Академический Документы
Профессиональный Документы
Культура Документы
S
ynthetic polymer support fluids in environmentally sensitive areas and construction, some of the to specifically answer these
have been used in the UK for and on urban sites with only limited frequently voiced concerns include: questions.
about a decade, although space for plant (Ground n the difference in load-settlement To shed light on some of these
naturally derived polymers such as Engineering, May 2001 and characteristics between piles issues, in particular load-settlement
xanthan gum have been used for December 2004). constructed under polymers and characteristics, effect of pile bore
much longer. Very little research At BBGE, polymers have become bentonites; open time, and hardened concrete
has been carried out to assess the the preferred choice of excavation n whether a polymer-supported quality, this technical note presents
effects of polymer fluids and espe- support fluid for their many benefits bore can be open for an extended the initial results of a full-scale pile
cially synthetic polymers on pile such as a smaller site footprint, ease period (eg >12 hours) without test programme carried out at a site
performance. of mixing and their ability to compromising the performance of in east London using both polymer
A field trial comprising the stabilise a wide range of soils the completed pile; and bentonite fluids.
construction and testing of three (Lennon et al 2006). n the effect of polymer fluids on the
piles has been carried out at However, despite more than a quality of hardened concrete; Ground conditions
Stratford in east London. The decade of use, many engineers are n the amount of sediment collecting The test site is located at 0.5km
objectives of the trial were to still unsure about the performance at base of pile; south-east of the Stratford
compare the effects of polymer and of these fluids and their impact on n rebar-concrete bond strength; International station box in east
bentonite support fluids on pile foundation performance, mainly n monitoring and control measures London. It sits on the surrounding
performance, to assess the effect of due to the very different properties for specific polymers. land that was raised by about 7m
extended bore open time for the of polymers as compared with Although early UK experience using the excavated materials from
polymer piles, and to quantify the bentonite and the lack of with synthetic polymers found a the CTRL tunnel and the box
effect of support fluid contamination documented case histories. number of beneficial effects on the construction (Dyson and Blight,
on the hardened properties of Importantly there is a lack of construction and the performance of 2007).
concrete. industry guidance such as foundation elements (European Exploratory boreholes drilled at
It was found that the two polymer specifications. When considering the Foundations, Summer 2003), so far the test location confirmed a thick
piles significantly outperformed the use of polymer fluids for pile design little research has been carried out layer of made ground/land raise
bentonite pile under the maximum
proof load, and that no adverse
Reaction frame Position of Ø1.26m
effect was caused by the extended temporary casing
SPT N (uncorrected)
soil-fluid exposure time in the Ø1.2m test pile Ø1.05m reaction pile
(blows/300mm)
(out of plane)
polymer-supported bore. The two +5.5 mOD 0 25 50 75 100
support fluids were also found to 0
Depth (m, below ground)
Made Ground
have similar effects on concrete +2.5 mOD
from +5.5 to -1mOD, which was which is several metres above the
underlain by the Lambeth Group current ground water table. To
from -1 to -14mOD and then the assess the effects of different support
Thanet Sand to at least -28mOD. fluids on concrete, the first pile was
The Lambeth group can be dug under a conventional bentonite
subdivided into the Woolwich and slurry to serve as a benchmark,
Reading Formations (sandy clay while the other two were dug under
with shell fragments) between -1 a synthetic polymer fluid with the
and -8mOD and the Upnor two bores kept open for different
Formation (slightly gravelly sandy times. Eight continuous-flight auger
clay) between -8 and -14mOD. piles of 1.05m diameter were also
The SPT N values for the installed to -18mOD to provide the
Woolwich and Reading Formations reaction for the load tests.
can be approximated to increase Figure 1 (left) shows the
linearly from 15 blows/300mm at schematic arrangement of the test
the top to 44 blows/300mm at the and reaction piles together with the
bottom. The blow counts increase ground conditions as described
further in the underlying Upnor earlier. After a minimum of 25 days
Formation from 44 blows/300mm from construction, the bored piles
at the top to 52 blows/300mm at the were tested by the maintained load Figure 3: Vented digging bucket immediately after extraction from
bottom of the layer. For the Thanet method according to the ICE a polymer-supported bore
Sand, the N values consistently Specification for Piling and
exceed 100 blows/300mm. Embedded Retaining Wall key information for the three test to near the base of the Lambeth
The ground water conditions (Institution of Civil Engineers, piles. Group before flooding the pile bore
have been modified by the 2007). To allow a proper interpretation with support fluid. The actual depth
construction of the Stratford box. As mentioned above, in addition of the test results, construction at which the fluid was introduced
As a result of the permanent to the assessment of pile details that are of particular depended on the stability of the
groundwater control that was put in performance, an investigation of the importance but dependent on the bores, but for the three test piles the
place to reduce the uplift force on effects of the different support fluids site conditions or the contractor’s depth was about 17m (-11.5mOD)
the structure (Whitaker, 2004), the on concrete quality was also experience are described below. and thus 2.5m above the Thanet
water table in the lower aquifer was included in the test programme. These include the excavation and Sand.
lowered to between -20 and During casting of the bentonite pile base-cleaning procedures, properties Excavation under the support
-27mOD in the vicinity of the box; (B1) and the second polymer pile of the support fluids, and the fluid was with a twin-flight auger or
standing at approximately -25mOD (P2), 100mm cubes were prepared concreting records. a vented digging bucket; both tools
at the pile test location. from concrete from the chutes of the allowed drainage of the fluid back to
delivery trucks and from the top of Excavation and base- the hole during tool extraction, thus
Test programme and the pile which was the interface cleaning procedures preventing suction being developed
arrangement between the fresh concrete and the Excavation for the three test piles in the fluid column. Figures 2 and 3
Three bored piles with nominal support fluid. The cubes were tested generally followed BBGE standard show the auger and the digging
diameters of 1.2m and embedded for compressive strength at seven, 10 procedures for that area. The initial bucket immediately after extraction
lengths of 27m were installed at the and 28 days and for elastic modulus steps included inserting a steel from a polymer-supported bore.
test location. The piles were spaced at 28 days according to BS EN casing through the made ground After excavation down to the final
at 6m centres and were founded in 12390-3:2002 and BS 1881- down to the top of the underlying toe depth, cleanliness of the base
the Thanet Sand at -21.5mOD, 121:1983. Table 1 summarises the clay layer, then excavating dry down was checked by lowering a
30
30
B1 (7.5h)
20 50
0 7 14 21 28 35 P1 (7.5h)
P2 (26h)
Age at test, t (days) 60
Figure 5: Test results of the concrete cubes prepared during
construction of bentonite pile B1 and polymer pile P2 Figure 6: Load-settlement curves for the test piles
present in places away from the than pile P1. This means that the on the three test piles showed can offer over the conventional
tremie pipe, for example at the pile- polymer fluid was able to maintain similar load-settlement response up bentonite slurry. More importantly,
soil interface. the condition of the pile bore for to a moderate load level (100% it is hoped that the results will help
much longer than might have been DVL), but showed much smaller speed up the development of a new
Load-settlement response anticipated, possibly for the same settlements for the two polymer guidance concerning polymer-
Figure 6 shows the load-settlement reasons that the two polymer piles piles under proof load supported excavation work, so that
curves for the test piles. The outperform their bentonite (100% DVL + 100 % SWL). engineers and clients can take full
settlements at each loading stage counterpart. Comparable performance was seen advantage of the synthetic polymer
have been projected to infinite time for the two polymer piles with system for the benefit of the society.
to remove the time-dependent Conclusions different soil-fluid exposure times
effects of creep and consolidation. It The concrete cube test results suggesting that there was little Acknowledgements
can be seen that at 9.1MN (100% of indicate that both bentonite and the change in the pile bore condition The authors would like to thank
the Design Verification Load, DVL) polymer fluids, if allowed to mix over the extended period. The Dave Ritchie, Stephen Chambers,
there was very little difference in the with concrete, have a similar overall results show that the benefits of Blair Woodward and other BBGE
performance of the three piles. degree of impact on compressive polymer fluids are not limited to the staff for carrying out the field trial.
However, under the proof load strength and elastic modulus. The commonly quoted environmental Thanks are also due to Chris Barker
of 18.1MN (100% DVL + 100% of effects are thought to be due to the and operational factors, but also of Arup Geotechnics for
the Specified Working Load, SWL) increased amount of liquid in the include better load-settlement commenting on the first draft. The
the two polymer piles showed mix rather than adverse chemical behaviour and longer excavation authors also would like to thank Dr
much stiffer response than the reactions. Fuller laboratory-based open time without compromising Chris Martin, Dr Peter Martin and
bentonite pile, with the head research on this would be useful as the performance of the foundation. Gif Goodhue for their participation
settlements of piles B1, P1 and P2 accurate assessment of the degree of It is hoped that the findings in the ongoing polymer research
being 51mm, 29mm, and 24mm intermixing was not possible in a presented in this technical note will project at the University of
respectively. This finding confirms field trial. make engineers more aware of the Oxford; EPSRC grant
that polymer fluids can give better Maintained load tests carried out many benefits that polymer fluid reference no. EP/C537815/1.
overall pile performance especially
at higher loads. References
One of the contributing factors
for this improvement is possibly the Ata, A A and O’Neill, MW (1998): “Side- Dyson, S and Blight, I (2007): Embedded Retaining Walls, 2nd
inhibition of clay swelling in the wall stability and side-shear resistance “Channel Tunnel Rail Link section 2: Edition, Thomas Telford Publishing,
Lambeth Group, as the polymer is in bored piles constructed with high- Stratford”, Proceedings of the London.
likely to maintain the suction molecular-weight polymer slurry”, Institution of Civil Engineers, Civil
Proceedings of the 3rd International Engineering, 160 (CE6), pp29-32. Jefferis, S A and Mavroulidou, M
pressure developed in the clay for a Geotechnical Seminar on Deep (2003): “The effects of the KBT vinyl
longer period than bentonite. The Foundations on Bored and Auger Piles, European Foundations (Summer polymer excavation support materials
absence of a filter cake formed on Balkema, Rotterdam, pp 111-117. 2003): “Piles unlock polymer on fresh concrete mixes”, a report to
the surface of the Thanet Sand may potential”, No 19, Emap Construct, Stent Foundations and Bachy
be another contributory factor for Berry, A G (2009): “Method for London, pp8-9. Soletanche, University of Surrey.
the better response. cleaning and checking the base of
diaphragm wall panels”, Ground Federation of Piling Specialists Lennon, D J, Ritchie, D, Parry, G O,
Interpretation of the Engineering, 42 (11), November, (2006): Bentonite support fluid in civil and Suckling, T P (2006): “Piling
instrumentation results and Emap Inform, London, pp29-31. engineering, 2nd Edition. UK, January projects constructed with vinyl
numerical load transfer analyses are 2006. polymer support fluid in Glasgow,
being carried out to confirm these BS 1881-121 (1983): “Testing Scotland”, Proceedings of the 10th
concrete – part 121: Method for Ground Engineering (May 2001): DFI/EFFC International Conference on
theses – the results will be reported “Way out of a tight spot”, 34 (5),
determination of static modulus of Piling and Deep Foundations,
in a separate publication. elasticity in compression”, British Emap Construct, London, pp16-17. Amsterdam, The Netherlands, pp499-
With regard to the difference Standards Institution, London. 506.
between the two polymer piles, it is Ground Engineering (December
surprising but reassuring to see that BS EN 12390-3 (2002): “Testing 2004): “Fisherman’s friend”, 37 (12), Whitaker, D (2004): “Groundwater
hardened concrete – part 3: Emap Construct, London, pp17. control for the Stratford CTRL station
polymer pile P2, which had the
longer soil-fluid exposure time (26 Compressive strength of test Institution of Civil Engineers (2007): box”, Proceedings of the Institution of
specimens”, British Standards ICE Specification for Piling and Civil Engineers, Geotechnical
hours as opposed to 7.5 hours), Institution, London. Engineering, 157 (GE4), pp183-191.
showed a slightly better response