ID Task Name Duration Start Finish Predecessors

Resource Names

May 10, '15 May 24, '15 Jun 7, '15 Jun 21, '15 Jul 5, '15 Jul 19, '15
S T M F T S W S T M F T S W S T M F T
1 Architectural Print 3 days? Thu 5/14/15 Mon 5/18/15 Mario Mario
2 Real estate purchase 3 days Tue 5/19/15 Thu 5/21/15 1 R. Pichler R. Pichler
3 Find/buy lot 3 days Fri 5/22/15 Tue 5/26/15 2 R.Teller R.Teller
4 survey 1 day? Wed 5/27/15 Wed 5/27/15 3 Urban Planners Urban Planners
5 dig basement 1 day? Thu 5/28/15 Thu 5/28/15 4 D&M Excavating D&M Excavating
6 place footings 5 days? Fri 5/29/15 Thu 6/4/15 5 Theut Theut
7 lay basement block 3 days? Fri 6/5/15 Mon 6/8/15 6 Lee Lee
8 floor joists 1st floor 2 days? Tue 6/9/15 Wed 6/10/15 7 Pytleski Pytleski
9 frame 1st floor 3 days? Thu 6/11/15 Mon 6/15/15 8 Pytjeski Pytjeski
10 frame second floor 3 days? Tue 6/16/15 Thu 6/18/15 9 Pytleski Pytleski
11 roof framing 2 days Fri 6/19/15 Sat 6/20/15 10 Pytleski Pytleski
12 doors and windows 2 days Fri 6/19/15 Sat 6/20/15 10 Charlie Rocker Charlie Rocker
13 electrical 2 days? Mon 6/22/15 Tue 6/23/15 11 Metro - T. Sullivan Metro - T. Sullivan
14 roofing 1 day? Mon 6/22/15 Mon 6/22/15 11 John Masters John Masters
15 plumbing 2 days? Mon 6/22/15 Tue 6/23/15 11 Glenn Valley Glenn Valley
16 heating and cooling 2 days? Mon 6/22/15 Tue 6/23/15 11 jon Morrow jon Morrow
17 brick/cedar siding 3 days? Mon 6/22/15 Wed 6/24/15 11 Rob Beauchanp Rob Beauchanp
18 drywall 4 days Wed 6/24/15 Mon 6/29/15 14 Dzuris Dzuris
19 paint 4 days? Tue 6/30/15 Fri 7/3/15 18 Always Ptg Always Ptg
20 kitchen 1 day? Mon 7/6/15 Mon 7/6/15 19 Romeo Kitchen Romeo Kitchen
21 Finish carpentry 1 day? Tue 7/7/15 Tue 7/7/15 20
22 Landscape 5 days Wed 7/8/15 Tue 7/14/15 21 L. Super L. Super
23 Permit to occupy 1 day? Wed 7/15/15 Wed 7/15/15 22 Bommarito Bommarito

Task Project Summary Inactive Summary Manual Summary External Milestone

Project: Exam 2 Gantt chart 2015 Pro Split External Tasks Manual Task Start-only Progress
Date: Thu 1/11/18 Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks