Академический Документы
Профессиональный Документы
Культура Документы
of Workers
June 12-16 40 3854 96.35 3
June 17-23 60 5729 95.48 3
June 24-30 36.5 3491 95.64 2
July 1-7 68.5 6647 97.04 3
July 8-14 62 6522 105.19 3
July 15-21 64 6540 102.19 2
July 22-28 76 7551 99.36 4
July 29-Aug 4 40 5200 130.00 4
Aug 5-11 65 10047 154.57
Aug 14-18 58 5880 101.38 4
Aug-19 7 720 102.86 5
Aug 21-25 78 8428 108.05 5
Aug 28-31 48.5 4950 102.06 6
Sept 1-8 83 8422 101.47 4
Sept 14-15 15 2156 143.73 3
Sept 16-22 73 9026 123.64 5
RECEIVING REPORT
Date No. ACTIVITY Amount
June 6 2017 9906 palanas 7500
9907 palanas 7500
June 8 2017 9909 palanas 7500
SEPT 3-9 JONATHAN BACAL pump house (welding of fence, trusses & roof inst.) 8000
pump house flooring 1562.5
CHB FABRICATION 500
SEPT 10-16 JONATHAN BACAL CHB FABRICATION (ADD'L 2 SETS) 1000
TOTAL 34072.5