Time
A Site activities being inspected Date
(24 hrs)
Waste/environment
Waste Material type
(if materials
E1 are being taken Carriers details
off site obtain Name of tip
carriers name
E2 and destination Check waste transfer note is in place O
E3 of load) Register carrier’s licence on file O
E4 Environmental Copy of tip/transfer station licence available O
E5 issues Right waste being put in right skip and labelled skips S
E6 Pollution Site registered as a hazardous waste producer O
prevention Consignments notes in place for hazardous waste uniquely numbered
E7 O
guidance (rule of 3- producer-carrier-receiver)
In relation to the selected activity are the necessary permissions/
E8 S
licenses/consents in place (e.g. discharge from interceptors)?
Oil/diesel storage are in bunds and no evidence of significant spillages,
E9 S
spill kits, emergency response
E10 Exemption for recycled materials from the EA (e.g. 19A, WRAP) O
E11 Wildlife (tree or ground nesting birds, bats, badger, licences, etc.) O&S
* Not checked
** Not applicable
© Construction Industry Training Board Extracted from Construction site safety (GE 700) publication
GA18 Weekly project SHE inspection continued
W3 Housekeeping (site tidy and to an acceptable standard – slips, trips and falls) S
Dust/mud suppression (is dust or mud a problem and is it being adequately controlled,
W4 S
cutting works using dust suppression)
W5 Site traffic management (signs, parking, fences, traffic plan) S&O
W8 Welfare is clean and tidy and cooking facilities are clean, adequate for numbers S
P People – Workforce
P3 Evidence of training (for example, CPCS, LANTRA, NPL, IPAF, NASWRA, etc.) O
Lifting equipment (select one, if being used note type and serial numbers)
Details of equipment
Serial numbers
PE7 Are thorough (e.g. 12 and six monthly) examination certifications on file and in date? O
PE8 General condition of lifting equipment (check for damage, incorrect use, etc.) S
PE9 Has it been PAT tested in last three months (check for sticker or tag)? S
PE10 General condition (cables, transformers, spider boxes, hand tools, etc.) S
PE11 Are daily plant operator sheets being completed and, where defects are noted, repairs done? S&O
M Materials
* Not checked
** Not applicable
© Construction Industry Training Board Extracted from Construction site safety (GE 700) publication
GA18 Weekly project SHE inspection continued
V4 VDU users are free from flicker or glare, ergonomic principles been applied, noise, dust, etc. S
WE Welfare
WE1 Are there sufficient facilities for the people in the area? S
Has appropriate information been posted (e.g. first aiders, route to hospital, emergency
WE6 S
contact details, and site rules, posters, policies, etc.)?
FI Fire
FI1 Fire risk assessment and fire-fighting equipment suitable, sufficient and tested S
FI2 Fire escape (fire escape routes, disabled person(s) obstructions, lighting, etc.) S&O
FI4 Fire prevention (permit systems, debris removal, electrical and test, smoking, etc.) S
* Not checked
** Not applicable
© Construction Industry Training Board Extracted from Construction site safety (GE 700) publication