Вы находитесь на странице: 1из 4

 You have calculated the Direct Costs of the work items in

the BOQ, as follows:

Direct Costs (LE)


Item
Rate Qty Total
Excavation 10 10,000 100,000
Plain Concrete 350 200 70,000
Reinforced Concrete 1,000 900 900,000
Finishing Works 20 36,500 730,000
Total 1,800,000

 Now that you have calculated the Indirect Costs (= LE


180,000) and the Mark-Up (= 15% of the Direct and Indirect
Costs), complete the following BOQ.

Item Rate Qty Total


Excavation 10,000
Plain Concrete 200
Reinforced Concrete 900
Finishing Works 36,500
Total

1
Direct Costs and Indirect Costs

Direct Costs (LE)


Item
Rate Qty Total
Excavation 10 10,000 100,000
Plain Concrete 350 200 70,000
Reinforced Concrete 1,000 900 900,000
Finishing Works 20 36,500 730,000
Total Direct Costs 1,800,000
Total Indirect Costs 180,000
%Indirect / Direct 10%

First calculate the % of the Indirect Costs / Direct Costs

Direct Costs + Indirect Costs

Indirect Costs
Direct Costs (LE)
(LE)
Item
Rate Qty Total Rate Qty Total

Excavation 10 10,000 100,000 1 10,000 10,000

Plain Concrete 350 200 70,000 35 200 7,000

Reinforced 1,000 900 900,000 100 900 90,000


Concrete
Finishing Works 20 36,500 730,000 2 36,500 73,000

Total 1,800,000 180,000

Add the Indirect Costs as a percentage to each item of work.


Indirect Costs = Direct Costs X 10%

2
Direct Costs + Indirect Costs

Indirect Costs Direct + Indirect


Direct Costs (LE)
(LE) Costs (LE)
Item
Rate Qty Total Rate Qty Total Rate Qty Total

Excavation 10 10,000 100,000 1 10,000 10,000 11 10,000 110,000

Plain Concrete 350 200 70,000 35 200 7,000 385 200 77,000

Reinforced 1,000 900 900,000 100 900 90,000 1,100 900 990,000
Concrete
Finishing Works 20 36,500 730,000 2 36,500 73,000 22 36,500 803,000

Total 1,800,000 180,000 1,980,000

Add the Direct and Indirect Costs

Direct Costs + Indirect Costs + Mark-Up

Indirect Costs Direct + Indirect


Direct Costs (LE) Mark Up (LE)
(LE) Costs (LE)
Item
Rate Qty Total Rate Qty Total Rate Qty Total Rate Qty Total

Excavation 10 10,000 100,000 1 10,000 10,000 11 10,000 110,000 2 10,000 16,500

Plain Concrete 350 200 70,000 35 200 7,000 385 200 77,000 58 200 11,550

Reinforced 1,000 900 900,000 100 900 90,000 1,100 900 990,000 165 900 148,500
Concrete
Finishing Works 20 36,500 730,000 2 36,500 73,000 22 36,500 803,000 3 36,500 120,450

Total 1,800,000 180,000 1,980,000 297,000

Add the Mark-Up as a percentage to each item of work.


Mark-Up = (Direct Costs + Indirect Costs) X 15%

3
Direct Costs + Indirect Costs + Mark-Up

Indirect Costs Direct + Indirect Direct + Indirect Costs +


Direct Costs (LE) Mark Up (LE)
(LE) Costs (LE) Mark Up (LE)
Item
Rate Qty Total Rate Qty Total Rate Qty Total Rate Qty Total Rate Qty Total

Excavation 10 10,000 100,000 1 10,000 10,000 11 10,000 110,000 2 10,000 16,500 13 10,000 126,500

Plain Concrete 350 200 70,000 35 200 7,000 385 200 77,000 58 200 11,550 443 200 88,550

Reinforced 1,000 900 900,000 100 900 90,000 1,100 900 990,000 165 900 148,500 1,265 900 1,138,500
Concrete
Finishing Works 20 36,500 730,000 2 36,500 73,000 22 36,500 803,000 3 36,500 120,450 25 36,500 923,450

Total 1,800,000 180,000 1,980,000 297,000 2,277,000