Solar Farm

EPC Approach Document

Source: ABB

Key Components

.....

Poly Crystalline (<300W Panels)


Thin Film (<60w Panels) 1MW Inverter Stations

+ Accessories
+ Structural
Central Inverter (500/250KW) Switch Gear Transformer Junction Box Components

Copyright 2010 © SolREA Renewables Pvt. Ltd.


Phase I – Scope of Work Definition (1 Week)

Phase II – Documentation Study (2 - 4 Weeks)

 Review of DPR

• If No DPR, DPR Needs to be Prepared

• This is in Addition to the Above Schedule

 Review of Design

 Review of Detailed Engineering

 We Will Check Location DNI Data is Validated & Certified

 We Will Review:

• Solar Farm Layout

• BOM/BOQs

o Structural – Layout etc.

o Electrical

 Inverters, Transformers, Switch Gears etc., Specs

 Electrical Safety Equipment

o We Will Validate All Calculations, Generation Numbers, Electrical Load


Info, Cable Lengths etc.

 Output

• Comments – Gen Review

• High Level Project Plan & Schedule

Copyright 2010 © SolREA Renewables Pvt. Ltd.


Phase III – Physical Site Study & Enquiry Generation for Procurement (2 – 4 Weeks)

 Check If any Landscaping Requirements, Make any changes required

 We Will Generate BOM/BOQ from Database of Std. Components/Vendors

 We Will Send out Firm Enquiries for High Cost Items like Panels, Inverters Etc.

 Output

• Revised BOM/BOQ with Final Price Quotes

• Detailed Project Plan

• Evacuation Details

Phase IV – Team Deployment & Execution (Project Specific)

 Weekly Progress Reports & Pictures as SolREA and our Partners Execute the Project

 Online Secure Project Website to Review Status with Embedded Comm. & Collaboration Facilities

 Build Quality Mgmt. Using SolREA BQAP (Build Quality Assurance Plan)

Phase V – Commissioning & Transfer

 Detailed Parameter Checklist Using SolREA BQV (Build Quality Verification) Process

 Simultaneously Install and Test On-Site & Remote Performance Monitoring & Mgmt. Systems

 Organize Certification Process

 Outputs

• Docs & Training To O&M Team

o SolREA Operating Manuals & Warranty Docs, Facility Operating Checklists

o SolREA Performance Monitoring Tools

o Troubleshooting Tips & FAQs

o Emergency Procedures

• Appropriate Certificates As Required

• Transfer Functioning Solar Farm

Copyright 2010 © SolREA Renewables Pvt. Ltd.


1MW / 5MW SOLAR FARM
Preliminary Questionnaire

Applicant Name:

Applicant Address:

Contact Info:

Site

Address:

Latitude, Longitude if Available:

DNI Data If Available:

Distance from Grid:

Grid Voltage (11KV/33KV/66KV/132KV):

Site Topography Map If Available:

MW: _<1MW _1MW _5MW

Scheme _State _Central

License Status _Applied _Awarded

Possible Start Date/Month:

DPR Done _Yes _No

(Please email copy to SolREA)

Copyright 2010 © SolREA Renewables Pvt. Ltd.