Вы находитесь на странице: 1из 26

WORK METHOD STATEMENT

FOR SITE PREPARATION WORKS BEFORE START OF ANY MAJOR


PROJECTS

00 Issue for information


Rev. Description Prepared Checked Approved Date

Data file: …………………………….


This document is the property of ……………..company name ………………….
CONTENTS

1 PURPOSE 3

2 SCOPE 3

3 REFERENCES 3
3.1 Company Specifications 3
3.2 Project Specifications 4
3.3 Drawings and Documents 4
3.4 Codes and Standards 4

4 RESPONSIBILITIES 4

5 METHODS 5
5.1 Definitions 5
5.2 Preliminary Activities 7
5.3 Top Soil Removal 7
5.4 Fill Material 8
5.5 Fill and Compaction 10
5.6 Slope Erosion Protection 13
5.7 Testing and Inspection 14
5.8 Disposal 15
Attachment #1 Topographical Survey Results 16
Attachment #2 Area classification for Site Preparation 18
Attachment #3 Field Fill Trials Program 20

Data file: …………………………….


This document is the property of ……………..company name ………………….
Purpose
The purpose of this Work Method Statement is to outline the general requirements and
precautionary description of the site preparation works to be performed for any project.

SCOPE

This Work Method Statement identifies the general steps, arrangements and
precautions to be followed for the execution of all activities of site preparation works
before the foundation works start by consultant and contractor.

The General Scope of Work of the Contractor includes, but is not limited to supply and
construction of the following:
- Site Preparation works (Top Soil Removal, Fill, Compaction and Slope Protection
Works);
- Other miscellaneous site preparation works not mentioned above;

The expected period of the Site Preparation Works is approximately 8 months.

REFERENCES

The Site Preparation Works shall be designed, planned and performed in compliance
with the following applicable Specifications and Codes.

In case of conflict, the order of precedence of the documents shall be:


 Client Specifications (as modified with NCR, if any)
 Project Specifications
 Design Drawings
 General Specifications and Standards
 Industry Codes and Standards

However, any discrepancies shall be brought to the attention of the Client.

Company Specifications

- Plant Layout
- General Requirements to Civil Works & Structures

Project Specifications

- Project Specification for Civil works and Earth


Movements
- Project General HSE Plan

Drawings and Documents

- Site Preparation General Grading Plan


- Site Preparation Sections (1~4)
- Areas Characterization for Site Preparation
- Geotechnical Report
Data file: …………………………….
This document is the property of ……………..company name ………………….
Codes and Standards

- ASTM D 2922 Test Methods for Density of Soil and Soil-Aggregate


in Place by Nuclear Methods (Shallow Depth)
- BS 1377 Method of test for Soils for Civil Engineering Purpose
- BS 5930 Code of practice for site investigations
- BS 6031 Code of practice for earthworks
- If any local country specification

RESPONSIBILITIES

Contractor will proceed and coordinate with concerned authorities to obtain work
permit, supply the construction materials and control all site activities by the personnel
as follows;

Superintendent
He has overall responsibility for the site preparation management in accordance with
the contract requirements.
He shall coordinate and control the execution of the Site Preparation, and ensure
completion within scheduled time and the observance of HSE and quality procedures
and practices in accordance with the relevant regulation of authorities.
Site HSE Supervisor
He has overall responsibility for the implementation of HSE plan according to the
Project HSE Plan in this specification.
He shall investigate and report all major accident, recommend protection measures,
and ensure the availability of safety equipment and first aid kits.

QA/QC Engineer
He has overall responsibility for the control and inspection of quality according to the
QA/QC plan in this specification.
He shall review the Contract specifications and drawings, identify project criteria and
prepare required checklist for QA/QC inspection.

TPI (Third Party Inspection)


Any organization, authority, person or persons, to which Contractor has subcontracted
the execution of inspection and/or laboratory testing, related activities.

Civil Engineer
He has overall responsibility for the implementation of Site Preparation Works in this
specification.
He shall arrange the manpower, equipment and materials required for the
implementation of the works, coordinate with HSE officer and QA/QC Engineer
involved in the tasks in accord to the method statement and reporting.

Data file: …………………………….


This document is the property of ……………..company name ………………….
METHODS

Definitions

General Fill

General Fill means the fill with Dune Sand and/or selected fill material, mainly this
concerns the non-congested area with low density of foundations, mainly this concerns
the off-site and some portions of process units. This fill will be up to local requirement
of site during Site Preparation period after completion of top soil removal. This is mostly
on bottom of structural fill.

Structural Fill

Structural Fill means the fill with Structural Fill Material imported from quarry, mainly
this concerns the congested area with high density of foundations, mainly this concerns
the process units. This fill will be up to 1.1m during Site Preparation period after
completion of top soil removal;

For the area of elevation exceeding 1.1m after completion of top soil removal,
Contractor shall verify the bearing capacity and settlement and determine fill method
whether the replacement will be needed or not.

Boundary between Congested and Non-Congested Area

Boundary area between congested and non-congested area means a boundary with
different elevations, mainly this concerns the slope stability during construction period.
These areas will be overlapped with General and Structural Fill Material to the extent of
app. 3.2 m of width and 1.6 m of height in order to secure the stability of slope. The
drawing in outline of this area is as below;

Preliminary Activities

Existing Service

Contractor shall make his own investigation to establish the exact location of existing
services which may affect or be affected by the construction of the Works. In addition,
Contractor shall before carry out adequate preliminary investigations using any suitable
means to verify the location of existing services.

Surveying

A topographical survey supervised by Contractor has been carried out so as to


commence the Site Preparation Works. Contractor has installed the Control Points to
set out the locations at good controlled places along the Site. For more details, refer to
attachment #1 Topographical Survey Report.

Dimensions and levels shall be pre-established from drawings prior to construction.


During construction period of the Works, surveying team will indicate and maintain the

Data file: …………………………….


This document is the property of ……………..company name ………………….
boundaries of the areas, especially the cut and fill area by putting temporary signs at
the exact positions using total station and auto level instruments.

Contractor will establish a number of permanent settings out station from which to set
out the Plant and establish and record their co-ordinates on the site grid.

All surveying reports shall be submitted to Company after inspection by Contractor.

Site clearance

All work areas shall be cleared of refuse, vegetation and deleterious material with all
necessary authorizations. Unsuitable materials shall be removed from Site in an area
approved by authorities.

Unsuitable materials and suitable material not intended for re-use shall be removed
from the work site and disposed in accordance with local and national laws and
regulations.

Top Soil Removal

Area classification and Work Sequence

The area classification and work sequence for Top Soil Removal Works is as below;
(1) The Site will be classified by 7 divisions as shown in the attachment #2 Area
Classification for Site Preparation according to the construction schedule.
(2) To meet the requirement for Specification, each division will be sectioned by various
levels according to the site ground condition.
(3) Considering the natural ground conditions and workability of equipment, each
section will be stepped and graded as shown in the attachment #2 Area
Classification for Site Preparation.
(4) The Contractor can secure a stockpile of topsoil placed in a limited area for
disposal or reuse after approval of Company.
(5) After finishing the top soil removal work, the area will be finally leveled and
compacted in order to prepare for fill works.
(6) The sequence of each unit will be according to the given Site Preparation Schedule

Work Methodology

• Prior to the work, Contractor shall obtain the Work Permit and request for Waste
Transportation and Disposal from authorities as per related regulations.
• Before starting the work, all bushes, vegetation, debris, materials or any other
obstruction will be removed by means of required equipment and machinery.
• The removed soil should be transported to the disposal area designated by
authorities.
• The work will be performed on the basis of the soil nature which shall be stripped
down to 200mm app. below the existing ground level for both areas
• The stripped soil will be heaped for further loading and transported to stockpile on the
Data file: …………………………….
This document is the property of ……………..company name ………………….
identified area.
• Adequate loading will be made within the allowable truck load and shall not be
exceeded.
• Truck will use the approved access road by authorities complying with local
regulations and practices.

Fill Material

Suitable Fill material

All fill material shall be either suitable excavated material or suitable imported material.
The suitability of materials shall be in accordance with the following

(1) Suitable material for earthworks shall be approved soil with a liquid limit not
exceeding 40%. The material passing the 0.075mm sieve shall not exceed 20%
and the organic matter content shall not exceed 2% (as determined by BS 1377-
Part 3).
(2) Where excavated rock is to be used as fill material elsewhere on the site, the
Contractor is responsible for ensuring that the excavated rock meets the
requirement of the Specification for fill material.
(3) The Contractor is responsible for mixing the excavated rock with suitable fill
material imported and/or excavated from within the site should it be necessary in
order to produce a suitable fill material that complies with the requirements of the
Specification.

Contractor shall supply suitable material and carry out such tests as required, to
demonstrate the suitability of the fill, especially with respect to compacting.

Contractor shall submit geotechnical test reports on dune sand, structural fill material
and selected fill material specification for Company’s review.

General Fill Material

Dune sand can be used as general fill.

Structural Fill Material

When structural fill material imported from borrow pits, it shall comply with the following
requirements as minimum:
1) Particle Size : 75mm max.
2) Gradation
Sieve Size % of Mass Passing
75 mm 100
28 mm 65 to 95
10 mm 30 to 75
5 mm 25 to 60
Data file: …………………………….
This document is the property of ……………..company name ………………….
2 mm 15 to 45
0.425 mm 8 to 30
3) Fines content : 20% max.
4) Liquid limit : 40 max.

5
Water for Compaction
Fresh water or ground water (brackish) shall be used for the fill operations. Water used
for compaction of fill material shall be reasonably free of salts, oil, acid, alkalis, organic
matter, or other deleterious substances, and imported from outside authorized source.

Fill and Compaction

Flow Chart

The flow chart for fill and compaction is as below;

Top Soil Removal Field Fill Trials

Fill Material
Preparation for Fill Selection

Soil Property &


Field Density Test/ Compaction Test
Plate Bearing Test

Moisture N.G
Content Check Moisture
Control Content

N.G
Checking Soil
Improvement
Capacity

O.K Filling for each O.K


Layer

N.G
Checking Compaction
Re-construction
Degree (FDT/PBT)

O.K

Data file: …………………………….


This document is the property of ……………..company name ………………….
Completion of
Field Fill Trials 1 Layer

Before the commencement of the fill and compaction work, field fill trials shall be
carried out in order to determine optimum properties of compacted fill and shall include;
• Layer thickness
• Compaction methods
• Number of passes
• Amount of watering
• Type of Equipment

Compaction shall be performed with equipment compatible with fill type according to
the results of Field Fill Trials. The Field Fill Trials will be carried out according to the
attachment #3.

Fill and Compaction

General Fill and Compaction

General fill may be used to raise certain areas of the site to the required grades. These
areas shall be limited to locations where no structures, pipelines, utilities are to be
constructed.

Contractor will perform the works in non-congested area in accordance with the
following sequence:

o CASE 1:
The non-congested areas inside “process areas Contractor will perform the works
in accordance approximately with the following sequence:
1. Clearing, grubbing and minimum 200 mm soil stripping on area defined on
design drawings
2. Compaction of the sub-grade to at least 90% of maximum density
3. Spreading, grading and compacting each fill layer with general fill material
4. Consecutive general fill and compaction up to established grade levels

o CASE 2:
The non-congested areas into “non process areas”, could be directly backfilled up
to that is the elevation to receive the final finishing (concrete paving/asphalt or
gravel), with dune sand including the last layer of structural fill material.
In those areas, the roads will be prepared up to EL. +99,40 providing sub-grade
with dune sand and sub-base with structural fill material, according to Drawing.

As a minimum, at least one field density test must be performed on every layer of fill
and further placement shall not be allowed until the required density has been
achieved.

General fill shall be placed in layers according to the results of Field Fill Trials. Each
layer shall be compacted with approved equipment to a minimum density of 95 % of
the maximum density obtained in BS 1377 or equivalent.

Data file: …………………………….


This document is the property of ……………..company name ………………….
The surface of each layer, to be tested, shall be in accordance with specification.

Structural Fill and Compaction

Structural fill shall be used to raise the site to the required grades. Wherever unsuitable
soil is found it shall be removed and replaced with material suitable for support of the
Works.

Contractor will perform the works in congested area in accordance with the following
sequence:
(1) Clearing, grubbing and soil stripping on area defined on design drawings
(2) Compaction of the sub-grade to at least 90% of maximum density
(3) Spreading, grading and compacting each fill layer with structural fill material
(4) Consecutive structural fill and compaction up to elevation +98.000

Structural fill shall be placed in layers according to the results of Field Fill Trials and
each layer shall be compacted with approved equipment to the densities specified
herein. Areas not meeting the required compaction shall be scarified and re-
compacted until the specified density is obtained. If the top of a layer has crusted, the
Contractor shall scarify the surface to ensure good bond with the following layer.

Each layer of Structural Fill shall be compacted to a minimum dry density of 95 % of


the maximum dry density obtained in BS 1377 or equivalent.

Tolerance

These earthworks shall be undertaken to obtain the final surfaces, elevations, and
slopes in the various areas as shown on drawings with tolerances +I- 30 mm.
Compacted surfaces of fill shall be finish graded to the cross sections, lines, grades,
and elevations as indicated on the approved drawings.

Slope Erosion Protection

General
A layer of minimum 50 mm thickness of bituminous mix accordingly to project
specification shall be applied for slopes in order to provide erosion protection. Special
care shall be placed at construction stage to avoid all situations where concentrated
flows may take place over unprotected slopes.

Material
An application of liquid asphalt primer or similar approved material shall be sprayed at
the rate of 1.5 kg/m2 to the surface.

The bitumen mix shall be made with a well graded aggregate, and the maximum size of
the aggregate shall be within 10 mm.

Data file: …………………………….


This document is the property of ……………..company name ………………….
The percentage of bitumen to be mixed shall vary from 4.5% to 6.0% by weight of
aggregates.

Placing
For placing of slope protection, the surface to be placed shall be leveled according to
the design elevations and shall have the established slopes according to the drawings.

An application of liquid asphalt primer or similar approved material shall be sprayed at


specified rate to the surface, and before proceeding with the covering work, an
appropriate weed-killer must be applied in accordance with the Suppliers instructions.

The spreading of the material must be made at a temperature of 120°C approx. and
spreading is carried out manually and the thickness of the loose layer shall correspond
to a finished thickness of 50mm.

Rolling is performed with a hand operated roller when the material is still hot, in order to
reach a satisfactory compaction. The layer thickness must be uniform and
homogeneous over the entire area covered, and the surface must be perfectly even.

Temporary Slope Protection


In accordance to Clause 5.5.3 in this specification, it will be necessary to protect the
slope of dune sand layer between the areas at different elevation using fabric material
such as non-woven geotextile (PET short fibre needle punched, 100g/m2) fixed on
base and top with a layer of structural fill material or equivalent.

Testing and Inspection


Testing

Testing shall be provided in order to adequately demonstrate the suitability and


acceptability of al fill materials. The testing shall also demonstrate that required
compaction requirements are met. Trials shall be carried out to confirm the adequacy of
al materials and methods prior to commencement of site fill operations.

Gradation, density, and moisture content control tests shall be performed at the
following minimum frequencies; one standard sieve analysis and one Modified Proctor
Test per BS 1377 or equivalent with corresponding Proctor curve performed for each
type of fill material.

Contractor shall also perform the above tests every day during filling work until the
Company’s approval of decrease in the frequency.

In-situ density and moisture content of soils shall be determined by the sand-cone
method per BS 1377 or equivalent and/or nuclear method per ASTM D2922.

Acceptance testing of in-situ density and moisture content (field density testing) on
compacted fill will be performed every 500m2 of the fill area. The layers will be deemed
suitably compacted if they meet the requirements of 95% maximum dry density.

Data file: …………………………….


This document is the property of ……………..company name ………………….
The number of tests shall be increased if a visual inspection determines that the
moisture content is not uniform or if the compacting effort is variable and not
considered sufficient to attain the specified density.

Inspection

The required inspection for each activity will be monitored by Contractor in proper as
per the General Earthwork specification.

An authorized and certificated TPI (Third Party Inspection) shall be carried out the
testing inspection and related activities during construction.

All inspection report shall be submitted to Company accordingly to specification


requirement as above mentioned.

Disposal
Unsuitable Material

Debris resulting from site clearance, stripped top soil which is not acceptable for use as
fill material shall be removed from the Site by the Contractor and disposed of in areas
allocated and/or acceptable to the responsible authorities. Arrangements for such
disposal shall be the responsibility of the Contractor.

Excess Material

Any excess soil resulting from the Site shall be removed from the work site and
disposed in local tips. Materials shall be disposed of in accordance with local and
national laws and regulations.

Areas used for temporary stockpiling shall be kept clean and tidy and shall be restored
to their original condition on completion of works.

Topographical Survey Results

1. Survey Details

2 Survey Location

3 Control Point Setting Out

4 Area classification for Site Preparation

Data file: …………………………….


This document is the property of ……………..company name ………………….
Attachment #3 Field Fill Trials Program

Field Fill Trials Program

1. Purpose
This plan describes the method and procedure to determine fill materials, compaction
equipment and compaction method etc. to meet the requirements of the Specification.

2. Flow Chart
The flow chart for Field Fill Trials is as below;

Case Definition Case-1 Dune Sand


Case-2 Structural Fill Material

Laboratory Test Moisture Content Test


for each Case
Sieve Analysis Test

Atterburg Limit Test

Specific Gravity Test

Organic Content Test

Compaction Test

Laboratory C.B.R Test


Filling for
each Case

Compaction
for each Case Moisture Content Test

Field Density Test (F.D.T)

Plate Bearing Test (P.B.T)


Surface Check &
Reporting

Data file: …………………………….


This document is the property of ……………..company name ………………….
Execution Plan

Trial Area and Equipment Proposed


1) Trial Area : Width 6 m, Length 180 m, 5 Blocks (5 Cases), Total Area 5,400 m2
2) Equipment Proposed (to be used for the work)
• Tripper Truck (40ton) : 6 nos
• Loader (3.5~4.0m3) : 2 nos
• Grader (W=3.6m) : 2 nos
• Vibratory Roller (10ton) : 2 nos
• Water Spray Truck (20ton) : 2 nos

Materials and Mixing Method


1) Materials
• Dune Sand :from Dune Sand stock Area of MIC
• Structural Fill Material : from Quarry to be used
2) Mixing Method (if required) 5

• Equipment : Loader
• Mixing Ratio Weighing : by Volume of Tripper trucks with same loading capacity

Test Plan

Items Description Frequency Remarks


Specific Gravity
Compaction Test
CBR Test
Atterberg Limit Test
Laboratory for Dune Sand &
Moisture Content Test 3 times per source
Test Structural fill material
Dry Density
Sulphate Content
Chloride Content
Organic Content Test
Moisture Content Test
1 time per division total 45 times
Field Test Field Density Test
Plate Bearing Test 3 times per block total 15 times

Reporting

Fill Trial Method and Measurement Results


• Thickness before Grading
Data file: …………………………….
This document is the property of ……………..company name ………………….
• Equipment used
• Compaction Times
• Moisture Content
• Dry Density
• Compaction Degree
• Load-Settlement Curve
• Thickness after Compaction
• Visual Inspection

Analysis and Conclusion


• Determination of Fill Materials to be used for its purpose
• Determination of Compaction Thickness of a layer
• Determination of Compaction Times
• Determination of Optimized Moisture Content
• Review of Load-Settlement Relation
• Conclusion

Data file: …………………………….


This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….
Data file: …………………………….
This document is the property of ……………..company name ………………….

Вам также может понравиться