Вы находитесь на странице: 1из 4

technical Paper

Effect of support fluids on


pile performance – a field
trial in east London
Carlos Lam (University of Oxford), Viv Troughton (formerly
Balfour Beatty Ground Engineering), Stephan Jefferis (University
of Oxford and Environmental Geotechnics), and
Tony Suckling (Balfour Beatty Ground Engineering)

S
ynthetic polymer support fluids in environmentally sensitive areas and construction, some of the to specifically answer these
have been used in the UK for and on urban sites with only limited frequently voiced concerns include: questions.
about a decade, although space for plant (Ground n the difference in load-settlement To shed light on some of these
naturally derived polymers such as Engineering, May 2001 and characteristics between piles issues, in particular load-settlement
xanthan gum have been used for December 2004). constructed under polymers and characteristics, effect of pile bore
much longer. Very little research At BBGE, polymers have become bentonites; open time, and hardened concrete
has been carried out to assess the the preferred choice of excavation n whether a polymer-supported quality, this technical note presents
effects of polymer fluids and espe- support fluid for their many benefits bore can be open for an extended the initial results of a full-scale pile
cially synthetic polymers on pile such as a smaller site footprint, ease period (eg >12 hours) without test programme carried out at a site
performance. of mixing and their ability to compromising the performance of in east London using both polymer
A field trial comprising the stabilise a wide range of soils the completed pile; and bentonite fluids.
construction and testing of three (Lennon et al 2006). n the effect of polymer fluids on the
piles has been carried out at However, despite more than a quality of hardened concrete; Ground conditions
Stratford in east London. The decade of use, many engineers are n the amount of sediment collecting The test site is located at 0.5km
objectives of the trial were to still unsure about the performance at base of pile; south-east of the Stratford
compare the effects of polymer and of these fluids and their impact on n rebar-concrete bond strength; International station box in east
bentonite support fluids on pile foundation performance, mainly n monitoring and control measures London. It sits on the surrounding
performance, to assess the effect of due to the very different properties for specific polymers. land that was raised by about 7m
extended bore open time for the of polymers as compared with Although early UK experience using the excavated materials from
polymer piles, and to quantify the bentonite and the lack of with synthetic polymers found a the CTRL tunnel and the box
effect of support fluid contamination documented case histories. number of beneficial effects on the construction (Dyson and Blight,
on the hardened properties of Importantly there is a lack of construction and the performance of 2007).
concrete. industry guidance such as foundation elements (European Exploratory boreholes drilled at
It was found that the two polymer specifications. When considering the Foundations, Summer 2003), so far the test location confirmed a thick
piles significantly outperformed the use of polymer fluids for pile design little research has been carried out layer of made ground/land raise
bentonite pile under the maximum
proof load, and that no adverse
Reaction frame Position of Ø1.26m
effect was caused by the extended temporary casing
SPT N (uncorrected)
soil-fluid exposure time in the Ø1.2m test pile Ø1.05m reaction pile
(blows/300mm)
(out of plane)
polymer-supported bore. The two +5.5 mOD 0 25 50 75 100
support fluids were also found to 0
Depth (m, below ground)

Made Ground
have similar effects on concrete +2.5 mOD

quality. Perched water table


-1 mOD in shallow aquifer 5

Synthetic polymer fluids Woolwich & Reading


Formations
Synthetic polymer support fluids (Lambeth Group) 10
can be used as replacements for -8 mOD
bentonite slurry for the construction Upnor Formation 15 Idealised
of bored piles and diaphragm walls. (Lambeth Group) profile
The technology was developed -14 mOD
in the US in the early 1990s Thanet Sand 20
and introduced to the UK by -18 mOD
Stent Foundations (now Balfour
25
Beatty Ground Engineering – -21.5 mOD

BBGE) for a piling project in central


-25 mOD
Glasgow in 1999. 30
Since then synthetic polymers -28 mOD
Approx. groundwater table in deep
aquifer after drawdown at Stratford box
have been used successfully in other
Set of four ‘sister bar’ strain gauges
parts of the country, and they are Retrievable extensometers
gradually gaining popularity as an
alternative to bentonite, especially Figure 1: schematic arrangement of the test and reaction piles and ground conditions

28 ground engineering October 2010


Figure 2: Twin-flight auger immediately after extraction from a
polymer-supported bore

from +5.5 to -1mOD, which was which is several metres above the
underlain by the Lambeth Group current ground water table. To
from -1 to -14mOD and then the assess the effects of different support
Thanet Sand to at least -28mOD. fluids on concrete, the first pile was
The Lambeth group can be dug under a conventional bentonite
subdivided into the Woolwich and slurry to serve as a benchmark,
Reading Formations (sandy clay while the other two were dug under
with shell fragments) between -1 a synthetic polymer fluid with the
and -8mOD and the Upnor two bores kept open for different
Formation (slightly gravelly sandy times. Eight continuous-flight auger
clay) between -8 and -14mOD. piles of 1.05m diameter were also
The SPT N values for the installed to -18mOD to provide the
Woolwich and Reading Formations reaction for the load tests.
can be approximated to increase Figure 1 (left) shows the
linearly from 15 blows/300mm at schematic arrangement of the test
the top to 44 blows/300mm at the and reaction piles together with the
bottom. The blow counts increase ground conditions as described
further in the underlying Upnor earlier. After a minimum of 25 days
Formation from 44 blows/300mm from construction, the bored piles
at the top to 52 blows/300mm at the were tested by the maintained load Figure 3: Vented digging bucket immediately after extraction from
bottom of the layer. For the Thanet method according to the ICE a polymer-supported bore
Sand, the N values consistently Specification for Piling and
exceed 100 blows/300mm. Embedded Retaining Wall key information for the three test to near the base of the Lambeth
The ground water conditions (Institution of Civil Engineers, piles. Group before flooding the pile bore
have been modified by the 2007). To allow a proper interpretation with support fluid. The actual depth
construction of the Stratford box. As mentioned above, in addition of the test results, construction at which the fluid was introduced
As a result of the permanent to the assessment of pile details that are of particular depended on the stability of the
groundwater control that was put in performance, an investigation of the importance but dependent on the bores, but for the three test piles the
place to reduce the uplift force on effects of the different support fluids site conditions or the contractor’s depth was about 17m (-11.5mOD)
the structure (Whitaker, 2004), the on concrete quality was also experience are described below. and thus 2.5m above the Thanet
water table in the lower aquifer was included in the test programme. These include the excavation and Sand.
lowered to between -20 and During casting of the bentonite pile base-cleaning procedures, properties Excavation under the support
-27mOD in the vicinity of the box; (B1) and the second polymer pile of the support fluids, and the fluid was with a twin-flight auger or
standing at approximately -25mOD (P2), 100mm cubes were prepared concreting records. a vented digging bucket; both tools
at the pile test location. from concrete from the chutes of the allowed drainage of the fluid back to
delivery trucks and from the top of Excavation and base- the hole during tool extraction, thus
Test programme and the pile which was the interface cleaning procedures preventing suction being developed
arrangement between the fresh concrete and the Excavation for the three test piles in the fluid column. Figures 2 and 3
Three bored piles with nominal support fluid. The cubes were tested generally followed BBGE standard show the auger and the digging
diameters of 1.2m and embedded for compressive strength at seven, 10 procedures for that area. The initial bucket immediately after extraction
lengths of 27m were installed at the and 28 days and for elastic modulus steps included inserting a steel from a polymer-supported bore.
test location. The piles were spaced at 28 days according to BS EN casing through the made ground After excavation down to the final
at 6m centres and were founded in 12390-3:2002 and BS 1881- down to the top of the underlying toe depth, cleanliness of the base
the Thanet Sand at -21.5mOD, 121:1983. Table 1 summarises the clay layer, then excavating dry down was checked by lowering a

ground engineering October 2010 29


technical note
100mm x 100mm x 20mm metal DC-3) was discharged into the pile
plate on a tape measure to the bores through a tremie pipe, with its CL Equivalent pile radii (m)
bottom of the pile bore. The impact tip kept below the rising concrete
0 0.55 0.575 0.60 0.625 0.65
as felt by the site engineer as the level at all times. Initially, the tremie
plate hit the pile base was given a pipe was rested on the base while 0

Depth (m, b.g.l.)


grade from 1 to 5 using the grading filled with concrete and then slightly Made Ground
Temporary
scale reported by Berry (2009). lifted to provide a surge effect. This casing position
All the three test piles received grade allowed a high initial discharge rate
3, meaning detection of a distinct of about 1.2m3/min to be achieved
base with slight embedding of the so that any sediment accumulated at P1
weight into the soil. This confirmed the base could be flushed aside. A
a similar base quality for the three lower discharge rate of around P2 Theoretical dimension
test piles. 0.5m3/min was used thereafter. 5
The successive rises in concrete
Fluid properties level were measured after every
The properties of the support truck load of concrete was Woolwich & Reading
B1 Formations
fluid can heavily influence the discharged. This information has (Lambeth Group)
conditions of the excavation and been converted to the equivalent
the performance of the completed radius along the pile length as
foundation element. Effects range shown in Figure 4. 10
from poor excavation stability It is interesting to see from the
to reduced integrity of the concrete. figure that the profiles of the three
Table 1 gives details of the support piles are actually quite similar,
fluid materials, dosage, fluid-soil suggesting comparable conditions
exposure time, and the control of the pile bores before concreting.
test results for both fresh and used This finding is consistent with the Upnor Formation
(Lambeth Group)
fluids. results of Ata and O’Neill (1998): 15
It can be seen that the fluid the sidewall profiles of their
properties (Marsh funnel viscosity, polymer-supported shafts remained
density, pH, and sand content) of almost the same for up to 19 hours.
the polymer fluid were very different However, the actual values of the
to those of the bentonite. However, inferred radii should be considered
for the two polymer piles there were with caution as there are many
only slight differences in the fluid factors that can affect their accuracy
20 Thanet Sand
properties and these were due to the including slight variations in
different times that the fluids had concrete volume between deliveries,
been in the pile bores. As the sand material wastage, etc.
content of the used bentonite fluid
exceeded the specified limit of 4% Results and discussions
(Federation of Piling Specialists, Hardened concrete properties
2006), it was exchanged for a fresh Figure 5 gives the test results of the Figure 4: Equivalent pile radius from concreting records
bentonite fluid before concreting to concrete cubes prepared during
prevent accumulation of soft construction of bentonite pile B1 was clearly affected when compared the elastic modulus. These effects
sediments at the pile base. and polymer pile P2, showing their with the strength of samples taken are likely to be due the intermixing
strength development curves and from the chute of the delivery truck. of fresh concrete and support fluid
Concreting the elastic modulus values at 28 The overall strength reduction at their interface during placing, but
Following standard bored piling days. As can be seen, the strength at was 26% and 29% for bentonites seem to have little correlation with
practice, self-compacting concrete the top of the concrete column, ie and polymers respectively. A similar the support fluid type.
(class C28/35 20mm CIIB-V S4 the concrete-support fluid interface, degree of reduction is also seen for This finding corresponds with the
conclusion of Jefferis and
Mavroulidou (2003) that polymer
Table 1: Support fluid properties fluids have little effect on fresh
Fluid details and exposure time Fluid test resultsa concrete mixes, except to increase
their workability and therefore
Marsh reduce their strength in proportion
Total fluid-soil Hours in hole Sand
Pile Name and funnel Density to the volume of liquid added.
Dosage exposure at time of content pH (-)
number supplier viscosity (g/cm3) It is important to note that the
time (h) fluid tests (h) (%)
(s) comparison shown in Figure 5 only
Berkbent applies to the concrete which has
1.02/ 10.5/ been subject to exposure to support
163
B1 40kg/m3 7.5 3 34/40/41 1.10/ 0/6.8/10 10.3/ fluid during casting, and certainly
(Steetley
1.15 10.3 does not represent the concrete
Bentonite)
conditions of the whole pile. Indeed,
1.0kg/m3 1.00/ 11.2/ to minimise the amount of
0/0.2/0.2
P1 for CDP 7.5 5 70/56/56 1.02/ 11.2/ contaminated concrete in the test
(1.3)b
SlurryPro 0.08kg/ 1.03 11.2 piles, during casting the concrete
CDP m3 for LA-1 near the top of the pile was removed
(KB Intl) and 10L 1.00/ 11.0/ by overflowing fresh concrete via
0/0.1/0.1
P2 of 1% MPA 26 23 69/50/50 1.02/ 11.0/ the tremie pipe – a standard practice
(1.4)b
solution 1.02 11.0 in the UK.
However, due to the complex
a
Test results are given in this format: fresh fluid from tank/used fluid from middle of bore/used fluid from bottom of bore flow behaviour of fresh concrete in
b
Results in brackets are sand contents at bottom of pile bores before addition of additive MPA pile bores, some contaminated
concrete is still expected to be

30 ground engineering October 2010


60
Mean compressive cube strength, fcm (MPa)

Chute of delivery truck Applied load (MN)


Elastic modulus
Bentonite pile Ec (GPa) 0 2 4 6 8 10 12 14 16 18 20
Polymer pile 0

Pile head settlement (mm)


29.25
50 Top of concrete column
27.75
Bentonite pile 10
Polymer pile

100% DVL + 100% SWL (18.1 MN)


21.75
40 20
21.25

30
30

100% DVL (9.1MN)


Trend line 40

B1 (7.5h)
20 50
0 7 14 21 28 35 P1 (7.5h)
P2 (26h)
Age at test, t (days) 60
Figure 5: Test results of the concrete cubes prepared during
construction of bentonite pile B1 and polymer pile P2 Figure 6: Load-settlement curves for the test piles

present in places away from the than pile P1. This means that the on the three test piles showed can offer over the conventional
tremie pipe, for example at the pile- polymer fluid was able to maintain similar load-settlement response up bentonite slurry. More importantly,
soil interface. the condition of the pile bore for to a moderate load level (100% it is hoped that the results will help
much longer than might have been DVL), but showed much smaller speed up the development of a new
Load-settlement response anticipated, possibly for the same settlements for the two polymer guidance concerning polymer-
Figure 6 shows the load-settlement reasons that the two polymer piles piles under proof load supported excavation work, so that
curves for the test piles. The outperform their bentonite (100% DVL + 100 % SWL). engineers and clients can take full
settlements at each loading stage counterpart. Comparable performance was seen advantage of the synthetic polymer
have been projected to infinite time for the two polymer piles with system for the benefit of the society.
to remove the time-dependent Conclusions different soil-fluid exposure times
effects of creep and consolidation. It The concrete cube test results suggesting that there was little Acknowledgements
can be seen that at 9.1MN (100% of indicate that both bentonite and the change in the pile bore condition The authors would like to thank
the Design Verification Load, DVL) polymer fluids, if allowed to mix over the extended period. The Dave Ritchie, Stephen Chambers,
there was very little difference in the with concrete, have a similar overall results show that the benefits of Blair Woodward and other BBGE
performance of the three piles. degree of impact on compressive polymer fluids are not limited to the staff for carrying out the field trial.
However, under the proof load strength and elastic modulus. The commonly quoted environmental Thanks are also due to Chris Barker
of 18.1MN (100% DVL + 100% of effects are thought to be due to the and operational factors, but also of Arup Geotechnics for
the Specified Working Load, SWL) increased amount of liquid in the include better load-settlement commenting on the first draft. The
the two polymer piles showed mix rather than adverse chemical behaviour and longer excavation authors also would like to thank Dr
much stiffer response than the reactions. Fuller laboratory-based open time without compromising Chris Martin, Dr Peter Martin and
bentonite pile, with the head research on this would be useful as the performance of the foundation. Gif Goodhue for their participation
settlements of piles B1, P1 and P2 accurate assessment of the degree of It is hoped that the findings in the ongoing polymer research
being 51mm, 29mm, and 24mm intermixing was not possible in a presented in this technical note will project at the University of
respectively. This finding confirms field trial. make engineers more aware of the Oxford; EPSRC grant
that polymer fluids can give better Maintained load tests carried out many benefits that polymer fluid reference no. EP/C537815/1.
overall pile performance especially
at higher loads. References
One of the contributing factors
for this improvement is possibly the Ata, A A and O’Neill, MW (1998): “Side- Dyson, S and Blight, I (2007): Embedded Retaining Walls, 2nd
inhibition of clay swelling in the wall stability and side-shear resistance “Channel Tunnel Rail Link section 2: Edition, Thomas Telford Publishing,
Lambeth Group, as the polymer is in bored piles constructed with high- Stratford”, Proceedings of the London.
likely to maintain the suction molecular-weight polymer slurry”, Institution of Civil Engineers, Civil
Proceedings of the 3rd International Engineering, 160 (CE6), pp29-32. Jefferis, S A and Mavroulidou, M
pressure developed in the clay for a Geotechnical Seminar on Deep (2003): “The effects of the KBT vinyl
longer period than bentonite. The Foundations on Bored and Auger Piles, European Foundations (Summer polymer excavation support materials
absence of a filter cake formed on Balkema, Rotterdam, pp 111-117. 2003): “Piles unlock polymer on fresh concrete mixes”, a report to
the surface of the Thanet Sand may potential”, No 19, Emap Construct, Stent Foundations and Bachy
be another contributory factor for Berry, A G (2009): “Method for London, pp8-9. Soletanche, University of Surrey.
the better response. cleaning and checking the base of
diaphragm wall panels”, Ground Federation of Piling Specialists Lennon, D J, Ritchie, D, Parry, G O,
Interpretation of the Engineering, 42 (11), November, (2006): Bentonite support fluid in civil and Suckling, T P (2006): “Piling
instrumentation results and Emap Inform, London, pp29-31. engineering, 2nd Edition. UK, January projects constructed with vinyl
numerical load transfer analyses are 2006. polymer support fluid in Glasgow,
being carried out to confirm these BS 1881-121 (1983): “Testing Scotland”, Proceedings of the 10th
concrete – part 121: Method for Ground Engineering (May 2001): DFI/EFFC International Conference on
theses – the results will be reported “Way out of a tight spot”, 34 (5),
determination of static modulus of Piling and Deep Foundations,
in a separate publication. elasticity in compression”, British Emap Construct, London, pp16-17. Amsterdam, The Netherlands, pp499-
With regard to the difference Standards Institution, London. 506.
between the two polymer piles, it is Ground Engineering (December
surprising but reassuring to see that BS EN 12390-3 (2002): “Testing 2004): “Fisherman’s friend”, 37 (12), Whitaker, D (2004): “Groundwater
hardened concrete – part 3: Emap Construct, London, pp17. control for the Stratford CTRL station
polymer pile P2, which had the
longer soil-fluid exposure time (26 Compressive strength of test Institution of Civil Engineers (2007): box”, Proceedings of the Institution of
specimens”, British Standards ICE Specification for Piling and Civil Engineers, Geotechnical
hours as opposed to 7.5 hours), Institution, London. Engineering, 157 (GE4), pp183-191.
showed a slightly better response

ground engineering October 2010 31

Вам также может понравиться