Chief Engineer
Preparations:
Dry docking survey is to be done every 2 ½ years interval , 2 times in 5 each year cycle , called
annual docking and special docking survey. Special survey is carried out every 5 years interval.
As a Chief Engineer of a vessel , he must study the time of dry docking due , verify annual or
special , and prepare documents & defect list to be repaired , at least 3 months priority for easy
and efficient supports from ship company.
Preparation of Documents:
Repair List
B. The following dock yard repair items to be mentioned details with their specifications as
follow:
C. During docking Chief Engineer must attend all Class Surveyor inspections .
D. Discuss and arrange with Ship Repair Manager to harmonize work program between yard
and ship staff, always regarding safety of the ship and lives.
E. Alternations and additional works may occur during the course of repairs. If any, Chief
Engineer should make additional repair list. Attending Superintendent or owner representative
will issue order to shipyard.
Engine room staff to be organized and assigned for the jobs to be done by dockyard as follows:
Engine room staffs to be organized and assigned for the jobs to be done by themselves as
follows:
2. Before entering dry dock , explain procedures and assigned duties. ( Times recording , Diesel
Generator stopping , Shore power and cooling water connection etc)
3. The following works to be assigned and distributed among engine room staff in group for
supervision:
Valves from bilge and ballast system , cooling water system , steam line and air lines….
to be overhauled.
Waste & corroded piping to be rectified as necessary.
Necessary coolers to be cleaned.
Scheduled maintenance to be done, if any .
C.S.M survey items to be done , if any.
E/R cleaning and painting.
6. Instructions and check lists to be issued for undocking procedures , to inform abnormal
condition.