KOVALAM - CHENNAI
ESTIMATE FOR CONSTRUCTION OF THREE CLASS ROOMS -
GROUND + TWO FLOORS BUILDING - INCLUDING STAIR-CASE
Plinth area : Class Room - 28.50 x 23.25 = 662.625 x 3 = 1988 sq.ft.
Stair-case - 3.05 x 23.25 = 90.913 x 4 = 284 sq.ft
Total = 2272 sq.ft
S.No Item Description Quantity Rate (Rs) Unit Amount (Rs)
FOUNDATION & BASEMENT
2 Earth work excavation for column footing 970.00 4.00 cft 3,880.00
4.5 x 4.5 x 4.5 & plinth beam 1.5 x 1.25
3 River sand filling in foundation for 6" thick 370.00 23.00 cft 8,510.00
& Plinth Beam 3" thick and under floor 6"
thick, including watering, leveling and
consolidation.
4 P.C.C. (1:5:10) in foundation mat concrete 270.00 50.00 cft 13,500.00
for column footing 4" tk, plinth beam 3" tk &
under floor 4" tk using 40mm jelly including
ramming, curing, etc
6 R.C.C. (1:2:4) using 20mm blue metal in 330.00 100.00 cft 33,000.00
footing Concrete, columns & plinth beam
9 Shuttering work for Column, Plinth Beam 750.00 18.00 sft 27,680.00
upto basement
4 Brick work in cm 1:5 using stock bricks for 425.00 85.00 cft 36,125.00
super-structure upto 9' 7.5" ht
16 Electrical wiring work - with switch boards 11.00 660.00 each 7,260.00
and switches, without fittings - for 3 fan
points, 4 light points and 2 plug points in
class room, one light point and one plug
point in verandah Total 312,490.00
III SUPER-STRUCTURE: - FIRST FLOOR
4 Brick work in cm 1:5 using stock bricks for 490.00 88.00 cft 43,120.00
super-structure upto 9' 7.5" ht
8 Hacking and rendering the RCC exposed 620.00 2.50 sft 1,550.00
surfaces suitable for plastering
15 White Washing two coats over a primer coat 2370.00 5.00 sft 11,850.00
using best shell lime/ with colour mix
16 Electrical wiring work - with switch boards 11.00 660.00 each 7,260.00
and switches, without fittings - for 3 fan
points, 4 light points and 2 plug points in
class room, one light point and one plug
point in verandah
Total 331,155.00
IV SUPER-STRUCTURE: - SECOND
FLOOR
S.No Item Description Quantity Rate (Rs) Unit Amount (Rs)
1 Cement Concrete 1:2:4 for all RCC works, 530.00 110.00 cft 58,300.00
like Columns, Lintel, Sunshades, Beams/
Roof slabs,
4 Brick work in cm 1:5 using stock bricks for 490.00 88.00 cft 43,120.00
super-structure upto 9' 7.5" ht
8 Hacking and rendering the RCC exposed 620.00 2.50 sft 1,550.00
surfaces suitable for plastering
15 White Washing two coats over a primer coat 2370.00 5.00 sft 11,850.00
using best shell lime/ with colour mix
16 Electrical wiring work - with switch boards 11.00 660.00 each 7,260.00
and switches, without fittings - for 3 fan
points, 4 light points and 2 plug points in
class room, one light point and one plug
point in verandah
Total 331,155.00
V STAIRCASE HEAD ROOM &
TERRACE WORK
S.No Item Description Quantity Rate (Rs) Unit Amount (Rs)
1 Cement Concrete 1:2:4 for all RCC works, 150.00 110.00 cft 16,500.00
like Columns, Lintel, Sunshades, Beams/
Roof slabs,
4 Brick work in cm 1:5 using stock bricks for 330.00 88.00 cft 29,040.00
super-structure upto 7' 6" ht
6 Plastering the walls inner & outer & ceiling 1110.00 10.00 11,100.00
in stair-case head room area in cm 1:5
7 Brick work in cm 1:5 using stock bricks for 85.00 88.00 cft 7,480.00
super-structure upto 2 ht - for terrace parapet
8 Plastering the parapet wall inner, top & outer 492.00 11.00 sft 5,412.00
in cm 1:5
9 Laying weathering course over roof slab 625.00 65.00 sft 40,625.00
using brick-jelly / lime mix in ratio 32:12-
1/2 average 3" thick, duly consolidating &
finishing the roof top with once course of
Pressed tiles size 9" x 9" in cm 1:3 with
water proof compound
10 Manufacturing, supplying & fixing 21.00 180.00 sq.ft 3,780.00
Aluminium glazed door of size 4' 6" x 7' 6"
complying with standard specification 1 No.
12 White Washing two coats over a primer coat 880.00 5.00 sft 4,400.00
using best shell lime/ with colour mix
13 Supplying & fixing 4" PVC rain water drop 33.00 135.00 4,455.00
pipes - including pipe fittings
Total 143,512.00
SUMMARY PER CLASS:
Foundation & Basement 199,555.00
Ground Floor 312,490.00
First Floor 331,155.00
Second Floor 331,155.00
Stair-head room & terrace work 143,512.00