Академический Документы
Профессиональный Документы
Культура Документы
FORM
STATEMENT OF WORK
Version:00 Number: SC-FRM-PK-EEH-012 Revised: 17 Oct 2015
General Information
* Services/Job Title: REPAIR OF TK-864
* Approver(s): Fayaz Ahmed Abbas/Agah Amjad/Tahir Khan
Stakeholders
Title Name Department Telephone E-mail
Maintenance MUHAMMAD ASKARI 0301-8202272 Muhammad.askari@exterran.com
MAINTENANCE
Manager NISAR AHMED 0300-2033235 Nisar.Ahmed@Exterran.com
AGHA M AMJAD PLANT 0300-2033240 Agah.amjad@exterran.com
Plant Manager
FAYYAZ ABBASI OPERATION 0300-2033237 Fayyaz.abbasi@exterran.com
Supply Chain
QHSSE Manager SYED RAHEEL ZAFAR QHSSE 03052226020 Syed.Zafar@exterran.com
Periodic Inspection of TK-864 was carried out through third party certified inspector. We need to get the tank repaired as
per API standards to ensure its service for the intended period.
NGL storage capacity is reduced due to Tank’s inspection / repair requirements. By bringing it back in service actual
storage capacity shall be achieved.
COPYRIGHT © EXTERRAN HOLDINGS, INC. Paper copies of this document are uncontrolled. This copy is valid only
at the time of printing. The controlled version of this document is stored on the Exterran intranet web site.
1. CIVIL WORK
To chip out damaged concrete at the outer circumference of tank bottom and repair accordingly as per
Exterran Recommendations to avoid ingress of water under the tank bottom.
2. WELDING
To remove old angle iron rafters (8 Nos. Size 2”x2”x 8 Feet) and weld new rafters on tank roof as shown in pics.
Fabrication of new sump 8 mm thickness shell and bottom. Install newly fabricated sump in to existing sump as
a double containment.
Provision of sump draw off valve (2” x 150 # flanged ball valve) outside tank.
3. APPLICATION OF BELZONA / EPOXY PAINT
Remove existing epoxy paint from the all over the roof top, prepare surface and apply layer of “BELZONA” on rooftop.
Epoxy application in and out of sump
Epoxy paint on tank inside and outside tank
NOTE: All material required to complete the job like; cement, sand, bitumen, angle iron, belzona, tools, etc. shall
be arranged by contractor.
Contractor may visit the site prior to submit the quotation to familiarize with the scope.
COPYRIGHT © EXTERRAN HOLDINGS, INC. Paper copies of this document are uncontrolled. This copy is valid only
at the time of printing. The controlled version of this document is stored on the Exterran intranet web site.
* 1.4 Out-of-Scope:
1. Work permit shall be provided by Exterran, but contractor shall be required to follow the instructions written in the
Permit to Work.
2. Utility water shall be provided by Exterran.
3. Appropriate work space shall be provided to the contractor.
This section defines the minimum requirements for accepting services and/or deliverables. It also describes the criteria
used for acceptance of services.
The Services Contract will be considered a success by its stakeholders if all the steps under para 1.3 are completed safely.
This section defines the standards (internal or external) applicable to the requested services. All deliveries and work
done should comply with the standards defined in this section of the document.
1. Contractor will be responsible to ensure availabilty of all kinds of Personal Protective Equipment required for
job excution in a sufficient quantity. (Specially Cotton coverall, safety shoes, safety helmet, safety goggles)
2. Contractor shall follow the instructions laid down under JHA Column of the work permit
3. Contractor shall sharedetails of their personnel (Names, CNIC numbers) for security clearance.
4. Contractor shallmaintain the area clean and tidy and leave the worksite clean, debris free after completion of the job
5. All tools and and equipment used for the scope including welding machine and grinders shall
have acceptable fitness status. Moreover, acetylene cylinders used for welding works must have
flash back arrestor.
COPYRIGHT © EXTERRAN HOLDINGS, INC. Paper copies of this document are uncontrolled. This copy is valid only
at the time of printing. The controlled version of this document is stored on the Exterran intranet web site.
7.0 Sign-off
Name Signature Date (DD/MM/YYYY)
Supply Chain
COPYRIGHT © EXTERRAN HOLDINGS, INC. Paper copies of this document are uncontrolled. This copy is valid only
at the time of printing. The controlled version of this document is stored on the Exterran intranet web site.
COPYRIGHT © EXTERRAN HOLDINGS, INC. Paper copies of this document are uncontrolled. This copy is valid only
at the time of printing. The controlled version of this document is stored on the Exterran intranet web site.