr-14 28-Apr-14 Steel doors & accessories
LCC11180 Final coat paint on ceiling 5 03-May-14 10-May-14 Final coat paint on ceiling
LCC11190 Final coat paint on walls 5 11-May-14 18-May-14 Final coat paint on walls
MEP 76 12-Jan-14 03-May-14 03-May-14, MEP
LCM11120 HVAC ducting & FCU installation 15 12-Jan-14 03-Feb-14 HVAC ducting & FCU installation
LCM11130 Fire fighting pipe Installation 7 03-Feb-14 13-Feb-14 Fire fighting pipe Installation
LCM11140 Chilled water Piping 7 13-Feb-14 23-Feb-14 Chilled water Piping
LCM11150 Light & Power 1st & 2nd fix 7 24-Feb-14 05-Mar-14 Light & Power 1st & 2nd fix
LCM11160 Fire alarm 1st & 2nd fix 7 05-Mar-14 16-Mar-14 Fire alarm 1st & 2nd fix
LCM11170 BMS 1st & 2nd fix 7 16-Mar-14 26-Mar-14 BMS 1st & 2nd fix
LCM11180 MEP testing 7 26-Mar-14 05-Apr-14 MEP testing
LCM11190 MEP final fix 7 23-Apr-14 03-May-14 MEP final fix
Level 16 117 14-Dec-13 02-Jun-14 02-Jun-14, Level 16
Apartments 117 14-Dec-13 02-Jun-14 02-Jun-14, Apartments
Civil / Arch 117 14-Dec-13 02-Jun-14 02-Jun-14, Civil / Arch
LAC12100 Masonry walls 15 14-Dec-13 05-Jan-14 Masonry walls
LAC12110 Plastering works 15 05-Jan-14 27-Jan-14 Plastering works
LAC12120 1st coat paint on walls 15 27-Jan-14 17-Feb-14 1st coat paint on walls
LAC12130 Wet area water proofing 10 18-Feb-14 04-Mar-14 Wet area water proofing
LAC12140 Wet area flooring 10 04-Mar-14 18-Mar-14 Wet area flooring
LAC12150 Wet area wall tile works 10 19-Mar-14 02-Apr-14 Wet area wall tile works
LAC12160 Dry area ceiling gypsum works 20 18-Feb-14 18-Mar-14 Dry area ceiling gypsum works
LAC12170 Wet area ceiling works 12 02-Apr-14 20-Apr-14 Wet area ceiling works
LAC12180 1st coat paint on ceiling 15 19-Mar-14 09-Apr-14 1st coat paint on ceiling
LAC12190 Aluminium doors & windows 12 09-Apr-14 27-Apr-14 Aluminium doors & windows

Actual Work Critical Remaining Work Summary Page 35 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC12200 Kitchen cabinets & wardrobes 15 20-Apr-14 12-May-14 Kitchen cabinets & wardrobes
LAC12210 Wooden doors& accessories 15 09-Apr-14 01-May-14 Wooden doors& accessories
LAC12220 Final coat paint on ceiling 15 08-May-14 31-May-14 Final coat paint on ceiling
LAC12230 Final coat paint on walls 15 12-May-14 02-Jun-14 Final coat paint on walls
MEP 95 22-Dec-13 08-May-14 08-May-14, MEP
LAM11200 HVAC Ducting & FCU installation 15 22-Dec-13 12-Jan-14 HVAC Ducting & FCU installation
LAM11210 Fire fighting pipe installation 15 22-Dec-13 12-Jan-14 Fire fighting pipe installation
LAM11220 Chilled water piping 15 22-Dec-13 12-Jan-14 Chilled water piping
LAM11230 Plumbing 1st & 2nd fix 10 22-Dec-13 05-Jan-14 Plumbing 1st & 2nd fix
LAM11240 Light, small power & Data 1st & 2nd fix 15 05-Jan-14 27-Jan-14 Light, small power & Data 1st & 2nd fix
LAM11250 Fire alarm 1st & 2nd fix 10 05-Jan-14 19-Jan-14 Fire alarm 1st & 2nd fix
LAM11260 MEP testing 15 27-Jan-14 17-Feb-14 MEP testing
LAM11270 MEP final fix 20 09-Apr-14 08-May-14 MEP final fix
Corridor 86 12-Jan-14 18-May-14 18-May-14, Corridor
Civil / Arch 76 27-Jan-14 18-May-14 18-May-14, Civil / Arch
LCC11200 Plastering works 7 27-Jan-14 05-Feb-14 Plastering works
LCC11210 1st coat paint on walls 5 06-Feb-14 13-Feb-14 1st coat paint on walls
LCC11220 Marble flooring 7 13-Feb-14 23-Feb-14 Marble flooring
LCC11230 Ceiling gypsum works 7 06-Apr-14 15-Apr-14 Ceiling gypsum works
LCC11240 1st coat paint on ceiling 5 15-Apr-14 22-Apr-14 1st coat paint on ceiling
LCC11250 Steel doors & accessories 4 23-Apr-14 28-Apr-14 Steel doors & accessories
LCC11260 Final coat paint on ceiling 5 03-May-14 10-May-14 Final coat paint on ceiling
LCC11270 Final coat paint on walls 5 11-May-14 18-May-14 Final coat paint on walls
MEP 76 12-Jan-14 03-May-14 03-May-14, MEP
LCM11200 HVAC ducting & FCU installation 15 12-Jan-14 03-Feb-14 HVAC ducting & FCU installation
LCM11210 Fire fighting pipe Installation 7 03-Feb-14 13-Feb-14 Fire fighting pipe Installation
LCM11220 Chilled water Piping 7 13-Feb-14 23-Feb-14 Chilled water Piping
LCM11230 Light & Power 1st & 2nd fix 7 24-Feb-14 05-Mar-14 Light & Power 1st & 2nd fix
LCM11240 Fire alarm 1st & 2nd fix 7 05-Mar-14 16-Mar-14 Fire alarm 1st & 2nd fix
LCM11250 BMS 1st & 2nd fix 7 16-Mar-14 26-Mar-14 BMS 1st & 2nd fix
LCM11260 MEP testing 7 26-Mar-14 05-Apr-14 MEP testing
LCM11270 MEP final fix 7 23-Apr-14 03-May-14 MEP final fix
Level 17 117 05-Jan-14 24-Jun-14 24-Jun-14, Level 17
Apartments 117 05-Jan-14 24-Jun-14 24-Jun-14, Apartments

Actual Work Critical Remaining Work Summary Page 36 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

Civil / Arch 117 05-Jan-14 24-Jun-14 24-Jun-14, Civil / Arch


LAC12240 Masonry walls 15 05-Jan-14 27-Jan-14 Masonry walls
LAC12250 Plastering works 15 27-Jan-14 17-Feb-14 Plastering works
LAC12260 1st coat paint on walls 15 18-Feb-14 11-Mar-14 1st coat paint on walls
LAC12270 Wet area water proofing 10 11-Mar-14 26-Mar-14 Wet area water proofing
LAC12280 Wet area flooring 10 26-Mar-14 09-Apr-14 Wet area flooring
LAC12290 Wet area wall tile works 10 09-Apr-14 24-Apr-14 Wet area wall tile works
LAC12300 Dry area ceiling gypsum works 20 11-Mar-14 09-Apr-14 Dry area ceiling gypsum works
LAC12310 Wet area ceiling works 12 24-Apr-14 12-May-14 Wet area ceiling works
LAC12320 1st coat paint on ceiling 15 09-Apr-14 01-May-14 1st coat paint on ceiling
LAC12330 Aluminium doors & windows 12 01-May-14 19-May-14 Aluminium doors & windows
LAC12340 Kitchen cabinets & wardrobes 15 12-May-14 02-Jun-14 Kitchen cabinets & wardrobes
LAC12350 Wooden doors& accessories 15 01-May-14 24-May-14 Wooden doors& accessories
LAC12360 Final coat paint on ceiling 15 31-May-14 22-Jun-14 Final coat paint on ceiling
LAC12370 Final coat paint on walls 15 03-Jun-14 24-Jun-14 Final coat paint on walls
MEP 95 12-Jan-14 31-May-14 31-May-14, MEP
LAM11280 HVAC Ducting & FCU installation 15 12-Jan-14 03-Feb-14 HVAC Ducting & FCU installation
LAM11290 Fire fighting pipe installation 15 12-Jan-14 03-Feb-14 Fire fighting pipe installation
LAM11300 Chilled water piping 15 12-Jan-14 03-Feb-14 Chilled water piping
LAM11310 Plumbing 1st & 2nd fix 10 12-Jan-14 27-Jan-14 Plumbing 1st & 2nd fix
LAM11320 Light, small power & Data 1st & 2nd fix 15 27-Jan-14 17-Feb-14 Light, small power & Data 1st & 2nd fix
LAM11330 Fire alarm 1st & 2nd fix 10 27-Jan-14 10-Feb-14 Fire alarm 1st & 2nd fix
LAM11340 MEP testing 15 18-Feb-14 11-Mar-14 MEP testing
LAM11350 MEP final fix 20 01-May-14 31-May-14 MEP final fix
Corridor 86 03-Feb-14 08-Jun-14 08-Jun-14, Corridor
Civil / Arch 76 18-Feb-14 08-Jun-14 08-Jun-14, Civil / Arch
LCC11280 Plastering works 7 18-Feb-14 27-Feb-14 Plastering works
LCC11290 1st coat paint on walls 5 27-Feb-14 06-Mar-14 1st coat paint on walls
LCC11300 Marble flooring 7 08-Mar-14 17-Mar-14 Marble flooring
LCC11310 Ceiling gypsum works 7 27-Apr-14 07-May-14 Ceiling gypsum works
LCC11320 1st coat paint on ceiling 5 07-May-14 14-May-14 1st coat paint on ceiling
LCC11330 Steel doors & accessories 4 14-May-14 20-May-14 Steel doors & accessories
LCC11340 Final coat paint on ceiling 5 25-May-14 01-Jun-14 Final coat paint on ceiling
LCC11350 Final coat paint on walls 5 01-Jun-14 08-Jun-14 Final coat paint on walls

Actual Work Critical Remaining Work Summary Page 37 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

MEP 76 03-Feb-14 25-May-14 25-May-14, MEP


LCM11280 HVAC ducting & FCU installation 15 03-Feb-14 25-Feb-14 HVAC ducting & FCU installation
LCM11290 Fire fighting pipe Installation 7 25-Feb-14 06-Mar-14 Fire fighting pipe Installation
LCM11300 Chilled water Piping 7 08-Mar-14 17-Mar-14 Chilled water Piping
LCM11310 Light & Power 1st & 2nd fix 7 17-Mar-14 27-Mar-14 Light & Power 1st & 2nd fix
LCM11320 Fire alarm 1st & 2nd fix 7 27-Mar-14 07-Apr-14 Fire alarm 1st & 2nd fix
LCM11330 BMS 1st & 2nd fix 7 07-Apr-14 16-Apr-14 BMS 1st & 2nd fix
LCM11340 MEP testing 7 17-Apr-14 27-Apr-14 MEP testing
LCM11350 MEP final fix 7 14-May-14 25-May-14 MEP final fix
Level 18 117 05-Jan-14 24-Jun-14 24-Jun-14, Level 18
Apartments 117 05-Jan-14 24-Jun-14 24-Jun-14, Apartments
Civil / Arch 117 05-Jan-14 24-Jun-14 24-Jun-14, Civil / Arch
LAC12380 Masonry walls 15 05-Jan-14 27-Jan-14 Masonry walls
LAC12390 Plastering works 15 27-Jan-14 17-Feb-14 Plastering works
LAC12400 1st coat paint on walls 15 18-Feb-14 11-Mar-14 1st coat paint on walls
LAC12410 Wet area water proofing 10 11-Mar-14 26-Mar-14 Wet area water proofing
LAC12420 Wet area flooring 10 26-Mar-14 09-Apr-14 Wet area flooring
LAC12430 Wet area wall tile works 10 09-Apr-14 24-Apr-14 Wet area wall tile works
LAC12440 Dry area ceiling gypsum works 20 11-Mar-14 09-Apr-14 Dry area ceiling gypsum works
LAC12450 Wet area ceiling works 12 24-Apr-14 12-May-14 Wet area ceiling works
LAC12460 1st coat paint on ceiling 15 09-Apr-14 01-May-14 1st coat paint on ceiling
LAC12470 Aluminium doors & windows 12 01-May-14 19-May-14 Aluminium doors & windows
LAC12480 Kitchen cabinets & wardrobes 15 12-May-14 02-Jun-14 Kitchen cabinets & wardrobes
LAC12490 Wooden doors& accessories 15 01-May-14 24-May-14 Wooden doors& accessories
LAC12500 Final coat paint on ceiling 15 31-May-14 22-Jun-14 Final coat paint on ceiling
LAC12510 Final coat paint on walls 15 03-Jun-14 24-Jun-14 Final coat paint on walls
MEP 95 12-Jan-14 31-May-14 31-May-14, MEP
LAM11360 HVAC Ducting & FCU installation 15 12-Jan-14 03-Feb-14 HVAC Ducting & FCU installation
LAM11370 Fire fighting pipe installation 15 12-Jan-14 03-Feb-14 Fire fighting pipe installation
LAM11380 Chilled water piping 15 12-Jan-14 03-Feb-14 Chilled water piping
LAM11390 Plumbing 1st & 2nd fix 10 12-Jan-14 27-Jan-14 Plumbing 1st & 2nd fix
LAM11400 Light, small power & Data 1st & 2nd fix 15 27-Jan-14 17-Feb-14 Light, small power & Data 1st & 2nd fix
LAM11410 Fire alarm 1st & 2nd fix 10 27-Jan-14 10-Feb-14 Fire alarm 1st & 2nd fix
LAM11420 MEP testing 15 18-Feb-14 11-Mar-14 MEP testing

Actual Work Critical Remaining Work Summary Page 38 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAM11430 MEP final fix 20 01-May-14 31-May-14 MEP final fix


Corridor 86 03-Feb-14 08-Jun-14 08-Jun-14, Corridor
Civil / Arch 76 18-Feb-14 08-Jun-14 08-Jun-14, Civil / Arch
LCC11360 Plastering works 7 18-Feb-14 27-Feb-14 Plastering works
LCC11370 1st coat paint on walls 5 27-Feb-14 06-Mar-14 1st coat paint on walls
LCC11380 Marble flooring 7 08-Mar-14 17-Mar-14 Marble flooring
LCC11390 Ceiling gypsum works 7 27-Apr-14 07-May-14 Ceiling gypsum works
LCC11400 1st coat paint on ceiling 5 07-May-14 14-May-14 1st coat paint on ceiling
LCC11410 Steel doors & accessories 4 14-May-14 20-May-14 Steel doors & accessories
LCC11420 Final coat paint on ceiling 5 25-May-14 01-Jun-14 Final coat paint on ceiling
LCC11430 Final coat paint on walls 5 01-Jun-14 08-Jun-14 Final coat paint on walls
MEP 76 03-Feb-14 25-May-14 25-May-14, MEP
LCM11360 HVAC ducting & FCU installation 15 03-Feb-14 25-Feb-14 HVAC ducting & FCU installation
LCM11370 Fire fighting pipe Installation 7 25-Feb-14 06-Mar-14 Fire fighting pipe Installation
LCM11380 Chilled water Piping 7 08-Mar-14 17-Mar-14 Chilled water Piping
LCM11390 Light & Power 1st & 2nd fix 7 17-Mar-14 27-Mar-14 Light & Power 1st & 2nd fix
LCM11400 Fire alarm 1st & 2nd fix 7 27-Mar-14 07-Apr-14 Fire alarm 1st & 2nd fix
LCM11410 BMS 1st & 2nd fix 7 07-Apr-14 16-Apr-14 BMS 1st & 2nd fix
LCM11420 MEP testing 7 17-Apr-14 27-Apr-14 MEP testing
LCM11430 MEP final fix 7 14-May-14 25-May-14 MEP final fix
Level 19 117 27-Jan-14 16-Jul-14 16-Jul-14, Level 19
Apartments 117 27-Jan-14 16-Jul-14 16-Jul-14, Apartments
Civil / Arch 117 27-Jan-14 16-Jul-14 16-Jul-14, Civil / Arch
LAC12520 Masonry walls 15 27-Jan-14 17-Feb-14 Masonry walls
LAC12530 Plastering works 15 18-Feb-14 11-Mar-14 Plastering works
LAC12540 1st coat paint on walls 15 11-Mar-14 02-Apr-14 1st coat paint on walls
LAC12550 Wet area water proofing 10 02-Apr-14 16-Apr-14 Wet area water proofing
LAC12560 Wet area flooring 10 17-Apr-14 01-May-14 Wet area flooring
LAC12570 Wet area wall tile works 10 01-May-14 15-May-14 Wet area wall tile works
LAC12580 Dry area ceiling gypsum works 20 02-Apr-14 01-May-14 Dry area ceiling gypsum works
LAC12590 Wet area ceiling works 12 17-May-14 02-Jun-14 Wet area ceiling works
LAC12600 1st coat paint on ceiling 15 01-May-14 24-May-14 1st coat paint on ceiling
LAC12610 Aluminium doors & windows 12 24-May-14 10-Jun-14 Aluminium doors & windows
LAC12620 Kitchen cabinets & wardrobes 15 03-Jun-14 24-Jun-14 Kitchen cabinets & wardrobes

Actual Work Critical Remaining Work Summary Page 39 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC12630 Wooden doors& accessories 15 24-May-14 14-Jun-14 Wooden doors& accessories


LAC12640 Final coat paint on ceiling 15 22-Jun-14 13-Jul-14 Final coat paint on ceiling
LAC12650 Final coat paint on walls 15 24-Jun-14 16-Jul-14 Final coat paint on walls
MEP 95 03-Feb-14 22-Jun-14 22-Jun-14, MEP
LAM11440 HVAC Ducting & FCU installation 15 03-Feb-14 25-Feb-14 HVAC Ducting & FCU installation
LAM11450 Fire fighting pipe installation 15 03-Feb-14 25-Feb-14 Fire fighting pipe installation
LAM11460 Chilled water piping 15 03-Feb-14 25-Feb-14 Chilled water piping
LAM11470 Plumbing 1st & 2nd fix 10 03-Feb-14 17-Feb-14 Plumbing 1st & 2nd fix
LAM11480 Light, small power & Data 1st & 2nd fix 15 18-Feb-14 11-Mar-14 Light, small power & Data 1st & 2nd fix
LAM11490 Fire alarm 1st & 2nd fix 10 18-Feb-14 04-Mar-14 Fire alarm 1st & 2nd fix
LAM11500 MEP testing 15 11-Mar-14 02-Apr-14 MEP testing
LAM11510 MEP final fix 20 24-May-14 22-Jun-14 MEP final fix
Corridor 86 25-Feb-14 30-Jun-14 30-Jun-14, Corridor
Civil / Arch 76 11-Mar-14 30-Jun-14 30-Jun-14, Civil / Arch
LCC11440 Plastering works 7 11-Mar-14 22-Mar-14 Plastering works
LCC11450 1st coat paint on walls 5 22-Mar-14 29-Mar-14 1st coat paint on walls
LCC11460 Marble flooring 7 29-Mar-14 08-Apr-14 Marble flooring
LCC11470 Ceiling gypsum works 7 19-May-14 29-May-14 Ceiling gypsum works
LCC11480 1st coat paint on ceiling 5 29-May-14 05-Jun-14 1st coat paint on ceiling
LCC11490 Steel doors & accessories 4 05-Jun-14 11-Jun-14 Steel doors & accessories
LCC11500 Final coat paint on ceiling 5 16-Jun-14 23-Jun-14 Final coat paint on ceiling
LCC11510 Final coat paint on walls 5 23-Jun-14 30-Jun-14 Final coat paint on walls
MEP 76 25-Feb-14 16-Jun-14 16-Jun-14, MEP
LCM11440 HVAC ducting & FCU installation 15 25-Feb-14 18-Mar-14 HVAC ducting & FCU installation
LCM11450 Fire fighting pipe Installation 7 19-Mar-14 29-Mar-14 Fire fighting pipe Installation
LCM11460 Chilled water Piping 7 29-Mar-14 08-Apr-14 Chilled water Piping
LCM11470 Light & Power 1st & 2nd fix 7 08-Apr-14 19-Apr-14 Light & Power 1st & 2nd fix
LCM11480 Fire alarm 1st & 2nd fix 7 19-Apr-14 28-Apr-14 Fire alarm 1st & 2nd fix
LCM11490 BMS 1st & 2nd fix 7 29-Apr-14 08-May-14 BMS 1st & 2nd fix
LCM11500 MEP testing 7 08-May-14 19-May-14 MEP testing
LCM11510 MEP final fix 7 05-Jun-14 16-Jun-14 MEP final fix
Level 20 117 27-Jan-14 16-Jul-14 16-Jul-14, Level 20
Apartments 117 27-Jan-14 16-Jul-14 16-Jul-14, Apartments
Civil / Arch 117 27-Jan-14 16-Jul-14 16-Jul-14, Civil / Arch

Actual Work Critical Remaining Work Summary Page 40 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LAC12660 Masonry walls 15 27-Jan-14 17-Feb-14 Masonry walls


LAC12670 Plastering works 15 18-Feb-14 11-Mar-14 Plastering works
LAC12680 1st coat paint on walls 15 11-Mar-14 02-Apr-14 1st coat paint on walls
LAC12690 Wet area water proofing 10 02-Apr-14 16-Apr-14 Wet area water proofing
LAC12700 Wet area flooring 10 17-Apr-14 01-May-14 Wet area flooring
LAC12710 Wet area wall tile works 10 01-May-14 15-May-14 Wet area wall tile works
LAC12720 Dry area ceiling gypsum works 20 02-Apr-14 01-May-14 Dry area ceiling gypsum works
LAC12730 Wet area ceiling works 12 17-May-14 02-Jun-14 Wet area ceiling works
LAC12740 1st coat paint on ceiling 15 01-May-14 24-May-14 1st coat paint on ceiling
LAC12750 Aluminium doors & windows 12 24-May-14 10-Jun-14 Aluminium doors & windows
LAC12760 Kitchen cabinets & wardrobes 15 03-Jun-14 24-Jun-14 Kitchen cabinets & wardrobes
LAC12770 Wooden doors& accessories 15 24-May-14 14-Jun-14 Wooden doors& accessories
LAC12780 Final coat paint on ceiling 15 22-Jun-14 13-Jul-14 Final coat paint on ceiling
LAC12790 Final coat paint on walls 15 24-Jun-14 16-Jul-14 Final coat paint on walls
MEP 95 03-Feb-14 22-Jun-14 22-Jun-14, MEP
LAM11520 HVAC Ducting & FCU installation 15 03-Feb-14 25-Feb-14 HVAC Ducting & FCU installation
LAM11530 Fire fighting pipe installation 15 03-Feb-14 25-Feb-14 Fire fighting pipe installation
LAM11540 Chilled water piping 15 03-Feb-14 25-Feb-14 Chilled water piping
LAM11550 Plumbing 1st & 2nd fix 10 03-Feb-14 17-Feb-14 Plumbing 1st & 2nd fix
LAM11560 Light, small power & Data 1st & 2nd fix 15 18-Feb-14 11-Mar-14 Light, small power & Data 1st & 2nd fix
LAM11570 Fire alarm 1st & 2nd fix 10 18-Feb-14 04-Mar-14 Fire alarm 1st & 2nd fix
LAM11580 MEP testing 15 11-Mar-14 02-Apr-14 MEP testing
LAM11590 MEP final fix 20 24-May-14 22-Jun-14 MEP final fix
Corridor 86 25-Feb-14 30-Jun-14 30-Jun-14, Corridor
Civil / Arch 76 11-Mar-14 30-Jun-14 30-Jun-14, Civil / Arch
LCC11520 Plastering works 7 11-Mar-14 22-Mar-14 Plastering works
LCC11530 1st coat paint on walls 5 22-Mar-14 29-Mar-14 1st coat paint on walls
LCC11540 Marble flooring 7 29-Mar-14 08-Apr-14 Marble flooring
LCC11550 Ceiling gypsum works 7 19-May-14 29-May-14 Ceiling gypsum works
LCC11560 1st coat paint on ceiling 5 29-May-14 05-Jun-14 1st coat paint on ceiling
LCC11570 Steel doors & accessories 4 05-Jun-14 11-Jun-14 Steel doors & accessories
LCC11580 Final coat paint on ceiling 5 16-Jun-14 23-Jun-14 Final coat paint on ceiling
LCC11590 Final coat paint on walls 5 23-Jun-14 30-Jun-14 Final coat paint on walls
MEP 76 25-Feb-14 16-Jun-14 16-Jun-14, MEP

Actual Work Critical Remaining Work Summary Page 41 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

LCM11520 HVAC ducting & FCU installation 15 25-Feb-14 18-Mar-14 HVAC ducting & FCU installation
LCM11530 Fire fighting pipe Installation 7 19-Mar-14 29-Mar-14 Fire fighting pipe Installation
LCM11540 Chilled water Piping 7 29-Mar-14 08-Apr-14 Chilled water Piping
LCM11550 Light & Power 1st & 2nd fix 7 08-Apr-14 19-Apr-14 Light & Power 1st & 2nd fix
LCM11560 Fire alarm 1st & 2nd fix 7 19-Apr-14 28-Apr-14 Fire alarm 1st & 2nd fix
LCM11570 BMS 1st & 2nd fix 7 29-Apr-14 08-May-14 BMS 1st & 2nd fix
LCM11580 MEP testing 7 08-May-14 19-May-14 MEP testing
LCM11590 MEP final fix 7 05-Jun-14 16-Jun-14 MEP final fix
Mezzanine Floor
Flo 97 27-Jan-14 17-Jun-14 17-Jun-14, Mezzanine Floor
Civil / Arch 97 27-Jan-14 17-Jun-14 17-Jun-14, Civil / Arch
MEC1000 Masorny walls 10 27-Jan-14 10-Feb-14 Masorny walls
MEC1010 Plastering works 10 10-Feb-14 25-Feb-14 Plastering works
MEC1015 Ceiling Painting 10 25-Feb-14 11-Mar-14 Ceiling Painting
MEC1020 1st coat paint on wall 10 11-Mar-14 26-Mar-14 1st coat paint on wall
MEC1030 Floor screeding 7 24-Apr-14 04-May-14 Floor screeding
MEC1040 Floor epoxy preparation 10 05-May-14 19-May-14 Floor epoxy preparation
MEC1050 Floor epoxy coating 10 19-May-14 02-Jun-14 Floor epoxy coating
MEC1060 Final Coat paint on wall 10 03-Jun-14 17-Jun-14 Final Coat paint on wall
MEP 45 11-Mar-14 15-May-14 15-May-14, MEP
MEM1000 Light & Small Power 1st & 2nd Fix 15 11-Mar-14 02-Apr-14 Light & Small Power 1st & 2nd Fix
MEM1010 Fire fighting 1st & 2nd Fix 30 11-Mar-14 24-Apr-14 Fire fighting 1st & 2nd Fix
MEM1020 HVAC ducting & FCU installation 15 11-Mar-14 02-Apr-14 HVAC ducting & FCU installation
MEM1030 BMS 1st & 2nd Fix 10 11-Mar-14 26-Mar-14 BMS 1st & 2nd Fix
MEM1035 Fire Alarm 1st & 2nd Fix 10 11-Mar-14 26-Mar-14 Fire Alarm 1st & 2nd Fix
MEM1040 AHU Installation 15 24-Apr-14 15-May-14 AHU Installation
MEM1050 MEP final Fix 15 24-Apr-14 15-May-14 MEP final Fix
Eleveators 250 30-Jun-13 29-Jun-14 29-Jun-14, Eleveators
EL 01 & 02 170 30-Jun-13 04-Mar-14 04-Mar-14, EL 01 & 02
EL1000 Scaffolding Erection 40 30-Jun-13 26-Aug-13 Scaffolding Erection
EL1010 Separator beams installation 15 27-Aug-13 17-Sep-13 Separator beams installation
EL1020 Guide rails 30 17-Sep-13 31-Oct-13 Guide rails
EL1030 Doors 20 31-Oct-13 30-Nov-13 Doors
EL1040 Machine room Mechanical works 10 30-Nov-13 14-Dec-13 Machine room Mechanical works
EL1050 Machine room Electrical works 10 14-Dec-13 29-Dec-13 Machine room Electrical works

Actual Work Critical Remaining Work Summary Page 42 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

EL1060 Roping 10 29-Dec-13 12-Jan-14 Roping


EL1070 Cabin 10 12-Jan-14 27-Jan-14 Cabin
EL1080 Removal of Scaffolding 20 27-Jan-14 25-Feb-14 Removal of Scaffolding
EL1090 Running at High speeds 5 25-Feb-14 04-Mar-14 Running at High speeds
EL 03 & 04 170 27-Aug-13 01-May-14 01-May-14, EL 03 & 04
EL1100 Scaffolding Erection 40 27-Aug-13 23-Oct-13 Scaffolding Erection
EL1110 Separator beams installation 15 24-Oct-13 14-Nov-13 Separator beams installation
EL1120 Guide rails 30 14-Nov-13 29-Dec-13 Guide rails
EL1130 Doors 20 29-Dec-13 27-Jan-14 Doors
EL1140 Machine room Mechanical works 10 27-Jan-14 10-Feb-14 Machine room Mechanical works
EL1150 Machine room Electrical works 10 10-Feb-14 25-Feb-14 Machine room Electrical works
EL1160 Roping 10 25-Feb-14 11-Mar-14 Roping
EL1170 Cabin 10 11-Mar-14 26-Mar-14 Cabin
EL1180 Removal of Scaffolding 20 26-Mar-14 24-Apr-14 Removal of Scaffolding
EL1190 Running at High speeds 5 24-Apr-14 01-May-14 Running at High speeds
EL 05 & 06 170 24-Oct-13 29-Jun-14 29-Jun-14, EL 05 & 06
EL1200 Scaffolding Erection 40 24-Oct-13 21-Dec-13 Scaffolding Erection
EL1210 Separator beams installation 15 22-Dec-13 12-Jan-14 Separator beams installation
EL1220 Guide rails 30 12-Jan-14 25-Feb-14 Guide rails
EL1230 Doors 20 25-Feb-14 26-Mar-14 Doors
EL1240 Machine room Mechanical works 10 26-Mar-14 09-Apr-14 Machine room Mechanical works
EL1250 Machine room Electrical works 10 09-Apr-14 24-Apr-14 Machine room Electrical works
EL1260 Roping 10 24-Apr-14 08-May-14 Roping
EL1270 Cabin 10 08-May-14 24-May-14 Cabin
EL1280 Removal of Scaffolding 20 24-May-14 22-Jun-14 Removal of Scaffolding
EL1290 Running at High speeds 5 22-Jun-14 29-Jun-14 Running at High speeds
Post Construction
Construc 155 13-Feb-14 27-Sep-14 27-Sep-14, P
Testing & Commissioning
Com 60 22-Jun-14 17-Sep-14 17-Sep-14, Tes
TC1000 Electrical system 45 22-Jun-14 26-Aug-14 Electrical system
TC1010 BMS system 60 22-Jun-14 17-Sep-14 BMS system
TC1020 CO system 20 22-Jun-14 21-Jul-14 CO system
TC1030 Chilled water system 30 22-Jun-14 04-Aug-14 Chilled water system
TC1040 Domestic water system 30 22-Jun-14 04-Aug-14 Domestic water system
TC1050 Fire fighting system 45 22-Jun-14 26-Aug-14 Fire fighting system

Actual Work Critical Remaining Work Summary Page 43 of 44 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish M J J A S O N D J F M A M J J A S O N D
Duration

TC1060 Fire alarm system 45 22-Jun-14 26-Aug-14 Fire alarm system


QCDD 40 31-Jul-14 27-Sep-14 27-Sep-14, Q
QCDD1000 QCDD Inspection 10 31-Jul-14 14-Aug-14 QCDD Inspection
QCDD1010 Necessary remedial works after inspection 20 14-Aug-14 13-Sep-14 Necessary reme
QCDD1020 QCDD approval 10 13-Sep-14 27-Sep-14 QCDD appro
Close out 155 13-Feb-14 27-Sep-14 27-Sep-14, C
CR1000 Submittal of As built drawings 110 13-Feb-14 23-Jul-14 Submittal of As built draw
CR1010 Submittal of O & M manuals 110 13-Feb-14 23-Jul-14 Submittal of O & M manu
CR1020 UDC forms for substantial completion 10 16-Jul-14 30-Jul-14 UDC forms for substan
CR1030 UDC forms for Occupancy 7 17-Sep-14 27-Sep-14 UDC forms fo
Snagging & d
desnagging 150 13-Feb-14 20-Sep-14 20-Sep-14, Sn
SD1000 Sagging Level 1 - 6 15 13-Feb-14 06-Mar-14 Sagging Level 1 - 6
SD1010 Desnagging Level 1 - 6 45 08-Mar-14 12-May-14 Desnagging Level 1 - 6
SD1020 Snagging Level 7 - 12 15 20-Apr-14 12-May-14 Snagging Level 7 - 12
SD1030 Desnagging Level 7 - 12 45 12-May-14 16-Jul-14 Desnagging Level 7 - 12
SD1040 Snagging Level 13 - 18 15 24-Jun-14 16-Jul-14 Snagging Level 13 - 18
SD1050 Desnagging Level 13 - 18 45 16-Jul-14 20-Sep-14 Desnagging Le
SD1060 Snagging Level 19 - 20 7 16-Jul-14 27-Jul-14 Snagging Level 19 - 20
SD1070 Desnagging Level 19 - 20 30 27-Jul-14 08-Sep-14 Desnagging Lev
SD1080 Snagging Podium 1 - 4 & Amenity Floor 10 16-Jul-14 30-Jul-14 Snagging Podium 1 - 4
SD1090 Desnagging Podium 1 - 4 & Amenity Floor 30 31-Jul-14 13-Sep-14 Desnagging Pod

Actual Work Critical Remaining Work Summary Page 44 of 44 TASK filter: All Activities